Chapter 4 Laboratory Testing Results
4.3 Ultimate Test A
4.3.1 Global Behavior
The overall responses during Test A are illustrated in Figure 4-18. Up to 60 kips of
loading the bridge specimen showed a linearly elastic response with an initial stiffness of
approximately 90 kips/in. As the load increased from 80 kips to 140 kips, some cracks in
the deck were noticed and at the same time, the stiffness of the specimen was decreasing
visibly. Twisting of the girders was observed as well. At the load of 140 kips, the capacity
of the bridge slightly decreased by 1 kip because one bolt in the bottom connection of the
cross-frame near mid-span was sheared. The intact girder started showing uplift at the
cantilever support. The specimen reached its maximum capacity at 156 kips with 2.5 in. of
displacement.
After reaching the maximum capacity of 156 kips, the concrete deck was crushed
by the loading pad and the load dropped to 133 kips. The test continued and the specimen
was still able to sustain some additional load with many ups and downs until it failed at 5.5
in. of displacement. These ups and downs in this loading period corresponded to several
damages observed, including: 1) the visible cracking and crushing in concrete propagating
toward the ends of specimen, 2) the bottom of the concrete deck between the two girders
both ends of intact girder. As seen in Figure 4-18, during this loading period, the load
fluctuated and reached a local maximum load of 144 kips at 4-in. displacement. It, then,
slowly dropped down to 123 kips at 5.5-in. displacement before the test was halted. This
sequence of failure suggests that the bridge was trying to transfer the load to the intact
girder through an alternative load path after the primary load path had failed. This load-
transfer mechanism is discussed further in the following section.
Figure 4-18 Load vs. deflection curve of the specimen during ultimate load Test A.
A 1 ft by 1 ft grid was marked on the concrete surface to map the damage area more
accurately as illustrated in Figure 4-19. In general, the major damage was observed in the
deck over an area of 5 ft long by 3 ft wide at where the load was applied. Cracking started
along the inside top flange of the damaged girder, then it propagated toward the intact
girder. The cracking pattern was approximated by the black lines in Figure 4-19. This
cracking pattern indicates that the deck failed predominantly in one-way shear failure
mode. The deck damage showed that the damage propagated toward the north support more First Crack
CF Failed
Deck Crushed
Uplift CFs Failed
than the south support. It could be due to the presence of the cantilever portion in the south
end. This cantilever made the south portion of the specimen measured from the loading
point was stiffer than the north portion of the specimen. Eventually, the deck was punched
by the loading pad along the inside top flange of the damaged girder when the specimen
reached its maximum capacity. The spalling of concrete in the bottom of the deck is
illustrated in Figure 4-20.
Figure 4-20 Punching in the bottom of the deck.
The concrete deck was also damaged at both ends of the specimen. The mechanism
for the observed failure can be explained by considering the hypothetical situation in which
the deck is cut longitudinally between the girders leaving two separate and independent
structures. The east structure is then damaged and the load point is displaced downward
the same magnitude as produced in the actual test. Obviously, the magnitude of load
causing this displacement will be much less than what observed in test. Due to the low
flexural capacity at the damage location, the displaced shape will essentially be a
mechanism with hinge rotation about the load point and linear segments to the supports. It
is important to note how the ends of the girder will now project above the supports and that
the undamaged girder has no load applied and is therefore straight and level. Finally,
keeping the load point of the damaged girder at the fixed level of displacement, consider
the forces required to re-join the two separate structures and fuse the deck back together.
At the ends of the girder, the (hypothetical) damaged girder will be above the undamaged
one and need to be pulled downward, which then imparts an equal and opposite upward
Figure 4-21 where the deck above the undamaged girder appears to have been pulled
upwards and seemingly ripped off at the ends.
This same hypothetical situation can be used to examine the failure mechanism near
the load point. In this region, the (hypothetical) damaged girder will be below the
undamaged. Since the displacement level is being held by the loading beam, the
undamaged girder will be pulled downward when the two separate structures are
hypothetically re-joined. The effect of the resulting shear force can be seen in Figure 4-20.
Figure 4-21 Damage at North end (left) and South end (right).
Another important behavior observed was the uplift at supports of the intact girder.
Displacements near the supports were monitored at location 1 (14 in. from the bearing line
of the South support) and location 2 (17 in. from the north end of steel box girders) as
depicted in Figure 4-22. Figure 4-23 and Figure 4-24 plot the vertical displacements at
these two locations. These plots show that the intact girder (or the West Girder) began to
uplift at the south support shortly at 100 kips before the specimen reached its maximum
capacity of 156 kips while the north support was uplifted just right after the maximum Shear stress pulling up Shear stress pulling down Shear stress pulling up
capacity was reached. The final uplifts were measured as 0.48 in. near the south support
and 0.11 in. near the north support.
Figure 4-22 Location of potentiometers at supports.
Figure 4-24 Displacement of the both girders near the north support.
(a) North support (b) South support