• No results found

What you need to plan for

Procurement Planning

When planning occurs

Identify 1 Evaluate 2 Define 3 Execute 4 Operate

Procurement Strategy

Procurement Plan

Materials Management Plan , if required

Purchasing and Contracts Initiation

Materials Management Plan, if required Contracts Plan, if required

Materials Field Administration

Contracts Plan , if required

Materials Management and Contracts Close-out

Procurement Planning

Project Procurement Strategy (PPS) is the:

Process for identifying and documenting the procurement opportunities applicable to the project

First step in developing the Project Procurement Plan

Typically, the PPS is first developed during the scoping stages of a project

Sometimes the customer provides the initial procurement strategy for further development in the Project Procurement Plan

Project Procurement Strategy

Procurement Planning

Purchasing activities can involve long lead times

Certain materials and equipment may be particularly critical to a project’s success

Purchasing activities usually involve multiple countries (infrastructure and logistics, local legislation etc.)

Market and technology developments can impact on the success of a project and therefore need to be monitored on an ongoing basis

During the development of the PPS, the following factors need to be considered:

Project Procurement Strategy

Procurement Planning

The PPS is a hierarchical matrix covering the entire work scope of a project, broken down into separate ‘work packages’

Only the major critical items are separately identified as work packages

These packages are created and identified according to:

Unique technical and commercial attributes of the work activities they comprise

Methods by which they are to be executed

Project Procurement Strategy

Procurement Planning

Example of a PPS matrix

Components Physical 

 Discipline

Special Equipment Item A

Special

Equipment Item B Balance of Plant Civil Works

Project Management

Project Management Services Contractor – Reimbursable Costs with Incentives Fee – $ 70m total

Design Design Contract – Lump Sum – $10m Facilities E & P Contract –

Reimbursable Costs with Fixed Fee –

$30m total Procurement Specialist

Supplier A – Lump

Purchase Order –

$100m total Fabrication

Construction Contract –

Reimbursable Cost and Equipment Rates with Incentives Fee - $100M total

Materials Control Construction / Erection Services

Installation Contract – Lump Sum –

$10m

Quality Inspection Specialist Quality Contract – All-in rates – $10m

Part of Project Management Services

Commissioning / Start-up

Assistance

Part of Supplier A Purchase Order

Part of Supplier B

Purchase Order Contract N/A

Procurement Planning

The structure of the PPS depends on the:

Scope of work

Nature and complexity of the project

Requirements of the customer

The PPS assists in:

Administrative and commercial planning

Cost/schedule control functions of a project

Project Procurement Strategy

Procurement Planning

Allows a concise, high-level overview of how procurement activities relate to the execution strategy of the project

Illustrates alternative ways of executing the project procurement activities

Identifies where:

Consolidation (or further break-down) of work scopes can work to the project’s advantage

Gaps may occur in hand-offs during execution

A Procurement Strategy is a deliverable that can be provided for projects in Identify and Evaluate phase

Benefits of a PPS

Procurement Planning

When planning occurs

Identify 1 Evaluate 2 Define 3 Execute 4 Operate

Procurement Strategy

Procurement Plan

Materials Management Plan , if required

Purchasing and Contracts Initiation

Materials Management Plan, if required Contracts Plan, if required

Materials Field Administration

Contracts Plan , if required

Materials Management and Contracts Close-out

Procurement Planning

Projects in Identify and Evaluate phases:

While you might not be able to fully identify these requirements, you should be able to identify them in broad scope

Concentrate on Procurement Strategy approach

Projects in Define phase:

The procurement needs of the project should be sufficiently identified to support the Customer’s overall project schedule

Full fledged procurement plan can be developed

Projects in Execute phase:

The procurement needs are clearly identified and a procurement plan shall be developed to achieve the timely delivery of the project

Full fledged procurement plan must be developed

Planning in the various WMPM project phases

Procurement Planning

Documents the basis for obtaining and managing materials,

equipment and third-party services required for project execution

Addresses relevant aspects of both materials management and contracts for the project

Maps out the various anticipated risks and constraints and identified mitigating actions

Identifies critical supplies (see also Procurement Strategy) and outlines general strategy

Ensures that the procurement activities align with the overall project schedule

Project Procurement Plan

Procurement Planning

The Project Procurement Plan:

Must clearly define the deliverables of the procurement process

Needs to be ‘fit for its purpose’

Project Procurement Plan

Procurement Planning

The Project Procurement Plan may also include details about the targeting of procurement efforts

The Project Procurement Manager will consider the assessment in the strategy development

Criticality-Value Assessment

Project Procurement Plan

Bottleneck, e.g. special alloy steel grade

Ensure continuity Develop alternatives Revise specifications

Critical, e.g. turbine compressor

Form closer relationships Direct negotiations

Routine, e.g. piping bulk blanket orders

Simplify procurement process

Automate

Rationalise supplier base

Leverage, e.g. customer’s standard agreement

Procurement Planning

Project Procurement Plan

Where the complexity and / or size of the project warrant it, the Project Procurement Plan may be further developed in separate plans:

A detailed Project Materials Management Plan

Separate detailed Project Contracts Plan for major contract packages

Separate detailed Procurement Plans for key procurement packages

Procurement Planning

The various elements of the Procurement Plan are further defined in the Materials Management Plan, including:

Specific strategies for buying materials and equipment

Associated activities for managing the expediting, traffic/logistics etc

The materials control and reporting systems

Prioritization of procurement activities and associated engineering deliverables in line with the ROS (Required on Site dates) as defined in the project schedule

Materials Management planning

Procurement Planning

Level of procurement effort based on cost, schedule, criticality, and other relevant factors

POs/activities already executed and/or underway prior to engagement of WorleyParsons

Transition of early purchase agreements from the customer

Material control systems

Quality management, verification and inspection, which includes an outline of inspection to be undertaken

Site materials management plans

Materials Management planning (cont’d)

Procurement Planning

Subsets of the Material Management Plan

Engineered equipment planning

Bulk materials planning

Prefabrication planning and modularization Materials Management planning

Procurement Planning

The primary objective is to ensure that items are acquired and released in time to meet the overall project schedule

The dates on which items are required on site to meet construction needs drive the engineering and procurement planning and activity for engineered equipment

A major equipment list for the project needs to be developed early Engineered equipment planning

Procurement Planning

Planning for bulk materials can be more complex than planning for engineered equipment

Bulk materials control starts with an examination of the project schedule to assess:

What bulk materials are required over time

Critical required on site (ROS) dates Bulk material planning

Procurement Planning

Procurement planning:

Is usually very complex for extensive prefabrication

modularization often involving multiple sites

An extensive prefabrication program demands an early procurement planning effort that addresses the interfaces between vendors,

fabricators and site construction

Related documents