Method Statement
FOR
Soil Investigation
Infratech ASTM CO., LTD.
1
TABLE OF CONTENTS
Chapter Title
Page
Table of Contents………..1
List of Appendix... 2
List of Table... 2
List of Figures... 2
1.0
INTRODUCTION AND BACK GROUND OF THE PROJECT ... 3
2.0
SCOPE OF WORK ... 3
3.0
FIELD INVESTIGATION AND BOUNDARY SURVEY ……….………….………3
3.1 General ... 3
3.2 Boring and Sampling ……….………4
3.4 Groundwater
Measurement... ...4
3.5 Field permeability Test ……….……….4
3.6 Soil Resistivity Test ……….…..5
3.7 Test Pit……….5
3.8 Down Hole Seismic Test…… ……….5
3.9 Dutch Cone Penetration Test ...………..5
3.10 Site Boundary Survey
4.0 LABORATORY TEST ………..6
4.1
Unconfined Compression test ……….…………
6
4.2 Atterberg
Limits
……….…6
4.3
Particle Size Analysis ..……….…
6
4.4
Unit Weight and Water Content Determination……….…7
4.5 Oedometer test ………..
7
4.6 Compaction Test and CBR Test ………7
4.7 Water Analysis ……….7
5.0 REPORT ………....8
Figures
Appendix
Tables
Infratech ASTM CO., LTD.
2
List of Appendix
Appendix A Sample of Soil Boring Log data sheet
Appendix B Sample of Summary of general laboratory test data sheet
Appendix C Sample of Pile calculation data sheet
Appendix D Sample of Shallow Foundation Bearing Capacity Analysis
Appendix E Sample of Prediction of long term settlement calculation
List of Table
Table 1 Sample of Unconfined Compression Test data sheet
Table 2 Sample of Atterberg Limit Tes
t data sheet
Table 3 Sample of Sieve Analysis Tes
t data sheet
Table 4 Sample of Unit Weight data sheet
Table 5 Sample of Water content Tes
t data sheet
Table 6 Sample of Consolidation Tes
t data sheet
Table 7 Sample of Field Permeability test
data sheet
Table 8 Sample of soil resistivity test
data sheet
Table 9 Sample of down hole seismic test
data sheet
Table 10 Sample of Dutch cone penetration test
data sheet
Table 11 Sample of compaction and CBR test
data sheet
Infratech ASTM CO., LTD.
3
1.0
INTRODUCTION AND BACK GROUND OF THE PROJECT
This method statement will summarizes the procedure on the subsoil investigation works and
boundary survey to be conducted by Infratech ASTM Company Limited for the
construction………
………..
2.0
SCOPE OF WORK
The scope of work for the geotechnical consultancy services of the project are summarized as
follows:
•
Soil boring, field testing and carrying out sufficient in-situ testing and sampling.
•
Laboratory testing of obtained samples to determine the properties of the subsoil.
•
Determination of geotechnical parameters required for foundation analyses.
•
Carrying out engineering analyses for foundation design.
3.0 FIELD
INVESTIGATION
3.1 General
The investigation program included drilling boreholes and collecting soil samples at desired
intervals for subsequent observation and laboratory testing.
The investigation program will consist of soil boring and sampling at desired intervals for
subsequent observation and laboratory testing to determine the capacity of pile foundation economically
and safely.
3.2
Boring and Sampling
The boreholes will be made by the rotary drilling machine.
Undisturbed sample will be taken in the soft and medium clay at 1.0, 1.5, 2.0 and 3.0 m depths
and at 1.5 m intervals
thereafter using a thin-walled sampler with dimensions conforming to standard
sampling tubes specification (ASTM D 1587).
Disturbed samples for very stiff clay to hard clay layer will be collected during Standard
Penetration Testing at 1.5 m intervals. (ASTM D 1586)
The borings shall be drilled vertically through soil approximately 30 meters deep or stop in firm
layer when SPT N-value is greater than 50 blows/ft.
Accuracy of bore hole position will be not more than 2.0 m. in horizontal direction and 0.20 in
vertical direction.
3.3
Standard Penetration Testing
Standard Penetration Tests (SPT) will be carried out to provide an indication of the density
and/or consistency of the ground and to obtain disturbed samples for visual inspection and laboratory
testing and classification. The results of the tests will be given on the boring logs in Appendix A and will
Infratech ASTM CO., LTD.
4
be expressed as an N value. The N value is defined as the blow-count for 12” (300mm) penetration
recorded after the seating drive of 15 cm. In the case of premature refusal conditions, the number of
blows for a recorded penetration (including the seating drive) is noted.
In SPT testing, the rope-and-pulley (R-P) method will be used. This consisted of a hollow
cylindrical mass sliding over a steel rod. It is operated by lifting the mass with a rope over a cat head. At
the instant the mass reached the required height (760 mm), the mass will be released manually driving
the split spoon into the soil. Disturbed samples collected from the split-spoon sampler during Standard
Penetration Test will be visually inspected before storing in a polyethylene bag for laboratory testing. A
graphical representation of the changes in the soil strata, water levels and SPT N values will be given in
the boring logs.
3.4 Groundwater
Measurement
Groundwater is one element that affects in the stability and foundation analyses. The
groundwater level was measured 24 hours after completion of the borehole.
However, the low permeability of the soil will mean that the water level in the borehole is
controlled more by drilling fluid rather than by the ground water itself. Significant fluctuations in the
location of ground water table should be anticipated throughout the year, depending upon the amount of
precipitation, evaporation and surface runoff.
3.5
Field Permeability Test
Permeability test of soil in the field will be performed at the depth of 2,4,6,8 and 10 m. by
constant head method.
3.6
Soil Resistity Test (Provisional)
The purpose of this test is to investigate for the need of cathode protection and to have data
necessary for the design of an adequate grounding system.
The soil Resistivity measurement shall be carried out in accordance with IEEE 81 standard “
Guide for Measuring Earth Resistivity, Ground Impedance and Earth Surface Potentials of a Ground
System “. The measurement shall be done using Wenner Four Points Method with equal test rods
spacing.
The area to be measured shall be the power block area of power plant, terminal substation and
switchyard. Before carrying out the measurement, the rectangular grid shall be drawn for the testing
areas with mesh spacing at approximately 5-10 m. The measurement shall be made at every intersection
point of grid lines. The measurement at any point shall be done for two directions, one from the
measured point along the direction from east to west and another shall be from the measured point
along the direction from north to south. The measurement at any point shall consist of the measured data
at the varying space between test rods for the following distance; 0.5, 1.0, 2.0, 3.0, 4.0, 5.0 m. For each
area of measurement, the results of measurement shall be shown in the table for each point of
measurement for each direction and every designated space of measurement. The measured resistivity
data shall be averaged for each of the same spacing of measured data. The overall averaged resistivity
of each area shall also be reported.
3.7
Test Pit (Provisional)
Test pit shall be preformed 3 points of 1x1m size 3 m deep, by mean of hand excavation. Bulk
sample taken from the test pits of not less than 50 kg each shall be sent to test at laboratory for
compaction and CBR test.
Infratech ASTM CO., LTD.
5
3.8
Seismic down hole test (Provisional)
The down hole Test is a method which determines soil stiffness properties by analyzing direct
compression and shear waves along a borehole.
Seismic down hole test shall be performed at 1.0 meter intervals to the depth of 30.0 m. or to the
same depth of soil bore hole (where SPT N-value is greater than 50 blows/ft)
The test shall be intended to collect shear wave velocity information that will be used in dynamic
analysis. The testing location shall be located in the power block area and close to expected location of
Steam Turbine foundation.
3.9
Dutch Cone Penetration Test (Provisional)
Dutch cone penetration test shall be preformed depth 30m. or to the depth when the total
resistant of the cone penetrometer reach 4.0 tons.
The test shall be carried out in accordance with the ASTM D 3441.
The cone penetration test shall be consists of pushing into the soil, at a sufficiently slow rate, a
series of cylindrical rods with a conical tip at the base for measuring the cone resistance and friction
resistance every 20 cm intervals.
4.0 LABORATORY
TESTING
Geotechnical laboratory tests will be performed on the soil samples to classify soil and to
determine their engineering characteristics. All laboratory tests will be conducted in accordance with
ASTM Standards. The soils will be also classified based on the Unified Soil Classification System
(USCS).
4.1
Unconfined Compression Tests
Unconfined compression test will be conducted in accordance with ASTM D2166. The tests will
be performed by compressing cylindrical samples to failure. Failure generally occurs when the greatest
ratio of shear stress to shear strength occurs. The cohesion (c) of the sample is taken as half the
unconfined compressive strength.
Sample of test results and data sheet has been shown in Table 1
4.2 Atterberg
Limits
Atterberg limits will be determined (ASTM D 4318) on representative soil samples of cohesive
soils. The Atterberg limits refer to arbitrarily defined boundaries between the liquid and plastic states,
and between the plastic and brittle states of grained soils, expressed as water content, in percentage.
The liquid limit is the water content at which a part of soil placed in a standard cup, cut by a standard
grooving tool, will flow together at the base of the groove when the cup is subjected to 25 standard
shocks. The one-point liquid limit test is usually carried out and distilled water may be added during soil
mixing to achieve a desired consistency.
Infratech ASTM CO., LTD.
6
4.3
Particle Size Analysis
Particle size analysis will be performed by means of sieving (ASTM D 422). For oven-dry
materials, sieving is carried out for particles that are being retained on a 0.063 mm sieve. In sieve
analysis, the mass of soil retained on each sieve is determined and expressed as a percentage of the
total mass of the sample. The particle size is plotted on a logarithmic scale so that two soils having the
same degree of uniformity are represented by curves of the distribution plot. In Hydrometer analysis is
based on the principle of sedimentation of soil grains in water. When a soil specimen is dispersed in
water, the particles settle at different velocities, depending on their shape, size, and weight. For
simplicity, it is assumed that soil particles are spheres and the velocity of soil particles can be express by
Stokes’ law.
Sample of test results and data sheet has been shown in Table 3
4.4
Unit Weight and Water Content Determination
As a routine laboratory test, unit weights of soils will be determined based on the mass of soil in
a standard volume steel cylinder with cutting edge. The unit weight refers to the unit weight of the soil at
the sampled water content. The dry unit weight is determined from the mass and the water content of the
specimen.
Water content (ASTM D 2216)is determined by oven-drying a moist/wet soil at a constant
temperature of 105 °C for 18 - 24 hours. The difference in mass before and after drying is used as the
mass of water in the specimen, while the mass of remaining material is used as the mass of solid
particles. The ratio between the mass of water and the mass of solid particles is the water content of the
soil material
Sample of test results and data sheet has been shown in Table 4 and Table 5
4.5
Oedometer Test /Consolidation test (Provisional)
In case of soft clay layer has been encountered, 1 undisturbed sample will be collected from mid
layer of soft clay for Oedometer test.
Oedometer tests will be conducted (ASTM D 2435) to determine the rate and magnitude of
consolidation of a laterally restrained soil specimen which is axially loaded in increments of constant
stress until the excess pore water pressures have dissipated for each increment. Each load increment is
maintained for at least 24 hours. The test is generally carried out on undisturbed cohesive specimens.
Sample of test results and data sheet has been shown in Table 6
4.6
Compaction Test and CBR Test (Provisional)
Bulk sample taken from the test pits of not less than 20 kg each shall be sent to test at laboratory
for compaction and CBR test conformed to ASTM D1883.
4.7
Ground Water Analysis
The bored hole shall be drilled at depth approximate 3 m. without bentonite and leave it 7 days
for collecting underground water to do water analysis test.
Infratech ASTM CO., LTD.
7
5.0 REPORT
Confirmed Preliminary Report findings along with the remainder of test results to be
Submitted in a Final Report.
The Final Report shall include but not limited to:
• Results of all of the above mentioned tests.
• Result of graph to show Cumulative Ultimate Skin Friction & Ultimate End
Bearing Capacity & Depth for driven pile for each borehole.
• Recommendations for :
1. Bearing capacity for shallow foundation.
2. Pile capacity resistance to compression and tension.
3. Settlement for shallow foundation.
• Underground water level and borehole elevation.
• Licensed engineer sign up responsible for the report
APPENDIX A
SOIL BORING LOG
Sample Sheet
ASTM TESTING CO., LTD.
BORING LOG
Borehole No. BH-08
BH-0
PROJECT:
SIAM ENERGY POWER PLANT
Page 1 of 1
24
LOCATION:
BANGKLA CHACHOENGSAO
Depth (m) Graphic Log Method Sample N
o . Recovery
SOIL DESCRIPTION
0 Borehole Elevation = 1.99 m. 0.80 m. Top soilST 1
2.00 m.ST 2
Brown,moist to saturated, medium plasticity, very soft to soft, Sandy Clay. 5
ST 3
(CL)ST 4
6.50 m.SS 1
Brown, moist, high plasticity, stiff, Sandy Clay.(CH)
SS 2
9.45 m.10
SS 3
Brown, moist, medium plasticity, very stiff to hard, Sandy Clay. (CL)SS 4
12.45 m.SS 5
15
SS 6
Brown, moist, high plasticity, stiff to very stiff,Sandy Clay.
SS 7
(CH) trace gravel.SS 8
20SS 9
19.95 m.SS 10
Brown, moist, medium plasticity, hard, Sandy Clay.
SS 11
(CL)SS 12
24.45 m.End of Boring = 24.45 m.
Start date:
8-มิ.ย.-09
Finished date:
8-มิ.ย.-09
Su (UC)Borehole Depth:
24.45 m.
Su (FV)Observed GWL.
-1.50 m.
Total Unit Weight Su (PP)Drilling Foreman:
Thawatchai
SPT, NABBREVIATIONS:
(Blow/30 cm.)ST = Undisturbed Sample LL = Liquid Limit gt = Total Unit Weight SS = Split Spoon Sample PL = Plastic Limit SPT = Standard Penetration Test
1.01 1.3 2.14 0.54 9 10 22 31 76 14 58 22 17 15 16 1.49 1.6 1.69 1.7 1.81 1.96 1.85 1.89 1.96 1.93
PL
LL
ASTM
W
n 40 80 1.0 2.0 2 4 6 8 10 20 40 60 80 100 SPT-N (Blow/30cm.) Atterberg Limitsγ
t (t/m3) Su (t/m2)APPENDIX B
SUMMARY OF GENERAL LABORATORY TEST
Sample sheet
PROJECT:
BORE HOLE NO.
BH - 8
LOCATION:
Water Level :
-1.50 M.
USCS
Wn,at
UC Test
γ
wet,
N
sptSample No
From
To
Soil
Received
S
Ugm./cc.
LL
PL
PI
# 4
# 10
# 40
# 200
(Blow /
Soil Description
group
(%)
(T / m
2)
(%)
(%)
(%)
Foot)
-
0.00
1.50
Top Soil
ST - 1
1.50
2.00
88.34
1.01
1.49
97.74
93.07
86.41
75.43
ST - 2
3.00
3.50
61.41
1.30
1.60
ST - 3
4.50
5.00
CL
55.20
2.14
1.69
40.05
24.33
15.72
100.00
99.77
98.51
94.33
ST - 4
6.00
6.50
54.24
0.54
1.70
Sandy Clay (CL,CH).
SS - 1
7.50
7.95
CH
31.07
1.81
56.08
23.51
32.56
99.04
98.92
98.11
91.63
9
SS - 2
9.00
9.45
10
SS - 3
10.50
10.95
CL
22.04
1.96
48.11
21.29
26.82
100.00
99.85
99.29
95.86
22
SS - 4
12.00
12.45
1.85
31
SS - 5
13.50
13.95
1.89
14
SS - 6
15.00
15.45
1.96
16
SS - 7
16.50
16.95
CH
32.88
60.30
28.53
31.77
93.45
91.79
89.23
85.09
15
Sandy Clay (CH)
SS - 8
18.00
18.45
17
trace gravel.
SS - 9
19.50
19.95
22
SS - 10
21.00
21.45
58
SS - 11
22.50
22.95
CL
17.82
41.11
18.58
22.54
99.70
99.30
96.57
82.52
76
Sandy Clay (CL).
SS - 12
24.00
24.45
1.93
89
ASTM TESTING CO.,LTD.
SUMMARY OF TEST RESULTS
END OF BORING AT 24.45 M.
Atterberg Limits
Gradation % Passing
Depth. (m.)
Appendix C
Pile Calculation
Appendix B 1 - BH-1
สรุปการคํานวณกําลังรับน้ําหนักของดิน
(Estimation of Soil Bearing Capacity)
Saraburi A Cogeneration Co.,ltd.
Saraburi
PROJECT :
Saraburi A Cogeneration Co.,ltd.
LOCATION :
Saraburi
BOREHOLE NO.:
BH-1
SOIL BEARING CAPACITY VS DEPTH FOR SHALLOW FOUNDATION
0
1
2
3
4
5
0
10
20
30
40
50
60
70
80
90 100
Ultimate End Bearing(t/sq.m.)
SHALLOW FOUNDATION SOIL BEARING CAPACITY
Project:
Saraburi A Cogeneration Co.,ltd.
Location:
Saraburi
Borehole No.:
BH-1
Factor of safety :
3.00
Allowable settlement, S
e25.0
mm.
Depth of water =
1.53
m
below ground level
Depth
Soil Description
SPT (N-value)
σ
vo,baseφ
USCS S=Sand
Field
Correct Design
B
L
Depth
q
allD
fC=Clay
t/m
2kN/m
2N
FN
cor.N
designt/m
2t/m
2kN/m
2t/m
2kN/m
2 om.
m.
q
u(kPa) q
all(kPa) q
all(t/m
2)
F
dq
all(kPa) q
all(t/m
2)
(m)
(t/m
2)
0.0
-
-
0.00
0.00
0
0
0
0.00
0.00
0.00
-
-
-
-
-
-
-
-
-
-
-
-
-1.0
CL
C
2.0
19.6
9
20
13
2.00
2.00
19.62
7.89
77.39
1.0
1.0
572.8
190.9
19.5
1.0
19.5
2.0
CL
C
2.0
19.6
12
20
15
4.00
3.53
34.63
9.15
89.80
1.0
1.0
775.4
258.5
26.3
2.0
26.3
3.0
CL
C
2.0
19.6
15
22
17
6.00
4.53
44.44
10.83
106.28
1.0
1.0
1048.8
349.6
35.6
3.0
35.6
4.0
CL
C
2.1
20.2
20
26
22
8.06
5.59
54.84
13.83
135.72
1.0
1.0
1506.8
502.3
51.2
4.0
51.2
Remark:
1) q
all= Net allowable soil bearing capacity
2) Corected Standard Penetration, N
correct= N
F*sqrt(95.6/σ'
v), After Liao and Whitman (1986)
3) The net ultimate bearing capacity for clayey soil (
φ
= 0 condition), q
net(u)= 5.14c
u(1+0.2D
f/B)(1+0.2B/L) , After Skempton (1951)
4) The net ultimate bearing capacity for sand, After Bowles (1977)
q
net(u)= 19.16N
corF
d(S
e/25.4)
(for B < 1.22 m.)
q
net(u)= 11.98N
cor[(3.28B+1)/3.28B]
2
F
d(S
e/25.4)
(for B > 1.22 m.)
SUMMARY
NET SOIL BEARING CAPACITY
CLAY
SAND
Appendix B 2 - BH-1
สรุปการคํานวณกําลังรับน้ําหนักปลอดภัยของเสาเข็มและความยาว
(Recommendation for Pile Capacity and length)
Saraburi A Cogeneration Co.,ltd.
Saraburi
RECOMMENDED PILE LENGTH AND CAPACITY FOR FOR SINGLE PILE
Project: Saraburi A Cogeneration Co.,ltd.
Location: Saraburi
Borehole No.:
BH-1
Soil Capacity F.S. =2.5(Tons)
Pile Structural
Pile Type
Pile Size
Length(m.)
Compression
Tension
Lateral
Capacity(Tons)
REMARK
Driven Pile
0.25x0.25
12.0
39
32
0.2
40
Can not be installed when SPT>=Limit
Driven Pile
0.30x0.30
12.0
48
38
0.3
55
Can not be installed when SPT>=Limit
Driven Pile
0.35x0.35
12.0
58
45
0.5
70
Can not be installed when SPT>=Limit
Driven Pile
0.40x0.40
12.0
68
51
0.6
80
Can not be installed when SPT>=Limit
Bored Pile
Dia.0.35
10.0
44
35
0.3
48
Bored Pile
Dia.0.40
11.5
61
49
0.4
63
Bored Pile
Dia.0.50
13.0
94
74
0.5
98
Bored Pile
Dia.0.60
14.5
140
105
0.7
141
RECOMMENDED ALLOWABLE LOAD FOR SINGLE SQUARE DRIVEN PILE
Project:
Saraburi A Cogeneration Co.,ltd.
Location:
Saraburi
Borehole No.:
BH-1
Factor of safety :
2.50
Depth of water :
1.53
m. below ground level
25 x 25 cm. Square Driven Pile
30 x 30 cm. Square Driven Pile
35 x 35 cm. Square Driven Pile
40 x 40 cm. Square Driven Pile
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
4.0
19.4
8.3
0.5
10.9
23.3
11.9
0.6
13.8
27.2
16.2
0.9
17.0
31.1
21.2
1.2
20.4
5.0
25.5
10.0
0.6
14.0
30.6
14.5
0.9
17.7
35.8
19.7
1.2
21.7
40.9
25.7
1.5
26.0
7.5
42.0
11.6
1.0
21.1
50.4
16.7
1.4
26.3
58.9
22.7
1.9
31.9
67.3
29.6
2.5
37.8
9.0
54.5
16.3
1.2
27.9
65.5
23.5
1.7
34.9
76.4
32.0
2.4
42.4
87.3
41.8
3.1
50.4
10.5
66.7
15.9
1.4
32.4
80.0
22.9
2.1
40.3
93.4
31.1
2.8
48.7
106.7
40.6
3.6
57.5
12.0
79.9
18.1
1.7
38.6
95.9
26.1
2.4
47.9
111.9
35.6
3.2
57.7
127.9
46.4
4.2
68.0
13.5
94.9
21.4
1.9
45.8
113.9
30.8
2.7
56.8
132.9
41.9
3.7
68.4
151.9
54.7
4.8
80.7
15.0
112.2
24.5
2.1
53.8
134.6
35.3
3.0
66.7
157.0
48.1
4.1
80.4
179.4
62.8
5.4
94.7
REMARK :
1. Negative skin friction is not consider in the calculation
2. Pile cut-off elevation -1.00 m. below ground level
Depth
RECOMMENDED ALLOWABLE LOAD FOR SINGLE BORED PILE
Project:
Saraburi A Cogeneration Co.,ltd.
Location:
Saraburi
Borehole No.:
BH-1
Factor of safety :
2.50
Depth of water :
1.53
m. below ground level
35 cm. Dia. Bored Pile
40 cm. Dia. Bored Pile
50 cm. Dia. Bored Pile
60 cm. Dia. Bored Pile
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
Cumm.Skin
Friction
End
Bearing
Pile
Weight
Allowable
Load
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
(tons)
4.0
31.2
12.8
0.7
17.3
35.7
16.7
0.9
20.6
44.6
26.0
1.4
27.7
53.6
37.5
2.0
35.6
5.0
41.1
15.5
0.9
22.3
47.0
20.2
1.2
26.4
58.7
31.5
1.9
35.4
70.5
45.4
2.7
45.3
7.5
67.7
17.8
1.5
33.6
77.3
23.3
2.0
39.5
96.7
36.4
3.1
52.0
116.0
52.4
4.4
65.6
9.0
87.8
25.1
1.8
44.4
100.4
32.8
2.4
52.3
125.5
51.3
3.8
69.2
150.5
73.9
5.4
87.6
10.5
107.4
24.4
2.2
51.8
122.7
31.9
2.9
60.7
153.4
49.9
4.5
79.5
184.0
71.8
6.4
99.8
12.0
128.7
27.9
2.5
61.6
147.1
36.5
3.3
72.1
183.8
57.0
5.2
94.3
220.6
82.1
7.5
118.1
13.5
152.8
32.9
2.9
73.1
174.6
43.0
3.8
85.5
218.3
67.1
5.9
111.8
261.9
96.7
8.5
140.1
15.0
180.6
37.8
3.2
86.0
206.4
49.3
4.2
100.6
257.9
77.1
6.6
131.4
309.5
111.0
9.5
164.4
REMARK :
1. Negative skin friction is not consider in the calculation
2. Pile cut-off elevation -1.00 m. below ground level
Depth
Appendix B 3 - BH-1
Graph แสดงความสัมพันธระหวางความลึกและกําลังตานของดิน
(Cumulative Ultimate Skin Friction & Ultimate End
Bearing Capacity & Depth)
Saraburi A Cogeneration Co.,ltd.
PROJECT :
Saraburi A Cogeneration Co.,ltd.
LOCATION :
Saraburi
BOREHOLE NO.:
BH-1
CUMMULATIVE ULTIMATE SKIN FRICTION AND ULTIMATE END BEARING CAPACITY VS DEPTH OF DRIVEN PILE
Ultinate Skin Friction(t/m.Perimeter)
0
2
4
6
8
10
12
14
16
0
50
100
150
200
Depth (m)
0
2
4
6
8
10
12
14
16
0
200
400
600
800
1,000
Ultimate End Bearing(t/sq.m.)
PROJECT :
Saraburi A Cogeneration Co.,ltd.
LOCATION :
Saraburi
BOREHOLE NO.:
BH-1
CUMMULATIVE ULTIMATE SKIN FRICTION AND ULTIMATE END BEARING CAPACITY VS DEPTH OF BORED PILE
Ultinate Skin Friction(t/m.Perimeter)
0
2
4
6
8
10
12
14
16
0
50
100
150
200
Depth (m)
0
2
4
6
8
10
12
14
16
0
200
400
600
800
1,000
Ultimate End Bearing(t/sq.m.)
Appendix B
4
รายการคํานวณขนาดและความยาวเสาเข็มตอก
( Driven Pile Calculation)
Saraburi A Cogeneration Co.,ltd.
Saraburi
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile size : 0.25 x 0.25 m. Area: 0.063 m2 Perimeter : 1.000 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 4.4 4.6 4.4 4.4 4.4 0.0 8.9 3.6 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 4.5 5.4 4.5 8.9 8.9 0.2 9.8 5.7 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 4.9 6.5 4.9 13.9 13.9 0.3 11.1 8.0 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 5.6 8.3 5.6 19.4 19.4 0.5 13.4 10.9 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 6.1 10.0 6.1 25.5 25.5 0.6 15.6 14.0 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 6.6 11.6 16.5 42.0 42.0 1.0 27.1 21.1 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 8.3 16.3 12.5 54.5 54.5 1.2 27.6 27.9 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 8.1 15.9 12.1 66.7 66.7 1.4 26.6 32.4 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 8.8 18.1 13.2 79.9 79.9 1.7 29.7 38.6 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 10.0 21.4 15.0 94.9 94.9 1.9 34.5 45.8 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 11.5 24.5 17.2 112.2 112.2 2.1 39.7 53.8 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile size : 0.30 x 0.30 m. Area: 0.090 m2 Perimeter : 1.200 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 4.4 6.6 5.2 5.2 4.4 0.0 11.8 4.7 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 4.5 7.8 5.5 10.7 8.9 0.2 13.0 7.3 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 4.9 9.3 5.9 16.6 13.9 0.4 14.8 10.2 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 5.6 11.9 6.7 23.3 19.4 0.6 17.9 13.8 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 6.1 14.5 7.4 30.6 25.5 0.9 20.9 17.7 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 6.6 16.7 19.8 50.4 42.0 1.4 35.1 26.3 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 8.3 23.5 15.0 65.5 54.5 1.7 36.8 34.9 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 8.1 22.9 14.6 80.0 66.7 2.1 35.4 40.3 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 8.8 26.1 15.9 95.9 79.9 2.4 39.6 47.9 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 10.0 30.8 18.0 113.9 94.9 2.7 46.0 56.8 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 11.5 35.3 20.7 134.6 112.2 3.0 53.0 66.7 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile size : 0.35 x 0.35 m. Area: 0.123 m2 Perimeter : 1.400 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 4.4 8.9 6.1 6.1 4.4 0.0 15.1 6.0 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 4.5 10.6 6.4 12.5 8.9 0.3 16.7 9.1 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 4.9 12.7 6.9 19.4 13.9 0.6 19.0 12.6 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 5.6 16.2 7.8 27.2 19.4 0.9 23.1 17.0 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 6.1 19.7 8.6 35.8 25.5 1.2 27.1 21.7 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 6.6 22.7 23.1 58.9 42.0 1.9 43.9 31.9 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 8.3 32.0 17.5 76.4 54.5 2.4 47.1 42.4 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 8.1 31.1 17.0 93.4 66.7 2.8 45.3 48.7 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 8.8 35.6 18.5 111.9 79.9 3.2 50.9 57.7 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 10.0 41.9 21.0 132.9 94.9 3.7 59.2 68.4 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 11.5 48.1 24.1 157.0 112.2 4.1 68.1 80.4 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile size : 0.40 x 0.40 m. Area: 0.160 m2 Perimeter : 1.600 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 4.4 11.7 7.0 7.0 4.4 0.0 18.7 7.5 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 4.5 13.8 7.3 14.3 8.9 0.4 20.7 11.1 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 4.9 16.6 7.9 22.2 13.9 0.8 23.7 15.2 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 5.6 21.2 8.9 31.1 19.4 1.2 28.9 20.4 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 6.1 25.7 9.8 40.9 25.5 1.5 34.0 26.0 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 6.6 29.6 26.4 67.3 42.0 2.5 53.5 37.8 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 8.3 41.8 20.0 87.3 54.5 3.1 58.7 50.4 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 8.1 40.6 19.4 106.7 66.7 3.6 56.4 57.5 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 8.8 46.4 21.2 127.9 79.9 4.2 63.4 68.0 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 10.0 54.7 24.0 151.9 94.9 4.8 73.9 80.7 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 11.5 62.8 27.6 179.4 112.2 5.4 85.0 94.7 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 392.3 112.2 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
Appendix B
5
รายการคํานวณขนาดและความยาวเสาเข็มเจาะ
( Bored Pile Calculation)
Saraburi A Cogeneration Co.,ltd.
Saraburi
SINGLE BORED PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile Dia.(m.) : 0.35 Area: 0.096 m2 Perimeter : 1.400 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 5.0 7.0 7.0 7.0 5.0 0.0 14.1 5.6 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 5.2 8.3 7.3 14.4 10.3 0.2 15.4 9.0 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 5.7 10.0 8.0 22.3 15.9 0.5 17.5 12.7 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 6.4 12.8 8.9 31.2 22.3 0.7 21.0 17.3 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 7.0 15.5 9.9 41.1 29.4 0.9 24.4 22.3 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 7.6 17.8 26.6 67.7 48.3 1.5 42.9 33.6 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 9.6 25.1 20.1 87.8 62.7 1.8 43.4 44.4 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 9.3 24.4 19.5 107.4 76.7 2.2 41.8 51.8 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 10.2 27.9 21.3 128.7 91.9 2.5 46.7 61.6 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 11.5 32.9 24.1 152.8 109.1 2.9 54.1 73.1 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 13.2 37.8 27.8 180.6 129.0 3.2 62.3 86.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 400 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE BORED PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile Dia.(m.) : 0.40 Area: 0.126 m2 Perimeter : 1.600 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 5.0 9.2 8.0 8.0 5.0 0.0 17.2 6.9 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 5.2 10.9 8.4 16.4 10.3 0.3 18.9 10.8 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 5.7 13.0 9.1 25.5 15.9 0.6 21.5 15.2 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 6.4 16.7 10.2 35.7 22.3 0.9 26.0 20.6 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 7.0 20.2 11.3 47.0 29.4 1.2 30.3 26.4 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 7.6 23.3 30.4 77.3 48.3 2.0 51.7 39.5 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 9.6 32.8 23.0 100.4 62.7 2.4 53.4 52.3 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 9.3 31.9 22.3 122.7 76.7 2.9 51.4 60.7 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 10.2 36.5 24.4 147.1 91.9 3.3 57.5 72.1 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 11.5 43.0 27.6 174.6 109.1 3.8 66.8 85.5 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 13.2 49.3 31.7 206.4 129.0 4.2 76.8 100.6 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 400 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE BORED PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile Dia.(m.) : 0.50 Area: 0.196 m2 Perimeter : 2.000 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 5.0 14.3 10.1 10.1 5.0 0.0 24.4 9.8 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 5.2 17.0 10.5 20.5 10.3 0.5 27.0 14.8 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 5.7 20.3 11.4 31.9 15.9 0.9 30.7 20.5 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 6.4 26.0 12.8 44.6 22.3 1.4 37.4 27.7 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 7.0 31.5 14.1 58.7 29.4 1.9 43.8 35.4 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 7.6 36.4 37.9 96.7 48.3 3.1 71.3 52.0 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 9.6 51.3 28.8 125.5 62.7 3.8 76.3 69.2 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 9.3 49.9 27.9 153.4 76.7 4.5 73.3 79.5 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 10.2 57.0 30.5 183.8 91.9 5.2 82.3 94.3 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 11.5 67.1 34.5 218.3 109.1 5.9 95.7 111.8 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 13.2 77.1 39.7 257.9 129.0 6.6 110.1 131.4 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 400 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE BORED PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Saraburi A Cogeneration Co.,ltd.
Location:Saraburi
Borehole No.: BH-1 Pile Dia.(m.) : 0.60 Area: 0.283 m2 Perimeter : 2.400 m Factor of safety : 2.50Depth of water = 1.53 m from ground level
Depth Soil Description Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
To USCS S=Sand Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay t/m2 kN/m2 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α
t/m2 t/m2 tons tons tons t/m. peri tons tons tons
0.0 - - 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 CL C 2.0 19.62 9 20 13 2.00 2.00 19.62 1.00 9.81 7.89 - - - - 0.55 73.0 5.0 20.6 12.1 12.1 5.0 0.0 32.7 13.1 2.0 CL C 2.0 19.62 12 20 15 4.00 3.53 34.63 2.77 27.12 9.15 - - - - 0.50 86.4 5.2 24.4 12.6 24.6 10.3 0.7 36.3 19.3 3.0 CL C 2.0 19.62 15 22 17 6.00 4.53 44.44 4.03 39.53 10.83 - - - - 0.46 103.5 5.7 29.3 13.6 38.2 15.9 1.4 41.5 26.5 4.0 CL C 2.1 20.21 20 26 22 8.06 5.59 54.84 5.06 49.64 13.83 - - - - 0.40 132.6 6.4 37.5 15.3 53.6 22.3 2.0 50.8 35.6 5.0 CL C 2.1 20.21 25 30 27 10.12 6.65 65.24 6.12 60.04 16.72 - - - - 0.37 160.6 7.0 45.4 16.9 70.5 29.4 2.7 59.6 45.3 7.5 CL C 2.1 20.40 30 31 30 15.32 9.35 91.72 8.00 78.48 18.88 - - - - 0.35 185.2 7.6 52.4 45.5 116.0 48.3 4.4 93.5 65.6 9.0 SC C 2.1 20.60 44 41 43 18.47 11.00 107.91 10.18 99.82 26.96 - - - - 0.31 261.1 9.6 73.9 34.5 150.5 62.7 5.4 103.0 87.6 10.5 SC C 2.0 19.62 43 38 41 21.47 12.50 122.63 11.75 115.27 25.83 - - - - 0.31 253.9 9.3 71.8 33.5 184.0 76.7 6.4 98.9 99.8 12.0 SC C 2.0 19.42 50 42 47 24.44 13.97 137.05 13.24 129.84 29.53 - - - - 0.30 290.2 10.2 82.1 36.6 220.6 91.9 7.5 111.2 118.1 13.5 CL C 2.0 19.42 60 48 56 27.41 15.44 151.47 14.71 144.26 34.93 - - - - 0.29 341.8 11.5 96.7 41.3 261.9 109.1 8.5 129.5 140.1 15.0 SG C 2.1 20.11 70 53 64 30.49 17.02 166.92 16.23 159.19 40.20 - - - - 0.29 392.3 13.2 111.0 47.6 309.5 129.0 9.5 149.1 164.4 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 392.3 129.0 15.0 15.0 15.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 400 t/sq.m. for sand (Reese and O' Neill, 1989)
Appendix C
Pile Calculation
Sample sheet
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Nong Saeng Power Plant - Saraburi
Location:Factory Area
Borehole No.: BH-2
Pile size : 0.25 x 0.25 m. Area: 0.063 m2
Perimeter : 1.000 m Factor of safety : 2.50
Depth of water = -0.80 m from ground level
Soil Description Depth Avg. Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
USCS S=Sand To Depth Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay m t/m^3 kN/m^3 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α t/m2 t/m2 tons tons tons t/m. peri tons tons tons
- - 0.0 0.00 0.00 0.00 0 0 1.00 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CH C 3.0 1.50 2.12 20.80 9 15 0.59 6.36 3.36 32.96 1.68 16.48 2.25 - - - - 1.00 183.9 2.3 11.5 6.8 6.8 6.8 0.0 18.2 7.3 CH C 7.0 3.50 2.12 20.80 15 17 0.90 14.84 7.84 76.91 5.60 54.94 3.75 - - - - 0.95 200.7 3.6 12.5 14.2 21.0 21.0 0.6 32.9 13.2 CL C 13.5 6.75 2.12 20.80 24 19 1.25 28.62 15.12 148.33 11.48 112.62 6.00 - - - - 0.64 231.2 3.8 14.5 25.0 45.9 45.9 1.6 58.8 23.5 SM S 16.0 8.00 2.13 20.90 51 38 1.36 33.95 17.95 176.04 16.53 162.18 12.75 28 8 0.50 22 - 451.0 6.8 28.2 17.0 63.0 63.0 2.0 89.2 35.7 SP S 17.5 8.75 2.13 20.90 80 56 1.42 37.14 19.64 192.67 18.79 184.35 20.00 42 80 0.50 34 - 676.2 12.5 42.3 18.7 81.7 81.7 2.2 121.8 48.7 SP-SM S 18.5 9.25 2.13 20.90 100 68 1.46 39.27 20.77 203.75 20.21 198.21 25.00 51 108 0.50 41 - 822.0 17.4 51.4 17.4 99.1 99.1 2.3 148.2 59.3
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Nong Saeng Power Plant - Saraburi
Location:Factory Area
Borehole No.: BH-2
Pile size : 0.30 x 0.30 m. Area: 0.090 m2
Perimeter : 1.200 m Factor of safety : 2.50
Depth of water = -0.80 m from ground level
Soil Description Depth Avg. Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
USCS S=Sand To Depth Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay m t/m^3 kN/m^3 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α t/m2 t/m2 tons tons tons t/m. peri tons tons tons
- - 0.0 0.00 0.00 0.00 0 0 1.00 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CH C 3.0 1.50 2.12 20.80 9 15 0.59 6.36 3.36 32.96 1.68 16.48 2.25 - - - - 1.00 183.9 2.3 16.6 8.1 8.1 6.8 0.0 24.7 9.9 CH C 7.0 3.50 2.12 20.80 15 17 0.90 14.84 7.84 76.91 5.60 54.94 3.75 - - - - 0.95 200.7 3.6 18.1 17.1 25.2 21.0 0.9 42.4 16.9 CL C 13.5 6.75 2.12 20.80 24 19 1.25 28.62 15.12 148.33 11.48 112.62 6.00 - - - - 0.64 231.2 3.8 20.8 30.0 55.1 45.9 2.3 73.7 29.5 SM S 16.0 8.00 2.13 20.90 51 38 1.36 33.95 17.95 176.04 16.53 162.18 12.75 28 8 0.50 22 - 451.0 6.8 40.6 20.4 75.6 63.0 2.8 113.3 45.3 SP S 17.5 8.75 2.13 20.90 80 56 1.42 37.14 19.64 192.67 18.79 184.35 20.00 42 80 0.50 34 - 676.2 12.5 60.9 22.5 98.0 81.7 3.1 155.8 62.3 SP-SM S 18.5 9.25 2.13 20.90 100 68 1.46 39.27 20.77 203.75 20.21 198.21 25.00 51 108 0.50 41 - 822.0 17.4 74.0 20.9 119.0 99.1 3.3 189.6 75.8
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Nong Saeng Power Plant - Saraburi
Location:Factory Area
Borehole No.: BH-2
Pile size : 0.35 x 0.35 m. Area: 0.123 m2
Perimeter : 1.400 m Factor of safety : 2.50
Depth of water = -0.80 m from ground level
Soil Description Depth Avg. Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
USCS S=Sand To Depth Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay m t/m^3 kN/m^3 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α t/m2 t/m2 tons tons tons t/m. peri tons tons tons
- - 0.0 0.00 0.00 0.00 0 0 1.00 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CH C 3.0 1.50 2.12 20.80 9 15 0.59 6.36 3.36 32.96 1.68 16.48 2.25 - - - - 1.00 183.9 2.3 22.5 9.5 9.5 6.8 0.0 32.0 12.8 CH C 7.0 3.50 2.12 20.80 15 17 0.90 14.84 7.84 76.91 5.60 54.94 3.75 - - - - 0.95 200.7 3.6 24.6 19.9 29.3 21.0 1.2 52.8 21.1 CL C 13.5 6.75 2.12 20.80 24 19 1.25 28.62 15.12 148.33 11.48 112.62 6.00 - - - - 0.64 231.2 3.8 28.3 35.0 64.3 45.9 3.1 89.5 35.8 SM S 16.0 8.00 2.13 20.90 51 38 1.36 33.95 17.95 176.04 16.53 162.18 12.75 28 8 0.50 22 - 451.0 6.8 55.2 23.8 88.2 63.0 3.8 139.6 55.8 SP S 17.5 8.75 2.13 20.90 80 56 1.42 37.14 19.64 192.67 18.79 184.35 20.00 42 80 0.50 34 - 676.2 12.5 82.8 26.2 114.4 81.7 4.3 193.0 77.2 SP-SM S 18.5 9.25 2.13 20.90 100 68 1.46 39.27 20.77 203.75 20.21 198.21 25.00 51 108 0.50 41 - 822.0 17.4 100.7 24.4 138.8 99.1 4.6 234.9 94.0
Remark:
1) Negative skin friction is not consider in the calculation
2) Pile cut-off level is at - 1.00 m. below ground level
3) Limited maximum end bearing, q
b= 1000 t/sq.m. for sand (Reese and O' Neill, 1989)
SINGLE SQUARE DRIVEN PILE CAPACITY CALCULATION-STATIC FORMULA
Project:
Nong Saeng Power Plant - Saraburi
Location:Factory Area
Borehole No.: BH-2
Pile size : 0.40 x 0.40 m. Area: 0.160 m2
Perimeter : 1.600 m Factor of safety : 2.50
Depth of water = -0.80 m from ground level
Soil Description Depth Avg. Unit Unit SPT (N-value) σvo σ'tip σ'tip σ'ave σ'ave Su φ Nq Ks δ Adh. qb qs Qb Qs Qs Qs Wp Qu Qa
USCS S=Sand To Depth Weight Weight Field Liao Corr. Factor Cumm. Cumm.
C=Clay m t/m^3 kN/m^3 t/m2 t/m2 kN/m2 t/m2 kN/m2 t/m2 o 0.80φ α t/m2 t/m2 tons tons tons t/m. peri tons tons tons
- - 0.0 0.00 0.00 0.00 0 0 1.00 0.00 0.00 0.00 0.00 0.00 - - - 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CH C 3.0 1.50 2.12 20.80 9 15 0.59 6.36 3.36 32.96 1.68 16.48 2.25 - - - - 1.00 183.9 2.3 29.4 10.8 10.8 6.8 0.0 40.2 16.1 CH C 7.0 3.50 2.12 20.80 15 17 0.90 14.84 7.84 76.91 5.60 54.94 3.75 - - - - 0.95 200.7 3.6 32.1 22.7 33.5 21.0 1.5 64.1 25.6 CL C 13.5 6.75 2.12 20.80 24 19 1.25 28.62 15.12 148.33 11.48 112.62 6.00 - - - - 0.64 231.2 3.8 37.0 40.0 73.5 45.9 4.0 106.5 42.6 SM S 16.0 8.00 2.13 20.90 51 38 1.36 33.95 17.95 176.04 16.53 162.18 12.75 28 8 0.50 22 - 451.0 6.8 72.2 27.3 100.8 63.0 5.0 167.9 67.2 SP S 17.5 8.75 2.13 20.90 80 56 1.42 37.14 19.64 192.67 18.79 184.35 20.00 42 80 0.50 34 - 676.2 12.5 108.2 30.0 130.7 81.7 5.6 233.3 93.3 SP-SM S 18.5 9.25 2.13 20.90 100 68 1.46 39.27 20.77 203.75 20.21 198.21 25.00 51 108 0.50 41 - 822.0 17.4 131.5 27.9 158.6 99.1 6.0 284.2 113.7