• No results found

(water tightness BS 8007: 1987)

Top

Index Scope Definition Responsibilities Safety

Method / Procedures Equipment

Attachment Scope

To transport the Sea Water to the Sea Water Basin and Testing the basin Definitions

PSM Project Site Manager CM Construction Manager

CS Construction Superintendent

FM Foreman

Responsibilities

CM shall plan and resource the required materials and plants ensuring that these are implemented according to this procedure.

CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.

CS shall ensure the implementation of technicalities involved.

FM shall control the work force ensuring the full implementation of the procedure.

Safety

Prior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Traffic directory signs for the ramp breakers on 3 nos road crossings shall be installed. On the exposed pipe route the safety tags shall be installed with cones. A protection arrangement shall be made for the plants at the intake. A full time attendant shall keep the watch and ward on the route.

Procedures involved

Laying a 100 mm dia hose from the sea to the sea water approximately1800 m. Refer to sketch point # 1 to # 8 i.e. intake at sea and discharge to the basin respectively.

Constructing a concrete anchor at the sea to fix the intake pipe spout horizontally and vertically as well as to fix 2 # heavy duty centrifugal pumps at point #1

There are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted in the form of the ramped speed breakers.Ref to the sketch. Otherwise, sleeves shall be inserted by road cutting, filling and making good when the job is over

Install a ‘round the clock’ generator to supply electricity to the pumps with the Distribution Board at point # 1 or to have electric connection through an alternative source.

Install a timber clamping platform on the ditch at point # 4 Water Heads calculations indicative only

At intake suction 1 m At intake disposal 1 m Vertical head loss 25 m At point Nos. 8 loss 10 m Total vertical head loss 37 m

Length of Pipe for friction loss 1800 m 4 f l v v / 2 g d

= 4x.015x1800x1.5x1.5 / 2x 9.81x.1=123.9m

Total head loss = static loss + dynamic loss = 37 +123.9 = 160.90 m

Work done= 42000x160.9 kgm, bhp = 42000x160.9 / 270000= 25 units, ihp = 35 units The water flow velocity has been assumed to be 1.5 m / sec giving a discharge of 42 cum per hour. It shall take 20 days to reach 20000 cum of water to the basin keeping round the clock pumping.

SEA WATER BASIN PLANNED PUMPING

DAY # QTYPUMPED

IN

QTY CUMM

CUM CUM

1 1008 1008

2 1008 2016

3 1008 3024

4 1008 4032

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches

5 1008 5040

6 1008 6048

7 1008 7056

8 1008 8064

9 1008 9072

10 1008 10080

11 1008 11088

12 1008 12096

13 1008 13104

14 1008 14112

15 1008 15120

16 1008 16128

17 1008 17136

18 1008 18144

19 1008 19152

20 1008 20160

21 1008 21168

First phase Testing

The tank completed with Protective Coatings as specified and sealant applied shall be cleaned and filled to the normal maximum level to meet the requirement of clause 9.2 BS 8007 : 1987 Testing of structures i.e. upto 11.5 m which should take 14 days and then be retained for a stabilising period of 7 days for a maximum design crack width of 0.1 mm, allowing absorption and the autogenous healing.

Test period starts now for 7 days and the drop in level recording be made every 24 hours during this 7 days period. Total permissible drop in level allowing evaporation etc. should not be more than 1 / 500 of the average water depth of the full tank which limits to 10 mm or another specified or calculated amount.

Having the test been successful, the backfill shall be carried out Second phase Testing

Let the tank be further filled upto 13 m level i.e another 7 days

Stabilisation period Another 7 days (for absorption and autogeneous healing) Test period Another 7 days (level drop recording at an interval of 24 hours) Basin Filling and Testing Schedule

S #

Description of the operation Duration in

days Remark

1 Ist phase water pumping 14 Pumping from sea

2 Retained water stabilisation to

allow absorption and

autogeneous healing

7

3 Testing at 24 hour intervals and monitoring

7 Loss should not be more than 1 / 500 of average fullwater depth or 10 mm or other specified value

but excluding evaporation.

4 Backfilling after successful testing

14

5 II phase water pumping 7 Pumping from sea

6 Retained water stabilisation and autogeneus healing

7 7 Testing at 24 hours intervals 7

8 Water loss monitoring Loss should not be more

than 1 / 500 of average fullwater depth or 10 mm or other specified value but excluding evaporation

The code provides that notwithstanding the satisfactory completion of the test, any evidence of seepage of the liquid to the outside faces of the liquid retaining walls should be assessed against the requirement of the specification. Any necessary remedial treatment of the concrete, cracks or joints should, where practicable, be carried out from the liquid face. When a remedial lining is applied to inhibit leakage at a crack, it should have adequate flexibility and have no reaction with the stored liquid.

Should the structure not satisfy the 7 days test then after the completion of the remedial work, it should be refilled and if necessary, left for a further stabilising period followed by a further test of 7 days’ duration should then be undertaken in accordance with this clause.

Equipment.

Pumps IHP 35, 2 Nos.

Other General Arrangements

Attachment

Sketch showing the Hose Route

#29