• No results found

SWITCHYARD EQUIPMENTS, SWITCHING SCHMES & LAYOUTS

N/A
N/A
Protected

Academic year: 2021

Share "SWITCHYARD EQUIPMENTS, SWITCHING SCHMES & LAYOUTS"

Copied!
66
0
0

Loading.... (view fulltext now)

Full text

(1)

EHV SWITCHYARD

EQUIPMENTS, SWITCHING

SCHMES & LAYOUTS

(2)

Switchyard Type

Conventional Air Insulated Type.

Gas Insulated type.

(3)

Selection of Bus Switching Scheme

PRE-REQUISITES

1)System security

2)Operational flexibility

3)Simplicity of protection arrangements

4)Ability to limit short circuit levels (ease of

sectionalizing)

5)Maintenance – Its effect on system

security

6)Ease of extension

7)Total land area

8)cost

(4)

DESIGN GUIDELINES CONTD…

OPTIONS/ALTERNATIVES

1)Single sectionalised bus

2)Main and transfer bus

3)Sectionalised Main bus with transfer bus

4)Sectionalised double main and transfer

bus

5)Double Bus Scheme

6)Ring bus

7)One and a half breaker

(5)

CONTD…

DESIGN PRACTICES/PHYLOSOPHY

1) Consideration in Selection of Bus

Switching Scheme

2) Comparison of Schemes

a) Sectionalized main bus with transfer bus

(Scheme-I)

b) Sectionalized double main and

transfer bus (Scheme-II)

c) One and a half breaker (Scheme-

III)

(6)

DISCUSSIONS OF SCHEMES

SCHEME 1

(7)

SCHEMES CONTD…

SCHEME 2

(8)

SCHEMES CONTD…

SCHEME 3

(9)

System Security (Reliability

i) feeder fault

ii) Bus fault

iii) Redundancy in design

Main & Transfer

i) require

operation of one breaker

ii) supply would be interrupted until all the feeders are transferred to the healthy bus iii) No alternate path (Offline redundancy available)

Double Main & Transfer

i) require

operation of one breaker

ii) supply would be interrupted until all the feeders are transferred to the healthy bus iii) No alternate path (Offline redundancy available)

One & Half Breaker i)require operation of two breakers ii) continuity of supply is maintained because each circuit gets fed through two paths

iii) Alternate path is available

(Online redundancy available)

(10)

Operational Flexibility: Simplicity of Protection Arrangements Ability to limit Short Circuit Levels (Ease of Sectionalizing) Switching operation to take out the breaker from the bay more extensive Protection arrangement involves AC & DC switching . Sectionalising of bus bars or introduction of reactors in buses with a view to limit short circuit level is adoptable.

Switching operation to take out the breaker from the bay more extensive

Protection arrangement involves AC & DC switching & bus differential protection is complicated as it involves CT switching. Sectionalising of bus bars or introduction of reactors in buses with a view to limit short circuit level is adoptable.

A breaker can be taken out of service without the need for additional switching Protection

arrangement is simplified as no AC & DC switching involve and Bus differential protection is simple. Sectionalising of bus bars or introduction of reactors in buses with a view to limit short circuit level is adoptable.

(11)

Ease of extension

Total land area

Cost Switchyard shall be suitable for future extension without loss of feeders. This scheme is flexible for such future additions

This scheme occupy more or less the same land area as of the other two

schemes.

one breaker per feeder is required Switchyard shall be suitable for future extension without loss of feeders. This scheme is flexible for such future additions

This scheme occupy more or less the same land area as of the other two

schemes.

one breaker per feeder is required Switchyard shall be suitable for future extension without loss of feeders. This scheme is flexible for such future additions

This scheme occupy more or less the same land area as of the other two

schemes.

Three breaker per 2 feeder is

(12)

Switchyard layout

Objective:

Substation layout consists essentially in

arranging a number of switchgear components

in an orderly pattern governed by their

function and rules of spatial separation as

described in electrical single line diagram.

Pre-requisites:

1) single line diagram

2) general layout plan of power plant

3) orientation of line evacuation

4) control room building

(13)

LAYOUT CONTD…

Options / Alternatives

The layout will vary for the

following:

1)

Switching schemes

2)

Type of insulation - Air

Insulated/Gas Insulated.

(14)

LAYOUT CONTD…

Design Philosophy / Practice

1) Space around the switchyard

2) Switchyard location

3) Switchyard fencing.

4) Clearance.

i) phase to earth clearance

ii) phase to phase clearance

iii) section clearance

(15)

TABLE I: INSULATION LEVELS & CLEARANCE

REQUIREMENTS AT DIFFERENT VOLTAGE LEVELS

NOMINAL SYSTEM VOLTAGE KV

INSULATION LEVELS HIGHEST SYSTEM VOLTAGE KV

MINIMUM CLEARANCE GROUND CLEARANCE (MM) SECTIONAL CLEARANCE (MM) HEIGHT OF SUPPORTS (mm) LIGHTNING IMPULSE LEVEL (kVp) SWITCHING SURGE LEVEL (kVp) POWER FREQUENCY IMPULSE LEVEL (kVrms) BETWEEN PHASE AND EARTH (MM) BETWEEN PHASES (MM) 33 66 132 220 400 765 170 325 650 1050 1425 2100 -1050 1550 70 140 275 460 630 830 36 72.5 145 245 420 800 320 630 1300 2100 3500 6400 320 630 1300 2100 4000 9400 3700 4000 4600 5500 8000 --2800 3000 3500 4300 6500 10300 2500 2500 2500 2500 2500 2500

(16)

Clearance contd…

5) Equipment spacing

a) Ease of maintenance/removal of

equipment.

b) Equipment foundation & their

cable

trenches.

c)

Distance between LA and

equipment based on the protection reach of

LA.

d)

The spacings are generally kept in

order to achieve various clearances

(17)

Clearance contd…

6) Bus bars:

The bus bars of 400 kV switchyard are generally made up 4 “IPS aluminum tube or Quad Moose rated for 3000 A”.

The bus bars of 220/132kV switchyard are generally made up of 3 “IPS aluminum tube or quad/ twin moose conductor”. Bus bars are placed at right angles to the feeders for tapping the power.

7) Equipment Interconnection

8) Spacer spans and locations

9) Connection Level

10) Land & Road Layout

(18)

Clearance contd….

12) Control Room Layout

13) Lighting System

14) Cabling Philosophy

15) Gravel Filling

16) Earthing System

(19)

EVOLVING A SUBSTATION

LAYOUT

LAYING OUT A SUBSTATION INVOLVES STEP-BY-STEP

PROCEDURE. MOST IMPORTANT POINTS TO BE

CONSIDERED ARE BRIEFLY DESCRIBED BELOW:

THE IMPORTANT ELECTRICAL PARAMETERS ARE

ESTABLISHED BY THE SYSTEM DESIGN. THE MAIN

PARAMETERS ARE:

1) THE VOLTAGE AND BASIC INSULATION LEVEL OR

SWITCHING SURGE LEVEL., THE SITE AND CLIMATIC

CONDITIONS, THE METHOD OF CIRCUIT CONNECTION,

AND SWITCHING OVER-VOLTAGE CONDITIONS.

2)

THE BUS BAR SYSTEM DIAGRAM, THE NUMBER OF

CIRCUITS AND THEIR PURPOSE I.E. THE CONTROL

OF GENERATORS, TRANSFORMERS, FEEDERS,

ETC.

THE DIAGRAM SHOULD INCLUDE DETAILS

OF

EXTENSIONS

AND FUTURE CONVERSION TO A

DIFFERENT BUS BAR

SYSTEM, IF INTENDED.

(20)

EVOLVING A SUBSTATION

LAYOUT

1)

THE CONTINUOUS CURRENT RATING OF THE BUS BARS

AND CIRCUITS.

2)

THE SHORT CIRCUIT RATING OF BUS BARS AND

EQUIPMENTS.

3)

PARTICULARS OF REACTORS, NEUTRAL EARTHING

EQUIPMENT AND REACTING, Interconnecting Transformers

REQUIRED.

4)

METHOD OF CONNECTION OF CIRCUITS, WHETHER BY

OVERHEAD LINES OR BY CABLES.

5)

DETAILS OF LIGHTNING PROTECTION EQUIPMENT.

6)

DETAILS OF PROTECTIVE EQUIPMENT, DETERMINING THE

INSTRUMENT TRANSFORMERS REQUIREMENTS, CARRIER

CURRENT EQUIPMENT ETC.

(21)

EVOLVING A SUBSTATION

LAYOUT

THE EXTENT TO WHICH CIRCUIT AND BUSBAR OUTAGES FOR MAINTENANCE WILL BE POSSIBLE.

SOME PARAMETERS WHICH INFLUENCE THE FORM OF THE LAYOUT ARE DETERMINED BY THE LOCAL CONDITIONS. THESE ARE:

1) THE AVAILABLE LAND AREA, SITE AND CLIMATE

CONDITIONS, PLANNING AUTHORITY REQUIREMENTS AND AESTHETIC CONSIDERATIONS DETERMINE THE TYPE OF SUBSTATION.

2) THE DIRECTION OF OVERHEAD LINE ENTIRES POSITION

AVAILABLE FOR TERMINAL TOWERS, LOCATION OF TRANSFORMERS AND REACTORS, ETC.

3) THE AVAILABILITY OF MATERIALS AND THE TRANSPORT AND

ACCESS FACILITIES.

4) THE CAPABILITY AND SKILL OF THE MAINTENANCE STAFF

DETERMINES THE IMPORTANCE OF CLARITY OF LAYOUT AND SIMPLICITY OF MAINTENANCE ZONING.

(22)

PREPARATION OF BASIC

LAYOUT

WHILE MEETING ALL THE NEEDS ESTABLISHED THE

FOLLOWING IDEALS SHOULD BE AIMED AT IN MAKING THE

BASIC CIRCUIT LAYOUT.

MINIMUM GROUND AREA

MINIMUM QUANTITIES OF CONDUCTOR, JOINTS AND

STRUCTURE

MINIMUM NUMBER OF INDEPENDENT INSULATORS,

ESPECIALLY IN THE BUS BAR ZONE.

AFTER HAVING DETERMINED THE ELECTRICAL CLEARANCE BE

USED A ROUGH CIRCUIT LAYOUT IS MADE. SEVERAL

POSSIBLE ALTERNATIVES ARE PREPARED FROM WHICH THE

MOST SUITABLE ONE WILL BE SELECTED. SOME VARIATION

IS NEEDED, TO MEET THE REQUIREMENTS OF DIFFERENT

TYPES OF CIRCUIT.

IT IS ALSO NECESSARY TO CALCULATE SHORT CIRCUIT AND

ATMOSPHERIC FORCES TO DETERMINE THE STRESSES IN

CONDUCTORS, INSULATORS AND STRUCTURES. THESE HELD

IN DECIDING THE MOST OPTIMUM DIMENSIONS.

(23)
(24)
(25)
(26)
(27)

PURPOSE OF EARTHING

THE OBJECT OF EARTHING IS TO MAINTAIN A

LOW POTENTIAL ON ANY OBJECT.

THE PURPOSE OF A EARTHING SYSTEM IN A

SUBSTATION AREA IS TO

LIMIT THE POTENTIAL

GRADIENT WITHIN AND IMMEDIATELY OUTSIDE

THE AREA

IS A VALUE, SAFE FOR THE WORKING

PERSONNEL. SAFETY IS TO BE ENSURED UNDER

NORMAL AS WELL AS ABNORMAL OPERATING

(28)

REQUIREMENTS OF A GOOD

EARTHING SYSTEM

FOLLOWING BASIC REQUIREMENTS ARE TO BE SATISFIED SO AS TO

ENSURE A PROPER AND SOUND EARTHING SYSTEM.

1)

THE EARTH RESISTANCE FOR THE SWITCHYARD AREA

SHOULD BE LOWER THAN A CERTAIN LIMITING VALUE

“RA” IN ORDER TO ENSURE THAT A SAFE POTENTIAL

GRADIENT IS MAINTAINED IN THE SWITCHYARD AREA

AND PROTECTIVE RELAY EQUIPMENT OPERATE

SATISFACTORILY. FOR MAJOR SWITCHYARDS AND

SUBSTATIONS IN INDIA, THIS LIMITING VALUE OF EARTH

RESISTANCE (RA) IS TAKEN TO BE LESS THAN 0.5 OHM.

2)

THE GROUNDING CONDUCTOR MATERIAL SHOULD BE

CAPABLE OF CARRYING THE MAXIMUM EARTH FAULT

CURRENT WITHOUT-OVERHEATING AND MECHANICAL

DAMAGE. THE MAXIMUM FAULT LEVEL IN THE 400 KV

SYSTEM HAS BEEN ESTIMATED TO BE 40 KA AND THIS

VALUE OF FAULT CURRENT TO USED IS THE DESIGN OF

EARTH MAT FOR THE 400 KV SUBSTATION.

(29)

REQUIREMENTS OF A GOOD

EARTHING SYSTEM

ALL METALLIC OBJECTS WHICH DO NOT CARRY

CURRENT AND INSTALLED THE SUBSTATION SUCH

AS STRUCTURES, PARTS OF ELECTRICAL

EQUIPMENTS, FENCES, ARMOURING AND SHEATHS

OF THE LOW VOLTAGE POWER AND CONTROL

CABLES SHOULD BE CONNECTED TO THE

EARTHING ELECTRODE SYSTEM.

.

THE DESIGN OF THE GROUND CONDUCTOR

SHOULD TAKE CARE OF THE EFFECT OF

CORROSION FOR THE TOTAL LIFE SPAN OF THE

PLANT.

(30)

Switchyard Equipments.

Circuit Breaker.

Disconnectors (Isolators)

Current Transformers.

Capacitor Voltage Transformers

(CVT).

Lightning Arrestors.

Post Insulators.

(31)

General Parameters

Dielectric Parameters .(IEC 694)

- Power Frequency Voltage.

- Lightning Impulse Voltage.

- Switching Impulse Voltage.

- Corona Extinction Voltage.

- RIV Level.

(32)

General Parameters (Contd.)

Rated Current.

Short Time Current.

(33)

400kV Equipments

a.

Rated voltage

420 kV

b.

Rated frequency

50 Hz

c.

Rated short time withstand

current capacity

40 kA rms for one (1) second

d.

Insulation levels for 420kV Circuit

breakers and Disconnecting

Switches

e.

i) Rated one minute power

Frequency withstand

voltage

a) 520 kV rms between live

terminals and earth.

b) 610 kV rms across isolating

distance.

ii) Rated lightning impulse

withstand voltage

a) +/ - 1425 kVp between live terminals

and earth.

b) +/- 1425 kVp impulse on one

terminal and 240 kVp po

wer

frequency of opposite polarity on

other terminal (across isolating

distance).

iii) Rated switching impulse

withstand voltage

a) +/- 1050 kVp between live

terminals and earth.

b) +/- 900 kVp impulse on one

terminal and 345 kVp power

frequency of opposite p

olarity on

other terminal (across isolating

distance).

f.

Max. Radio interference voltage

at 266kVrms

1000 micro volts for frequency

between 0.5 Mhz and 2.0 Mhz for all

equipment. However, for insulator

strings the measurement would be

at 305 kV .

(34)

Circuit Breakers Type (IEC: 62271-100)

MOCB.

ABCB.

SF6

Rated operating duty cycle- O-0.3 sec-CO-3

min.-CO

Operating mechanism

Total Break Time

(35)

Disconnectors

HCB Type.

Double Break Type

.

Pantograph type.

Vertical Break type.

Provision of Earth Switches.

Motor / manual operated.

(36)

Current Transformer ( IEC 60044, IS

2705)

Dead tank/Live tank type.

Bar Primary type.

Ring Type.

No. of Cores.

Ratio.

Accuracy.

rated primary current

Rated burden for metering

Knee Point voltage

(37)

Capacitor Voltage Transformer (IEC

60044, IS 3156)

Capacitance.

Voltage Ratio.

No. Of Cores.

Accuracy.

Output Burden

(38)

Lightning Arrestor ( IEC 60099)

Gap Type / Gapless Type.

Voltage Rating.

Energy Capability.

Monitoring.

Location.

(39)

Post Insulators

Voltage Rating.

Cantilever Strength.

Fixing Details.

(40)

Wave Trap (IEC 60353)

Rated Inductance(0.5/1.0 mH).

Rated current.

Band Width.

(41)

SWITCHYARD AUXILIARY SYSTEMS

CONTROL ROOM

HVAC FOR CONTROL ROOM

A RELIABLE 415V AC SUPPLY ( LT SWGR)

220 V & 48 V DC SUPPLY( BATTERY & BATTERY

CHARGER)

POWER & CONTROL CABLE

LIGHTING ( Yard lighting & indoor lighting of control

room)

Other items-Clamps, connectors , Insulator strings , BMK

(42)

192 69 ~10% 400kV GIS 275kV GIS Trfr 1 Trfr 2 Trfr 3 Trfr 4 SVC Trfrs 400kV AIS 275kV AIS

COMPARASON BETWEEN AIS AND GIS SUBSTATION

FOOTPRINT FOR HECTOR

(43)
(44)
(45)

Conductor Phase Spacing

(46)
(47)

9,81.m

i

f

s

SAG DUE TO CONDUCTOR

f

s

= 9,81.mi.Lc2

8.T

f

s

= maximum conductor sag (m)

m

i

= mass of conductor (kg/m)

L

c

= conductor span length (m)

T = tension per conductor (N)

T

(48)
(49)
(50)
(51)

M

M

M

Attraction

Repulsion

CANTILEVER FORCES DUE TO FAULT CURRENT

COMBINATION SUPPORT STRUCTURE FOR 3 PHASES

(52)

F

S

TUBE

(53)
(54)

Upgradation of transmission voltage

from 400kV AC to 765kV AC.

Presently the highest AC Transmission voltage is 400kV only.

NTPC is fully geared up for implementing next AC voltage of

765kV.

Advantages:

Step up from generation voltage to 765kV.

High Capacity Transmission to the order of 2500MW per line

with lower right of way requirement.

765kV Transmission system is techno economically better

option whenever power transmission system requires multi

point tapping at various location for catering the load

requirement of high growth area.

765kV system offers low transmission losses, resulting in

higher utilisation of generating capacity and optimises the

resource required for capacity addition.

(55)

765kV Major Parameters

Highest system voltage : 800 kV rms

Lightning Impulse voltage : ± 2100 kVp Switching impulse voltage : ± 1550 kVp

Power frequency withstand : 830kV(rms) for 1 min. (rms) :

Max. fault level (1 sec.) : 40 kA

Minimum creepage distance : 20000 mm

Max. Radio Interference Voltage : 2500 micro volts.level at 508kV (rms).

Corona extinction voltage : 508kV (rms minimum)Phase to earth clearance : 4900 mm Conductor to Structure

: 6400 mm Rod to StructurePhase to phase clearance : 7600 mm Conductor to Conductor

: 9400 mm Rod to ConductorSection clearance : 10300 mm

Average electric field at 1.8 m from ground 10kV/mAverage magnetic field 500 micro tesla

(56)
(57)
(58)
(59)

ADOPTION OF CONTROLLED SWITCHING OF TRANSFORMER AND

REACTORS.

Switching of transformer, shunt reactors, capacitors and uncharged overhead

lines is normally a 'three-phase' process, where all three phases are switched

simultaneously. The actual circuit closing or opening instant is left up to

chance. This results in high inrush currents or switching surges causing undue

repercussions to switchgear equipment and networks system. For overcoming

this the switching in and out is done at desired point on wave so that the

(60)
(61)
(62)
(63)
(64)
(65)
(66)

References

Related documents

2005 Retention Survey for Graduates of General Full-time Retraining Courses of the Employees Retraining Board Empolyees Retraining Board (ERB), HKSAR. 2005 Asian Private

On behalf of the Healthcare Billing and Management Association’s (HBMA) over 750 member companies, we are pleased to submit our comments on the Office of Civil Rights Notice

To maximize service life of all such transformers in its network and to increase operational reliability vis-à-vis MTBF (mean time between failures), the practices followed in CESC

In order to identify the best methods to protect an online identity from online threats, it is essential to look at international systems for single sign-on

The Association formalised itself as ‘The University of Wales Association for the Study of Welsh Writing in English’ and then (as colleagues from Trinity College Carmarthen and

Untuk mencapai objektif ini dua persoalan perlu dijawab; apakah ciri personaliti guru yang diberi keutamaan oleh pelajar dalam pengajaran dan pembelajaran

I argued that the Greenwood-Hercowitz-Krusell (GHK) model is a special case of a two-sector, neoclassical growth model with differing rates of technical progress in the two

We present a framework, METEOR-S Web service Annotation Framework (MWSAF), to semi- automatically annotate WSDL descriptions of the services with relevant ontologies.. MWSAF is a