• No results found

UNIT-3 PM.pdf

N/A
N/A
Protected

Academic year: 2020

Share "UNIT-3 PM.pdf"

Copied!
26
0
0

Loading.... (view fulltext now)

Full text

(1)

UNIT-3 PROJECT ANALYSIS

ILA MEHTA

Assistant Professor

(2)

1.1.1. Machinery &

Equipment

 Machinery & Equipment requirement depends upon the

production technology and plant capacity of the proposed project.

 Steps to select machinery and equipment for a project:

1. Estimate levels of production over time 2. Define various machining and operations 3. Calculate machine hours required for each type of

operations

(3)

 Types of Machinery and equipment:

1. Plant equipment

2. Mechanical equipment 3. Electrical equipment 4. Instruments

5. Controls and internal transportation system 6. Spare parts & tools

 Things to be considered while selecting machinery and equipment:

1. Availability of power to rum machines 2. Transporting heavy equipment

3. Ease of use

4. Import policies of Govt. if the machines are to be imported from a foreign country

 Factored affecting the procurement of machinery:

1. Quality of machinery

2. Level of technical sophistication 3. Reputation of supplier

4. Expected delivery schedule 5. Payment terms

(4)

Choice of Machinery

(with the example of an excavation project)

Size of the job: Larger volumes of excavation will require larger

excavators, or smaller excavators in greater number.

Activity time constraints: Shortage of time for excavation may force

contractors to increase the size or numbers of equipment for activities related to excavation.

Availability of equipment: Productivity of excavation activities will

diminish if the equipment used to perform them is available but not the most adequate.

Cost of transportation of equipment: This cost depends on the size of the

job, the distance of transportation, and the means of transportation.

Type of excavation: Principal types of excavation in building projects are

(5)

Soil characteristics: The type and condition of the soil is

important when choosing the most adequate equipment since each piece of equipment has different outputs for different soils. Moreover, one excavation pit could have different soils at different stratums.

Geometric characteristics of elements to be

excavated: Functional characteristics of different types of equipment makes such considerations necessary.

Space constraints: The performance of equipment is

influenced by the spatial limitations for the movement of excavators.

Characteristics of haul units: The size of an excavator will

depend on the haul units if there is a constraint on the size and/or number of these units.

Location of dumping areas: The distance between the

construction site and dumping areas could be relevant not only for selecting the type and number of haulers, but also the type of excavators.

Weather and temperature: Rain, snow and severe

(6)

1.1.2. Choice of Technology

 WHY?

For manufacturing a product, more than one process/technology may be available.

For example, steel can be manufactured either by the

Bessemer process or by the open-hearth process.

Cement can be manufactured either by the wet process

(7)

Selection of Process/

Technology

 Depends on quality and quantity of product.

 If quantity increases then, mass production technique

with relevant technology is required.

 Quality depends upon what use it is meant for. Eg:

(a) Any pharmaceutical grade product should have high quality and hence demands sophisticated

technology.

(8)

 For technology, latest technology should be chosen

provided it has no constraints & proves successful for large scale production at factory.

 Any technology protected by patent rights can be

purchased outright if the cost of acquisition is affordable.

 The term ‘appropriate technology’ is the one

(9)

Appropriate Technology

Appropriate technology can be identified by asking the following questions:

1. Does the technology makes use of the locally available

raw material ?

2. Can the technology by implemented and maintained

by the locally available man power ?

3. Is the technology in tune with the local social and

cultural conditions ?

(10)

Approaches to project

implementation

Top-down approach

 The top-down approach to defining project tasks involves starting

with the project goal or final deliverable, and breaking it down into smaller planning chunks. We call them work packages. Each of these work packages or “chunks” is further refined into greater detail, and then work items are assigned to team members.

 The top-down approach works well when there’s clear insight into

the details of a project, and the leading project manager has a big-picture of how the project contributes to the organization.

 The benefit of top-down is that the major tasks are quickly

(11)

The bottom-up approach

• The bottom-up approach to answering “what are the tasks” relies on project team members identifying the tasks and then organizing them into specific groups or work packages.

• If you applied a bottom-up approach to identify tasks for the software upgrade mentioned above, the entire project team would brainstorm all the tasks required to correctly upgrade the system. There’s also a greater chance that a team member will identify an operating system conflict or at least include a step to test that feature than in top-down planning. Ideas get flowing and tasks can be written top-down on sticky note pads or index cards. All these tasks can then be logically grouped into categories that make up each work package.

• The bottom-up approach results in a more detailed schedule, but it’s also a time-consuming approach compared with the top-down task planning approach. The schedule you create is based on direct input from experts who will be implementing the project; it’s also a useful technique to build teamwork.

(12)

Project implementation plan

includes:

 The following methods may be used to answer the

above questions:

 Gantt chart

 Critical Path Method (CPM) or Net work analysis

 Project Evaluation and Review Techniques (PERT)

(13)

What is a GANTT Chart?

 The Gantt chart is also referred to as the progress

chart.

 It is a chart showing the timing of project activities

using horizontal bars.

 It is one of the techniques of project scheduling,

(14)

How to determine a GANTT

chart

 Determine the parts or implementation phases of the

project and the sequence in which the associated activities shall be carried out

 Then estimate the amount of time required for each

activity

 List the activities that can be carried out at the same

(15)

How to construct a GANTT

chart

 Time represented on the horizontal axis, and activities on

the vertical axis.

 Bars are entered to indicate the time period allocated for

(16)
(17)

1.2. Environmental Aspects

 Often, the basic flaw in project planning and design

is the complete neglect or minimal consideration of environmental and social costs and dependence only on economic analysis for project preparation and investment.

 A failure to understand and internalize adverse or

(18)

 Environment management reduces the unforeseen

obstacles and bottlenecks that may otherwise

hamper the delivery of project objectives while helping to improve the environmental performance of project operations.

Environmental impact assessment (EIA) study is

(19)
(20)

Example:

 For Example, a forest ecosystem is a complete

(21)

FAQ : Environmental aspects

 Surface water quality ?

 Air quality ?

 Seismology/geology impact?

 Erosion ?

 Land quality ?

 Fisheries ?

 Forests ?

 Terrestrial wildlife ?

 Noise?

 Archaeological/historical significance ?

(22)

1.3. Structures and Civil

Works

 Site preparation and development ( grading and levelling

of the site, demolition and removal of existing structure, relocation of existing pipelines, cables, roads, power lines etc. connection of public network like electric power, water, communications, transportations etc. )

 Building and Structures ( involves construction of factory

or process building, ancillary buildings, administrative buildings, residential buildings)

 Outdoor works ( involves the supply and distribution of

(23)

 Technical Analysis of a project for buildings, structures

and civil works involves the preparation and development of site which includes

1. Grading and levelling of land

2. Demolition of existing structures

3. Relocation of pipeline, cables, roads 4. Reclamation of sewers and drainage 5. Connections for utilities

(24)

1.4. Project charts and

Layout

 General functional layout

 Material flow diagram

 Production line diagram

 Transport layout

 Utility consumption layout

 Communication layout

 Organizational layout

(25)

 General Functional Layout shows the functional

relationship between building, civil works and machines. It facilitates smooth and economical movement of raw materials, work in progress and finished products.

 Material flow diagram shows the quantum of flow of

materials, work-in-progress, finished products etc. along with the basic flow of these items.

 Product Line Diagram shows the production process

envisaged for the project. It also shows the vital information for the main machines and equipment's (description, location, foundation, space requirement, power and utilities required, distance between one centre to another etc.)

 Plant Layout indicates the physical layout of the entire

(26)

 Utility Consumption Layout shows main points of consumption of

utilities and the qualities and quantities required.

 Transport Layout indicates the distance and means of

transportation outside the production line.

 Communication layout shows how various departments of the

project are connected with the communication system.

 Organization layout indicates the organization structure of the

project, the interrelationship between different departments and the manpower required for the various departments.

 Plant Layout refers to the arrangement of physical facilities

References

Related documents

• Mergers and acquisitions are undertaken by ‘strong’ firms, that is firms active in sectors with a revealed comparative advantage as measured by the Balassa index, in accordance

It was found that a major transmission channel in which non-oil sector can be enhanced are real GDP and real exchange rate.On the contrary, Aliya (2012) found that

The annual Sustainable Agriculture Research and Education–Conservation Technology Information Center (SARE– CTIC) survey found that nationally cover crop acreage doubled from 2011

• If the remote Storage Center is using iSCSI virtual ports, add the IP addresses of the control port. • If the remote Storage Center is not using iSCSI virtual ports, add the

only amperometric responses signi ficantly different from that obtained in the absence of target DNA were apparent for the mitochondrial lysate prepared from horse meat which con

This was measured as the number of unique units (= putative species) from each of the five methods applied on (a) single individuals, namely morpho- types obtained with

from the Blues Brothers Movie Think Big Band Arranged by Philippe Marillia Vocal (Aretha) Aretha F ranklin Ted White Think f.. Think Think Think you think think

The MOP control board contains the microphone pre-amplifier to boost the microphone level to 0dBm on a 600 Ω line driver circuit, two 600 Ω line input circuits connected to a