Community Development
Department
SUBJECT: First Consideration of an Ordinance for
Comprehensive Plan Amendment, Official Map Amendment, Rezoning, and Conditional Use for Canaan Church at 1255 Milwaukee Avenue
AGENDA ITEM: 11.a
MEETING DATE: October 2, 2018
TO: Village President and Board of Trustees
FROM: Jeff Brady, Director of Planning, (847) 904-4306
THROUGH: Matthew J. Formica, Village Manager
CASE # :
P2018-0029
LOCATION:
1255 Milwaukee Avenue
PROJECT NAME:
Canaan Presbyterian Church
ACTION REQUESTED:
Staff requests first consideration by the Village Board of Trustees of a Plan Commission recommendation for approval of a Comprehensive Plan Amendment, Official Map Amendment, Rezoning, and Conditional Use for Canaan Church at 1255 Milwaukee Avenue to allow the existing building upon the property to be used as a building primarily devoted to religious worship, a conditional use in the R-1 Residential Zoning District.
Following the completion of the Plan Commission process, Staff amended the language used in the draft ordinance to better clarify the Plan Commission’s intention with regards to parking and special uses.
BACKGROUND:
The subject property is currently improved with an office building. The building was primarily used for medical office land uses until it was vacated several years ago. The property is subject to the recommendations of the 2017 Comprehensive Plan and the Milwaukee Avenue Corridor Plan. Within the Comprehensive Plan, the subject property is one of several properties for which Commercial zoning changes are supported. The Comprehensive Plan does not provide specific guidance on religious uses in this area, although residential zoning within the area adjacent to The Grove was considered as an appropriate land use.
PLAN COMMISSION DISCUSSION:
At the August 28, 2018 Plan Commission meeting, staff presented an overview of the project which included the following:
Applicant proposes to operate a church of approximately 100 congregants;
Request for Comprehensive Plan Amendment, Official Map Amendment, Rezoning to residential zoning, and Conditional Use to allow operation of a church;
No exterior site plan changes are proposed at this time; Sufficient parking exists for approximately 230 congregants;
Following staff’s summary, the Plan Commission began discussing the proposal and focused on the following issues:
Size of Congregation:
The Plan Commission reviewed the potential impacts of larger events that may be held on the subject property. The Plan Commission felt that special events which exceeds 100 occupants would require a special event permit that may necessitate additional traffic control and review by the Village.
Comprehensive Plan:
Staff clarified that the 2017 Village of Glenview Comprehensive Plan does not provide specific guidance regarding the proposed rezoning of the property from I-1 Limited Commercial District to R-1 Single-Family District as requested by the applicant to allow the operation of a religious institution.
Milwaukee Avenue Corridor:
The Plan Commission discussed the future requirement for Milwaukee Avenue Corridor cross-access easements. These easements would not be required in association with the current proposal since no exterior changes are proposed, but any future changes to the site plan would trigger this requirement. One member of the public spoke during the public hearing to provide comments in favor of the request. The Plan Commission moved to recommend approval of the proposal with additional language which clarifies the terms for future request for special event permits.
PLAN COMMISSION ACTION:
On August 28, 2018, Commissioner Witt moved, seconded by Commissioner Korman, to recommend approval, by a 6-0 vote, of Comprehensive Plan Amendment, Official Map Amendment Rezoning and Conditional Use, for the subject property commonly known as 1255 Milwaukee Avenue from I-1 Limited Commercial District to R-1 Single-Family District to allow the subject property to be utilized as a building primarily devoted to religious worship in accordance with the following conditions:
A. Comprehensive Plan Amendment to reflect the rezoning of the subject property from I-1 Limited Commercial District to R-1 Single-Family District.
B. Official Map Amendment to reflect the rezoning of the subject property from I-1 Limited Commercial District to R-1 Single-Family District.
C. Rezoning of the subject property from I-1 Limited Commercial District to R-1 Single-Family District.
D. Conditional Use in accordance with the provisions of Chapter 98, Article II, Section 98-50 (a)(1)
and Article II, Section 98-106(d)(2) of the Code to allow the operation a building primarily devoted to religious worship upon the subject property, a conditional use in the R1 Residential Zoning District, shall be permitted subject to the following conditions:
1. The use shall be permitted to operate from 7:00 am to 8:00 pm daily, with exceptions for
the following:
2. There shall be a maximum occupancy of 234 people during normal services, however any
special events exceeding 100 persons and/or with the potential for impact on the community or traffic safety shall be required to obtain a special event permit from the Village of Glenview. In addition, petitioner understands that in the event that they need to obtain a special event permit from the Village, that there might be additional traffic control personnel required by the Village in addition.
3. The petitioner shall be in receipt of a building permit within 1 year following the adoption
of said ordinance, or the conditional use will lapse.
4. If the conditional use is abandoned or discontinued for more than three (3) months,
without substantial attempt to resume such use, the conditional use shall be rescinded.
E. All materials presented to the Commission on August 28, 2018 and associated revisions required
by the Plan Commission.
Commissioner Korman seconded the motion.
YEAS: Commissioners Burton, Duff, Fallon, Igleski, Korman, and Witt (6)
NAYS: None (0)
ABSTAIN: None (0)
ATTACHMENTS:
1. Plan Commission Staff Report and Exhibits
2. Excerpt from Minutes of the August 28, 2018 Plan Commission Meeting
3.
Draft Ordinance and ExhibitsCASE #:
P2018-029
LOCATION:
1255 Milwaukee Avenue
PROJECT NAME:
Canann Presbyterian Church
PROPOSAL:
The applicant, Canaan Presbyterian Church, represented by Lawrence M. Freedman, requests approval of a Comprehensive Plan Amendment, Official Map
Amendment, and Rezoning of the subject property from I-1 Limited Commercial District to R-1 Single-Family Residential District and a subsequent Conditional Use
Permit in accordance with the provisions of Chapter 98, Article II, Section 98-50(a)(1) and Article III, Section 98-84 of the Glenview Municipal Code to allow the
existing building upon the property to be used as a building primarily devoted to religious worship, a conditional use in the R-1 Residential Zoning District.
Staff Report
August 28, 2018
Village of Glenview
Plan Commission
TO:Chairman and Plan Commissioners
FROM:
Community Development Department
CASE MANAGER:
Tony Repp, Planner
SUBJECT:
Comprehensive Plan Amendment, Official Map Amendment,
Rezoning, and Conditional Use
ACTION REQUESTED:
Staff requests consideration of a Plan Commission recommendation to the Village Board of Trustees
APPLICANT:
Canaan Presbyterian Church 8930 Waukegan Road Morton Grove, IL OWNER: 1255 Glenview LLC 500 Park Blvd., Suite 1010 Itasca, IL 60143 CONTACT: Lawrence M. Freedman 77 W. Washington Street, Ste. 1211
Chicago, IL 60602
Report Disclaimer: Village staff makes no representations regarding support, endorsement, or the
likelihood of approval or disapproval by any Glenview regulatory commission or the Village Board of Trustees.
Site Assessment
VILLAGE OF GLENVIEW ZONING:
PIN(s): 04-32-101-032-0000
Current I-1 Limited Commercial District
North I-1 Limited Commercial District
East P-1 Public Lands District
South I-1 Limited Commercial District
West B-2 General Business District
AERIAL PHOTOGRAPHY:
PICTOMETRIC PHOTOGRAPHY:
South Elevation(s)
East Elevation(s)
Project Summary
BACKGROUND:
The subject property is currently improved with an office building. The building was primarily used for medical office land uses until it was vacated in recent years. The property is subject to the recommendations of the 2017 Comprehensive Plan and the Milwaukee Avenue Corridor Plan.
PROJECT DESCRIPTION:
The applicant requests a recommendation to the Board of Trustees for approval of a Comprehensive Plan Amendment, Official Map Amendment, Rezoning, and Conditional Use to allow a religious institution to occupy the existing building. Interior renovations would be completed to allow for a gathering space of approximately 100 people.
Weekly activities would be consistent with the following summary:
Day Event Time Attendance
Tuesday and Friday Evenings
Prayer Meetings 6:00 p.m. – 6:30 p.m. 10 People
Thursday Evenings Bible Study 7:30 p.m. – 10:00 p.m. 5 people
Monday through Friday Music Lessons 3:00 p.m. – 6:00 p.m. 10 people
Friday Evenings Prayer Service 8:00 p.m. – 10:00 p.m. 20 people
Sunday Morning Mass 8:30 a.m. – 9:30 a.m. 20 people
Sunday Morning Mass 11:00 a.m. – 12:00 p.m. 70 people
As needed Weddings / Special Events - 100 people
The applicant is not proposing any other alterations to the property at this time. There will be no kitchen or banquet facilities on-site. It is likely the applicant will request signage at a point in the future which will require additional review and approval from the Appearance Commission.
The applicant may pursue a childcare/daycare facility on-site in the future. This would require the applicant to return to the Plan Commission and Board of Trustees for review of alterations to the Conditional Use and any associated site plan modifications.
POTENTIAL NEIGHBORHOOD IMPACTS:
The subject property lies adjacent to existing commercial properties. No correspondence has been received regarding this petition to date. No impacts are expected from the added traffic. During special events or large events, the applicant may be required to provide traffic control services through the Glenview Police Department. This determination is made by Village Officials during review of a special event permit.
Plan Commission Review
COMPREHENSIVE PLAN AMENDMENT:
The 2017 Village of Glenview Comprehensive Plan does not provide specific guidance regarding the proposed rezoning of the property from I-1 Limited Commercial District to R-1 Single-Family District as requested by the applicant to allow the operation of a religious institution. An amendment to the Comprehensive Plan would be required to allow the proposed conditions.
OFFICIAL MAP AMENDMENT:
The Village’s Official map prescribes appropriate land uses for property within the Village and property within 1.5 miles of the Village’s corporate limits. Also, the Village’s Official Map is incorporated by reference within the Village’s Comprehensive Plan to provide guidance regarding rezoning petitions. Since the 2017 Village of Glenview Comprehensive Plan does not provide specific guidance regarding the proposed rezoning of the property from P-1 Public Lands District to I-2 Light Industrial District as requested by the applicant, an amendment to the Official Map would be required to allow the proposed conditions.
REZONING STANDARDS:
The Plan Commission should consider the following judicial standards and requisites for rezoning: 1. The existing uses and zoning of nearby property.
2. The extent to which property values may be diminished by the particular zoning restrictions. 3. The extent to which the destruction of property values upon the plaintiff promotes the health,
safety, morals, and general welfare of the public.
4. The relative gain to the public as compared to the hardship imposed upon the individual property owner.
5. The suitability of the subject property for the zoned purposes.
6. The length of time the property has been vacant as zoned considered in the context of land development in the area in the vicinity of the subject property.
7. The community need for the proposed use.
8. The care with which the community has undertaken to plan its land use development.
CONDITIONALUSESTANDARDS:
Per Sec. 98-50 of the Municipal Code, the Plan Commission shall evaluate any petition for Conditional Use Permit in accordance with the following standards before offering a recommendation to the Village Board of Trustees:
1. The proposed conditional use at the particular location is necessary or desirable for the public
convenience; and it will not be injurious to the use and enjoyment of property already permitted in the immediate vicinity; nor will it diminish or impair property values in the neighborhood; nor will it affect a significant change in the character of the neighborhood.
2. The location and size of the conditional use, the nature and intensity of the operation involved in
or conducted in connection with it, the size of the site in relation to it, and the location of the site with respect to streets giving access to it, shall be such that it will be in harmony with present development and the appropriate and orderly future development of the district in which it is located, as well as other butting districts.
3. The location, nature, and height of buildings, walls, and fences, and the nature and extent of the
landscaping on the site shall be such that the use will not unreasonably hinder or discourage the appropriate development and use of adjacent and nearby land and buildings.
4. Parking areas shall be of adequate size for the particular use, properly located, and suitably
screened from adjoining residential uses, and the entrance and exit drives shall be laid out so as to prevent traffic hazards and nuisances, and minimize traffic congestion in the area.
5. A use which is permitted in another district by conditional use shall comply with all applicable bulk
regulations of the district in which the use is located.
Please refer to the applicant’s Conditional Use application within the attached application materials for details regarding the applicant’s responses and justifications for the proposed use in regard to the Conditional Use Standards.
Existing Proposed Allowed/Permitted Compliance Zoning I-1 R-1 R-1 No – Rezoning Required Lot Size 43,560 sq. ft. 43,560 sq. ft. 111,911 sq. ft. Yes
Building Height 18.00 feet 18.00 feet 32.00 feet Yes
Minimum Front Yard
Setback (West) 114.59 feet 114.59 feet 30.00 feet Yes
Minimum Side Yard
Setback (North) 7.69 feet 7.69 feet 15.00 feet
No – Existing Non-conforming Minimum Side Yard
Setback (South) 26.79 feet 26.79 feet 15.00 feet Yes
Minimum Rear Yard Setback
(East)
559.95 feet 559.95 feet 25.00 feet Yes
Maximum Building Size
13,934 square
feet 13,934 square feet 21,424 square feet Yes
Impervious Lot Coverage 53,752 square feet 53,752 sq. ft. 20,143 sq. ft. Controlled by Site Plan Review PARKING REQUIREMENTS:
The Zoning Ordinance stipulates formulas to be applied to various possible land uses in order to establish the minimum number of required parking stalls. These parking formulas have been examined by staff to establish the most restrictive requirements, which can be summarized as follows:
Parking
Requirements Formula Quantity Total Required
Total
Proposed Compliance
Assembly Worship Space
1 Parking stall per 3 fixed seats
100 Seats
33 stalls 78 stalls Yes
Specialty School / Lessons
1 per student / instructor
15 Students /
3 instructors 18 stalls 78 Stalls Yes
33(Sundays)
18 (Weekday) 78 stalls Yes
Technical Review
TRAFFIC IMPACT ANALYSIS:
A parking / traffic study was prepared for the proposed project which evaluated the use and scope of proposed traffic. A review of projected impacts and site analysis was conducted by James J. Benes and Associates. The Village’s third-party consultant concurred with the results of the applicant’s study which showed the proposed parking and traffic was suitable for the location. Given the relatively small size of the congregation, vehicles exiting onto Milwaukee Avenue are not expected to cause any addition congestion. On Sundays, the busiest time for the facility, the traffic on Milwaukee Avenue is off-peak and traffic circulation is not expected to be an issue.
COMPLIANCEWITHVILLAGEPLANS:
PROJECT TIMELINE & OUTREACH:
Submittal/Meeting/Action Date
A. Application Submitted 07/26/2018
B. Public notice published in the Glenview Announcements 08/09/2018
C. Public notice sign posted upon the subject property 08/09/2018
D. Public notices mailed to surrounding property owners 08/09/2018
E. Plan Commission Meeting 08/28/2018
F. Appearance Commission Meeting (if needed) TBD
G. Board of Trustees Meeting (1st Consideration) TBD
H. Board of Trustees Meeting (2nd Consideration) TBD
I. Permit Issuance TBD
J. Inspections TBD
K. Certificate of Occupancy N/A
Village Plan
Compliance
Yes / No / N/A Comments
Comprehensive Plan Yes The proposal would require an amendment to
the Plan
Official Map Yes The proposal would require an amendment to
the Map to reflect the change in zoning.
Waukegan Road Corridor Plan N/A -
Milwaukee Avenue Corridor Plan N/A At any point in the future where Final Site Plan
Review is requested, the granting of Milwaukee Avenue Corridor Cross-Access easements and slip road configuration may be required.
Downtown Revitalization Plan N/A -
Natural Resources Plan N/A -
Bicycle & Sidewalk Master Plan Yes The property is currently served by existing
sidewalk.
The GNAS Design Guidelines N/A -
REQUIRED APPROVAL(s):
The following chart details the necessary required approvals:
Required Regulatory Review
A. Annexation
B. Annexation with Annexation Agreement
√ C. Comprehensive Plan Amendment
√ D. Official Map Amendment
√ E. Rezoning
F. Planned Development
√ G. Conditional Use
H. Final Site Plan Review I. Second Curb Cut
J. Subdivision (Preliminary, Final, and Waivers) K. Variation(s) (Zoning Board of Appeals)
L. Certificate of Appropriateness (Appearance Commission)
√ M. Final Engineering Approval & Outside Agency Permits
√ N. Building Permits
√ O. Building & Engineering Inspections
P. Recorded Documents (Development Agreements, Easements, Covenants, etc.)
√ Q. Business License
√ R. Certificate of Occupancy
JAMES J. BENES AND ASSOCIATES, INC.
950 Warrenville Road Suite 101 Lisle, Illinois 60532 Tel. (630) 719-7570 Fax (630) 719-7589
MEMORANDUM
Date: August 24, 2018
To: Anthony Repp
Planner
Village of Glenview
From: Thomas Adomshick, P.E., PTOE Daniel H. Schoenberg, P.E.
President Project Engineer
Re: Canaan Presbyterian Church, 1255 Milwaukee Avenue
Glenview, Illinois
Job No. 1394.154
At your request, we have performed a review of the proposed redevelopment of existing structure and parking at 1255 Milwaukee Avenue into a church and weekday child day care center. The lot is currently vacant. Access is from a full driveway on Milwaukee Avenue. A Traffic Impact Study (TIS) prepared by KLOA and dated August 20, 2018 was prepared for our review.
We offer the following comments:
Vehicular Access and Internal Circulation
The TIS implies there are no proposed changes within the Milwaukee Road right-of-way, which would have required IDOT approval. Milwaukee Avenue is a Strategic Regional Arterial (SRA) designed to improve regional mobility. Restricting curb cuts is an IDOT design goal for SRAs. There have been discussions about consolidating access along this corridor to a parallel road ultimately connecting to a shared full access opposite the full Abt access on the west side of Milwaukee. This site is not interconnected today because grading differences make a connection to the property to the east difficult. This development does not affect the grade differential and a required interconnection is not appropriate at this time.
Pedestrian Access
There is no pedestrian accessible route from the Milwaukee right-of-way to the building as may be required by ADA rules.
1255 Milwaukee Avenue Canaan Presbyterian Church
August 24, 2018
Page 2
Traffic Impact
The 10th Edition of ITE has very limited data for congregations of this small size. The smallest data
point has 300 church attendees. Actual data from similarly sized religious assemblies would verify the projections in the TIS. The TIS says 100 adults will attend, but the ITE methodology is based upon all attendees including children and support staff. What is the full attendance during services? Provide more details of religious schedules.
The 0.75% projected background network growth is similar to past CMAP projections in this corridor, but the letter from CMAP was not in the TIS.
The directional distribution of peak hour trips of this development are reasonable. Given the traffic volumes on Milwaukee, left turns from and onto Milwaukee at driveways must wait a while for gaps. It is appropriate to use a gap analysis to confirm left turns in and out have sufficient opportunity to move during peak periods. The backup to Table 1 was not in the TIS. We cannot tell if the existing traffic at the driveway immediately southeast has been taken into account. Vehicles using this neighboring driveway compete with visitors of this development for gaps during which turns can be executed.
Some of the exhibits are incorrectly labelled. Confirm that Figure 3 tracks Sunday peak hour and not Saturday traffic and that the AM and PM peaks are weekday.
Parking
Section 98-293b7 of the Code requires one parking space per three seats of religious use. The actual number of seats is not specified, but one seat per adult was assumed to determine a required total of 34 spaces are required. A total of 75 spaces exist today and are proposed to remain. Nursery schools shall provide 3 spaces for each two classrooms. We assume there will be less than 50 classrooms, suggesting compliance. No information was provided about the dimensions of the existing spaces. The number of handicapped accessible spaces exceeds code requirements.
--END--
VILLAGE OF GLENVIEW
PUBLIC NOTICE
P2018-029
Notice is hereby given that a public hearing will be held by the Glenview Plan Commission to
consider a petition requesting approval of a Conditional Use of the Glenview Municipal Code. The
meeting will be held on Tuesday, August 28, 2018 at 7:00 P.M., in the Village Hall, 2500 East
Lake Avenue, Glenview, Illinois in accordance with Chapter 65, Section 5/11-13-5 of the Illinois
Compiled Statutes.
The property involved is commonly known as 1255 Milwaukee Avenue and is legally described
as:
LOT 1 IN THE BLOOD CENTER OF NORTHERN ILLINOIS, INC. RESUBDIVISION, BEING A PART OF THE SOUTHWEST QUARTER OF SECTION 29 AND THE NORTHWEST QUARTER OF SECTION 32, TOWNSHIP 42 NORTH, RANGE 12, EAST OF THE THIRD PRINCIPAL MERIDIAN, IN COOK COUNTY, ILLINOIS.
The applicant, Canaan Presbyterian Church, represented by Lawrence M. Freedman, requests
approval of a Rezoning of the subject property from I-1 Limited Commercial District to R-1
Single-Family Residential District and a subsequent Conditional Use Permit in accordance with
the provisions of Chapter 98, Article II, Section 98-50(a)(1) and Article III, Section 98-84 of the
Glenview Municipal Code to allow the existing building upon the property to be used as a
building primarily devoted to religious worship
, a conditional use in the R-1 Residential
Zoning District.
All persons interested should attend and will be given an opportunity to be heard. For additional
information regarding this case, please contact Tony Repp, Planner, at (847) 904-4309.
Glenview Plan Commission
Steven K. Bucklin, Chairman
ATTEST:
Jeff Rogers
Planning Manager
Publication Date: August 9, 2018
PROJECT NARRATIVE
Applicant is a church servicing the Korean-American community. It has been in existence for
over ten years and has been operating for the last three years in a facility in Buffalo Grove. Its
membership is comprised of approximately 100 adults. Operations of the proposed facility are
contemplated to be as follows:
Weekdays: Tuesday and Friday evenings – prayer meetings from 6:00pm to 6:30pm attended
by approximately 10 people.
Thursday evenings – bible study class at 7:30pm, attended by approximately 5
people
Monday thru Friday – After school music lessons will be available for a small
number of members.
Friday evenings – Prayer service at 8:00pm attended by approximately 20 people.
Sundays:
Two services are contemplated, one from 8:30am to 9:30am, attended by
approximately 20 adults, and one from 11:00am to 12:00pm, attended by
approximately 70 adults.
There will be occasional weddings or other events on a non-regular basis.
No kitchen is planned for the facility.
In the near future, it is contemplated to have preschool and daycare facilities to service between
20 to 30 children, which facilities will be available to members and non-members alike and the
cost of which will be partially underwritten by the Applicant.
KLOA, Inc. Transportation and Parking Planning Consultants
9575 West Higgins Road, Suite 400 | Rosemont, Illinois 60018 p: 847-518-9990 | f: 847-518-9987
MEMORANDUM TO:
Richard Kim
CK & Associates, LLC
FROM:
Brendan S. May
Consultant
Luay R. Aboona, PE, PTOE
Principal
DATE:
August 20, 2018
SUBJECT:
Summary Traffic Evaluation
Proposed Canaan Presbyterian Church of Chicago
Plainfield, Illinois
This memorandum summarizes the methodologies, results, and findings of a traffic impact study
conducted by Kenig, Lindgren, O’Hara, Aboona, Inc. (KLOA, Inc.) for the proposed Canaan
Presbyterian Church to be located in Glenview, Illinois. The site, which is currently occupied by
a vacant medical office building, is located at 1255 Milwaukee Avenue (IL Route 21). As
proposed, the existing building will be converted to a church to accommodate its 100 adult
members. Additionally, the building will be used on weekdays for a daycare facility for up to 30
children.
The purpose of this study was to examine background traffic conditions, assess the impact that the
proposed development will have on traffic conditions in the area, and determine if any roadway or
access improvements are necessary to accommodate traffic generated by the proposed
development.
Existing Conditions
The site, as previously indicated, is located at 1255 Milwaukee Avenue, approximately 700 feet
south of Kennicott Lane and is currently occupied by a vacant medical office building. The
surrounding land uses are Guarantee Trust Life Insurance and Delta Hotels by Marriot Chicago
North Shore Suites to the north, US Law Group, Lucy’s Garage and Life Storage to the south and
Abt Electronics to the west. Figure 1 shows the location of the site in relation to the area roadway
system. Figure 2 shows an aerial view of the site area.
Site Location Figure 1
SITE
Aerial View of Site Location Figure 2
Milwaukee Avenue (IL 21) is generally a north-south principal arterial providing two lanes in each
direction separated by a center left-turn lane. At its unsignalized intersection with the Abt
Electronics full movement access drive, Milwaukee Avenue provides an exclusive left-turn lane,
a through lane and a shared through/right-turn lane on the northbound approach and an exclusive
left-turn lane, two through lanes and an exclusive right-turn lane on the southbound approach. At
its unsignalized intersection with the Abt Electronics right-in/right-out access drive, Milwaukee
Avenue provides two through lanes on the northbound approach and a through lane and a shared
through/right-turn lane on the southbound approach. At its unsignalized intersection with the site
access drive, Milwaukee Avenue provides a through lane and a shared through/right-turn lane on
the northbound approach and an exclusive left-turn lane and two through lanes on the southbound
approach. Milwaukee Avenue is under the jurisdiction of the Illinois Department of Transportation
(IDOT), is designated as a Strategic Regional Arterial (SRA), carries an AADT volume of 37,300
vehicles (IDOT AADT 2017) and has a speed limit of 45 miles per hour.
Existing Traffic Volumes
In order to determine current traffic conditions in the vicinity of the site, KLOA, Inc. conducted
peak period traffic counts utilizing Miovision Scout Collection Units on Tuesday, August 14, 2018
during the weekday morning (7:00 to 9:00 A.M.) and evening (4:00 to 6:00 P.M.) peak periods
and on Sunday, August 12, 2018 during the morning/midday (8:00 A.M. to 1:00 P.M.) peak period
at the intersections of Milwaukee Avenue with the Abt Electronics full movement access drive
and Milwaukee Avenue with the Abt Electronics right-in/right-out access drive. The results of the
traffic counts indicated that the weekday morning peak hour of traffic occurs from 7:74 A.M.
to 8:74 A.M., the weekday evening peak hour of traffic occurs from 4:45 P.M. to 5:45 P.M. and
the Sunday midday peak hour of traffic occurs from 12:00 Noon to 1:00 P.M.
Gap Study Results
A gap study was also conducted on Tuesday, August 14, 2018 and on Sunday, August 12, 2018
during the previously determined peak hours along Milwaukee Avenue at the location of the site
access drive to determine the availability of gaps or interruptions in the Milwaukee Avenue traffic
stream. Gaps in the northbound direction on Milwaukee Avenue, which allow traffic to turn left
from Milwaukee Avenue onto the site access drive and right from the site access drive onto
Milwaukee Avenue and gaps in both directions on Milwaukee Avenue, which allow traffic to turn
left from the site access drive onto Milwaukee Avenue, were surveyed. The critical gap and
follow-up gap periods required to turn to and from Milwaukee Avenue were based on information
provided in the Highway Capacity Manual (HCM) published by the Transportation Research
Board (TRB). Table 1 summarizes the results of the gap study. As can be seen, the results indicate
that numerous gaps are available in the traffic stream to accommodate turning movements.
Table 1
GAP STUDY RESULTS – MILWAUKEE AVENUE
Proposed Development Plan
As proposed, the existing building will be converted to a church to accommodate approximately
100 members. Services will be held on Sundays at 8:30 A.M. and 11:00 A.M., a Friday evening
service at 8:00 P.M. and a Bible study class will also be held on Thursday at 7:30 P.M. In the
future, the church building will also be utilized for a pre-school daycare facility for up to 30
children. Access to the site will continue to be provided a single full movement access drive located
approximately 110 feet south of the Abt Electronics right-in/right-out access drive. This access
drive provides one inbound lane and one outbound lane. Left-turning movements from Milwaukee
Avenue onto the access drive will continue to be accommodated via the existing center left-turn
lane. Approximatley 75 parking spaces will continue to be provided.
Directional Distribution
The directions from which members of the Canaan Presbyterian Church will approach and depart
the site were estimated based on existing travel patterns, as determined from the traffic counts. The
existing traffic counts indicated that approximately 50 percent of the traffic on Milwaukee Avenue
travels to/from the north and 50 percent of the traffic travels to/from the south.
Estimated Site Traffic Generation
The volume of traffic that will be generated by the proposed development is based on the type of land
uses and the size of the development. The number of peak hour vehicle trips estimated to be generated
by the proposed church and future day care center is based on vehicle trip generation rates contained
in Trip Generation Manual, 10
thEdition, published by the Institute of Transportation Engineers (ITE).
Land-Use Codes 560 and 565 rates were used to estimate the trips to be generated by the church and
day care, respectively. The ITE Trip Generation Sheets are included in the Appendix. Table 2 shows
the site-generated traffic volumes for the proposed development.
Number of Potential Movements Based on Gaps Available
Time Periods
Southbound
Table 2
ESTIMATED SITE-GENERATED TRAFFIC VOLUMES
Land
Use
Code
Weekday Morning
Peak Hour
Weekday Evening
Peak Hour
Sunday Midday
Peak Hour
Type/Quantity
In
Out
Total
In
Out
Total
In
Out
Total
560
Church
(100 Attendees)
--
--
--
--
--
--
26
27
53
565
Day Care Center
(30 Students)
15
13
28
12
14
26
--
--
--
Total
15
13
28
12
14
26
26
27
53
Total Projected Traffic Volumes
The estimated weekday morning, evening and Sunday midday peak hour traffic volumes that will
be generated by the proposed development were assigned to the roadway system in accordance
with the previously described directional distribution.
Additionally, the existing traffic volumes were increased by a regional growth factor to account
for the increase in existing traffic related to regional growth in the area (i.e., not attributable to any
particular planned development). Based on ADT projections provided by the Chicago
Metropolitan Agency for Planning (CMAP) the existing traffic volumes were increased by
approximately 0.75 percent per year for six years (approximately 4.5 percent total) to project Year
2024 conditions (one-year buildout plus five years). It should be noted that the regional growth
factor was only applied to the through volumes along Milwaukee Avenue.
The development-generated traffic volumes were added to the background traffic volumes to
determine the Year 2024 traffic volumes. The existing and Year 2024 total projected traffic
volumes are illustrated in Figure 3.
S
I T
E
S
I T
E
AV EN UE MIL WA UK EE R I / R O A C C E S S E L E C T R O N I C S A B T 21 F U L L A C C E S S A B T E L E C T R O N I C S AV EN UE MIL WA UK EE R I / R O A C C E S S E L E C T R O N I C S A B T 21 F U L L A C C E S S A B T E L E C T R O N I C S Figure: 3 [00] LEGEND 00 (00)Kenig,Lindgren,O'Hara,Aboona,Inc. Job No: 18-173
Glenview, Illinois
Church
Canaan Presbyterian
Existing and Projected Traffic Volumes
- AM PEAK HOUR (7:45-8:45 AM) - PM PEAK HOUR (4:45-5:45 PM) - SATURDAY MIDDAY PEAK HOUR (12:00-1:00 PM)
Traffic Analyses
Roadway and adjacent or nearby intersection analyses were performed for the weekday morning,
weekday evening and Sunday midday peak hours for the existing (Year 2018) and projected (Year
2024) traffic volumes.
The traffic analyses were performed using the methodologies outlined in the Transportation
Research Board’s Highway Capacity Manual (HCM), 2010 and analyzed using the HCS &
computer software. The analyses for the unsignalized intersections determine the average control
delay to vehicles at an intersection. Control delay is the elapsed time from a vehicle joining the
queue at a stop sign (includes the time required to decelerate to a stop) until its departure from the
stop sign and resumption of free flow speed. The methodology analyzes each intersection approach
controlled by a stop sign and considers traffic volumes on all approaches and lane characteristics.
The ability of an intersection to accommodate traffic flow is expressed in terms of level of service,
which is assigned a letter from A to F based on the average control delay experienced by vehicles
passing through the intersection. The Highway Capacity Manual definitions for levels of service
and the corresponding control delay for signalized and unsignalized intersections are included in
the Appendix of this report.
Summaries of the traffic analysis results showing the level of service and overall intersection delay
(measured in seconds) for the existing and Year 2024 total projected conditions for the study area
intersections are presented in Tables 3 and 4, respectively. A discussion of the operation of the
intersections follows. Summary sheets for the capacity analyses are included in the Appendix.
Table 3
CAPACITY ANALYSIS RESULTS – EXISTING CONDITIONS – UNSIGNALIZED
Weekday
Morning
Peak Hour
Weekday
Evening
Peak Hour
Sunday
Midday
Peak Hour
LOS Delay LOS Delay LOS Delay
Milwaukee Avenue with Abt Full Access Drive
•
Eastbound Approach
C
17.1
F
85.1
E
35.6
•
Westbound Approach
C
23.1
F
54.9
B
11.8
•
Northbound Left Turns
B
11.2
B
14.8
B
11.5
•
Southbound Left Turns
B
13.0
B
12.6
B
10.0
Milwaukee Avenue with Abt Right-In/Right-Out Access Drive
•
Eastbound Approach
B
12.4
C
16.7
B
14.1
LOS = Level of Service Delay is measured in seconds.
Table 4
CAPACITY ANALYSIS RESULTS – PROJECTED CONDITIONS – UNSIGNALIZED
Weekday
Morning
Peak Hour
Weekday
Evening
Peak Hour
Sunday
Midday
Peak Hour
LOS Delay LOS Delay LOS Delay
Milwaukee Avenue with Abt Full Access Drive
•
Eastbound Approach
C
17.9
F
104.8
E
41.0
•
Westbound Approach
C
24.8
F
61.0
B
12.1
•
Northbound Left Turns
B
11.5
C
15.6
B
12.0
•
Southbound Left Turns
B
13.5
B
13.1
B
10.3
Milwaukee Avenue with Abt Right-In/Right-Out Access Drive
•
Eastbound Approach
B
12.7
C
17.5
B
14.6
Milwaukee Avenue with Site Access Drive
•
Westbound Approach
D
25.6
D
29.5
C
18.8
•
Southbound Left Turns
B
13.5
B
14.0
B
10.8
LOS = Level of Service Delay is measured in seconds.
Discussion and Recommendations
The following summarizes how the intersections are projected to operate and identifies any
roadway and traffic control improvements necessary to accommodate the development-generated
traffic.
Milwaukee Avenue with Abt Electronics Access Drives
The results of the capacity analysis indicate that the full movement access drive serving Abt
Electronics currently operates at level of service (LOS) C during the weekday morning peak hour,
LOS F during the weekday evening peak hour and at LOS E Sunday midday peak hour.
Additionally, the westbound approach currently operates at LOS C during the weekday morning
peak hour, LOS F during the weekday evening peak hour ant at LOS B during the Sunday midday
peak hour. However, the levels of service and delay experienced during the weekday evening peak
hour is expected for access driveways that have unsignalized intersections with arterial roadways
such as Milwaukee Avenue. Under Year 2024 projected conditions, the eastbound and westbound
approaches are projected to continue operating at existing levels of service during the weekday
morning, weekday evening and Sunday midday peak hours. The increases in delay experienced at
this intersection are primarily attributed to the background growth factor as the proposed
development is projected to increase the traffic traversing this intersection by less than one-half
percent during the weekday morning and evening peak hours and by approximatley one percent
during the Sunday midday peak hour.
The northbound left-turn movements are projected to operate at LOS C or better during peak hours
with increases in delay of less than one second and 95
thpercentile queues of one to two vehicles
which will continue to be accommodated by the exiting northbound left-turn lane on Milwaukee
Avenue. The southbound left-turn movements are projected to operate at LOS B during the peak
hours with increases in delay of less than one second and 95
thpercentile queues of one to two
vehicles which will continue to be accommodated by the existing center left-turn lane provided on
Milwaukee Avenue.
Eastbound right-turn movements from the right-in/right-out access drive onto Milwaukee Avenue
currently operate at LOS B during the weekday morning and Sunday midday peak hours and at
LOS C during the weekday evening peak hour. Under Year 2024 projected conditions, the
eastbound right-turn movements are projected to continue operating at existing levels of service
with increases in delay of less than one second and 95
thpercentile queues of one to two vehicles.
As such, the traffic projected to be generated by the proposed development will have a limited
impact on the operations of the access drives serving Abt Electronics and no roadway or traffic
control improvements will be required.
Milwaukee Avenue with Site Access Drive
The results of the capacity analysis indicate that outbound movements from the site access drive
onto Milwaukee Avenue are projected to operate at LOS D during the weekday morning and
weekday evening peak hours and at LOS C during the Sunday midday peak hour with 95
thpercentile queues of one to two vehicles. Furthermore, southbound left-turn movements from
Milwaukee Avenue onto the site access drive are projected to operate at LOS B during the peak
hours with 95
thpercentile queues of one to two vehicles. As such, the existing access drive serving
the site will be adequate in accommodating the traffic projected to be generated by the proposed
church and day care and the existing center left-turn lane will be adequate in accommodating the
southbound left-turning movements onto the access drive.
Gap Study Evaluation
Tables 5 shows the number of potential movements based on the number of available gaps
compared to the number of required gaps that are needed to accommodate the projected traffic
turning between Milwaukee Avenue and the site access drive. As shown in Table 5, there are more
than sufficient gaps in traffic to accommodate the westbound left turns and westbound right turns
from the site access drive onto Milwaukee Avenue, and the southbound left turns from Milwaukee
Avenue onto the site access drive during the weekday morning, weekday evening and Sunday
midday peak hours of adjacent roadway traffic. This indicated that the intersection of Milwaukee
Avenue with the site access drive will operate adequately.
Table 6
REQUIRED GAPS AT INTERSECTION OF MILWAUKEE AVENUE WITH ACCESS
Number of Potential Movements Based on Gaps AvailableTime Periods Southbound Left-Turn
Westbound
Right-Turn Westbound Left-Turn
Available Required Available Required Available Required
Parking Evaluation
Based on Village of Glenview municipal code, churches are required to provide one parking space
for each three seats or bench seating spaces. With 100 total members (assuming 100 seats) a total
of 34 parking spaces will be required. The site currently provides a total of 75 parking spaces
meeting the Village requirement, resulting in a surplus of 41 parking spaces. Additionally, the
proposed parking ratio of 0.75 spaces per attendee exceeds the average and 85
thpercentile peak
parking demand for churches of 0.45 spaces per attendee and 0.60 spaces per attendee,
respectively, based on information published in the ITE Parking Generation Manual. As such, the
proposed apartment development will provide a sufficient number of parking spaces to
accommodate its projected parking demand.
Conclusion
Based on the preceding evaluation, the following is concluded:
•
The proposed development traffic can be accommodated by the existing adjacent roadway
system.
•
The intersections of Milwaukee Avenue with the Abt Electronics full movement and
right-in/right-out access drives have sufficient reserve capacity to accommodate the traffic
projected to be generated by the proposed development.
•
The provision of one inbound lane and outbound lane coupled with the provision of the
center left-turn lane on Milwaukee Avenue will provide sufficient capacity to
accommodate the development generated traffic.
•
Adequate gaps exist in the Milwaukee Avenue traffic stream to accommodate the projected
left and/or right turning movements from proposed full movement access drive.
•
The existing 75 on-site parking spaces will be adequate in accommodating the projected
parking demand.
Appendix
Traffic Count Summary Sheets
ITE Trip Generation Sheets
Level of Service Criteria
Capacity Analysis Summary Sheets
Traffic Count Summary Sheets
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Full Access Site Code: Start Date: 08/12/2018 Page No: 1
Turning Movement Data
Start Time
Abt Access Drive
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Full Access Site Code: Start Date: 08/12/2018 Page No: 3
Turning Movement Peak Hour Data (12:00 PM)
Start Time
Abt Access Drive
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Full Access Site Code: Start Date: 08/12/2018 Page No: 4
Turning Movement Peak Hour Data (7:45 AM)
Start Time
Abt Access Drive
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Full Access Site Code: Start Date: 08/12/2018 Page No: 5
Turning Movement Peak Hour Data (4:45 PM)
Start Time
Abt Access Drive
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Right- In/Right-Out Access Site Code: Start Date: 08/12/2018 Page No: 1
Turning Movement Data
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Right- In/Right-Out Access Site Code: Start Date: 08/12/2018 Page No: 3
Turning Movement Peak Hour Data (12:00 PM)
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Right- In/Right-Out Access Site Code: Start Date: 08/12/2018 Page No: 4
Turning Movement Peak Hour Data (7:45 AM)
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400
Rosemont, Illinois, United States 60018
(847)518-9990
Count Name: Milwaukee Avenue with Right- In/Right-Out Access Site Code: Start Date: 08/12/2018 Page No: 5
Turning Movement Peak Hour Data (4:45 PM)
ITE Trip Generation Sheets
Level of Service Criteria
LEVEL OF SERVICE CRITERIA
Signalized Intersections
Level of
Service
Interpretation
Average Control
Delay
(seconds per vehicle)
A
Favorable progression. Most vehicles arrive during the
green indication and travel through the intersection
without stopping.
≤10
B
Good progression, with more vehicles stopping than for
Level of Service A.
>10 - 20
C
Individual cycle failures (i.e., one or more queued
vehicles are not able to depart as a result of insufficient
capacity during the cycle) may begin to appear.
Number of vehicles stopping is significant, although many
vehicles still pass through the intersection without
stopping.
>20 - 35
D
The volume-to-capacity ratio is high and either
progression is ineffective or the cycle length is too long.
Many vehicles stop and individual cycle failures are
noticeable.
>35 - 55
E
Progression is unfavorable. The volume-to-capacity ratio
is high and the cycle length is long. Individual cycle
failures are frequent.
>55 - 80
F
The volume-to-capacity ratio is very high, progression is
very poor, and the cycle length is long. Most cycles fail
to clear the queue.
>80.0
Unsignalized Intersections
Level of Service
Average Total Delay (SEC/VEH)
A
0 - 10
B
> 10 - 15
C
> 15 - 25
D
> 25 - 35
E
> 35 - 50
F
> 50
Source: Highway Capacity Manual, 2010.
Capacity Analysis Summary Sheets
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and South Drive
Agency/Co. KLOA,Inc Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street South Access Drive
Analysis Year 2018 North/South Street Milwaukee Avenue
Time Analyzed Existing Morning Peak Hour Factor 0.93
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 1 1 0 1 0 0 1 2 0 0 1 2 1
Configuration LT R LTR L T TR L T R
Volume (veh/h) 3 0 9 1 0 3 0 40 1382 1 0 5 987 60
Percent Heavy Vehicles (%) 0 0 0 0 0 0 0 0 0 0
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized No No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 7.5 6.5 6.9 7.5 6.5 6.9 4.1 4.1
Critical Headway (sec) 7.50 6.50 6.90 7.50 6.50 6.90 4.10 4.10
Base Follow-Up Headway (sec) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2
Follow-Up Headway (sec) 3.50 4.00 3.30 3.50 4.00 3.30 2.20 2.20
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 3 10 4 43 5
Capacity, c (veh/h) 139 498 203 628 458
v/c Ratio 0.02 0.02 0.02 0.07 0.01
95% Queue Length, Q₉₅ (veh) 0.1 0.1 0.1 0.2 0.0
Control Delay (s/veh) 31.5 12.4 23.1 11.2 13.0
Level of Service (LOS) D B C B B
Approach Delay (s/veh) 17.1 23.1 0.3 0.1
Approach LOS C C
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 2:44:36 PM
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and South Drive
Agency/Co. KLOA,Inc Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street South Access Drive
Analysis Year 2018 North/South Street Milwaukee Avenue
Time Analyzed Existing Evening Peak Hour Factor 0.97
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 1 1 0 1 0 0 1 2 0 0 1 2 1
Configuration LT R LTR L T TR L T R
Volume (veh/h) 71 0 74 2 0 0 0 44 1388 11 0 4 1513 24
Percent Heavy Vehicles (%) 0 0 0 0 0 0 0 2 0 0
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized No No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 7.5 6.5 6.9 7.5 6.5 6.9 4.1 4.1
Critical Headway (sec) 7.50 6.50 6.90 7.50 6.50 6.90 4.14 4.10
Base Follow-Up Headway (sec) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2
Follow-Up Headway (sec) 3.50 4.00 3.30 3.50 4.00 3.30 2.22 2.20
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 73 76 2 45 4
Capacity, c (veh/h) 83 342 74 411 476
v/c Ratio 0.88 0.22 0.03 0.11 0.01
95% Queue Length, Q₉₅ (veh) 4.6 0.8 0.1 0.4 0.0
Control Delay (s/veh) 154.6 18.5 54.9 14.8 12.6
Level of Service (LOS) F C F B B
Approach Delay (s/veh) 85.1 54.9 0.5 0.0
Approach LOS F F
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 2:45:19 PM
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and South Drive
Agency/Co. KLOA,Inc Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street South Access Drive
Analysis Year 2018 North/South Street Milwaukee Avenue
Time Analyzed Existing Sunday Peak Hour Factor 0.92
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 1 1 0 1 0 0 1 2 0 0 1 2 1
Configuration LT R LTR L T TR L T R
Volume (veh/h) 88 0 103 0 0 2 0 97 896 0 0 3 941 38
Percent Heavy Vehicles (%) 0 0 0 0 0 0 0 1 0 0
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized No No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 7.5 6.5 6.9 7.5 6.5 6.9 4.1 4.1
Critical Headway (sec) 7.50 6.50 6.90 7.50 6.50 6.90 4.12 4.10
Base Follow-Up Headway (sec) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2
Follow-Up Headway (sec) 3.50 4.00 3.30 3.50 4.00 3.30 2.21 2.20
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 96 112 2 105 3
Capacity, c (veh/h) 154 513 532 656 716
v/c Ratio 0.62 0.22 0.00 0.16 0.00
95% Queue Length, Q₉₅ (veh) 3.4 0.8 0.0 0.6 0.0
Control Delay (s/veh) 60.9 14.0 11.8 11.5 10.0
Level of Service (LOS) F B B B B
Approach Delay (s/veh) 35.6 11.8 1.1 0.0
Approach LOS E B
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 2:47:02 PM
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and North Drive
Agency/Co. KLOA,Inc. Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street North Access Drive
Analysis Year 2018 North/South Street Milwaukee Avenue
Time Analyzed Existing Morning Peak Hour Factor 0.96
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 0 1 0 0 0 0 0 2 0 0 0 2 0
Configuration R T T TR
Volume (veh/h) 1 1397 1043 3
Percent Heavy Vehicles (%) 0
Proportion Time Blocked
Percent Grade (%) 0
Right Turn Channelized No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 6.9
Critical Headway (sec) 6.90
Base Follow-Up Headway (sec) 3.3
Follow-Up Headway (sec) 3.30
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 1
Capacity, c (veh/h) 488
v/c Ratio 0.00
95% Queue Length, Q₉₅ (veh) 0.0
Control Delay (s/veh) 12.4
Level of Service (LOS) B
Approach Delay (s/veh) 12.4
Approach LOS B
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 2:43:17 PM
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and North Drive
Agency/Co. KLOA,Inc. Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street North Access Drive
Analysis Year 2018 North/South Street Milwaukee Avenue
Time Analyzed Existing Evening Peak Hour Factor 0.98
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 0 1 0 0 0 0 0 2 0 0 0 2 0
Configuration R T T TR
Volume (veh/h) 38 1469 1478 35
Percent Heavy Vehicles (%) 0
Proportion Time Blocked
Percent Grade (%) 0
Right Turn Channelized No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 6.9
Critical Headway (sec) 6.90
Base Follow-Up Headway (sec) 3.3
Follow-Up Headway (sec) 3.30
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 39
Capacity, c (veh/h) 347
v/c Ratio 0.11
95% Queue Length, Q₉₅ (veh) 0.4
Control Delay (s/veh) 16.7
Level of Service (LOS) C
Approach Delay (s/veh) 16.7
Approach LOS C
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 2:44:59 PM
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and North Drive
Agency/Co. KLOA,Inc. Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street North Access Drive
Analysis Year 2018 North/South Street Milwaukee Avenue
Time Analyzed Existing Sunday Peak Hour Factor 0.93
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 0 1 0 0 0 0 0 2 0 0 0 2 0
Configuration R T T TR
Volume (veh/h) 95 994 960 27
Percent Heavy Vehicles (%) 0
Proportion Time Blocked
Percent Grade (%) 0
Right Turn Channelized No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 6.9
Critical Headway (sec) 6.90
Base Follow-Up Headway (sec) 3.3
Follow-Up Headway (sec) 3.30
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 102
Capacity, c (veh/h) 498
v/c Ratio 0.21
95% Queue Length, Q₉₅ (veh) 0.8
Control Delay (s/veh) 14.1
Level of Service (LOS) B
Approach Delay (s/veh) 14.1
Approach LOS B
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 2:46:27 PM
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst ANB Intersection Milwaukee and South Drive
Agency/Co. KLOA,Inc Jurisdiction IDOT
Date Performed 8/20/2018 East/West Street South Access Drive
Analysis Year 2024 North/South Street Milwaukee Avenue
Time Analyzed Projected Morning Peak Hour Factor 0.93
Intersection Orientation North-South Analysis Time Period (hrs) 0.25
Project Description Glenview Presbyterian
Lanes
Major Street: North-South Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 10 11 12 7 8 9 1U 1 2 3 4U 4 5 6
Number of Lanes 0 1 1 0 1 0 0 1 2 0 0 1 2 1
Configuration LT R LTR L T TR L T R
Volume (veh/h) 3 0 9 1 0 3 0 40 1451 1 0 5 1036 60
Percent Heavy Vehicles (%) 0 0 0 0 0 0 0 0 0 0
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized No No
Median Type | Storage Left Only 1
Critical and Follow-up Headways
Base Critical Headway (sec) 7.5 6.5 6.9 7.5 6.5 6.9 4.1 4.1
Critical Headway (sec) 7.50 6.50 6.90 7.50 6.50 6.90 4.10 4.10
Base Follow-Up Headway (sec) 3.5 4.0 3.3 3.5 4.0 3.3 2.2 2.2
Follow-Up Headway (sec) 3.50 4.00 3.30 3.50 4.00 3.30 2.20 2.20
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 3 10 4 43 5
Capacity, c (veh/h) 129 479 186 600 429
v/c Ratio 0.03 0.02 0.02 0.07 0.01
95% Queue Length, Q₉₅ (veh) 0.1 0.1 0.1 0.2 0.0
Control Delay (s/veh) 33.7 12.7 24.8 11.5 13.5
Level of Service (LOS) D B C B B
Approach Delay (s/veh) 17.9 24.8 0.3 0.1
Approach LOS C C
Copyright © 2018 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.5 Generated: 8/20/2018 3:01:24 PM