E NVIRONMENTAL MANAGEMENT PLAN
A. Pre-construction Phase
3.2. Downstream 1 Air Quality
3.2.16 Social Stratification A. Operational Phase
1) Significant Impact and Source of Significant Impact a) Environmental Parameter
Social Stratification.
EMP Matindok Gas Development Project III-61 b) Source of Impact
Operational activities of the LNG refinery, Special Port and supporting facilities.
2) Impact Criteria
• Emerging social stratification/social classes in the study areas caused by the great amount of newcomers who generally posses better education level, better skills, and much greater income than the local residents.
• A great difference regarding the lifestyle of the newcomers compared to the native residents.
3) Environmental Management Objective
To prevent and/or eliminate new social classes in the community.
4) Environmental Management Effort
• Various facilities such as education, health care, sport and religious affairs are not exclusively given to the employees, but are also provided for the local residents.
• Facilitating various activities together with local residents, such as social
gatherings, comemorating religious/national events and other social and religious activities.
5) Environmental Management Location
Villages surrounding project location in the region of Batui and Kintom District, Banggai Regency.
6) Environmental Management Period Once every 6 months during operation.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
c) Reporting : Office of Manpower Affairs of the Banggai Regency, Bappedal of Central Sulawesi Province, and the Ministry of Environmental Affairs.
EMP Matindok Gas Development Project III-62 3.2.17 Public Attitude and Perception
A. Pre-construction Phase
1) Significant Impact and Source of Significant Impact a) Environmental Parameter
Public attitude and perception.
b) Source of Impact
• Land acquisition and planting activity.
• Labor recruitment process.
2) Impact Criteria
• Negative public attitude and perception regarding the land acquisition and planting process.
• Negative public attitude and perception regarding the labor recruitment process.
3) Environmental Management Objective
To prevent and/or decrease negative attitudes and perception from the community.
4) Environmental Management Effort Land acquisition and planting activity
• Giving transparent information to the community regarding the land acquisition process.
• Listing the land ownership rights of the land to be acquired.
• Deciding the land value in accordance to the agreement made with the land owners along with the payment process.
• Coordinating with related institutions: Team-9 from BPN.
• The detailed process is shown in figure 3.2.
Labor recruitment process
• Providing transparent information on job opportunities to members of the surrounding community, including the amount of employees, qualifications (education and skill) and the selection process.
• Acceptance of unskilled labors from the local community as a priority considering the company’s requirements.
• Skilled labors are selected in accordance to the required skill qualifications.
• The unskilled labor selection process will be performed in coordination with local legal institutions (KUD for example) and for the skilled labor involving regional and national labor recruitment institutions.
EMP Matindok Gas Development Project III-63 5) Environmental Management Location
Villages surrounding project location in the region of Batui and Kintom District, Banggai Regency.
6) Environmental Management Period
• Twice: before and during the land acquisition process
• Twice: before and during labor recruitment.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
c) Reporting : Office of Land Affairs of the Banggai Regency, Bappedal of Central Sulawesi Province, and the Ministry of Environmental Affairs
B. Construction Phase
1) Significant Impact and Source of Significant Impact b) Environmental Parameter
Public attitude and perception.
b) Source of Impact
Construction of the LNG refinery and Special Port.
2) Impact Criteria
• Impacts of physical components: increase of dust concentration, noise, and transportation problems.
• Jealousy or conflicts between local residents and newcomers who generally have better job and business opportunities, and also higher income than the locals.
3) Environmental Management Objective
To prevent and/or decrease negative attitudes and perception from the community.
4) Environmental Management Effort
• Socializing every activity plan to the community.
• Overcome impacts of physical components: dust, gas emission (smoke), noise.
• Facilitating various social activities performed by local residents together with newcomers.
EMP Matindok Gas Development Project III-64 5) Environmental Management Location
Villages surrounding project location in the region of Batui and Kintom District, Banggai Regency.
6) Environmental Management Period
Once every 6 months during construction activities.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
c) Reporting : Office of Manpower Affairs of the Banggai Regency, Bappedal of Central Sulawesi Province, and the Ministry of Environmental Affairs.
C. Operational Phase
1) Significant Impact and Source of Significant Impact a) Environmental Parameter
Public attitude and perception.
b) Source of Impact
• Labor recruitment process.
• Operational activities of the LNG refinery, Special Port, and supporting facilities.
2) Impact Criteria Labor recruitment
Emerging conflicts or inharmonic social relationship in the community, especially between local residents/workers with workers from outside the area.
Refinery Operation, Special Port and Supporting Facilities
• Physical impacts of activities: increase in dust concentration, noise, and transportation problems.
• Jealousy or conflicts between locals and newcomers who generally posses better job and business opportunities, and also higher income.
• Formation of new social classes or stratifications in th region caused by the difference of education, skills, and income between local residents and the newcomers.
3) Environmental Management Objective
To prevent and/or decrease negative attitudes and perception from the community.
4) Environmental Management Effort Labor recruitment
EMP Matindok Gas Development Project III-65
• Providing transparent information on job opportunities to members of the surrounding community, including the amount of employees, qualifications (education and skill) and the selection process.
• Acceptance of unskilled labors from the local community as a priority considering the company’s requirements.
• Skilled labors are selected in accordance to the required skill qualifications.
• The unskilled labor selection process will be performed in coordination with local legal institutions (KUD for example) and for the skilled labor involving regional and national labor recruitment institutions.
Operational activities of LNG refinery and other supporting facilities.
• Socialization on activity plans to members of the local community.
• Facilitating social community activities such as community gathering, or other social or religious activities.
• Various facilities (education, sport, health care, religious events) are not exclusively given to the employees but are also provided for the surrounding community.
5) Environmental Management Location
Villages surrounding project location in the region of Batui and Kintom District, Banggai Regency.
6) Environmental Management Period Once every 6 months during operation.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
c) Reporting : Office of Manpower Affairs of the Banggai Regency, Bappedal of Central Sulawesi Province, and the Ministry of Environmental Affairs.
D. Post-operational Phase
1) Significant Impact and Source of Significant Impact a) Environmental Parameter
Public attitude and perception.
b) Source of Impact
Dismissing labor process.
2) Impact Criteria
The amount of complaints, protests, and negative judgements towards unemployment.
EMP Matindok Gas Development Project III-66 3) Environmental Management Objective
To prevent and/or decrease negative attitudes and perception from the community.
4) Environmental Management Effort
• Strengthening social communication network through socialization before dismissing labors.
• Help increase skills by conducting trainings in entrepreneurship or other skills.
5) Environmental Management Location
Villages surrounding project location in the region of Batui and Kintom District, Banggai Regency.
6) Environmental Management Period Before and during labor dismissing.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
c) Reporting : Office of Manpower Affairs of the Banggai Regency, Bappedal of Central Sulawesi Province, and the Ministry of Environmental Affairs.
3.2.12 Environmental Sanitation A. Construction Phase
1) Significant Impact and Source of Significant Impact a) Environmental Parameter
Environmental sanitation quality.
b) Source of Impact
Solid waste from construction activities, and domestic solid and liquid waste of the workers working in the LNG refinery, Special Port, and supporting facilities.
2) Impact Criteria
• Decrease of environmental esthetics.
• Minimum sanitation facilities (MCK).
• No appropriate location to collect solid waste from construction activities.
3) Environmental Management Objective
To maintain good condition of environmental sanitation on land and sea surrounding the LNG refinery and Special Port.
4) Environmental Management Effort
• Providing containers for solid waste from construction activities.
• Providing containers for solid domestic waste.
• Providing appropriate sanitation facilities (MCK).
EMP Matindok Gas Development Project III-67
• Giving information to the workers and local residents regarding healthy and clean lifestyle (PHBS).
5) Environmental Management Location
Around locations of the LNG refinery, Special Port and supporting facilities.
6) Environmental Management Period
During construction of the LNG refinery and Special Port.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
c) Reporting : Health Department of Banggai Regency, Bapedalda of Central Sulawesi Province, and the Ministry of Environmental Affairs
B. Post-operational Phase
1) Significant Impact and Source of Significant Impact a) Environmental Parameter
Environmental sanitation quality.
b) Source of Impact
Unloaded and equipment mobilization (refinery and Special Port).
2) Impact Criteria
• Location of unloaded activity becomes filthy and dirty.
• Emerging water filled holes on former refinery, Special Port, pipes, and other facilities.
3) Environmental Management Objective
To maintain good condition of environmental sanitation of various buildings and other facilities.
4) Environmental Management Effort
• Cleaning of former refinery wasteland, SpecialPort, pipes, and other facilities.
• Rearrangment wasteland of former building sites and other facilities.
5) Environmental Management Location
In the wreckage locations of the refinery, Special Port, and supporting facilities.
6) Environmental Management Period
Once after wrecking and equipment demobilization.
7) Environmental Management Institution
a) Implementation: PT. Donggi Senoro LNG (PT. DSLNG) b) Supervision : Bappedal of Banggai Regency
EMP Matindok Gas Development Project III-68 c) Reporting : Health Department of Banggai Regency, Bapedalda of Central
Sulawesi Province, and the Ministry of Environmental Affairs