The findings of this study cannot be generalised statistically to all of Ghana because it is geographically constrained, with respondents only drawn from a purposive sampling of construction organisations in the Greater Accra Region. Furthermore, the study did not distinguish between local and foreign contractors.

As Adams (2008) demonstrated, perceptions of risks between the two groups tend to vary. Nevertheless, as asserted by Chileshe (2004), the findings represent a snapshot of the perceptions of construction professionals regarding the likelihood and the degree of impact of the identified risks on construction projects. The second limitation pertains to the usage of survey data based on self-reported opinions of professionals within organisations. Such data may not provide reliable estimates of the likelihood of occurrence and severity of impact of risks. However, there is consistency between the quantitative and qualitative parts (such as the literature review) of this study. Moreover, the results do appear to be consistent with previous research examining the likelihood of occurrence and severity of impact of risk factors on construction projects.

be the least important. These results also provide some insights into the Ghanaian contractors’ understanding of the risk of financial failure. Given that no distinction was provided between ‘contractor failure’ and ‘client failure’ within the catalogue of risks, as in previous studies classifying financial failure, the lower ranking (8th) of this risk by contractors compared with either clients or consultants suggests the contractor sub-group could have made incorrect assumptions. Kartam and Kartam (2001) suggest that this risk is linked to economic conditions, and the importance attached by contractors to it would be dependent on the economic climate at the given time. Thus, during recessionary periods, contractors would be expected to desire a risk-sharing approach.

Magnitude of the impact of quality and performance Quality and performance control was ranked fifth based on the overall sample score; it was ranked fourth and fifth by clients and consultants, respectively, whereas contractors ranked it tenth. This finding is very notable given that contractors have a major influence on the end product during the construction process. However, as observed by Agyakwa-Baah (2009), specifications from clients are not always adequate, and contractors seek to make profit by compromising and using low-quality materials. Corruption is another contributor to the lack of control over quality and performance (Agyakwa-Baah, 2009). One of the mitigating measures for this risk is the adoption of effective quality control procedures.

Analysis of the results revealed that there was complete agreement among the three samples (clients, contractors and consultants) regarding the ranking of the financial risk factor ‘delay in payment’. There was also complete agreement between the clients and consultants on the ranking of the economic risk factor ‘inflation’. Nevertheless, some differences in the perception of risk occurrence were found to exist in relation to ‘construction methods’, ‘inflation’, ‘weather conditions’, ‘ground conditions and contaminant conditions’, and ‘poor communication amongst project team’. Whereas the clients and contractors did not regard some of these risk factors as crucial, the contractors ranked ‘construction methods’, ‘weather conditions’ and ‘ground conditions and contaminant conditions’ moderately higher than did the clients and consultants. In contrast, poor communication amongst project team’ and ‘inflation’ were ranked higher by

‘consultants’. Several implications emerge that affect the implementation of mitigation measures targeting the consequences of the risks affecting construction projects in the Ghanaian construction industry. Three can be singled out as having major implications.

Economic implications

The issue of economic risk factors is of paramount importance given that the construction industry is facing a number of challenges that the present economic crisis has exacerbated. Moreover, price fluctuations and high CONCLUSIONS

This paper has presented the perceptions of contractors, clients and consultants within medium and large Ghanaian construction-related organisations regarding the likelihood of occurrence and severity of impact of construction project risk factors. The risk factors identified from an extensive literature review have been analysed using analysis of variance in order to identify differences in perception among the respondent sub-groups (contractors, clients and consultants), and descriptive statistics such as mean scores and standard deviations were used to rank the factors.

It can also be concluded that the ranking and importance of different factors vary between developed and developing economies. For example, a study by Odeyinka et al. (2008) limited to contractors in the UK ranked ‘changes to initial design’ first in both frequency and severity of impact, whereas ‘delay in payment from the client’ is the major risk factor in developing economies. The different risk variable rankings between developing countries (as identified in this study) and developed countries (e.g., Odeyinka et al., 2008) illustrates how the country context sheds new theoretical light on the interpretation and importance of risk variables.

Relationship implications

In terms of the relationship risk factor, it is worth noting that effective communication is vital to project success and must be established early in the project.

Another risk factor is that of resources. In Ghana, finding labour for a project is not a problem, but factories and equipment are a major problem for most construction firms, especially local firms. One major challenge mentioned by professionals who work for local firms was that local construction organisations are gradually dying out because foreign firms carry out almost all the projects, leaving very few projects for local firms.

ACKNOWLEDGEMENTS

The material for this paper was extracted from an MSc dissertation in project management on ‘Implementation of risk assessment and management practices (RAMP) in medium and large Ghanaian Construction Organisations’ on which the authors carried out further analysis.

inflation have contributed to considerable instability in the industry. It can also be argued that financial risks are vital to organisations and the economy as a whole.

Freezes on capital, delays in payment, bankruptcy of stakeholders or financial failure all create difficult situations for firms carrying out projects. This situation calls for movement towards bespoke contracts, which might introduce contract flaws, as opposed to the over-reliance on standard contracts. This change would not only enable contractors to allocate risk to the client by ensuring that interest is paid on delayed payments, but it could also incorporate better payment terms.

Government implications

The political risk factor was ranked fourth by the three groups in terms of the severity of impact. Change of government and change in government policy are ever-present risk factors in view of the frequency of elections (every four years in Ghana). Therefore, the inference to be drawn is that during that period (election years), most government projects and pending payments are put on hold until the next ruling party comes into office.

This situation creates problems for the industry because monies are locked up and, therefore, organisations are not able to take on other private jobs.

Ahmed, A., Kayis, B. and Amornsawadwatana, S. (2007).

A review of techniques for risk management in project.

Benchmarking: An International Journal, 14(1): 22–36.

Aje, O.I., Odusami, K.T. and Ogunsemi, D.R. (2009). The impact of contractors management capability on cost and time performance of construction projects in Nigeria. Journal of Financial Management of Property and Construction, 14(1): 171–187.

Akintoye, A.S. and MacLeod, M.J. (1997). Risk analysis and management in construction. International Journal of Project Management, 15(1): 31–38.

Akoi-Gyebi Adjei, E. (2009). Motivational Strategies to Improve Productivity in the Construction Industry in Ghana. MSc dissertation. Kwame Nkrumah University of Science and Technology, Kumasi, Ghana.

Assibey-Mensah, G.O. (2009). Ghana’s construction industry and global competition: A research note. Journal of Black Studies, 39(6): 974–989.

Ayirebi-Dansoh, K. (2005). Strategic planning practice of construction firms in Ghana. Construction Management and Economics, 23(2): 148–163.

Badu, Y.A. and Amagoh, F.D.K.N. (2002). An empirical analysis of net interest cost, the probability of default and the credit risk premium: A case study using the Commonwealth of Virginia. Managerial Finance, 28(4): 31–48.

Bednar, M.K. and Westphal, J.D. (2006). Surveying the corporate elite: Theoretical and practical guidance on improving response rates in top management survey questionnaires.

In David J. Ketchen and Donald D. Bergh (eds.). Research Methodology in Strategy and Management. Volume 3. San Diego: Emerald Group Publishing Limited, 37–55.

REFERENCES

Adams, F.K. (2008). Risk perception and Bayesian analysis of international construction contract risks: The case of payment delays in a developing economy. International Journal of Project Management, 26(2): 138–148.

Addo-Abedi, F.Y. (1999). Sustainable development of the local contracting industry in a developing country. Proceedings:

The 2nd International Conference on Construction Industry Development and 1st Conference of CIB TG 29 on Construction in Developing Countries. Ritterdam, Netherlands, 27–29 October 1999.

Agyakwa-Baah, A. (2009). A Study into Risk Assessment and Management Practices within Ghanaian Medium and Large Construction Organisations. MSc project dissertation.

Sheffield Hallam University, United Kingdom.

_____. (2007). Stakeholders’ Perceptions of the Causes of Delay on Construction Projects. BSc dissertation. Kwame Nkrumah University of Science and Technology, Kumasi, Ghana.

Agyakwa-Baah, A., Chileshe, N. and Stephenson, P. (2010).

A risk assessment and management framework to support project delivery. In Pantovakis, J.P. (ed). Proceedings: The 5th Scientific Conference on Project Management (PM-05), Advancing Project Management for the 21st Century

“Concepts, Tools & Techniques for Managing Successful Projects”. Heraklion, Crete, Greece, 29–31 May. Athens:

Centre for Construction Innovation, National Technical University of Athens, 52–59.

Ahadzie, D.K., Proverbs, D.G. and Olomolaiye, P.O. (2008).

Critical success criteria for mass house building projects in developing countries. International Journal of Project Management, 26(6): 675–687.

Dulaimi, M.F., Ling, F.Y.Y., Ofori, G. and De Silva. (2002).

Enhancing integration and innovation in construction.

Building Research & Information, 30(4): 237–247.

Dunn, K.A. and Huss, H.F. (2004). Mail survey reliability through follow-up mailings: the case of auditing changes.

Managerial Auditing Journal, 19(8): 1048–1054.

Dommeyer, C.J. and Moriarty, E. (2000). Comparing two forms of an e-mail survey: Embedded vs. Attached. International Journal of Market Research, 42(1): 39–50.

Edwards, P.J. and Bowen, P.A. (1998). Risk and risk management in construction: a review and directions for research.

Engineering, Construction and Architectural Management, 5(4): 339–349.

Enshassi, A., Al-Najjar, J. and Kumaraswamy, M. (2009). Delays and cost overruns in the construction projects in the Gaza strip. Journal of Financial Management of Property and Construction, 14(2): 126–151.

Field, A. (2000). Discovering Statistics using SPSS for Windows.

London: SAGE Publications.

Frimpong, Y., Oluwoye, J. and Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study.

International Journal of Project Management, 21(5): 321–

326.

Garland, R. (1991). The mid-point on a rating scale: Is it desirable? Research Note 3. Marketing Bulletin, 2: 66–70.

Gill, J. and Johnson, P. (1991). Research Methods for Managers.

London: Paul Chapman Publishing Ltd.

Gunderman, R.B. and Applegate, K.E. (2005). Managing risk:

Threat or opportunity? American Roentgen Ray Society, 185(1): 43–45.

Berko, P. (2007). Project Cost Overrun in the Road Construction Industry in Ghana. Unpublished M.Sc. Project Management dissertation. Sheffield Hallam University, Sheffield, United Kingdom.

Bing, L., Akintoye, A. Edwards, P.J. and Hardcastle, C. (2005).

The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1):

25–35.

Chileshe, N. (2004). The Application of TQM within Small and Medium Sized Construction Related Organisations. PhD dissertation. Sheffield Hallam University, Sheffield, United Kingdom.

Dada, J.O. and Jagboro, G.O. (2007). An evaluation of risk factors impacting construction cash flow forecast. Journal of Financial Management of Property and Construction, 12(1): 37–44.

De la Cruz, M.P., del Cano, A. and de la Cruz, E. (2006).

Downside Risks in Construction Projects Developed by the Civil Service: The Case of Spain. Journal of Construction Engineering and Management, 132(8): 844–852.

Denini, F. (2009). Delays on large construction projects in Libya.

In Abu Bakar (ed). Proceedings: The 3rd International Conference on Built Environment in Development Countries (Sustainable Built Environment: Tomorrow’s Agenda Today).

Universiti Sains Malaysia, Penang, 2–3 December 2009.

Penang: School of Housing, Building and Planning, Universiti Sains Malaysia, 819–835.

Diallo, A. and Thuillier, D. (2005). The success of International Development Projects, Trust and Communication: An African Perspective. International Journal of Project Management, 23(3): 237–252.

Lai, I.K.W. and Lam, F.K.S. (2010). Perception of various performance criteria by stakeholders in the construction sector in Hong Kong. Construction Management and Economics, 28(4): 377–391.

Lalitan, D.A.A. and Loanata, V.R. (2010). Owner and contractor perceptions towards factors causing delays in structural and finishing works. Civil Engineering Dimension, 12(1): 8–17.

Lester, A. (2007). Project Management, Planning and Control.

5th Edition. Maryland Heights: Elsevier Ltd.

Lowe, J.G. (1987). Cash flow and the construction client: A theoretical approach. In Lansley, P.R. and Harlow, P.A.

(eds). Managing Construction Worldwide. Volume 1.

London: E&FN Spon, 327–336.

Manelele, I. and Muya, M. (2008). Risk identification on community-based construction projects in Zambia. Journal of Construction, 12(1): 2–7.

Mills, A. (2001). A systematic approach to risk management for construction. Structural Survey, 19(5): 245–252.

Ministry of Works and Housing. (1988). Articles of Agreement and Conditions of Contract for Building Works-Ghana (Pink Form). 5th Edition. Accra: Assembly Press.

Odeyinka, H.A., Lowe, J. and Kaka, A. (2008). An evaluation of risk factors impacting construction cash flow forecast.

Journal of Financial Management of Property and Construction, 13(1): 5–17.

Ofori, G. (1994). Construction technology development: Role of an appropriate policy. Engineering, Construction and Architectural Management, 1(2): 147–168.

Oladapo, A.A. (2007). A quantitative assessment of the cost and time impact of variation orders on construction Harinarain, N. and Othman, A.A.E. (2007). A framework for

identifying, quantifying and classifying risk with the principal building agreement in South African. Proceedings: The 2nd Built Environment Conference. Port Elizabeth, South Africa, 17–19 June 2007. Johannesburg: Association of Schools of Construction of Southern Africa, 138–151.

Harinarain, N., Othman, A.A.E. and Pearl, R.G. (2008).

Investigating the contractor’s risk sources associated with the Principal Building Agreement in South African. Proceedings:

The 5th Postgraduate Conference. Stellenbosch, South Africa, 16–18 March 2008. Pretoria: Construction Industry Development Board, 146–157.

Hassanein, AMR A.G. and Afify, Halaa M.F. (2007). Risk management practices of contractors: A case study of power station projects in Egypt. Journal of Financial Management of Property and Construction, 12(3): 164–179.

Hassim, S., Jaafar, S.M. and Abu Hasan Sazalli, S.A. (2009). The contractor perception towers industrialised building risk in construction projects in Malaysia. American Journal of Applied Sciences, 6(5): 937–942.

Hlaing, N.N., Singh, D., Tiong, R.L.K. and Ehrlich, M. (2008).

Perceptions of Singapore construction contractors on construction risk identification. Journal of Financial Management of Property and Construction, 13(2): 85–95.

Jackson, A. and DeCormier, R. (1999). E-mail survey response rates: targeting increases response. Marketing Intelligence

& Planning, 17(3): 135–139.

Kartam, N.A. and Kartam, S.A. (2001). Risk and its management in the Kuwaiti construction industry: A contractors’

perspective. International Journal of Project Management, 19(6): 325–335.

Tah, J.H.M. and Carr, V. (2000). Information modelling for a construction project risk management system. Engineering, Construction and Architectural Management and Economics, 7(2): 107–119.

Tchankova, L. (2002). Risk identification: Basic stage in risk management. Environmental Management and Health, 13(3): 290–297.

Tuuli, M.M., Baiden, B.K. and Badu, E. (2007). Assessment and enforcement of liquidated damages in construction contracts in Ghana. Structural Survey, 25(3/4): 204–219.

Wang S., Dulaimi, M. and Aguira, M. (2004). Risk Management Framework for Construction Projects in Developing Countries. Construction Management and Economics, 22(3): 237–252.

Wang, J. and Yuan, H. (2011). Factors affecting contractors’

risk attitudes in construction projects: Case study from China. International Journal of Project Management, 29(2):

209–219.

World Bank. (2003). Country Procurement Assessment Report:

Ghana. Report No. 29055. Volume 2. Washington, DC:

World Bank.

projects. Journal of Engineering Design and Technology, 5(1): 35–48.

Othman, A.A.E. and Harinarain, N. (2009). Managing risk associated with the JBCC (Principal Building Agreement) from the South African contractor’s perspective. Acta Structilia, 16(1): 83–119.

Othman, A.A., Torrance, J.V. and Ab. Hamid, M. (2006). Factors influencing the construction time of civil engineering projects in Malaysia. Engineering, Construction and Architectural Management, 13(5): 481–501.

Perera, B.A.KS., Dhanasinghe, I. and Rameezdeen, R. (2009). Risk management in road construction: The Case of Sri Lanka.

International Journal of Strategic Property Management, 13(2): 87–102.

Rameezdeen, R. and Ramachandra, T. (2008). Construction linkages in a developing economy the case of Sri Lanka.

Construction Management and Economics, 26(5): 499–506.

Salifu, Z., Osei, K.A. and Adjasi, C.K.D. (2007). Foreign exchange risk exposure of listed companies in Ghana. The Journal of Risk Finance, 8(4): 380–393.

Santoso, D.S., Ogunlana, S.O. and Minato, T. (2003). Assessment of risks in high rise building construction in Jakarta.

Engineering, Construction and Architectural Management, 10(1): 43–55.