The cost of material shall be evaluated considering the cost at crushing plants and cost of carriage including loading and unloading or the rates for

In document SOR-8th-Ed-2013 (Page 79-85)

supply at site depending upon system being followed at particular

locations. These rates should be compared with the rates for own crushing

and carriage by the construction agency.

Item

No. Descriptions Unit Rate (in Rs.)

1.1 Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum. (Placing tipper at loading point, loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip)

cum 135.00

1.2 Loading and Unloading of Boulders by Manual Means cum 160.00

1.3 Loading and Unloading of Cement or Steel by Manual Means and stacking. tonne 229.00

1.4 Cost of Haulage Excluding Loading and Unloading

(i) Surfaced Road tonne.km 6.60

(ii) Unsurfaced Gravelled Road tonne.km 7.90

(iii) Katcha Track and Track in river bed / nallah bed and choe bed. tonne.km 15.90 1.5 Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone, hand

breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50 mm

sieve) and stacking as directed) cum 689.00

1.6 Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone

aggregates of 13.2 mm nominal size.) cum 793.00

1.7 Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 20 mm nominal size.)

cum 673.00

1.8 Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 40 mm nominal size.)

cum 568.00

CHAPTER-1

1 RCD/SOR_8th edition_April 2013

1 RCD/SOR_8th edition_April2013 Sr

No

Ref. to MoRTH

Spec. Description Unit Quantity Rate Rs Cost Rs Remarks

/ Input ref.

1.1 Loading and Unloading of Stone Boulder/ Stone aggregates/Sand/ Kanker/Moorum

cum

Placing tipper at loading point, loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip

Unit = cum

Taking output = 5.5 cum Time required for

i) Positioning of tipper at loading point 1 Min ii) Loading by front end loader 1 cum bucket capacity

@ 25 cum per hour

13 Min

iii) Maneuvering, reversing, dumping and turning for return

2 Min

iv) Waiting time, unforeseen contingencies etc 4 Min

Total 20 Min

a) Machinery

Tipper 5.5 tonnes capacity hour 0.330 787.00 259.71 P&M-048

Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.330 1071.00 353.43 P&M-017

b) Overhead charges @ 0.1 on (a) 61.31

c) Contractor's profit @ 0.1 on (a+b) 67.45

Cost for 5.5 cum = a+b+c 741.90

Rate per cum = (a+b+c)/ 5.5 134.89

Note Unloading will be by tipping. say 135.00

1.2 Loading and Unloading of Boulders by Manual

Means Unit = cum

Taking output = 5.5 cum a) Labour

Mate day 0.110 171.00 18.81 L-12

Mazdoor for loading and unloading day 0.750 157.00 117.75 L-13

b) Machinery

Tipper 5.5 tonne capacity hour 0.750 787.00 590.25 P&M-048

c) Overhead charges @ 0.1 on (a+b) 72.68

d) Contractor's profit @ 0.1 on (a+b+c) 79.95

Cost for5.5 cum = a+b+c+d 879.44

Rate per cum = (a+b+c+d)/5.5 159.90

Note Unloading will be by tipping. say 160.00

1.3 Loading and Unloading of Cement or Steel by

Manual Means and Stacking.

Unit = tonne

Taking output = 10 tonnes a) Labour

Mate day 0.080 171.00 13.68 L-12

Mazdoor for loading and unloading day 2.000 157.00 314.00 L-13

b) Machinery

Truck 10 tonne capacity hour 2.000 782.00 1564.00 P&M-057

c) Overhead charges @ 0.1 on (a+b) 189.17

d) Contractor's profit @ 0.1 on (a+b+c) 208.08

Cost for10 tonnes = a+b+c+d 2288.93

Rate per tonnes = (a+b+c+d)/10 228.89

say 229.00

1.4 Cost of Haulage Excluding Loading and

Unloading

Haulage of materials by tipper excluding cost of loading, unloading and stacking.

Taking output 10 tonnes load and lead 10 km = 100 t.km

(i) Surfaced Road

Chapter - 1

Spec. Description Unit Quantity Rate Rs Cost Rs Remarks

/ Input ref.

Speed with load : 25 km / hour.

Speed while Returning empty :35 km / hour.

a) Machinery.

Tipper 10 tonne capacity

Time taken for onward haulage with load hour 0.400 787.00 314.80 P&M-048

Time taken for empty return trip. hour 0.290 787.00 228.23 P&M-048

b) Overhead charges @ 0.1 on (a) 54.30

c) Contractor's profit @ 0.1 on (a+b) 59.73

cost for 100 t km = a+b+c 657.07

Rate per t.km = (a+b+c)/100 6.57

say 6.60

1.4 (ii) Unsurfaced Graveled Road Speed with load: 20 km / hour

Speed for empty return trip :30 km / hour a) Machinery

Tipper 10 tonnes capacity

Time taken for onward haulage with load hour 0.500 787.00 393.50 P&M-048

Time taken for empty return trip hour 0.330 787.00 259.71 P&M-048

b) Overhead charges @ 0.1 on (a) 65.32

c) Contractor's profit @ 0.1 on (a+b) 71.85

Cost for 100 t .km = a+b+c 790.38

Rate per t.Km = (a+b+c)/100 7.90

say 7.90

1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and Choe Bed

Speed with load :10 km / hour

Speed while returning empty:15 km / hour a) Machinery

Tipper 10 tonnes capacity

Time taken for onward haulage hour 1.000 787.00 787.00 P&M-048

Time taken for empty return trip hour 0.670 787.00 527.29 P&M-048

b) Overhead charges @ 0.1 on (a) 131.43

c) Contractor's profit @ 0.1 on (a+b) 144.57

Cost for 100 t .km = a+b+c 1590.29

Rate per t.Km = (a+b+c)/100 15.90

say 15.90

3 RCD/SOR_8th edition_April2013 Sr

No

Ref. to MoRTH

Spec. Description Unit Quantity Rate Rs Cost Rs Remarks

/ Input ref.

1.5 Hand Broken Stone Aggregates 63 mm Nominal Size

Supply of quarried stone, hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50 mm sieve) and stacking as directed Unit = cum

Taking output = 1 cum a) Labour

Mate day 0.060 171.00 10.26 L-12

Mazdoor day 1.500 157.00 235.50 L-13

b) Material

Supply of quarried stone 150 - 200 mm size cum 1.100 294.26 323.69 M-002

c) Overhead charges @ 0.1 on (a+b) 56.94

d) Contractor's profit @ 0.1 on (a+b+c) 62.64

Rate per cum = a+b+c+d 689.03

say 689.00 1.6 Crushing of Stone Aggregates 13.2 mm Nominal

Size

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 13.2 mm nominal size.

Unit = cum

Taking Output = 600 cum at crusher location.

a) Labour

Mate day 0.760 171.00 129.96 L-12

Mazdoor Skilled day 2.000 200.00 400.00 L-15

Mazdoor including breaking of any oversize boulder. day 17.000 157.00 2669.00 L-13 b) Material

Stone Boulder of size 150 mm and below cum 800.000 294.26 235408.00 M-001 c) Machinery

Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens

Hour 6.000 23050.00 138300.00 P&M-028

Front end loader 1 cum bucket capacity Hour 20.000 1071.00 21420.00 P&M-017

Tipper 5.5 cum capacity Hour 20.000 787.00 15740.00 P&M-048

d) Overhead charges @ 0.1 on (a+b+c) 41406.70

e) Contractor's profit @ 0.1 on (a+b+c+d) 45547.37

Cost for 600 cum = (a+b+c+d+e)x0.95 475969.97

Rate per cum = (a+b+c+d+e) * 0.95 / 600 793.28

say 793.00 Note 1. 800 cum of stone boulders are needed to get 600 cum of

stone chips of size 13.2 mm.

2. 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 13.2 mm size and balance 5 per cent to the production of stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary crushing units.

1.7 Crushing of Stone Aggregates 20 mm Nominal Size

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 20 mm nominal size.

Chapter - 1

Spec. Description Unit Quantity Rate Rs Cost Rs Remarks

/ Input ref.

Unit = cum

Taking Output = 670 cum at crusher location.

a) Labour

Mate day 0.760 171.00 129.96 L-12

Mazdoor Skilled day 2.000 200.00 400.00 L-15

Mazdoor including breaking of any size boulder. day 17.000 157.00 2669.00 L-13 b) Material

Stone Boulder of size 150 mm and below cum 800.000 294.26 235408.00 M-001 c) Machinery

Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens

Hour 6.000 23050.00 138300.00 P&M-028

Front end loader 1 cum bucket capacity Hour 20.000 1071.00 21420.00 P&M-017

Tipper 5.5 cum capacity Hour 20.000 787.00 15740.00 P&M-048

d) Overhead charges @ 0.1 on (a+b+c) 41406.70

e) Contractor's profit @ 0.1 on (a+b+c+d) 45547.37

Cost for 670 cum = (a+b+c+d+e)x0.90 450918.92

Rate per cum = (a+b+c+d+e) * 0.90 / 670 673.01

say 673.00 Note 1. 800 cum of stone boulders are needed to get 600 cum of

stone chips of size 20 and 40 mm.

2. 90 per cent of above cost will be attributed to the production of 670 cum of stone aggregates of 20mm size and balance 10 per cent will be for smaller size aggregates and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary crushing units.

1.8 Crushing of Stone Aggregates 40 mm Nominal Size

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 40 mm nominal size.

Unit = cum

Taking Output = 750 cum at crusher location.

a) Labour

Mate day 0.760 171.00 129.96 L-12

Mazdoor Skilled day 2.000 200.00 400.00 L-15

Mazdoor day 17.000 157.00 2669.00 L-13

b) Material

Stone Boulder of size 150 mm and below cum 800.000 294.26 235408.00 M-001 c) Machinery

Integrated stone crusher of 200 TPH including belt

conveyor and vibrating screens Hour 6.000 23050.00 138300.00 P&M-028

Front end loader 1 cum bucket capacity Hour 20.000 1071.00 21420.00 P&M-017

Tipper 5.5 cum capacity Hour 20.000 787.00 15740.00 P&M-048

d) Overhead charges @ 0.1 on (a+b+c) 41406.70

e) Contractor's profit @ 0.1 on (a+b+c+d) 45547.37

Cost for 750 cum = (a+b+c+d+e)x0.85 425867.87

Rate per cum = (a+b+c+d+e)x0.85/750 567.82

say 568.00 Note 1. 800 cum of stone boulders are needed to get 600 cum of

stone chips of size 13.2 mm.

2. 85 per cent of above cost will be attributed to the production of 750 cum of stone aggregates of 40mm size and balance 15 per cent will be for smaller size aggregates and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary crushing units.

Chapter – 2

Site Clearance

Preamble:

1. Unless otherwise stated, the rates include sorting and disposal of

In document SOR-8th-Ed-2013 (Page 79-85)