RBR-SBBS-1 1 Granular Sub-base with Well Graded Material / Close Graded Material (Table 400.1)

In document AP Standard Data- All (Page 97-100)

A By Mix in Place Method

Construction of granular sub-base by providing well graded material / Close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller 80-100 kN / Vibratory Roller to achieve the desired density, complete as per Technical Specification Clause 401 MORD / MORTH.

i For Grading I Material (CBR Value minimum 30)

Unit = cum

Taking output = 300 cum a) Labour

Mate day -

Mazdoor (Skilled) day 2.48

Mazdoor (Unskilled) day 10.00

b) Machinery

Motor Grader 110 HP @ 50 cum per hour hour 6.00 Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00

OR

vibratory roller 80-100 kN hour 6.00

Tractor with Rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 3.00

c) Material

Well graded / Close Graded granular sub-base material as per Table 400.1

53 mm to 9.5 mm @ 50 per cent cum 192.00

9.5 mm to 2.36 mm @ 20 per cent cum 77.00

2.36 mm below @ 30 per cent cum 115.00

Water kl 18.00

d&e) Overheads & Contractors Profit

Cost for 300cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/300

Cost for 300 cum = a+b+c+d+e (Vibratory Roller) Rate per cum = (a+b+c+d+e)/300

ii For Grading II Material(CBR Value minimum 25)

Unit = cum

Taking output = 300 cum a) Labour

Mate day -

Mazdoor (Skilled) day 2.48

Mazdoor (Unskilled) day 10.00

b) Machinery

Motor Grader 110 HP @ 50 cum per hour hour 6.00 Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00

OR

vibratory roller 80-100 kN hour 6.00

Tractor with Rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 3.00

c) Material

Well graded/ Close Graded granular sub-base material as per Table 400.1

26.5 mm to 9.5 mm @ 35 per cent cum 134.00

9.5 mm to 2.36 mm @ 25 per cent cum 96.00

2.36 mm below @ 40 per cent cum 153.00

Water kl 18.00

d&e) Overheads & Contractors Profit

Cost for 300cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/300

Cost for 300 cum = a+b+c+d+e (Vibratory Roller) Rate per cum = (a+b+c+d+e)/300

Andhra Pradesh Standard Data

I. Roads and Bridges

Chapter - 4

GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS

S. No 1

RBR-SBBS

Index-code Description Unit Quantity Rate

Rs. Amount Rs. Remarks 2 3 4 5 6 7 S. No 1

iii For Grading III Material(CBR Value minimum 20)

Unit = cum

Taking output = 300 cum a) Labour

Mate day -

Mazdoor (Skilled) day 2.40

Mazdoor (Unskilled) day 8.00

b) Machinery

Motor Grader 110 HP @ 50 cum per hour hour 6.00 Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00

OR

vibratory roller 80-100 kN hour 6.00

Tractor with Rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 3.00

c) Material

Well graded/ Close Graded granular sub-base material as per Table 400.1

9.5 mm to 4.75 mm @ 66 per cent cum 255.00

2.36 mm below @ 34 per cent cum 129.00

Or

9.5 mm to 4.75 mm @ 35 per cent cum 134.40

4.75 mm to 2.36 mm @ 12.5 per cent cum 48.00

2.36 mm below @ 52.5 per cent cum 201.60

Water kl 18.00

Total d&e) Overheads & Contractors Profit

Cost for 300cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/300

Cost for 300 cum = a+b+c+d+e (Vibratory Roller)

Rate per cum = (a+b+c+d+e)/300

B Plant Mix Method

(i) Construction of granular sub-base by providing well graded /

Close Graded material, mixing in a mechanical mix plant at OMC, carriage of mixed material to work site upto lead of 1000 m spreading in uniform layers with motor grader on prepared surface and compacting with smooth wheel roller 80-100 kN to achieve the desired density, complete as per Technical Specification Clause 401

i For Grading I Material ( CBR Value minimum 30) Unit = cum

Taking output = 225 cum (450 t) a) Labour

Mate day -

Mazdoor (Skilled) day 2.40

Mazdoor (Unskilled) day 8.00

b) Machinery

Wet mix plant @ 60 /75 t capacity per hour hour 7.50 Water tanker 6 kl capacity 5 km lead with one trip per hour hour 4.00

Front end loader 0.9 cum / 1 cum bucket capacity 37.5 cum per hour

hour 6.00

Tipper 5.5 cum @ 3 trips per hour hour 13.60

Motor grader 110 HP @ 50 cum per hour hour 4.50 Three wheel 80-100 kN static roller 10 cum per hour hour 22.50

OR

vibratory roller 80-100 kN hour 6.00

c) Material

Well graded/ Close Graded granular sub-base material as per Table 400.1

53 mm to 9.5 mm @ 50 per cent cum 144.00

9.5 mm to 2.36 mm @ 20 per cent cum 57.00

2.36 mm below @ 30 per cent cum 86.40

Water kl 24.00

d&e) Overheads & Contractors Profit

Cost for 225 cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/225

Cost for 225 cum = a+b+c+d+e (Vibratory Roller) Rate per cum = (a+b+c+d+e)/225

Index-code Description Unit Quantity Rate Rs. Amount Rs. Remarks 2 3 4 5 6 7 S. No 1

ii For Grading II Material (CBR Value minimum 25)

Unit = cum

Taking output = 225 cum (450 t) a) Labour

Mate day -

Mazdoor (Skilled) day 2.40

Mazdoor (Unskilled) day 8.00

b) Machinery

Wet mix plant @ 75 t capacity per hour hour 7.50 Water tanker 6 kl capacity 5 km lead with one trip per hour hour 4.00

Front end loader 0.9 cum bucket capacity 37.5 cum per hour hour 6.00

Tipper 5.5 cum, 3 trips per hour hour 13.60

Motor grader 110 HP @ 50 cum per hour hour 4.50

Three wheel 80-100 kN static roller 10 cum output hour 22.50

OR

vibratory roller 80-100 kN hour 6.00

c) Material

Well graded / Close Graded granular sub-base material as per Table 400.1

26.5 mm to 9.5 mm @ 35 per cent cum 100.80

9.5 mm to 2.36 mm @ 25 per cent cum 72.00

2.36 mm below @ 40 per cent cum 115.20

Water kl 24.00

d&e) Overheads & Contractors Profit

Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)

Rate per cum = (a+b+c+d+e)/225

Cost for 225 cum = a+b+c+d+e (Vibratory Roller) Rate per cum = (a+b+c+d+e)/225

iii For Grading III Material(CBR Value minimum 20)

Unit = cum

Taking output = 225 cum (450 t) a) Labour

Mate day -

Mazdoor (Skilled) day 2.40

Mazdoor (Unskilled) day 8.00

b) Machinery

Wet mix plant @ 60 t capacity per hour hour 7.50 Water tanker 6 kl capacity 5 km lead with one trip per hour hour 4.00

Front end loader 0.9 cum bucket capacity 37.5 cum per hour hour 6.00

Tipper 5.5 cum, 3 trips per hour hour 13.60

Motor grader 110 HP @ 50 cum per hour hour 4.50

Three wheel 80-100 kN static roller 10 cum output hour 22.50

OR

vibratory roller 80-100 kN hour 6.00

c) Material

Well graded / Close Graded granular sub-base material as per Table 400.1

9.5 mm to 4.75 mm @ 35 per cent cum 100.80

4.75 mm to 2.36 mm @ 12.5 per cent cum 36.00

2.36 mm below @ 52.5 per cent cum 151.20

Water kl 24.00

d&e) Overheads & Contractors Profit

Cost for 225 cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/225

Cost for 225 cum = a+b+c+d+e (Vibratory Roller) Rate per cum = (a+b+c+d+e)/225