• No results found

Analysis of Key Factors Affecting the Variation of Labour Productivity in Construction Projects

N/A
N/A
Protected

Academic year: 2020

Share "Analysis of Key Factors Affecting the Variation of Labour Productivity in Construction Projects"

Copied!
9
0
0

Loading.... (view fulltext now)

Full text

(1)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

152

Analysis of Key Factors Affecting the Variation of Labour

Productivity in Construction Projects

Shashank K

1

, Dr. Sutapa Hazra

2

, Kabindra Nath Pal

3

1

Student MTECH (CEM), 2Associate Professor, Department of civil Engineering, MIT (Manipal), Karnataka, India

3General Manager (Technical), Gopalan Enterprises, Bangalore, Karnataka, India

Abstract Productivity plays an important role in the construction industry. It helps construction industries to be competitive, to achieve goals and to meet the stakeholder and value propositions. The objectives of this research are; one, identifying the key factors affecting the variation of labour productivity in the construction projects in Bangalore, India, second, assessing the impact of the influenced factors on the variation of labour productivity and lastly, providing recommendations to reduce the variation of labour productivity.

The above objectives have been achieved through the analysis of 53 questionnaires and the result of this analysis shows that, there are six main groups which have significant impact on the labour productivity variation in the construction projects. They are Manpower group, Managerial group, Motivation group, Material/Equipment group, Safety group and Quality group.

Keywords Construction, Labour Productivity, Labour

Productivity Variation, Multiple Linear Regression,

Influenced factors.

I. INTRODUCTION

Productivity has been generally defined as the ratio of outputs to inputs. Construction projects are mostly labour based with basic hand tools and equipment, as labour costs comprise 30 % to 50 % of overall project cost. Productivity in economics refers to measures of output from production processes, per unit of input. Productivity may be conceived of as a measure of the technical or engineering efficiency of production.

There are many factors that influence the productivity in construction industry. Labour productivity is one of the most important factors that affect the physical progress of any construction project. Construction labourers are responsible to operate a variety of equipment. To perform their jobs effectively, construction labourers must be familiar with the duties of other craft workers and with the materials, tools, and machinery they use.

Construction labour productivity is influenced by various factors whose impact can be quantified in productivity models. These models play an important role in estimating cost, in scheduling, and in planning.

A number of models have been developed using regression analysis to provide a qualitative evaluation of the impact of different factors on construction labour productivity. The present study intends to quantify these factors and to provide a model for predicting labour productivity.

II. OBJECTIVES OF THE STUDY

This study is conducted to achieve the following objectives.

To identify the factors affecting the variation of labour productivity in the construction projects.

To assess the impact of influenced factors on the variation of labour productivity.

To suggest recommendations in order to reduce variation of labour productivity in the construction projects.

III. LITERATURE REVIEW

Productivity in construction is often broadly defined as output per labour hour. Since labour constitutes a large part of the construction cost and the quantity of labour hours in performing a task in construction is more susceptible to the influence of management than are materials or capital, this productivity measure is often referred to as labour productivity. However, it is important to note that labour productivity is a measure of the overall effectiveness of an operating system in utilizing labour, equipment and capital to convert labor efforts into useful output, and is not a measure of the capabilities of labour alone.

Homyun Jang et al (2009) identified 25 critical variables and were grouped into 4 groups, namely work management, work technique, work characteristic and worker component.

(2)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

153

Enshassi (2007) classifies factors affecting productivity in the construction projects into 10 groups, namely: factors associated with the internal workforce, factors associated with leadership, factors associated with work motivation factor associated with time, factors associated with materials and equipment, factors related to supervision, factors related to project characteristic, factors related to security, factors related to quality and external factors.

Soekiman et al (2011) identified 113 variables affecting construction labour productivity and these variables were grouped into 15 groups of factors according to their characteristics, namely: Design, execution plan, material, equipment, labor, health and safety, supervision, working time, project factor, quality, financial, leadership and co-ordination, organization, owner/consultant and external factor.

Nabil Ailabouni et al (2007) identified 32 significant variables affecting the productivity in the construction industry and these were grouped into 4 groups based on their characteristic, namely: environment factors, organizational factors, group dynamics and personal factors.

[image:2.612.309.573.137.699.2]

In summary, based on the previous research, 34 factors are selected and grouped into 8 groups according to their characteristics, namely: Manpower, Managerial, Environmental, safety, Material/Equipment, Schedule, Motivation, and Quality as shown in the TABLE I.

Table I

Factors Affecting Labour Productivity

SL NO GROUP FACTORS

A MANPOWER

A1 Lack of labour skills

A2 Increase of labourer age

A3 Labour absenteeism

A4 Lack of training

A5 Labour personal problem

B MANAGERIAL

B1 Poor site management

B2 Poor communication

B3 Misunderstanding between labour and supervisor

B4 Lack of periodic meeting with labours

C ENVIRONMENTAL

C1 Weather changes

C2 Project location

C3 Working with confined place

C4 Large project size

D MOTIVATION

D1 Payment delay

D2 Non provision of transport means

D3 Lack of financial motivation system

D4 Lack of places for eating

and relaxation

E MATERIAL/EQUI-PMENT

E1 Material shortage

E2 Unsuitable material storage location

E3 Old and inefficient equipment

E4 Tools and equipment shortages

F SCHEDULE

F1 Working 7 days per week without taking holiday

F2 Poor work planning

F3 Overcrowding

F4 Misuse of time schedule

G SAFETY

G1 Ignore safety precautions

G2 Accident

G3 No safety engineer in site

G4 Insufficient lighting

G5 Working at high places

H QUALITY

H1 Low quality raw materials

H2 High quality of required works

H3 Rework

(3)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

154

Theoretical model

As shown in Figure 1, theoretical model consisting of 8 hypotheses from H1 to H8, in there, the group factors are independent and quantitative variables, they affect directly on labour productivity variation, a dependent variable.

Manpower group H1+

Managerial group H2+

Environmental group H3+

Motivation group H4+

Material/Equipment group H5+

Schedule group H6+

Safety group H7+

[image:3.612.47.270.198.393.2]

Quality group H8+

Figure 1: Theoretical model

Based on the past studies and theoretical concepts. The theoretical model was constructed with eight independent groups including manpower, managerial, environmental, motivation, schedule, material/equipment, safety and quality which have positive impact on the dependent factor of labour productivity variation.

IV. RESEARCH METHODOLOGY

The method used in the study is shown in Figure 2.

Questionnaire survey

Reliability analysis

Factor analysis

Multiple regression analysis

Figure 2: Research method

Questionnaire survey: Data on factors that influences labour productivity in construction projects.

Reliability analysis: This was conducted for each group in order to assess the reliability of the questionnaire. Unreliable factors were discarded.

Factor analysis: Factors were classified into components. At this stage, components classified on the basis of the relevant literature review (manpower, managerial, environmental, motivation, material/equipment, schedule, safety and quality). The components that were properly classified were examined, and those that were not classified were reclassified so that the components could properly represent the factors. Then, a reliability analysis was conducted on the factors in each classified component to verify the reliability of the component.

Regression analysis: This was the last stage of the statistical analysis in which the factors that significantly influenced labour productivity variation in construction were identified. The significance of the components was analyzed and insignificant components were discarded at this stage. In addition, the regression model was evaluated, and the impact of each component was analyzed.

V. RESULTS OF DATA ANALYSIS AND DISCUSSION

A total of 60 questionnaires were distributed to the construction firms in the population. Of these, 53 questionnaires were successfully filled. The response rate was therefore 88.33%.

Once the data was collected the analysis was done as per questionnaires that were used to collect the data.

A. Reliability Analysis

Cronbach‘s alpha method was used for reliability analysis. This method assesses basic consistency on the basis of the average correlation between the data that were measured in an identical manner. This method combines the split-half method and item-total correlation, and calculates the mean value of the reliability, obtained by the split-half method for all the data of the concept. Using this method, the reliability of group level and individual level can be evaluated.

The value of cronbach‘s alpha and item-total correlation must be more than 0.6 and 0.3 respectively. After considering the result of the first reliability analysis, three factors were deleted due to low Item-total correlation. As shown in Table II the final reliability analysis were conducted after deleting 3 factors.

[image:3.612.91.234.490.603.2]
(4)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

[image:4.612.42.297.155.375.2]

155

Table II

Reliability Analysis Results

SL NO GROUP CRONBACH‘S

ALPHA VALUE

A Manpower 0.692

B Managerial 0.662

C Environmental 0.625

D Motivation 0.664

E Material/Equipment 0.746

F Schedule 0.779

G Safety 0.670

H Quality 0.644

B. Factor Analysis

The main aim of factor analysis is to describe the larger number of variables by the smaller set of composite variables. Factor analysis is a statistical technique that explains the common underlying dimensions that compose variables (which are called ―components‖ in this study) by analyzing the correlation between the variables.

The theoretical model of this study identified 34 independent variables affecting the variation of labour productivity in the construction project. After conducting reliability analysis, three factors were deleted due to low Item-total correlation.

The result of the first factor analysis using rotated component matrix shows that the factors C1, C2, G1 got a blank space because of loading score less than 0.5 and factors A1, F1 did not cluster with any factors. Hence, these variables were deleted.

[image:4.612.44.296.156.376.2] [image:4.612.316.571.277.387.2]

As shown in Table III, the KMO value (0.59) is greater than 0.5, which means the data is likely to factor well and in Bartlett‘s test the significant value is lower than 0.05, which indicates that the correlation matrix is different from an identity matrix

Table III KMO And Bartlett’s Test

KMO measure of sampling adequacy 0.590

Bartlett‘s test of sphericity

Approx chi-square 557.5594

Df 325

Sig .000

(5)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

156

Table IV KMO And Bartlett’s Test

An orthogonal factor rotation analysis was conducted to clearly classify the components, and the rotated component matrix was analyzed, as shown in Table V.

The results of reliability analysis and factor analysis showed that three independent factors and one independent group were rejected due to low corrected item- total coefficient and loading score.

[image:5.612.76.536.168.493.2]

For the reason above, the theoretical model has been revised and the Hypothesis from H1, H2, H4, H5, H6, H7, and H8 has the same statement that is: There is a positive impact of the influenced factors on the variation of labour productivity. The hypothesis H3 is deleted.

(6)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

157

C. Multiple Regression Analysis

The coefficient of determination (R2) is equal to 0.822. This shows that manpower group, managerial group, material/equipment group, schedule group, safety group, and quality group can explain 82.2 percent of the variations in labour productivity and 17.8 percent cannot be explained. The P value of 0.000 implies that labour productivity is significant at the 5 percent significance level.

Result in table VI, indicate that about 82.2% of the variation in labour productivity can be explained by the seven independent variables. This indicates that the model is adequate in the prediction of the response of the dependent variable.

As shown in Table VII, F value of 35.380 indicates that the overall regression model is significant and has some explanatory value (P- value p=0.00<0.05). This also indicates that there is a significant relationship between the predictor variables (manpower, managerial, motivation, material/equipment, schedule, safety and quality) and response variable (labour productivity variation).

From Table VIII, the following regression model was fitted.

LPF = -3.105 + 0.233F1 + 0.199F2 + 0.344F4 + 0.225F5 + 0.124F6 + 0.218F7+0.168F8

(F1: manpower group, F2: managerial group, F4: motivation group, F5: material/equipment group, F6: schedule group, F7: safety group, F8: quality group)

D. Hypothesis Testing

Hypothesis H1:

Null hypothesis (H0): The manpower group has no impact on Labour Productivity Variation (LPV).

Research hypothesis (H1): The manpower group has significant impact on Labour Productivity Variation (LPV).

Based on the value of Beta and Sig in Table VIII, the testing for Hypothesis was conducted. The Standardized Regression coefficient (beta) of Manpower group on LPV is 0.233 and value of t is 3.205 (>2) and p = 0.002(<0.05).

[image:6.612.72.539.462.514.2]

This means at 95 % confident level, there is a statistic evidence to conclude that there is a positive impact of Manpower group on the variation of labour productivity. Therefore, Hypothesis H1 is accepted. Furthermore, the results of other hypotheses tests of research are presented in Table IX.

Table VI

Model Summary For Multiple Linear Regression Analysis

Table VII

[image:6.612.145.465.546.651.2]
(7)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

158

Table VIII

[image:7.612.107.505.170.342.2]

Coefficient Of Multiple Linear Regression Analysis

Table IX Hypothesis Summary

HYPOTH ESIS

GROUP T Sig Decision

H1 Manpower 3.205 .002 Reject H0

H2 Managerial 3.111 .003 Reject H0

H4 Motivation 4.825 .000 Reject H0

H5 Material/Equipment 3.263 .002 Reject H0

H6 Schedule 1.631 .110 Accept H0

H7 Safety 3.398 .001 Reject H0

H8 Quality 2.693 .010 Reject H0

E. Final research model

Manpower group H1+

Managerial group H2+

Motivation group H4+

Material/Equipment group H5+

Safety group H7+

Quality group H8+

VI. CONCLUSION

The theoretical model of this study proposed eight independent groups affecting the variation of Labour Productivity in the construction projects namely Manpower group, Managerial group, Environmental group, Motivation group, Material/Equipment, Schedule group, Safety group and quality group.

(8)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

159

The results of reliability analysis and factor analysis showed that three independent factors and one independent group were rejected due to low corrected item- total coefficient and loading score.

The results of multiple regression analysis showed that, six independent groups, which have a positive impact on labour productivity variation, and one group, which has no impact on labour productivity variation.

Multiple linear regression analysis indicates that the model can explain 82.2% of the variance in labour productivity.

Among six independent groups, motivation group has the highest impact on labour productivity variation.

The six independent groups were ranked based on the impact strength on labour productivity variation.

1) Motivation group

2) Manpower group

3) Material/Equipment group

4) Safety group 5) Managerial group

6) Quality group

VII. RECOMMENDATION

Firstly, the Motivation factor has the highest impact on Labour Productivity variation with the highest standardized beta of 0.344. The low labour satisfaction could have negative impact on labour productivity. So, the construction company should increase labour satisfaction by paying a reasonable salary, developing financial reward or recognition program and improving the living condition on site.

Secondly, manpower group plays an important role during the process of project. Bad workforce is a major problem and affects the time to accomplish the project task. The project manager of construction companies should increase their leadership skill and the labour skill in the project by appropriate training program. It is also necessary to improve labour commitment and the relationship among workers by increasing labour benefit and team building program.

Lastly, to ease the variation of labour productivity, the construction companies should improve supervision by implementing periodic meeting and ensure supervisors were correctly selected. The designing team should also be quite experienced to avoid revised drawings.

Material delay and material arrangement, tool and equipment management should be improved by adopting proper material management system. The planning software should be used in the project to have a proper planning of the work to reduce the frequency of working overtime.

REFERENCES

[1] AbouRizk, S., Knowles, P. and Hermann, U. (2001), ―Estimating labor production rates for industrial construction activities‖, Journal of Construction Engineering and Management, Vol. 127 No. 6, pp. 502-11.

[2] Allmon, E., Haas, C.T., Borcherding, J.D., Allmon, E. and Goodrum, P.M. (2000), ―US construction labor productivity trends, 1970-1998‖, Journal of Construction Engineering and Management, Vol. 126 No. 2, pp. 97-104.

[3] Bernstein, H.M. (2003), ―Measuring productivity: an industry challenge‖, Civil Engineering, Vol. 73 No. 12, pp. 46-53.

[4] Building Futures Council (2006), Measuring Productivity and Evaluating Innovation in theUS Construction Industry, BFC, Alexandria, VA.

[5] Dai, J., Goodrum, P.M. and Maloney, W.F. (2009), ―Construction craft workers‘ perceptions of the factors affecting their productivity‖, Journal of Construction Engineering and Management, Vol. 135 No. 3, pp. 217-26.

[6] Dissanayake, M., Fayek, R.A., Russell, A.D. and Pedrycz, W. (2005), ―A hybrid neural network for predicting construction labour productivity‖, Proceeding of ASCE International Conference on Computing in Civil Engineering, 12-15 July, Cancun, Mexico. [7] Durdyev, S., & Mbachu, J. (2011). On-site Labour Productivity of

New Zealand Construction Industry: Key Constraints and Improvement Measures. Australasian Journal of Construction Economic and Building, 1(3), 18-33.

[8] Enshassi, A., Mohamed, A., Mustafa, Z. A., & Mayer, P. E. (2007). Factors affecting labour productivity in building project in the Gaza strip. Journal of Civil Engineering and Management, 8(4), 245-254. [9] Henry, M. J., Jackson, A. M., Bengt, H. (2007). Factors affecting the

productivity of building craftmen – studies of Uganda. Journal of Civil Engineering and Management, 8(3), 169-176.

[10] Homyun Jang, Kyonghoom Kim, Juhyung Kim, and Jaejun Kim. (2011). Labour productivity model for reinforced concrete construction projects. Construction Innovationm Process, Management, 11(1), 92-113.

[11] Soekiman, A., Pribadi, A. S., Soemardi, B. W., & Wirahaddikusumah, R. D. (2011). Fatcors relating to labor productivity affecting the project schedule performance in indonesia. Procedia Engineering, 14(10), 865-873.

[12] Smith, S.D. (1999), ―Earthmoving productivity estimation using linear regression techniques‖, Journal of Construction Engineering and Management, Vol. 125 No. 3, pp. 133-41.

[13] Alvani, M., Ahmadi, P., 2001, ‗Designing a model for human resources productivity by using management productivity approach‘, Journal Research Scientific, vol. 5, pp. 19-27.

(9)

International Journal of Emerging Technology and Advanced Engineering

Website: www.ijetae.com (ISSN 2250-2459,ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)

160

[15] Attar, A.A, Gupta, A.k, Desai, D.B, ‗A Study of Various Factors Affecting Labour Productivity and Methods to Improve It‘, Journal of Mechanical and Civil Engineering, 11-14.

[16] Jimoh, I.A, ‗Effects of delay factors on labour productivity on nigerian construction sites‘, Interdisciplinary Journal of contemporary research in business, vol 5, no 4.

[17] Ibrahim Mahamid, September 2013 ‗Principal Factors Impacting Labor Productivity of Public Construction Projects in Palestine: Contractors‘ Perspective‘, International Journal of Architecture, Engineering and Construction, Vol 2, No 3, 194-202.

[18] Mistry Soham, Bhatt Rajiv. April 2013, ‗Critical Factors Affecting Labour Productivity in Construction Projects Case Study Of South Gujarat Region Of India‘, International Journal of Engineering and Advanced Technology, vol.2, no. 4.

[19] Schneider, Scott P, 2007, Economics of Health and Safety in Construction. Laborers' Health and Safety Fund of North America. [20] Schwartzkopf, William, 1995, Calculating Lost Labor Productivity

in Construction Claims. 2nd ed. Aspen.

[21] Abdulaziz M. Jarkas,ph.D., P.Eng.1; And Camille G. Bitar, P.Eng, 2012, ‗Factors Affecting Construction Labor Productivity In Kuwait‘, Journal Of Construction Engineering And Management .ASC.

[22] Wen Yi, Albert P.C. Chan, 2013, ‗Critical Review Of Labor Productivity Research In Construction‘, Journal Of Management In Engineering.

[23] Abdul Kadir, M. R., Lee, w. P., Jaafar, M. S., Sapuan, S. M., and Ali, A. A. (2005). ―Factors Affecting Construction Labour Productivity for Malaysian Residential Projects.‖ Struct. Surv., 23 (1), 42–54.

[24] Chithkar, k. k, Construction project management, Tata Mcgraw hill education private limited, New Delhi.

[25] Al-Shahri, M., Assaf S., A., Atiyah S., and AbdulAziz.A, (2001). ―The management of construction company overhead costs.‖ International Journal of Project Management, 19, 295-303. [26] Hanna, A. S., and Heale, D. G. (1994). "Factors affecting

Figure

Table I Factors Affecting Labour Productivity
Figure 1: Theoretical model
Table III KMO And Bartlett’s Test
Table V Factor Analysis Result
+3

References

Related documents

21 Department of Neurosurgery, Tangdu Hospital, The Second Affiliated hospital of the Fourth Military Medical University, 1 Xinsi Road, Xian, Shanxi Province 710038, People ’ s

AHS: anticonvulsant hypersensitivity syndrome; ADR: adverse drug reac- tion; AEDS: antiepileptic drugs; LP: lumber puncture; EBV: Epstein Barr virus; CMV: cytomegalovirus; HSV:

High order locally one dimensional methods for solving two dimensional parabolic equations Chen and Ge Advances in Difference Equations (2018) 2018 361 https //doi org/10 1186/s13662

CUAJ ? March April 2017 ? Volume 11, Issues 3 4 ? 2017 Canadian Urological Association E93 Wan Song, MD;1 Chan Kyo Kim, MD;2 Byung Kwan Park, MD;2 Hwang Gyun Jeon, MD;1 Byong Chang

Our approach in using H5P in the A&amp;P units provided substantial additional support and enhanced curriculum design, where H5P interactives were tightly aligned

Second, indigenous research must engage in a dialogue with the mainstream literature and frontiers of business research in the world so that important research questions can be

Es wird gezeigt, dass eine vorzeitige Belastung des Beckens beim Seitenaufprall tatsächlich zu einer Verringerung der Verletzungsgefahr für den Thorax führen kann.. Über

The utilization of neurodiagnostic tests in the initial work-up in children with brain tumors was relatively stable during the three years before computed tomography (CT)