Chapter 6: Conclusion and Recommendations

6.2 Recommendations

 ESKOM needs to align the PDRI instrument graphical displays with the score in the PDRI instrument; this was observed when analysing results of the PDRI. Elements displays did not match the results in the result tables.

 Upfront training must be completed for those involved in the capital projects at the beginning of the project; when it is time for the PDRA they should be familiar with the instrument.

 Contractors executing the capital projects should be requested to also use the PDRI to determine if the preparatory work was completed before the works/actual construction begin to minimise change orders later in the project.

 ESKOM must consider defining small and large projects and be consistent in the rules. There were incidents where capital projects for refurbishment were executed as small projects, missing the opportunity of using the PDRI instrument in FEP. These projects bypassed the FEP lengthy time but discontinue requiring more time and funds because of a lack of proper preparations compared to those who experience FEP with PDRI.

 Currently the only costs are used to classify the size of a project, so if the project is divided into smaller pieces, it can be completed without using the PDRI instrument. The complexity remains and when it has to be integrated, more scope creep is experienced. When it is executed, it leads to greater scope creep, costs escalations and time extensions.

52

Bibliography

[1] P. Govendor, “Eskom Overview & National Development Plan SIPs,” in CESA, Johannesburg, 2013.

[2] J. Sandelandas, “Addressing South Africa's engineering skill gaps,” Education+ Training, vol. 51, no. 2, pp. 215-219, 2009.

[3] P. Malunga, “Project Management Guidebook,” Eskom, Johannesburg, 2012.

[4] National Environmental Management, “Air Quality Act (Act No. 39 of 2004),” South Africa Government, Pretoria, 2004.

[5] ESKOM, “New Build,” ESKOM, [Online]. Available:

http://www.ESKOM.co.za/Whatweredoing/Newbuild/Pages/New_Build_Programme.aspx. [Accessed 21 March 2017].

[6] M.Murray, “Project definition Readiness Assessments: Introduction to the PDRA procedure, PDRI instruments and the project definition readiness assessment,” Eskom, Johannesburg, 2011. [7] R. J. Muller, “The impact of project methodologies on project success in various project

environments,” International Journal of Managing Projects in Business, vol. 9, no. 2, pp. 364-388, 2016.

[8] K. Y. S. Hee Sung Cha, “Predicting Project costs Performance Level by Assessing Risk Factors of Building Construction in South Korea,” Journal of Asian Architecture and Building Engineering, vol. 10, no. 2, pp. 437-444, 2011.

[9] Construction Industry Institute, “Project Definition Rating Index (PDRI): Small Industrial Projects, Implementation Resource 314-2,” Texas, USA, 2015.

[10] Construction Industry Institute, pp27-31., “Project Definition Rating Index (PDRI): Industrial Projects, Implementation Resource 113-2, 3.2 ed.,” Construction Industry Institute,, Texas, USA, 2009.

[11] C.Cho and G.E. Gibson Jr, “Building Project Scope Defintion Using Project Definition Rating Index,” Journal of Architectural Engineering, vol. 7, pp. 115-125, 2001.

[12] S. Staats, “Interface Management in multidisciplinary infrastructure project development,” Delft University of Technology, Lexmond, 2014.

[13] U.S. Department of Energy, “Project Definition Rating Index Guide forTraditional Nuclear and Non-NuclearConstruction Projects,” 2010. [Online]. Available: https://www.directives.doe.gov/. [Accessed 21 March 2017].

[14] D. Lock, Project Management -4th ed., Vermont, USA: Gower, 1988.

[15] G.E Gibson, P.R Dumont, J.R Fish, “Scope Management Using Project Definition Rating Index,”

Management in Engineering, 1997.

53

International Transactions, no. EST. 604, pp. 1-17, 2011.

[17] P. Moncrief, costs Control for the Project Manager, Colorado USA: Long International, 2004. [18] J. R. M. a. Samuel, “Project Management: A Managerial Approach 8th e.d.,” in Project

Management, U.S.A, John Wiley & Sons, 2012, pp. 1-568.

[19] A.A. Andrashov et al., “I&C systems refurbishment projects for plant life extension,” in

International Conference on Nuclear Power Plant Life Management (PLiM) for Long Term Operations (LTO), Salt Lake City,US., 2012.

[20] R. Olsson, “Risk management in a multi-project environment: An approach to manage portfolio risks,” Internation Journal of Quality & Reliability Managenent, vol. 25, no. 1, pp. 60-71, 2008. [21] A. Ali, H.Hassan and I. Rahmat, “Involvement of crucial design participants in refurbishment

design process,” Facilities, vol. 26, no. 9/10, pp. 389-400, 2008. [22] B. Botha, Lecture 2 - Requirement Analysis, Johannesburg: UJ, 2016.

[23] S. J. Lotz, “Generalized application of the Project Definition Rating Index,” in INCOSE, Pretoria, 2015.

[24] G.E.Gibson and M. R. Hamilton, “Analysis of pre-project planning effort and success variables for capital projects,” University of Texas, Texas, 1994.

[25] Construction Industry Institute, “Assessment of Effective Front End Planning Processes,” CII, US, 2013.

[26] C. J. Van Wyngaard, J. H. C. Pretorius, L. Pretorius, “Theory of the Triple Constraint – a Conceptual Review,” IEEE IEEM, vol. 12, pp. 1991-1997, 2012.

[27] B. A. K. S. M. Welde, “Low estimates- high stakes:underestimation of costs at the front-end of projects,” Internation Journal of Managing Projects in Business, vol. 9, no. 1, pp. 171-193, 2016. [28] R. T. 314, “Project Definition Rating Index –Small Industrial Projects,” in CII Annual Conference,

Austin, 2015.

[29] ICD Eskom, “Project Development Front-End Planning Guidebook - Rev 3,” Eskom, Johannesburg, 2016.

[30] A. van Aartsengel and S.Kurtoglu, Handbook on Continuous Improvement Transformation:The Lean Six Sigma Framework and Systematic Methodology for Implementation, Heidelberg: Springer, 2013, pp. 65-74.

[31] P.B. Schaub and E Franfenberger, “ Analysis of design projects,” Design Studies, vol. 20, no. 5, pp. 465-480, 1999.

[32] Azlan-Shah Ali and Cheong-Peng Au-Yong, “The designer in refurbishment projects: implications to the compatibility of design,” Structural Survey, vol. 31, no. 3, pp. 202-213, 2013.

[33] A. Zika-Viktorsson,et., “Project overload: An exploratory study of work and management in multi- project settings,” International Journal of Project Management, vol. 24, pp. 385-394, 2006.

54

[34] Y.Wang, “Pre-Project Planning And its Practice in Industry,” ISARC, 2006.

[35] M. Kraljic, “An empirical investigation of the relationship between intellectual capital and project success,” Journal of Intellectual Capital, vol. 17, no. 2, pp. 471-488, 2006.

[36] NASA Pre-Project Planning Team, “PDRI Use on NASA Facilities,” NASA, Washington,D.C., 2000.

[37] R. K.Yin, Case Study Research: design and Methods, US: SAGE, 2014.

[38] G. D. Bouma, “Doing qualitative research,” in The Research Process, Melbourne, Oxford University Press, 196, pp. 169-187.

[39] PMI, “A Guide to the Project Management Body of Knowledge,” Project Management Institute, Penneyslvania, 2004.

[40] G. Bouma, “Selecting Research Design,” in The Research Process, Melbourne, Oxford University Press, 1996, pp. 86-105.

[41] G. Vinten, “Open vs Closed Questions- A Closed Question?,” Managerial Auditing Journal, vol. 3, no. 1, pp. 11-13, 1988.

[42] R. Kumar, Research Methodology, London: SAGE Publications, 2005.

[43] U. Dwivedi, “Earned-value-management-explained,” January 2009. [Online]. Available:

www.projectsmart.co.uk/earned-value-management-explained.php. [Accessed 23 January 2018]. [44] R. K.Yin, Application of Case Study Research, California: SAGE, 1993.

[45] Department of Minerals and Enegry, “White paper on Renewable Energy of the Republic of South Afica,” Government Printers, Pretoria, 2003.