chapter 9: selection criteria
About this Chapter
Selection criteria are the rules for choosing the winning bidder. This chapter describes the principles of selection criteria and provides advice on appropriate selection criteria for use in local development procurement. It also discusses when pre-qualification should be used.
Pass-Fail criteria and comparison criteria
Selection criteria must be decided beforethe bid is advertised. The bid document must state clearly what the selection criteria are. Selection criteria should be objective – two different evaluators, using the same criteria independently, should come to the same decision. There are two kinds of criteria – pass/fail and comparison.
Bid price is usually a comparison criteria, though in some cases (for example, Fixed Budget Selection for consultants) it may be a pass/fail criteria.
Pass/fail criteria are mainly used either
for qualification or to determine whether bids are responsive Comparison criteria are used to identify the best bid from amongst the responsive bids submitted by qualified bidders. Comparison criteria may include the bid price and other (non- price) considerations.
Normally, the qualification criteria (pass/ fail) are not used again to compare between bids. There is an exception to this rule in the comparison of technical proposals from consultants – the technical score is used to compare proposals, amongst those proposals that achieve a pre-defined minimum score (see box).
1. The Request for Proposals states that the consultant must have at least a Master’s degree. If the bidder does not have a master’s degree, the bid fails and the bidder is eliminated. So this is a pass/fail criterion.
2. The Request for Proposals states that a score will be awarded for the number of years of relevant experience the bidder has. So, a bidder with 15 years’ experience gets a higher score than a bidder with 10 years’ experience. This is a comparison criterion.
The standard procedure for evaluating requests for proposals for consultant services is:
1. Calculate a technical score; 2. Eliminate the bids that have less
than the minimum acceptable score (say, 75%);
3. Combine the technical score with a score for the financial proposal (price) to identify the best overall proposal.
Chapter 9: Selection Criteria
46
Qualification criteria
Qualification criteria vary. The basic principle is that only criteria that are relevant to the bidder’s ability to undertake the contract may be applied. Criteria will usually include the following.
1 Is the bidder legally entitled to undertake the contract? In most countries, bidders
for public contracts are obliged to show that they are properly registered businesses and have paid any taxes that are due. These requirements can cause complications for very small or community-based contractors and regulations should allow such “informal contractors” to participate where appropriate. The bidder may be asked to submit evidence such as copies of registration certificates, tax returns, etc.
2 Is the bidder barred from bidding because of a previous event? Contractors that
default on their obligations (either by refusing to accept a contract they have bid for, or by failing to fulfill the contract) or that are found to engage in corrupt practices (for example, offering bribes to procurement officials) may be barred from bidding either for a fixed period or permanently. In some cases, bidders may be barred because of other circumstances, for example, if the bidder is involved in an ongoing legal dispute. Bidders may be asked to sign declarations that they are not barred from bidding.
3 Does the bidder have the technical capacity to undertake the contract? Evidence
of technical capacity may be required. In some countries, the government maintains lists of contractors who are considered to have capacity to undertake certain types of work, and contracts up to a certain value. It is common to ask contractors to provide evidence of previous experience with similar types of contracts – for example, three contracts of a similar nature during the previous five years. Bidders may also be asked to provide evidence of the qualifications of key staff members who will work on the project, and to provide evidence that they have access to the equipment needed for the contract. Only details of key staff and equipment should be requested. It does not matter whether the staff proposed are permanent staff of the bidder or not, provided that there is a clear commitment that they will be available for the contract. Similarly, it does not matter whether the equipment is owned by the bidder or whether the bidder will rent it.
4 Does the bidder have enough financial stability to undertake the contract? The
contractor will need sufficient working capital to undertake the contract. Normally, he/ she will have to buy materials, pay workers, etc. before receiving any payment from the buyer. If the contractor becomes insolvent during implementation of the contract this may cause financial loss to the buyer. It is normal to require a contractor to provide evidence of financial stability, but this can be difficult for small firms – and difficult for local governments to verify. The bid documents may require the contractor to provide evidence of an adequate bank balance, but this is not necessarily sufficient evidence in itself. If a firm is able to show evidence of having successfully completed a number of contracts of similar size in the past, this may be taken as evidence of financial stability.
Pre or Post-Qualification?
Bidders’ qualifications may be checked at the beginning of the procurement process (pre- qualification or short-listing) or at the end of the process (post-qualification). The relative merits of pre and post-qualification systems are discussed in Chapter 4 above.
47
Chapter 9: Selection Criteria
It is recommended that post-qualification systems should generally be preferred for local development contracts for works or supply of goods. The reasons for preferring post- qualification are that:
1. It allows more firms to compete. Pre-qualification may have the effect of restricting the number of firms that can compete for contracts, even if the qualification criteria are applied fairly; and
2. It is more efficient. The buyer only has to check the qualifications of one contractor (the winning bidder).
responsiveness criteria
Bids are categorized as “responsive” or “non-responsive” according to whether they are fully and correctly completed and represent a clear commitment by the bidder to undertake the contract on the terms proposed by the buyer. Bids that do not make this commitment clear (for example, if the form of the bid is not properly signed) are rejected. The full list of responsive criteria varies but for small contracts the criteria might include:
• All parts of the bid document are properly completed and signed;
• The bidder does not propose any changes to the proposed design, specifications or conditions of the contract;
• Any required supporting documents are included.
Bidders submit evidence of qualifications
Bidder is Qualified?
Increasing Community Ownership
In cr eas in g C BO C ap ac ity Community Grants Labour Contracting
Range of Modalities for Community Contracting
Invitation to Bid Conference Pre-Bid Site Visit Deadline for Bid Submission Bid Opening Recommendation for Award of Contract Award of Contract Award of Contract Construction Completion Inspection Hand-Over Defects Liability Final Inspection MAX 30 Days Payment Certificate Request for Payment Selection Criteria Quality Quality 100% 80% 60% 40% 20% 0% 100% 80% 60% 40% 20% 0% 100% 80% 60% 40% 20% 0% 100% 80% 60% 40% 20% 0% Price Appropriate to Estimate Social Preferences Lowest Price Bangladesh Cambodia Laos Timor Leste Bangladesh Cambodia Laos Timor Leste Bangladesh Cambodia Laos Timor Leste Bangladesh Cambodia Laos Timor Leste Procurement Methods Competitive Bidding Direct Contracting Direct Works Community Contracting
Roles and Responsibilities
Elected Politician Responsible
Community
Responsible Local Administration Responsible
Higher Govt Responsible
Size and Type
Average contract (% of $25,000) % of Government funding % of Works Contract as % of budget
A
B
Monitors Approves Community Oversees Recommend Technicians and Administrators Council ExecutiveDiagram : Roles and Responsibilities in Local Procurement
BID
BID
BID
Non-qualified bidders rejected Short-listed bidders submit bids Bid is responsive? Non-responsive bids rejectedWINNING BID WINNING BID
Which bid is best value for money? Other bids rejected
Any bidder can submit a bid with evidence of
qualifications
Bid is responsive? Non-responsive bids rejected
Check qualifications of highest ranked
bidder
Bid rejected and next best bid becomes
preferred bid
PRE-QUALIFICATION SYSTEM POST-QUALIFICATION SYSTEM
Rank the bids to find the one offering best value
for money Staff Qualifications Methodology Firm's Qualifications
Technical Score, S
T Financial Score, S FTIME-LINE FOR BIDDING
TIME-LINE FOR CONTRACT ADMINISTRATION
TIME-LINE FOR PAYMENTS Product Contract $ Purchaser Contractor Bid Preparation Final Payment Stage of work complete Inspection Progress Report Community Monitoring Group comments Payment Bid Evaluation Post-Qualification Work Program Insurance
Chapter 9: Selection Criteria
48
comparison criteria
The main criterion for comparison of bids (from amongst the responsive bids submitted by qualified bidders) should be the bid price.
In large or complex contracts, the lowest bid price does not necessarily represent the best value for money. Therefore, bid evaluation requires careful financial analysis, taking into consideration such matters as the expected timing of payments. If the contract is a re-measured contract, variations in the quantities could result in large changes in the final cost (see box).
Most contracts for local development are let on a lump-sum basis: The final price is the same as the winning bid price. The time needed for implementation is usually short. Therefore, the best value-for-money normally just means the lowest bid price.
The buyer may wish to take other factors into consideration in the evaluation of bids – for example, to favour locally based contractors or to ensure that local labour is employed in the contract. It is possible to devise “point scoring” schemes to take such matters into account and then to somehow combine the “non-price criteria” points with a score based on the price. However this is usually the least desirable means of incorporating these concerns. Better approaches include:
Example: The contract for a road construction includes a price per cubic metre for
excavating rock. The amount of rock excavation that will be needed is not known exactly so an estimate is included in the bill of quantities. The contractor will be paid for the actual quantity, re-measured at the end of the contract. A contractor with local knowledge spots that the estimated amount of rock excavation is much too low. He bids a low price for earthworks but a very high price for rock excavation. Therefore his bid price is lower than that of the other contractors, but he will make a large profit from the “extra” rock excavation.
Example: East West Sub-District has a policy to encourage women entrepreneurs.
Therefore, it decides to apply a price preference of 5% to bids submitted by firms owned by women. The lowest bid received for the school construction is from Mr. A whose bid price is $US 62,000. The lowest price submitted by a woman entrepreneur is from Mrs. B whose price is $US 64,000.
After applying the preference, the adjusted bid price for Mrs. B is $64,000 – ($64,000 x 5%) = $64,000–$3,200 = $60,800.
Therefore, Mrs. B is awarded the contract. The contract price is her original bid price, i.e. $64,000. BID EARTH 9,900 @ 1 9,900 ROCK 100 @ 100 10,000 19,900 PAYMENT EARTH 9,000 @ 1 9,000 ROCK 1,000 @ 100 100,000 109,000
49
Chapter 9: Selection Criteria
comparison criteria
The main criterion for comparison of bids (from amongst the responsive bids submitted by qualified bidders) should be the bid price.
In large or complex contracts, the lowest bid price does not necessarily represent the best value for money. Therefore, bid evaluation requires careful financial analysis, taking into consideration such matters as the expected timing of payments. If the contract is a re-measured contract, variations in the quantities could result in large changes in the final cost (see box).
Most contracts for local development are let on a lump-sum basis: The final price is the same as the winning bid price. The time needed for implementation is usually short. Therefore, the best value-for-money normally just means the lowest bid price.
The buyer may wish to take other factors into consideration in the evaluation of bids – for example, to favour locally based contractors or to ensure that local labour is employed in the contract. It is possible to devise “point scoring” schemes to take such matters into account and then to somehow combine the “non-price criteria” points with a score based on the price. However this is usually the least desirable means of incorporating these concerns. Better approaches include:
Example: The contract for a road construction includes a price per cubic metre for
excavating rock. The amount of rock excavation that will be needed is not known exactly so an estimate is included in the bill of quantities. The contractor will be paid for the actual quantity, re-measured at the end of the contract. A contractor with local knowledge spots that the estimated amount of rock excavation is much too low. He bids a low price for earthworks but a very high price for rock excavation. Therefore his bid price is lower than that of the other contractors, but he will make a large profit from the “extra” rock excavation.
Example: East West Sub-District has a policy to encourage women entrepreneurs.
Therefore, it decides to apply a price preference of 5% to bids submitted by firms owned by women. The lowest bid received for the school construction is from Mr. A whose bid price is $US 62,000. The lowest price submitted by a woman entrepreneur is from Mrs. B whose price is $US 64,000.
After applying the preference, the adjusted bid price for Mrs. B is $64,000 – ($64,000 x 5%) = $64,000–$3,200 = $60,800.
Therefore, Mrs. B is awarded the contract. The contract price is her original bid price, i.e. $64,000.
• Deal with matters such as local labour employment by making them conditions of the contract, e.g. the contractor will be obliged to employ a certain amount of local labour. All bidders then have to take this into account in their bids; or
• Apply an adjustment to the bid price to express a “preference” for firms meeting certain criteria. The winning bid is selected based on the lowest price after this adjustment is applied. Note that the adjustment is only for the purpose of bid evaluation. The final contract price will be the actual bid price submitted by the winning bidder (see box).
can a Bid be too Low?
The procurement guidelines of the major international development banks imply that, provided the bidder is judged to be qualified and its bid is judged to be responsive, after any necessary adjustments have been applied to the bid price, the lowest bid should be accepted. This appears to be common sense: All the bidders are offering the same thing, so the one with the lowest price represents the best value-for-money. Remember that the bidder is not under any obligation to
“compete fairly” or to make a profit from the contract: If a bidder offers to build a school, say, for USD 1, and does so in accordance with the drawings, specifications and contract conditions, this is nobody’s business but his/her own.
Nevertheless, it is very common to find procurement rules in force that allow, or require, bids below a certain “minimum price” to be rejected. The justification advanced for this is usually that if the price is too low, the contractor will be forced to cut corners in order to complete the contract and so quality will suffer. Two possible cases are that:
1. The bidder deliberately bids an unreasonably low price, expecting that he/she will be able to reduce the quality or quantity of works, from that described in the bid document, and so will still make a profit.
2. The bidder has simply made a mistake and under-estimated the cost of implementing the contract.
The Borrower shall award the contract, within the period of the validity of bids, to the bidder who meets the appropriate standards of capability and resources and whose bid has been determined (i) to be substantially responsive to the bidding documents and (ii) to offer the lowest evaluated cost.
Source: Guidelines for Procurement Under IBRD Loans and IDA Credits, World Bank, 2006.
Chapter 9: Selection Criteria
50
The bidder in “case 1” can only gain if construction supervision is weak. With good supervision, the contractor can only be paid if it constructs according to the design, specifications and conditions of the contract. Therefore, if the bidder expects strong supervision, it will not adopt this strategy.
The key expertise of a private sector construction contractor is, or should be, estimation: The contractor should be “more expert” at determining the appropriate price for a contract, than the consultant or official who calculates the price estimate on which the “minimum price” is based. So a price that is different from the estimate is not necessarily “wrong.” A minimum price can be used to facilitate
bid manipulation, particularly when the minimum price is concealed from the bidders (see box). Alternatively, if the minimum price is published, the effect may be that all the bidders bid the minimum price so it is impossible to pick a “winner.” For these reasons, arbitrary minimum prices, sometimes referred to as “bracketing,” should never be applied and are prohibited by the rules of the major development banks.
Despite these considerations, it is the view of this Guide that it is sometimes justified to reject a bid because it is too low. In the circumstances of limited capacity of bidders to estimate costs, and limited capacity of buyers to enforce contract conditions, excessively low contract prices can lead to poor results. Rejection of a bid as too low should be treated as an exceptional circumstance and should be done according to a careful process that
eliminates the possibility of bid manipulation. The recommended process is:
1. Estimated costs should be public. There is no reason to keep the estimated cost secret from the bidders – and in most countries, at least some of the bidders will always have a way to find out. It is better if everybody has the same information.
2. Bids should not be identified as too low based only on a comparison with the
estimated price. If all the bidders bid far below the estimate, it is probably the estimate that is wrong. Therefore, bids should only be identified as too low if it is (1) a certain percentage, say 10%, below the estimate, and (2) a certain percentage, say 5%, below the next lowest bid.
3. When a bid is identified as potentially too low, the bidder should be offered the opportunity to withdraw the bid without further penalty.
4. If the bidder chooses not to withdraw the bid, the bidder should be asked to provide a detailed calculation to show that its bid price is justified. This calculation should be checked by an independent engineer (not the engineer who made the original estimate).
How to manipulate a bid using a minimum price
Engineer A is responsible for estimating the cost of a bridge construction in North-South sub-district. Any bid that is lower than 90% of the estimated cost will automatically be rejected. Engineer