ADDENDUM NO. 2 Page 1
ADDENDUM NO. 2
TO
REQUEST FOR QUALIFICATIONS
FOR NEW DEVELOPMENT OF
OAKLAND UNIFIED SCHOOL DISTRICT PROPERTIES,
INCLUDING THE PARCELS HOUSING THE PAUL ROBESON ADMINISTRATION
BUILDING AND DEWEY HIGH SCHOOL
1025 SECOND AVENUE •
1105 SECOND AVENUE
OAKLAND CA 94606
July 29, 2014
TO ALL POTENTIAL RESPONDENTS:
This Addendum forms a part of the above-referenced request for qualifications (RFQ) and
modifies the RFQ. All other provisions in the RFQ remain unchanged.
•
Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following:
1.1. BACKGROUND AND CONTEXT
Sometime during the night of January 7, 2013 a substantial water leak occurred on the
top floor of the Oakland Unified School District's (the “District” or “OUSD”) Paul Robeson
Administration Building, located at 1025 2nd Avenue, causing excessive flooding on all
four floors and significant damage to the entire structure. As a result of this water
damage, the Paul Robeson Administration Building has been vacated and staff relocated
to leased space at the Trans Pacific Center, 1000 Broadway. The Administration Building
and an adjacent Annex Building, also vacant, are both presumed to be beyond repair.
The District will issue a separate solicitation for demolition and hazardous materials
remediation of these structures. In addition, the Oakland Unified School District will
temporarily relocate and surplus the adjacent Dewey Academy High School at
1105-1111 2
ndAve. (“Dewey High School”). The Board of Education has convened a surplus
property advisory committee (“7-11 Committee”) (Ed. Code §§17387, 17388). Finally,
the District will seek approval from the City to vacate 11
thStreet and merge the 1025
and 1105 parcels into one contiguous parcel (the “Site”). Following the District’s
demolition and remediation of the aforementioned Administration Buildings and the
temporary relocation of Dewey, the District anticipates delivery of expects to deliver a
“clean and graded” Site.
•
Revise Section 1.2 (DISTRICT OBJECTIVES) to the following:
1.2. DISTRICT OBJECTIVES
Primarily, the District anticipates a long-term ground lease structure with a joint
occupancy component (Ed. Code §17387; §17515) that will allow it to participate in
an increasing revenue stream over the lease term, most importantly to off-set the
costs associated with the leased Administration space at 1000 Broadway, and/or the
costs of rebuilding and returning the Administration Building and Dewey High School to
District property. However, this Request for Qualifications ( “ R F Q ” ) does not limit the
ADDENDUM NO. 2 Page 2
type of development project and encourages proposals that will achieve the above
objectives of the District while also obtaining community support.
The District’s s p e c i f i c objectives include:
•
Redeveloping the site with income-generating uses under a sixty-six year (66)
to ninety-nine year (99) ground lease.
•
Maximizing an income stream to supplement its annual operating and capital
project budget.
•
Merging parcels and further subdividing to create a separate Assessor’s
Parcel. Number (APN) and preserving the ownership over the Site to the
District.
•
Building a replacement campus for Dewey High School.
•
Building a replacement building for District Administration to include board
chambers and community meeting space.
For purposes of developing this RFQ, it is contemplated that medium to high density
multi-family residential, which may include some component of affordable housing or
teacher housing, is the primary use proposed for the Site in order to meet the goals of
maximizing annual revenue to the District over the long term. However, proposers may
also propose commercial and/or retail uses which generate equivalent or greater lease
revenue. In addition, the District will consider proposals to exchange property for equal
consideration (Ed. Code § 17536), and will also consider proposals for the adaptive
reuse of the Administration Building (Paul L. Robeson Building) and the Annex
Building (Ethel Moore Memorial Clinic) located on the 1025 2
nd. Avenue parcel.
Potential options might include:
•
Developer maintains control over entire Site through a long term ground lease,
with construction of the Administration Building and Dewey HS achieved through
a lease leaseback financing structure on smaller parcel - District/Dewey lease
rents to Developer would be off-set by ground lease rents due the District on the
larger Developer parcel;
•
After lot merger and parcel realignment, District constructs its own
Administration / Dewey HS Building(s) on smaller parcel with remaining acreage
available to Developer under a long term ground lease;
•
Developer identifies appropriate exchange site for District Administration and
Dewey HS relocation and District leases entire Site to Developer under long term
ground lease.
______________________________________________________________________
The following questions were raised during the pre-proposal conference on July 1,
2014 and were asked to be submitted for review and response by District:
ADDENDUM NO. 2 Page 3
1. Will the Oakland Unified School District (“District”) consider any reuse of existing
buildings?
Answer: Yes, the District will consider proposals for adaptive reuse of the
existing Administration and Annex buildings. The RFQ has been modified as
indicated above.
2. Are there any reports available regarding the condition of the existing Administration
building and the costs of repair?
Answer: Yes. A report was prepared by HY Architects, Inc. after the January
2013 flood. It will be posted online with this Addendum No. 2.
3. Are any Community Benefits Agreements to be included with the development of the
District’s Site?
Answer: It is unknown at this time if Community Benefits Agreements will be
included in the development.
4. Will local businesses be given preference in the selection process?
Answer: Yes. Please refer to Section 1.9 of the RFQ: BOARD POLICY 7115 -
CAPITAL PROGRAM / CONSTRUCTION RELATED LOCAL, SMALL LOCAL AND
SMALL LOCAL RESIDENT BUSINESS ENTERPRISE PROGRAM (2014 L/SL/SLRBE).
5. Will local businesses that have done Lease Leaseback projects with the District be
given preference over other local firms?
Answer: No.
6. Is the District looking to use Measure J funds for the construction of the new
Administration Building and new Dewey High School?
Answer: Measure J funds have not been earmarked for the construction of the
new Administration Building and new Dewey High School. The intent is to have
the developer finance the cost of construction of the new Administration Building
and new Dewey High School.
7. Is affordable housing to be included?
Answer: The District will consider proposals that include affordable housing;
however it is not mandatory that a response include affordable housing.
8. What does the District consider “affordable housing”?
Answer: The District will rely on proposers who decide to include an affordable
housing component in their response to define “affordable housing”.
ADDENDUM NO. 2 Page 4
9. Who owns 11
thStreet?
Answer: 11
thStreet is a public street.
10. Are as-built plans and square footages for the Administration and Annex Buildings
available?
Answer: The District is attempting to locate plans and square footage
documents for the Administration and Annex Buildings and will post such
documents online if available.
11. Has the District conducted demographic studies or growth plans for Dewey High
School? What are the growth trends for Dewey High School over the past five (5)
years?
Answer: No.
12. Will the District consider a low income proposal?
Answer: The RFQ does not limit the type of development project, but
encourages proposals that will achieve the stated objectives of the District while
also obtaining community support. The stated objective is: a long-term
ground lease structure with a joint occupancy component that will allow District
to participate in an increasing revenue stream over the lease term, most
importantly to off-set the costs associated with the leased Administration space
at 1000 Broadway, and the costs of rebuilding the Administration Building and
Dewey High School.
13. Is the District aware of the 100 ft. setback along the estuary? Will the District do
research to see how that set-back impacts the buildable space?
Answer: The District will rely upon qualified proposers to conduct the necessary
due diligence to determine the impact, if any, of the purported “set-back”.
300 – 27th Street, 2nd Floor | Oakland, CA 94612 | phone: (510) 446-2222 | fax: (510) 446-2211
Oakland Davis Los Angeles
H
Y
HIBSER YAMAUCHI Architects, Inc.
OAKLAND UNIFIED SCHOOL DISTRICT
Architectural Evaluation of the Robeson Building
District Administration Building
1025 2nd Street
Oakland, California
300 – 27th Street, 2nd Floor | Oakland, CA 94612 | phone: (510) 446-2222 | fax: (510) 446-2211
Oakland Davis Los Angeles
H
Y
OUSD Administration Building
Water Damage Remediation
May 16, 2013
Executive Summary
The building was constructed in 1926 remodeled in 1929 and per district records was added to and
remodeled in 1967 and 1968. The two 1960’s remodels have Division of the State Architect approval
numbers but no record has been found that indicates that the original building was approved or
remodeled to meet the Field Act Seismic Standards which were adopted in 1933. The building is posted
with a sign that identifies it as a structurally non-conforming building per California State Education
Code.
Significant portions of all floors of the building sustained water damage earlier this year. The building
has subsequently been vacated by the District. Restoration Management Company has completed a
clean-up of the damaged areas and the building is now ready for restoration to its former use. The
required restoration includes replacement of walls, finishes, electrical and mechanical items. Based on
the scope of the work and the use of the building, the District is obligated to submit the drawings to the
Division of the State Architect (DSA). DSA will consider this project an “alteration” and as such approval
will need to be obtained for Access Compliance and Fire/ Life Safety items as well as structural review of
any new work.
Based on the building’s age it was never submitted to the DSA for review and approval for original
construction (the agency that is now DSA was created in 1933). Per conversations with DSA, further
investigation is required to determine if any remediation was completed on the building subsequent to
its original construction. If no remediation has occurred, then DSA will consider this a “rehabilitation”
project. The process for rehabilitation includes bringing the entire building up to current Title 24
standards. This would include extensive evaluation of existing conditions, energy compliance upgrades
as well as structural upgrades. The exact scope of this work cannot be determined at this time; however
we have made an attempt to consider the cost of a seismic upgrade (see below).
Scope of Work
As it relates to Accessibility Standards the building is deficient in most areas. The only room in the
building that is accessible from the exterior is the Board Room which can be accessed from the front of
the building at outside sidewalk level. Once in the Board Room there is no access to toilet rooms or the
main floors except by stairs. The building entries are stairs only and need to be modified via lifts to
provide access at the front and the rear of the building. Internally, the building has access to each floor
via elevators. Some modifications will need to be made to the elevator system. The building lacks
adequate signage and the restrooms have compliance issues and will require a complete remodel to
meet current code.
Access to the front of the building will need to be reviewed by DSA. At this time, our estimate assumes
a lift to provide accessible route to the front and rear entrances (due to proximity of the building to the
sidewalk). Elevator controls will also need to be upgraded to meet current accessibilty code.
300 – 27th Street, 2nd Floor | Oakland, CA 94612 | phone: (510) 446-2222 | fax: (510) 446-2211
Oakland Davis Los Angeles
H
Y
OUSD Administration Building
Water Damage Remediation
May 16, 2013
As to fire life/ safety the building lacks basic requirements. The fire alarm system is almost non-existent
and upon DSA review will be required to be replaced with a fully addressable system. The upgrade
would need to occur at all five floors of the building as well and the exit stair towers. Additionally the
interior stair wells will need to be enclosed and the interior corridor walls that form the exit path need
to be reconstructed to meet current fire code.
Estimated Construction Cost
The construction cost estimate attached is based on a multiple site visits and floor plans as supplied by
District and is conceptual only. A more detailed estimate should be made once schematic plans are
created to define the full scope of the project.
The estimate identifies a floor by floor cost which includes the work required due to the water damage,
the remodel of the Toilet Rooms on each floor to meet accessibility standards and a new fully
addressable Fire Alarm System for the full building and the reconstruction of the corridor walls to create
fire rated exit corridors.
Additionally, a separate estimate has been provided to identify costs should the building require a
complete “rehabilitation” by DSA. Please note that these are estimates only. A rehabilitation project
will require extensive building testing and investigations which could lead to significantly more work
than what was initially anticipated by this study.
As a summary, we estimate the construction cost of upgrades as follows:
“Alteration” project
$ 7,342,766
“Total Construction Cost”
$26,339,456
Schedule
If investigations conclude that this is an “alteration” project then the anticipated schedule for design,
permitting and construction will be approximately 30 months. If this becomes a “rehabilitation” project,
we anticipate the time for testing, design, permitting and construction to be approximately 48 months.
Schedule OUSD ‐ Administration Building Restoration Project
Schedule for Building as an "Alteration" Project:
Project Scoping and Requirements
1 Months
Schematic Design and Approval
2 Months
Design Development and approval
2 Months
Construction Documents Development
3 Months
DSA Design approval
6 Months
Construction Bid & Approval
2 Months
Construction
14 Months
Total
30 Months
Schedule for Building as a "Rehabilitation" project
Project Study and Scope determination
4 Months
Schematic Design and Approval
2 Months
Design Development and Approval
3 Months
Construction Document Development
4 Months
DSA Design Approval
6 Months
Construction Bid & Approval
2 Months
Construction
27 Months
Total
48 Months
OAKLAND UNIFIED SCHOOL DISTRICT
"Alteration" ProjectConceptual Estimate including Code Upgrades of Door Hardware and Restroom remodels at each floor.
The square footage used are estimates based on site visit and district floor plans. Detailed site dimensions were not made.
Fourth Floor Qnty Unit Cost per Unit Total
Walls -- Furring, Gyp. Bd & Finish--Replace 1350 SF $ 6.00 $ 8,100.00
Painting all walls 7600 SF $ 1.00 $ 7,600.00
Ceilings --- Painting 3000 SF $ 1.25 $ 3,750.00 Flooring --- Linoleum 3456 SF $ 15.80 $ 54,604.80 Base --- Rubber 450 LF $ 4.50 $ 2,025.00 Marble 200 LF $ 35.00 $ 7,000.00 Toilet Room:
Remodel to Accessibility Standards 286 SF $ 375.00 $ 107,250.00 Doors & Hardware:
Sand , Paint or Stain 20 EA $ 150.00 $ 3,000.00
New Access Compliant Hardware:
Panic Hardware 5 EA $ 750.00 $ 3,750.00
Locksets 10 EA $ 200.00 $ 2,000.00
Closers 17 EA $ 75.00 $ 1,275.00
Remove & Replace Doors 20 EA $ 250.00 $ 5,000.00 -$ Cabinetry - Kitchen 50 LF $ 350.00 $ 17,500.00 Stairwells Flooring - Treads 30 EA $ 150.00 $ 4,500.00 Painting 1150 SF $ 1.25 $ 1,437.50 Landing 2 EA $ 750.00 $ 1,500.00
Mechanical/ Plumbing (ADA upgrades NIC) $ 5,194.00
Electrical: Light Fixture replacement/ Outlets & Wiring $ 36,000.00
Fire Alarm $ 41,000.00
Fourth Floor -Subtotal $ 312,486.30
Cleaning & Moving at 15% $ 46,872.95 Total Fourth Floor Cost $ 359,359.25
Third Floor Qnty Unit Cost per Unit Total
Walls -- New Walls 1745 LF $ 55.00 $ 95,975.00
Storefront 50 LF $ 125.00 $ 6,250.00
Furring, Gyp. Bd & Finish--Replace 5620 SF $ 6.00 $ 33,720.00
Painting all walls 10870 SF $ 1.25 $ 13,587.50
Ceilings --- $ -Painting 3400 SF $ 1.25 $ 4,250.00 Suspended Ceiling 1900 SF $ 6.50 $ 12,350.00 Flooring --- Carpet 3775 SF $ 15.50 $ 58,512.50 Linoleum 1750 SF $ 15.80 $ 27,650.00 Base --- Rubber 980 LF $ 4.50 $ 4,410.00 Marble 300 LF $ 35.00 $ 10,500.00 Toilet Room:
Remodel to Accessibility Standards 195 SF $ 375.00 $ 73,125.00 -$
Doors & Hardware: $
-Sand , Paint or Stain 11 EA $ 150.00 $ 1,650.00
New Doors 7 EA $ 750.00 $ 5,250.00
New Access Compliant Hardware: $
-Panic Hardware 1 EA $ 350.00 $ 350.00
Locksets 36 EA $ 200.00 $ 7,200.00
Closers 27 EA $ 75.00 $ 2,025.00
Remove & Replace Doors 18 EA $ 250.00 $ 4,500.00 -$ Stairwells $ -Flooring - Treads 32 EA $ 150.00 $ 4,800.00 Painting $ -Landing 2 EA $ 750.00 $ 1,500.00
Mechanical/ Plumbing (ADA upgrades NIC) $ 17,668.00
Electrical: Light Fixture replacement/ Outlets & Wiring $ 123,000.00
Fire Alarm $ 41,000.00
Third Floor -Subtotal $ 549,273.00
Cleaning & Moving at 15% $ 82,390.95
Second Floor Qnty Unit Cost per Unit Total Walls --
Furring, Gyp. Bd & Finish--Replace 6270 SF $ 6.00 $ 37,620.00
Painting all walls 8965 SF $ 1.00 $ 8,965.00
Paint Wood Base 1120 LF $ 1.25 $ 1,400.00
Ceilings --- Painting 2400 SF $ 1.00 $ 1,050.00 Suspended Ceiling 1050 SF $ 6.50 $ 6,825.00 Flooring --- Carpet 4000 SF $ 15.50 $ 62,000.00 Linoleum 2975 SF $ 15.80 $ 47,005.00 Base --- Rubber 575 SF $ 4.50 $ 2,587.50 Marble 330 SF $ 35.00 $ 11,550.00 Wood 1120 LF $ 18.00 $ 20,160.00 Toilet Room:
Remodel to Accessibility Standards 260 SF $ 375.00 $ 97,500.00 Doors & Hardware:
Sand , Paint or Stain $
-New Doors 13 EA $ 750.00 $ 9,750.00
New Access Compliant Hardware:
Panic Hardware 2 EA $ 350.00 $ 700.00
Locksets 40 EA $ 200.00 $ 8,000.00
Closers 28 EA $ 75.00 $ 2,100.00
Remove & Replace Doors 40 EA $ 250.00 $ 10,000.00 -$
Stairwells $
-Flooring - Treads 32 EA $ 150.00 $ 4,800.00
Landing 2 EA $ 750.00 $ 1,500.00
Mechanical/ Plumbing (ADA upgrades NIC) $ 16,884.00
Electrical: Light Fixture replacement/ Outlets & Wiring $ 80,100.00
Fire Alarm $ 41,000.00
Subtotal Second Floor $ 471,496.50
Cleaning & Moving at 15% $ 70,724.48
First Floor Qnty Unit Cost per Unit Total
Walls --
Furring, Gyp. Bd & Finish--Replace 1620 SF $ 6.00 $ 9,720.00
Painting all walls 4760 SF $ 1.00 $ 4,760.00
Paint Wood Base $
-Ceilings --- $ -Painting 3638 SF $ 1.00 $ 3,638.00 Suspended Ceiling $ -Flooring --- $ -Carpet 1583 SF $ 15.80 $ 25,011.40 Linoleum 4250 SF $ 15.50 $ 65,875.00 Base --- Rubber $ Marble $ Wood 984 LF $ 18.00 $ 17,712.00 Toilet Room: $
Remodel to Accessibility Standards 260 SF $ 375.00 $ 97,500.00 -$
Doors & Hardware: $
-Sand , Paint or Stain $
-New Doors $
-New Access Compliant Hardware: $
-Panic Hardware 7 EA $ 350.00 $ 2,450.00
Locksets 40 EA $ 200.00 $ 8,000.00
Closers 38 EA $ 75.00 $ 2,850.00
Remove & Replace Doors $
-$ Stairwells $ -Flooring - Treads 32 EA $ 150.00 $ 4,800.00 Landing 2 EA $ 750.00 $ 1,500.00 -$ Mechanical $
-Electrical: Light Fixture replacement/ Outlets & Wiring $ 43,000.00
Fire Alarm $ 41,000.00
Subtotal First Floor $ 327,816.40
Cleaning & Moving at 15% $ 49,172.46
Basement Level: Qnty Unit Cost per Unit Total Painting:
Walls 1350 SF $ 1.00 $ 1,350.00
Wood Base 100 LF $ 1.00 $ 100.00
Install Wood Base 100 LF $ 15.00 $ 1,500.00
Toilet Room:
Remodel to Accessibility Standards 92 SF $ 375.00 $ 34,500.00
AC Ceiling 300 SF $ 2.85 $ 855.00
Cleaning and repairs $ 15,000.00
Mechanical $
-Electrical-Replace Outlet/ Wiring & Inspect Main SWBD $ 9,600.00
Fire Alarm $ 41,000.00
Subtotal Basement Level $ 62,905.00
Cleaning & Moving at 15% $ 9,435.75
Total Second Floor $ 72,340.75
Sum of Four Floors and Basement area $ 1,982,573.78
which includes new door hardware, toilet room remodeling and new fire alarm to meet Fire and ADA Standards Additional Required Code Upgrades:
Stair enclosure modifications: Each of the stair well shafts are not enclosed.
Staircases need to be removed and rplaced to meet current standards. $ 800,000.00
Elevator and Machine Room upgrades - $ 170,000.00
New handrails in the stair wells interior of the building and at stair towers
5 Locations 4 stories high. $ 37,500.00
Fire Sprinkler System $ 235,344.00
Provide accessible entries at the front and the back of the buiding.
Cut entry stairways to insert a Lift and reconfigure stairs & railing. $ 175,000.00 Provide Handicap parking spaces and signage $ 12,000.00 Curb cut at front entry sidewalk $ 8,000.00
Emergency Egress lighting & exit signage $ 100,000.00
Provide accessibile signage throughout site $ 42,000.00
New Telecommunication System $ 360,000.00
Subtotal $ 3,922,417.78
General Condition Items @ 20% $ 784,483.56
Contractor O & P $ 941,380.27
Total Constuction Cost $ 5,648,281.60
Soft Cost- Studies/ Arch/CM $ 1,694,484.48
OAKLAND UNIFIED SCHOOL DISTRICT
"Rehabilitation" ProjectAnticipated Code Upgrades Required:
Seismic Upgrades 58,836 SF $ 100.00 /SF $ 5,883,600.00 Title 24 Energy Requirements
Replace all windows with dual glazed units. $ 1,500,000.00 Furr-out all interior side of exterior walls for insulation $ 1,500,000.00
Code Upgrade Total $ 8,883,600.00
General Condition Items @ 20% $ 1,776,720.00
Contractor O & P $ 2,132,064.00
SUB-TOTAL UPGRADES $ 12,792,384.00
Design Contingency 10% $ 1,279,238.40
TOTAL UPGRADES $ 14,071,622.40
Project Soft Cost-Studies/Arch/CM $ 4,925,067.84 Total Rehab Const. Cost. $ 18,996,690.24
Total Construction Cost $ 7,342,766.08