Regional Projects
8.3 Cost Allocation Options
8.3.3 Summary of Cost Allocation Options
Exhibit 8-3 summarizes cost allocation options potentially of value in a variety of situations. It does not prescribe specific solutions, but provides a basis for the involved parties to evaluate potential options. The first section of Exhibit 8-3 addresses the allocation of costs related to potential upgrades or rehabilitation projects related to existing emergency interconnection facilities, and the second section addresses new facilities associated with the WSIRRA.
In conclusion, the representatives of local and state governments have many options, and the widely varying
circumstances of each situation suggest that costs will need to be recovered in more than one way. Some of the key points to be considered include:
• The costs of new facilities can be allocated using a variety of measures; these measures can be categorized as reflecting the need of each system for the improvements in question or the ability of the system to pay for the needed improvements.
• The relative need of each QWS as reflected by the Critical Scenario Deficits estimated as part of this study may represent the most equitable single approach for cost allocation.
• Combinations of approaches could be utilized, particularly if some portion of the improvements in question were determined to provide regional benefit.
Exhibit 8-4 reflects a simplified decision tool demonstrating a series of steps that could be used in evaluating the allocation of costs among QWSs for interconnection projects in the future. The decision tree can be easily modified to incorporate additional allocation or cost factors. Total costs are first segmented into those related to existing facilities (generally, operating, maintenance, and repair costs (OMR)), and those related to new facilities (capital costs as well as OMR). An allowance is then made for potential third party support of major projects to indicate that financial support of particular projects by state or other agencies would be removed prior to the allocation of costs among the participating QWSs. This allowance for third party financial support merely acknowledges the potential for partial funding of projects deemed to serve a particularly important interest beyond that of the QWSs involved. The net costs of a project can then be allocated as a function of projected
8.0—MODEL AGREEMENTS AND SUMMARY OF INNOVATIVE FINANCING BEST PRACTICES
water supply deficits or some other measure or mix of measures. The magnitude of the cost burden to each QWS could be estimated, and an example evaluation metric of $1.00 per customer per month is shown to illustrate one potential view of the possible benefit of alternative funding mechanisms for especially large projects.
8.0—MODEL AGREEMENTS AND SUMMARY OF INNOVATIVE FINANCING BEST PRACTICES
EXHIBIT 8-3
Cost Allocation Options
Type of Costs Potential Allocation Approach Relative Advantages Relative Disadvantages Comments
Costs of producing / providing water from existing emergency interconnection facilities
Volume of water used through the connection Usage is often seen as being related to costs;
volumetric cost allocations are common Interconnection usage is not always metered; capacity costs are not always well recovered through volumetric charges; use of an interconnection for peaking purposes can be particularly troublesome if volumetric charges are not well crafted
Not likely to be the best option in cases except where the interconnection is a primary source of supply for one QWS and an existing agreement is in place Potential capacity use as measured by
connection / meter size Capacity is clearly related to the costs of providing water for emergency usage Capacity may not reflect burden of actual usage patterns as some interconnections are used for more than emergency water; cost- based capacity allocations may be significantly higher than many utilities are accustomed to paying for emergency capacity
Not likely to be the best option if any periodic use is associated with the interconnection
New cost-based combination of capacity and volumetric charges
Provides equitable means of recovering costs of providing capacity as well as costs of water production
Negotiation, calculation, and implementation costs of transition to new system
New, cost-based rate structures following cost-of- service principles as outlined in Principles of Water
Rates, Fees, and Charges published by AWWA help to achieve equity in cost recovery, but transaction and implementation costs may be high
Any method currently used by the parties Already accepted and in use; transaction /
negotiation costs are minimized May not fit a common standard for cost allocations May be the best option for recovery of costs from existing facilities in most cases Incremental costs of new facilities
associated with WSIRRA Volume of water used through the interconnection Usage is often seen as being related to costs; volumetric cost allocations are common Interconnection usage is not always metered; capacity costs are not always well recovered through volumetric charges; use of an interconnection for peaking purposes can be particularly troublesome if volumetric charges are not well crafted; may not reflect cost drivers for WSIRRA improvements
Not likely to be the best option in many cases
Potential capacity use as measured by interconnection / meter size
Capacity is clearly related to the costs of providing water for emergency usage
Capacity may not reflect burden of actual usage patterns as some interconnections are used for more than emergency water; cost- based capacity allocations may be significantly higher than many utilities are accustomed to paying for emergency capacity; may not reflect drivers for WSIRRA improvements
Not likely to be the best option if any periodic use is associated with the interconnection
New cost-based combination of capacity and volumetric charges
Provides equitable means of recovering costs of providing capacity as well as costs of water production
Negotiation, calculation, and implementation costs of transition to new system
New, cost-based rate structures following cost-of- service principles as outlined in Principles of Water
Rates, Fees, and Charges published by AWWA help to
achieve equity in cost recovery; cost-based rate structures may be especially appropriate in cases of significant new investment
Any method currently used by the parties Already accepted and in use; transaction / negotiation costs are minimized
Current cost allocation methods did not anticipate WSIRRA improvements and likely would not equitably allocate these costs
Not likely to be the best option in cases except where new WSIRRA-related investment is de minimis Population served by the QWS May reflect system size; could be said to reflect
system need in some cases; could reflect system funding ability in some cases
Does not account for non-residential usage; does not reflect capacity or volumetric utilization of the interconnection; potentially seen as punishing prepared systems; does not reflect cost drivers for WSIRRA improvements
Subject to the stated disadvantages, population served by the QWS could be a potential method of allocation for a portion of the costs of regional interconnection projects if such projects were determined to be of region-wide benefit
Population served by the interconnection May reflect capacity associated with the
interconnection; could reflect need associated with the interconnection; could reflect system funding ability in some cases
Does not account for non-residential usage; does not reflect capacity or volumetric utilization; potentially seen as punishing prepared QWSs; does not reflect cost drivers for WSIRRA improvements
8.0—MODEL AGREEMENTS AND SUMMARY OF INNOVATIVE FINANCING BEST PRACTICES
EXHIBIT 8-3
Cost Allocation Options
Type of Costs Potential Allocation Approach Relative Advantages Relative Disadvantages Comments
Incremental costs of new facilities associated with WSIRRA
(Continued)
Total number of customers May reflect system size; could be said to reflect system need in some cases; could reflect system funding ability in some cases
Does not reflect capacity or volumetric utilization of
interconnection; potentially seen as punishing prepared QWSs; does not reflect cost drivers for WSIRRA improvements
Subject to the stated disadvantages, total number of customers could be a potential method of allocation for a portion of the costs of regional interconnection projects if such projects were determined to be of region-wide benefit
Total annual system usage Reflects system size; captures non-residential usage; could be said to reflect system need in some cases; could reflect system funding ability in some cases
Does not reflect capacity or volumetric utilization of
interconnection; potentially seen as punishing prepared QWSs; does not reflect drivers for WSIRRA improvements
Subject to the stated disadvantages, total annual QWS usage could be a potential method of allocation for a portion of the costs of regional interconnection projects if such projects were determined to be of region-wide benefit
Maximum monthly usage Reflects system size; reflects seasonal demands;
could be said to reflect system need in some cases Does not reflect capacity or volumetric utilization of interconnection; potentially seen as punishing prepared QWSs; does not reflect drivers for WSIRRA improvements
Not likely to be the best option in many cases
Relative estimated critical supply deficits Reflects relative need as estimated in this study; could be adjusted to reflect multiple points of connection if appropriate
May result in allocation of costs that is beyond the ability of some
QWSs to bear without significant revenue enhancement Likely the best single option for allocation of these costs in many cases Relative ratios of critical deficits to Long
Range Reliability Targets
Reflects relative need as estimated in this study; could be seen as recognizing planning and
investment by comparatively prepared QWSs; could be adjusted to reflect multiple points of
interconnection if appropriate
May result in allocation of costs that is beyond the ability of some QWSs to bear without significant revenue enhancement; does not reflect drivers for WSIRRA improvements
Potentially of use in combination with other allocation approaches
Annual revenues Reflects system size and financial capacity; could minimize cost burden on smaller, less financially strong QWSs
Does not reflect capacity or volumetric utilization of
interconnection; potentially seen as punishing prepared QWSs; does not reflect drivers for WSIRRA improvements
Not likely to be the best option in many cases
Cash balances Reflects system size and financial capacity; could minimize cost burden on smaller, less financially strong QWSs
Does not reflect capacity or volumetric utilization of
interconnection; potentially seen as punishing prepared QWSs; does not reflect drivers for WSIRRA improvements
Not likely to be the best option in many cases
Credit rating Reflects system size and financial capacity; could
minimize cost burden on smaller, less financially strong QWSs
Does not reflect capacity or volumetric utilization of
interconnection; potentially seen as punishing prepared QWSs; does not reflect drivers for WSIRRA improvements
Not likely to be the best option in many cases
Any form of regional allocation beyond the
specific QWSs in question Could reflect a region-wide benefit of increasing interconnectedness among QWSs Does not reflect capacity or volumetric utilization of interconnection; potentially seen as punishing prepared QWSs; does not reflect drivers for WSIRRA improvements; may require legislative or other authority to impose costs on QWSs not participating in specific improvements
May be worth considering for a portion of costs,
perhaps administrative and program management costs if a larger program than is currently envisioned were to be adopted
8.0—MODEL AGREEMENTS AND SUMMARY OF INNOVATIVE FINANCING BEST PRACTICES
EXHIBIT 8-4