Relevant Materials
Chapter 2 EVPL Service Configuration using Station by Station Method (PORT-Shared)
2.2 Service Requirements
The headquarters of company H; H1 is located to NE A, while there are two branches which are H2 and H3 are located to NE B and NE D each. Both branches needed to have Ethernet communication with the headquarters and a bandwidth of 2Mbits/s is needed each.
2.3 Parameters Description
The network planning is shown below:
1. EVPL service between company H headquarters, H1 and branch H2;
2. EVPL service between company H headquarters, H1 and branch H3;
EVPL service between company H headquarters, H1 and branch H2:
− Use VC-12 timeslot number 4 of VC4 number 1 for SDH link between NE A and NE B(VC4-1:VC12:4).
− Use VC-12 timeslot number 4 of VC4 number 4(VC4-4:VC12:4) of N2EFS4 board for NE A and VC-12 timeslot number 1 of VC4 number 4 (VC4-4:VC12:1)of N2EFS4 board for NE B to add drop services.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
22
Parameters of external Ethernet ports on the Ethernet boards:
Parameters NE A NE B
Board N2EFS4 N2EFS4
Port PORT2 PORT1
Enabled/Disabled Enabled Enabled
Entry Detection Enabled Disabled
TAG Tag Aware Tag Aware
Default VLAN ID
Port Type PE PE
Parameters of internal ports on the Ethernet boards:
Parameters NE A NE B
Board N2EFS4 N2EFS4
Internal Port VCTRUNK2 VCTRUNK2
Bound Path VC4-4:VC12-4 VC4-4:VC12-1
Entry Detection Enabled Disabled
TAG Access Tag Aware
Default VLAN ID 100
Port Type PE PE
EPL Service Parameters (NE A station parameters):
Parameters EPL service of company H
Board N2EFS4
Service Type EPL
Service Direction Bidirectional
Source Port PORT2
Source Port C-VLAN(e.g.1,3-6)
100
Sink Port VCRTUNK2
Sink C-VLAN(e.g. 1,3-6) 100
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
23
EPL Service Parameters (NE B station parameters):
Parameters EPL service of company H
Board N2EFS4
Service Type EPL
Service Direction Bidirectional
Source Port PORT1
Source Port C-VLAN(e.g.1,3-6)
100
Sink Port VCRTUNK2
Sink C-VLAN(e.g. 1,3-6) 100
EVPL service between company H headquarters, H1 and branch H3:
− Use VC-12 timeslot number 1 of VC4 number 1 for SDH link between NE A and NE D(VC4-1:VC12:1).
− Use VC-12 timeslot number 5 of VC4 number 4(VC4-4:VC12:5) of N2EFS4 board for NE A and VC-12 timeslot number 1 of VC4 number 4 (VC4-4:VC12:1)of N2EFS4 board for NE D to add drop services.
Parameters of external Ethernet ports on the Ethernet boards:
Parameters NE A NE D
Board N2EFS4 N2EFS4
Port PORT2 PORT1
Enabled/Disabled Enabled Enabled
Entry Detection Enabled Disabled
TAG Tag Aware Tag Aware
Default VLAN ID
Port Type PE PE
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
24
Parameters of internal ports on the Ethernet boards:
Parameters NE A NE D
Board N2EFS4 N2EFS4
Internal Port VCTRUNK3 VCTRUNK1
Bound Path VC4-4:VC12-5 VC4-4:VC12-1
Entry Detection Enabled Disabled
TAG Access Tag Aware
Default VLAN ID 200
Port Type PE PE
EPL Service Parameters (NE A station parameters):
Parameters EPL service of company H
Board N2EFS4
Service Type EPL
Service Direction Bidirectional
Source Port PORT2
Source C-VLAN(e.g. 1,3-6) 200
Sink Port VCRTUNK3
Sink C-VLAN(e.g. 1,3-6) 200
EPL Service Parameters (NE D station parameters):
Parameters EPL service of company H
Board N2EFS4
Service Type EPL
Service Direction Bidirectional
Source Port PORT1
Port C-VLAN(e.g. 1,3-6) 200
Sink Port VCRTUNK3
Sink C-VLAN(e.g. 1,3-6) 200
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
25
2.4 Configuration Procedure
Configuration at NE A
Step 1 Configure Ethernet Port Parameters:
1、 Login to U2000 Main Topology.
2、 Right click on NE A to select “NE Explorer”.
3、Select N2EFS4 board from the Board List.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
26 4、From the Function Tree select “Configuration> Ethernet Interface Management> Ethernet Interface”.
5、select “External Port”.
6、The diagram below shows the 4 external port of the Ethernet board, all the ports are disabled by default. Port 2 needs to be enabled manually by double-click on the “Enabled/Disabled” tab for Port 2 and select “Enabled” as shown below.
After selecting, click the “Apply” button at the right bottom of the panel.
7、Select “Internal Port”. Change TAG Attributes of VCTRUNK1 and VCTRUNK2 to “Access” with VLAN ID of 100 and 200 respectively.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
27
Step 2 Configure Ethernet Line Service:
1 、At the Function Tree, select ”Configuration> Ethernet Service>
Ethernet Line Service”.
2、As shown on the diagram below, there is an existing EPL service which is created in Chapter 1. As for now, click “New” to create a new EVPL service between NE A and NE B.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
28 3、In the Create Ethernet Service configuration panel, select “PORT2”
as Source Port , “VCTRUNK2” as Sink Port and type in 100 for the Source VLAN and Sink VLAN as shown below.
4、At this moment, the “Bound Path” panel is empty. To configure a bound path to VCTRUNK2, click “Configure” button. At the “Bound Path”
panel, select VCTRUNK2 and click “>>” button. Click the “OK” button at the bottom right of the panel and return to the Create Ethernet Line configuration panel.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
29 5、Make sure the Ethernet Line configuration is configured correctly and click the “OK” button.
6、System prompt will show that the configuration is successful. Confirm and close the system prompt dialog box.
7、Finally the Ethernet Line service has been successfully created and the Ethernet service will be displayed in the Ethernet Line panel.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
30 8、After configuring the EVPL service between NE A and NE B, now we have to configure EVPL service between NE A and NE D with VLAN ID 200 by clicking “New” and select the options as shown below.
9、Click “Configure” , select VCTRUNK3 and bound VC12-5 by clicking
“>>” button. Click “OK” when done.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
31 10、Make sure the Ethernet Line configuration is configured correctly and click the “OK” button.
11、The Ethernet Line service has been successfully created and you will see 3 EPL Ethernet service in the Ethernet Line panel.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
32
Step 3 Configure SDH service:
1、To configure a SDH service is to create a cross-connection between the Ethernet board and Line board. Select “NE A” at the NE explorer.
2 、 At the “Function Tree”, select “Configuration> SDH Service Configuration”.
3、There is an existing SDH service from the configuration in Chapter 1, Click on the “Create” button to create another new SDH service.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
33 4、At the Create SDH service panel, select the correct information from the options for NE A. (In this case, VC4-4 is selected for N2EFS4 board because only VC4-4 can support for VC-12 level virtual concatenation).
After obtaining display as shown below, (The “Source Slot” and the
“Sink Slot” position have to be the same as the actual board slot number), click “OK”.
5、Then, configure SDH service for Ne D as shown below and click “OK”.
6、The SDH service created will be displayed as shown below.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
34 Configuration at NE B
Step 1 Configure Ethernet Port Parameters:
1、Login to U2000 Main Topology.
2、Right click on NE B to select “NE Explorer”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
35 3、Select N2EFS4 board from the Board List.
4、From the Function Tree select “Configuration> Ethernet Interface Management> Ethernet Interface.
5、select “External Port”.
6、The diagram below shows the 4 external port of the Ethernet board, all the ports are disabled by default. Port 1 need to be enabled manually by double-click on the “Enabled/Disabled” tab for Port 1 and select
“Enabled” as shown below.
After selecting, click the “Apply” button at the right bottom of the panel.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
36 7 、 Next, click on the “TAG Attributes” tab. At the “TAG” column, double-click and select “Access” for Port 1 follow by changing the
“Default VLAN ID” to 100. After done selecting, remember to click on the
“Apply” button at the bottom right of the panel to activate the changes.
8、Select “Internal Ports” and change the Entry Detection of VCTRUNK 2 to “Disabled”.
Step 2 Configure Ethernet Line Service:
1 、 At the Function Tree, select ”Configuration> Ethernet Service>
Ethernet Line Service”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
37 2、Click “New”, select “PORT 1” as the Source Port and “VCTRUNK2” as the sink port. Fill in “100” for both Source VLAN and Sink VLAN.
3、Click “Configure” and click on “>>” button to bound VC12-1 into VCTRUNK1 and click “OK”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
38 4、 After verifying the “Bound Path” at the Create Ethernet Service
configuration, click “OK”.
6、System prompt will show that the configuration is successful. Confirm and close the system prompt dialog box.
Step 3 Configure SDH service:
1、To configure a SDH service is to create a cross-connection between the Ethernet board and Line board. Select “NE B” at the NE explorer.
2 、 At the “Function Tree”, select “Configuration> SDH Service Configuration”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
39 3、 To create a new SDH service, click on the “Create” button.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
40 4、At the Create SDH service panel, select the correct information from the options for NE B. (In this case, VC4-4 is selected for N2EFS4 board because only VC4-4 can support for VC-12 level virtual concatenation).
After obtaining display as shown below, (The “Source Slot” and the
“Sink Slot” position have to be the same as the actual board slot number), click “OK”.
5、The SDH service has been successfully created and the SDH service is shown as below in the panel.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
41 Configuration at NE D
Step 1 Configure Ethernet Port Parameters:
1、Login to U2000 Main Topology.
2、Right click on NE D to select “NE Explorer”.
3、Select N2EFS4 board from the Board List.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
42 4、From the Function Tree select “Configuration> Ethernet Interface Management> Ethernet Interface”.
5、select “External Port”.
6、The diagram below shows the 4 external port of the Ethernet board, all the ports are disabled by default. Port 1 need to be enabled manually by double-click on the “Enabled/Disabled” tab for Port 1 and select
“Enabled” as shown below.
After selecting, click the “Apply” button at the right bottom of the panel.
7、Next, click on the “TAG Attributes” tab. At the Entry Detection column, change the Entry Detection of Port 1 to “Disabled”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
43 8、Select “Internal Ports” and change VCTRUNK3 Entry Detection to
“Disabled”.
Step 2 Configure Ethernet Line Service:
1 、 At the Function Tree, select ”Configuration> Ethernet Service>
Ethernet Line Service”.
2、Click “New”, select “PORT 1” as the Source Port and “VCTRUNK3” as the sink port. Fill in “200” for both Source VLAN and Sink VLAN.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
44 3、Click the “Configure” button and select VCTRUNK3. Click on “>>”
button to bound VC12-1 into VCTRUNK3 and click “OK”.
4、After verifying the “Bound Path” at the Create Ethernet Service configuration, click “OK”.
5、System prompt will show that the configuration is successful. Confirm and close the system prompt dialog box.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
45
Step 3 Configure SDH service:
1、To configure a SDH service is to create a cross-connection between the Ethernet board and Line board. Select “NE D” at the NE explorer.
2 、 At the “Function Tree”, select “Configuration> SDH Service Configuration”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
46 3、To create a new SDH service, click on the “Create” button.
4、At the Create SDH service panel, select the correct information from the options for NE D. (In this case, VC4-4 is selected for N2EFS4 board because only VC4-4 can support for VC-12 level virtual concatenation).
After obtaining display as shown below, (The “Source Slot” and the
“Sink Slot” position have to be the same as the actual board slot number), click “OK”.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
47 5、The SDH service has been successfully created and the SDH service is shown as below in the panel.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
48
2.5 Test Service Configuration
When all the configuration has been completed, the configurations have to be tested to make sure it works. First, you must make sure the Tag Attributes of the external port of NE A is configured as “Access” (PCs cannot ping each other when the ports are in Tag Aware mode as PCs do not have VLAN IDs.
Test Ethernet Service between NE A and NE B:
Two PCs are needed to test the connectivity, connect two PCs to port 2 of Ethernet board in NE A and port 1 of Ethernet board in NE B each.
PCs with IP addresses of 188.20.7.100 and 188.20.7.101 were used for the
“ping” test in this case. The results below show the EPL service is working normally.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
49
Test Ethernet Service between NE A and NE D:
Two PCs are needed to test the connectivity, connect two PCs to port 2 of Ethernet board in NE A and port 1 of Ethernet board in NE D each.
PCs with IP addresses of 188.20.7.100 and 188.20.7.101 were used for the
“ping” test in this case. The results below show the EPL service is working normally.
More
Learning
Resources:
http://learning.huawei.com/en
OHCNATS11 Ethernet Configuration Practice Guide
Confidential Information of Huawei. No Spreading without Permission
50