Proposed Two-Storey Residential Building with Roofdeck
I. Concreting Works II. Rebar Works
PRICE LIST PRICE LIST
MATERIAL PRICE MATERIAL
LAFARGE REPUBLIC PORTLAND PLUS 40KG
₱
203.00 /bag 10 mmWASHED SAND
₱
600.00 /m³ 12 mmCRUSHED GRAVEL 1"
₱
850.00 /m³ 16 mmConcreting of Column Footing
#16 G.I. WIRETotal Volume of Column Footing (m³) 5.4 REINFORCEMENT BARS FOR COLUMN FOOTING (F1)
D IM EN SIO N S WIDTH 1.5
Total Length for of RSB for Column Footing (m)
LENGTH 1.5 HEIGHT/THICKNESS 0.2 D IM EN SIO N S NUMBER OF CF 12 CEMENT 48.6 TOTAL COST
₱
12825.54MATERIAL COST LABOR COST
₱
9865.8₱
2959.74₱
2375.1 /m³ 16 mmØ x 6m REINFORCEMENT STEEL BAR105.6 SAND
2.7 m³ of Washed Sand TOTAL COST MATERIAL COST
₱
2106 LABOR COSTMATERIAL COST LABOR COST COST
₱
1620₱
486₱
390 /m³ #16 G.I. WIRENUMBER OF INTERSECTIONS
GRAVEL NUMBER OF FOOTING
5.4 m³ of Crushed Gravel 1" TOTAL COST LENGTH OF TIE WIRE
₱
5967 302.4MATERIAL COST LABOR COST
₱
4590₱
1377₱
1105 /m³ MATERIAL COSTLABOR COST
Concreting of Column
TOTAL COSTTotal Volume of Column (m³) 11.56 ₱
REINFORCEMENT BARS FOR COLUMN FOOTING (F2)
D IM EN SIO N S WIDTH 0.25 LENGTH 0.4
Total Length for of RSB for Column Footing (m)
C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A
D IM EN SIO N S HEIGHT/THICKNESS 6.8
Total Length for of RSB for Column Footing (m)
NUMBER OF COLUMN 17 D IM EN SIO N S CEMENT 104.04 TOTAL COST
₱
27456.156MATERIAL COST LABOR COST
₱
21120.12₱
6336.036₱
2375.1 /m³16 mmØ x 6m REINFORCEMENT STEEL BAR SAND
9.9
5.78 m³ of Washed Sand TOTAL COST
₱
4508.4 MATERIAL COSTMATERIAL COST LABOR COST LABOR COST
₱
3468₱
1040.4₱
390 /m³ COST#16 G.I. WIRE
GRAVEL NUMBER OF INTERSECTIONS
11.56 m³ of Crushed Gravel 1" TOTAL COST NUMBER OF FOOTING
₱
12773.8 LENGTH OF TIE WIREMATERIAL COST LABOR COST
24.3
₱
9826₱
2947.8₱
1105 /m³MATERIAL COST
Concreting of Wall Footing
LABOR COSTTotal Volume of Wall Footing (m³) 4.4925 TOTAL COST
₱ D IM EN SIO N S WIDTH 0.5
REINFORCEMENT BARS FOR COLUMN (C1)
THICKNESS 0.15
LENGTH OF WF1 59.9
Total Length for of RSB for Column (m) CEMENT 40.4325 TOTAL COST D IM EN SIO N S
₱
10670.13675MATERIAL COST LABOR COST
₱
8207.7975₱
2462.33925₱
2375.1 /m³16 mmØ x 6m REINFORCEMENT STEEL BAR
SAND 119.68
2.24625 m³ of Washed Sand TOTAL COST
₱
1752.075 MATERIAL COSTMATERIAL COST LABOR COST LABOR COST
₱
1347.75₱
404.325₱
390 /m³ COST #16 G.I. WIRE C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland CementGRAVEL NUMBER OF LATERAL TIES
4.4925 m³ of Crushed Gravel 1" TOTAL COST NUMBER OF RSB
₱
4964.2125 NUMBER OF COLUMNMATERIAL COST LABOR COST LENGTH OF TIE WIRE
₱
3818.625₱
1145.5875₱
1105 /m³ 1180.8Concreting of Beam
MATERIAL COSTTotal Volume of Beam (m³) 16.9425 LABOR COST
TOTAL COST D IM EN SIO N S WIDTH 0.5 ₱ THICKNESS 0.15
REINFORCEMENT BARS FOR COLUMN (C2)
LENGTH OF BEAMS 225.9
LENGTH OF FTB-1 34.95
Total Length for of RSB for Column (m)
LENGTH OF RCB-1 190.95 CEMENT DIM EN SIO N S 152.4825 TOTAL COST
₱
40240.13175MATERIAL COST LABOR COST
₱
30953.9475₱
9286.18425₱
80480.2635 /m³ 16 mmØ x 6m REINFORCEMENT STEEL BAR9.97 SAND
8.47125 m³ of Washed Sand TOTAL COST MATERIAL COST
₱
6607.575 LABOR COSTMATERIAL COST LABOR COST COST
₱
5082.75₱
1524.825₱
13215.15 /m³LENGTH OF COLUMN LATERAL TIES (m)
GRAVEL PERIMETER OF COLUMN
16.9425 m³ of Crushed Gravel 1" TOTAL COST NUMBER OF COLUMN
₱
18721.4625 NUMBER OF LATERAL TIESMATERIAL COST LABOR COST NUMBER
₱
14401.125₱
4320.3375₱
37442.925 /m³ SPACINGREMAINING LENGTH
Concreting of Slab (GF)
SPACINGTotal Volume of Slab (m³) 14.3445 10 mmØ x 6m REINFORCEMENT STEEL BAR
166.12 D IM EN SIO N S THICKNESS 0.15
TOTAL AREA 95.63 MATERIAL COST
LABOR COST C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A
CEMENT COST
86.067 TOTAL COST #16 G.I. WIRE
₱
22713.0813 NUMBER OF LATERAL TIESMATERIAL COST LABOR COST NUMBER OF RSB
₱
17471.601₱
5241.4803₱
1583.4 /m³ NUMBER OF COLUMNLENGTH OF TIE WIRE SAND
98.4
7.17225 m³ of Washed Sand TOTAL COST
₱
5594.355 MATERIAL COSTMATERIAL COST LABOR COST LABOR COST
₱
4303.35₱
1291.005₱
390 /m³ TOTAL COST₱
GRAVEL
REINFORCEMENT BARS FOR WALL FOOTING
14.3445 m³ of Crushed Gravel 1" TOTAL COST
₱
15850.6725 Total Length of RSB for Wall Footing (m)MATERIAL COST LABOR COST
₱
12192.825₱
3657.8475₱
1105 /m³ D IM EN SIO N SConcreting of Slab (2F and RD)
Total Volume of Slab (m³) 35.23545
D IM EN SIO N S THICKNESS 0.15
TOTAL AREA 234.903 12 mmØ x 6m REINFORCEMENT STEEL BAR
32.95 CEMENT
317.11905 TOTAL COST MATERIAL COST
₱
83687.717295 LABOR COSTMATERIAL COST LABOR COST COST
₱
64375.16715₱
19312.550145₱
2375.1 /m³ 10 mmØ x 6m REINFORCEMENT STEEL BAR18.49 SAND
17.617725 m³ of Washed Sand TOTAL COST MATERIAL COST
₱
13741.8255 LABOR COSTMATERIAL COST LABOR COST COST
₱
10570.635₱
3171.1905₱
390 /m³ #16 G.I. WIRENUMBER OF HOOP BARS
GRAVEL NUMBER OF RSB
35.23545 m³ of Crushed Gravel 1" TOTAL COST LENGTH OF TIE WIRE
40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement
35.23545 m³ of Crushed Gravel 1"
₱
38935.17225 180.6MATERIAL COST LABOR COST
₱
29950.1325₱
8985.03975₱
1105 /m³ MATERIAL COSTLABOR COST
Concreting of Stairs
TOTAL COSTTotal Volume of Column (m³) 0.9 ₱
REINFORCEMENT BARS FOR CONCRETE BEAM (FTB-1)
D IM EN SIO N S WIDTH 1.5
LENGTH 0.2 Total Length of RSB for FTB-1
HEIGHT/THICKNESS 0.2 DIM EN SIO N S NUMBER OF STEPS 15 CEMENT 8.1 TOTAL COST
₱
2137.59 12 mmØ x 6m REINFORCEMENT STEEL BARMATERIAL COST LABOR COST
41.94
₱
1644.3₱
493.29₱
2375.1 /m³MATERIAL COST
SAND LABOR COST
0.45 m³ of Washed Sand TOTAL COST COST
₱
351 Total Length of Stirrups for FTB-1MATERIAL COST LABOR COST
₱
270₱
81₱
390 /m³ PERIMETER OF FTB-110 mmØ x 6m REINFORCEMENT STEEL BAR
GRAVEL 61.16
0.9 m³ of Crushed Gravel 1" TOTAL COST
₱
994.5 MATERIAL COSTMATERIAL COST LABOR COST LABOR COST
₱
765₱
229.5₱
1105 /m³ COST#16 G.I. WIRE
NUMBER OF STIRRUPS NUMBER OF RSB LENGTH OF TIE WIRE 550.4625
MATERIAL COST LABOR COST
TOTAL COST
₱
REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1)
C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement
REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1) Total Length of RSB for RCB-1
D IM EN SIO N S
16 mmØ x 6m REINFORCEMENT STEEL BAR
305.52
MATERIAL COST LABOR COST
COST
Total Length of Stirrups for RCB-1 PERIMETER OF RCB-1
10 mmØ x 6m REINFORCEMENT STEEL BAR 334.16 MATERIAL COST LABOR COST COST #16 G.I. WIRE NUMBER OF STIRRUPS NUMBER OF RSB LENGTH OF TIE WIRE 4009.95
MATERIAL COST LABOR COST
TOTAL COST
₱
REINFORCEMENT FOR GROUND FLOOR SLAB
Total Length of RSB for GF Slab A
B
LENGTH OF RSB ALONG A ALONG B
12 mmØ x 6m REINFORCEMENT STEEL BAR 257.91 MATERIAL COST LABOR COST COST #16 G.I. WIRE NUMBER OR INTERSECTIONS
LENGTH OF TIE WIRE 1310.4
MATERIAL COST LABOR COST
TOTAL COST
₱
REINFORCEMENT FOR 2F AND RD SLAB
NUMBER OF STEEL BARS AREA
12 mmØ x 6m REINFORCEMENT STEEL BAR 144.74
MATERIAL COST LABOR COST
COST
NUMBER OF STEEL BARS AREA
10 mmØ x 6m REINFORCEMENT STEEL BAR 144.74 MATERIAL COST LABOR COST COST #16 G.I. WIRE NUMBER OR INTERSECTIONS
LENGTH OF TIE WIRE Total Length of 12mmØ RSB
80.886
MATERIAL COST LABOR COST
TOTAL COST
II. Rebar Works III. Masonry Works
PRICE LIST PRICE LIST
MATERIAL PRICE MATERIAL
10 mm
₱
125.00 /pc CONCRETE HOLLOW BLOCK 5" THK12 mm
₱
192.00 /pc CONCRETE HOLLOW BLOCK 4" THK16 mm
₱
315.00 /pc LAFARGE REPUBLIC PORTLAND PLUS 40KG#16 G.I. WIRE
₱
180.00 /kg WASHED SANDREINFORCEMENT BARS FOR COLUMN FOOTING (F1) CRUSHED GRAVEL 1"
CONCRETE HOLLOW BLOCKS FOR WALL (EXTERIOR)
Total Length for of RSB for Column Footing (m) 633.6
LENGTH 3.3 NUMBER OF RSB
GROUND FLOOR
ALONG (B) 1.5 9 SECOND FLOOR
ALONG (L) 1.5 7
CONCRETE HOLLOW BLOCK 5" THK
NUMBER OF FOOTING (F1)
12
CEMENT MORTAR (CLASS C)
16 mmØ x 6m REINFORCEMENT STEEL BAR CEMENT
105.6 pcs TOTAL COST SAND
₱
43243.2
PLASTERING @ 12mm THK (CLASS B)MATERIAL COST
₱
33264
AREA OF WALLS (TWO SIDES)LABOR COST
₱
9979.2
CEMENTCOST ₱ 19219.2 /m SAND
#16 G.I. WIRE TOTAL COST
NUMBER OF INTERSECTIONS 63 MATERIAL COST
NUMBER OF FOOTING 16 CHB 5" THK
LENGTH OF TIE WIRE 0.3 m CEMENT
302.4 meters 5.71 kg. SAND
CHB 5" THK
MATERIAL COST
₱
1027.0188679245 CEMENTLABOR COST
₱
308.1056603774 SANDTOTAL COST
₱
1335.1245283019CONCRETE HOLLOW BLOCKS FOR WALL (INTERIOR) 593.3886792453
REINFORCEMENT BARS FOR COLUMN FOOTING (F2)
Total Length for of RSB for Column Footing (m) 59.4 GROUND FLOOR
R EIN FO R C EM EN T B AR S 16 m m Ø x 6 m R E IN FO R C E M E N T S T E E L B A R
Total Area of Exterior Walls (m²)
/m²
Total Area of Interior Walls (m²)
16 m m Ø x 6 m R E IN FO R C E M E N T S T E E L B A R
Total Length for of RSB for Column Footing (m)
Total Length for of RSB for Column Footing (m) 59.4
SECOND FLOOR
LENGTH 3.3 NUMBER OF RSB CONCRETE HOLLOW BLOCK 4" THK
ALONG (B) 1.5 9 CEMENT MORTAR (CLASS C)
ALONG (L) 1.5 9 CEMENT
NUMBER OF FOOTING (F1)
1
SANDPLASTERING @ 8mm THK (CLASS B)
16 mmØ x 6m REINFORCEMENT STEEL BAR AREA OF WALLS (TWO SIDES)
9.9 pcs TOTAL COST CEMENT
₱
4054.05
SANDMATERIAL COST
₱
3118.5
TOTAL COSTLABOR COST
₱
935.55
MATERIAL COSTCOST ₱ 68.25 /m CHB 5" THK
#16 G.I. WIRE CEMENT
NUMBER OF INTERSECTIONS 81 SAND
NUMBER OF FOOTING 1 CHB 5" THK
LENGTH OF TIE WIRE 0.3 m CEMENT
24.3 meters 0.46 kg. SAND
Total Length of RSB for Vertical Bars
MATERIAL COST
₱
82.5283018868LABOR COST
₱
24.758490566 TOTAL WIDTH OF WALLSTOTAL COST
₱
107.2867924528 SPACING47.6830188679 LENGTH
REINFORCEMENT BARS FOR COLUMN (C1) 12 mmØ x 6m REINFORCEMENT STEEL BAR
67.5229166667
Total Length for of RSB for Column (m) 718.08
MATERIAL COST LENGTH OF COLUMN 6.8
₱
12964.4 COST NUMBER OF RSB/COLUMN 6Total Length of RSB for Horizontal Bars
NUMBER OF COLUMN 16
16 mmØ x 6m REINFORCEMENT STEEL BAR HEIGHT OF WALL
119.68 pcs TOTAL COST WIDTH
₱
49008.96
10 mmØ x 6m REINFORCEMENT STEEL BARMATERIAL COST
₱
37699.2
8.98
LABOR COST
₱
11309.76
COST ₱ 68.25 /m MATERIAL COST
#16 G.I. WIRE LABOR COST
16 m m Ø x 6 m R E IN FO R C E M E N T S T E E L B A R /m² 16 m m Ø x 6 m R EIN FO R C EM EN T S TE EL BA R
NUMBER OF LATERAL TIES 41 COST
NUMBER OF RSB 6
NUMBER OF COLUMN 16
LENGTH OF TIE WIRE 0.3 /m
1180.8 meters 22.28 kg.
MATERIAL COST
₱
4010.2641509434LABOR COST
₱
1203.079245283TOTAL COST
₱
5213.3433962264766.6681465039 /m
REINFORCEMENT BARS FOR COLUMN (C2)
Total Length for of RSB for Column (m) 59.84
LENGTH OF COLUMN 6.8
NUMBER OF RSB/COLUMN 8
NUMBER OF COLUMN 1
16 mmØ x 6m REINFORCEMENT STEEL BAR
9.97 pcs TOTAL COST
₱
4084.08
MATERIAL COST
₱
3141.6
LABOR COST
₱
942.48
COST ₱ 68.25 /m
LENGTH OF COLUMN LATERAL TIES (m) 996.71
PERIMETER OF COLUMN 1.3 m
NUMBER OF COLUMN 17
NUMBER OF LATERAL TIES 40.5
NUMBER 11
TOTAL NUMBER OF LATERAL TIES
SPACING 0.1
REMAINING LENGTH 5.7
41
SPACING 0.2
10 mmØ x 6m REINFORCEMENT STEEL BAR
166.12 pcs TOTAL COST
₱
26994.2291666667
MATERIAL COST₱
20764.7916666667
LABOR COST₱
6229.4375
16 m m Ø x 6 m R EIN FO R C EM EN T S TE EL BA RCOST ₱ 27.0833333333 /m
#16 G.I. WIRE
NUMBER OF LATERAL TIES 41
NUMBER OF RSB 8
NUMBER OF COLUMN 1
LENGTH OF TIE WIRE 0.3 /m
98.4 meters 1.86 kg.
MATERIAL COST
₱
334.1886792453LABOR COST
₱
100.2566037736TOTAL COST
₱
434.445283018963.8890122087 /m
REINFORCEMENT BARS FOR WALL FOOTING
Total Length of RSB for Wall Footing (m) 197.67
NUMBER OF RSB 3
LENGTH OF WALL FOOTING 59.9
Total Length of Hoop Bars (m) 110.92
SPACING OF HOOP BARS 0.3
WIDTH OF HOOP BARS 0.5
12 mmØ x 6m REINFORCEMENT STEEL BAR
32.95 pcs TOTAL COST
₱
8223.072
MATERIAL COST
₱
6325.44
LABOR COST
₱
1897.632
COST ₱ 41.6 /m
10 mmØ x 6m REINFORCEMENT STEEL BAR
18.49 pcs TOTAL COST
₱
3003.9930555556
MATERIAL COST₱
2310.7638888889
LABOR COST₱
693.2291666667
COST ₱ 27.0833333333 /m #16 G.I. WIRENUMBER OF HOOP BARS 200.67
NUMBER OF RSB 3
LENGTH OF TIE WIRE 0.3 m
12 m m Ø a nd 1 0 m m Ø R EIN FO R C EM EN T S TE EL B AR S
180.6 meters 3.41 kg.
MATERIAL COST
₱
613.358490566LABOR COST
₱
184.0075471698TOTAL COST
₱
797.366037735813.3116199956 /m
REINFORCEMENT BARS FOR CONCRETE BEAM (FTB-1)
Total Length of RSB for FTB-1 251.64 m
NUMBER OF RSB 6
TOP BARS 3
BOTTOM BARS 3
TOTAL LENGTH OF FTB-1 34.95 m
12 mmØ x 6m REINFORCEMENT STEEL BAR
41.94 pcs TOTAL COST
₱
10468.224
MATERIAL COST
₱
8052.48
LABOR COST
₱
2415.744
COST ₱ 41.6 /m
Total Length of Stirrups for FTB-1 366.975
PERIMETER OF FTB-1 1.2 m
10 mmØ x 6m REINFORCEMENT STEEL BAR
61.16 pcs TOTAL COST
₱
9938.90625
MATERIAL COST₱
7645.3125
LABOR COST₱
2293.59375
COST ₱ 284.375 /m #16 G.I. WIRE NUMBER OF STIRRUPS 305.8125 NUMBER OF RSB 6LENGTH OF TIE WIRE 0.3
550.4625 meters 10.39 kg.
MATERIAL COST
₱
1869.4952830189LABOR COST
₱
560.8485849057TOTAL COST
₱
2430.3438679245810.1146226415 /m
REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1) REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1)
Total Length of RSB for RCB-1 1833.12 m
WEB BARS 2
TOP BARS 3
BOTTOM BARS 3
TOTAL LENGTH OF RCB-1 190.95 m
16 mmØ x 6m REINFORCEMENT STEEL BAR
305.52 pcs TOTAL COST
₱
125110.44
MATERIAL COST
₱
96238.8
LABOR COST
₱
28871.64
COST ₱ 68.25 /m
Total Length of Stirrups for RCB-1 2005.0
PERIMETER OF RCB-1 1.2 m
10 mmØ x 6m REINFORCEMENT STEEL BAR
334.16 pcs TOTAL COST
₱
54301.40625
MATERIAL COST₱
41770.3125
LABOR COST₱
12531.09375
COST ₱ 284.375 /m #16 G.I. WIRE NUMBER OF STIRRUPS 1670.8125 NUMBER OF RSB 8LENGTH OF TIE WIRE 0.3
4009.95 meters 75.66 kg.
MATERIAL COST
₱
13618.6981132075LABOR COST
₱
4085.6094339623TOTAL COST
₱
17704.307547169892.7169811321 /m
REINFORCEMENT FOR GROUND FLOOR SLAB
Total Length of RSB for GF Slab 1547.46
7.05 m SPACING ALONG A 48
13.5 m 0.15 m ALONG B 91
LENGTH OF RSB 1289.55 m
ALONG A 648 m
12 mmØ x 6m REINFORCEMENT STEEL BAR 257.91 pcs TOTAL COST
₱
64374.336
MATERIAL COST₱
49518.72
LABOR COST₱
14855.616
COST ₱ 14.7377142857 /m #16 G.I. WIRE NUMBER OR INTERSECTIONS 4368LENGTH OF TIE WIRE 0.3 m
1310.4 meters 24.72 kg.
MATERIAL COST
₱
4450.4150943396LABOR COST
₱
1335.1245283019TOTAL COST
₱
5785.53962264151.3245283019 /m
REINFORCEMENT FOR 2F AND RD SLAB
868.45
NUMBER OF STEEL BARS 3.221 m
AREA 269.62
12 mmØ x 6m REINFORCEMENT STEEL BAR
144.74 pcs TOTAL COST
₱
36127.354432
MATERIAL COST₱
27790.27264
LABOR COST₱
8337.081792
COST ₱ 133.9936 /m 868.45NUMBER OF STEEL BARS 3.221 m
AREA 269.62
10 mmØ x 6m REINFORCEMENT STEEL BAR
144.74 pcs TOTAL COST
₱
23520.4130416667
MATERIAL COST₱
18092.6254166667
LABOR COST₱
5427.787625
COST ₱ 87.2354166667 /m #16 G.I. WIRE NUMBER OR INTERSECTIONS 269.62LENGTH OF TIE WIRE 0.3 m
Total Length of 12mmØ RSB
m²
Total Length of 10mmØ RSB
80.886 meters 1.53 kg.
MATERIAL COST
₱
274.7071698113LABOR COST
₱
82.4121509434TOTAL COST
₱
357.1193207547III. Masonry Works III. Formworks
PRICE LIST PRICE LIST
MATERIAL PRICE MATERIAL
CONCRETE HOLLOW BLOCK 5" THK
₱
9.00 /pc Form Lumber 2" x 3" x 12' Coco Lumber CONCRETE HOLLOW BLOCK 4" THK₱
8.00 /pc Form Lumber 2" x 2" x 12' Coco LumberLAFARGE REPUBLIC PORTLAND PLUS 40KG
₱
203.00 /bag 1/2"x4'x8' Ordinary Plywood WASHED SAND₱
600.00 /m³ FORMS FOR COLUMNCRUSHED GRAVEL 1"
₱
850.00 /m³ SIDES OF THE COLUMNCONCRETE HOLLOW BLOCKS FOR WALL (EXTERIOR) SHORTER SIDE
LONGER SIDE 167.929
LATERAL PERIMETER OF THE COLUMN
GROUND FLOOR 85.3155 COLUMN HEIGHT
SECOND FLOOR 82.6135 NUMBER OF COLUMNS
CONCRETE HOLLOW BLOCK 5" THK 2099.1125 pcs. TOTAL AREA
1/2"x4'x8' Ordinary Plywood CEMENT MORTAR (CLASS C)
CEMENT 1601.62 bag TOTAL COST
SAND 177.17 MATERIAL COST
PLASTERING @ 12mm THK (CLASS B) LABOR COST
AREA OF WALLS (TWO SIDES) 335.86 m²
₱
42.651CEMENT 48.36 bag WOOD FRAME OF COLUMNS
SAND 4.03 m³
Form Lumber 2" x 2" x 12' Coco Lumber
TOTAL COST
₱
601323.43MATERIAL COST LABOR COST TOTAL COST
₱
18892.0125₱
5667.60375 MATERIAL COST₱
334947.2370685₱
100484.17112055 LABOR COST₱
108717.23₱
32615.17038₱
29.000CHB 5" THK
₱
146.25 /m² SCAFFOLDING FOR COLUMNSCEMENT
₱
2592.94945 /m²HORIZONTAL BRACES
SAND
₱
841.62 /m²CONCRETE HOLLOW BLOCKS FOR WALL (INTERIOR) VERTICAL BRACES
DIAGONAL BRACES 150.005
Form Lumber 2" x 2" x 12' Coco Lumber
GROUND FLOOR 65.2
Total Area of Exterior Walls (m²)
m³
SECOND FLOOR 84.805 TOTAL COST
CONCRETE HOLLOW BLOCK 4" THK 1875.0625 pcs. MATERIAL COST
LABOR COST
CEMENT MORTAR (CLASS C)
₱
1675.960CEMENT 1430.67 bag
Form Lumber 2" x 3" x 12' Coco Lumber
SAND 158.26
PLASTERING @ 8mm THK (CLASS B) TOTAL COST
AREA OF WALLS (TWO SIDES) 300.01 m² MATERIAL COST
CEMENT 28.80 bag LABOR COST
SAND 2.40 m³
₱
66.733TOTAL COST
₱
529966.92 FORMS FOR BEAMMATERIAL COST LABOR COST PERIMETER OF TWO SIDES FORM
₱
15000.5₱
4500.15 TWO SIDE FORMS₱
296273.1504425₱
88881.94513275 BOTTOM FORM₱
96393.21₱
28917.9639 LENGTH OF BEAM CHB 5" THK₱
130 /m² TOTAL AREA CEMENT₱
2567.61505 /m² 1/2"x4'x8' Ordinary Plywood SAND₱
835.38 /m²Total Length of RSB for Vertical Bars 405.1375 m TOTAL COST
MATERIAL COST
TOTAL WIDTH OF WALLS 107.77 m LABOR COST
SPACING 0.8 m
₱
42.651LENGTH 3.00 m WOOD FRAME OF COLUMNS
12 mmØ x 6m REINFORCEMENT STEEL BAR
Form Lumber 2" x 3" x 12' Coco Lumber
67.5229166667 pcs. TOTAL COST
₱
16853.72 TOTAL COSTMATERIAL COST LABOR COST MATERIAL COST
12964.4
₱
3889.32 LABOR COST₱ 156.3860072376 /m
₱
55.126Total Length of RSB for Horizontal Bars 53.885 m SCAFFOLDING FOR COLUMNS
HORIZONTAL BRACES
HEIGHT OF WALL 3
WIDTH 107.77 VERTICAL BRACES
10 mmØ x 6m REINFORCEMENT STEEL BAR
Form Lumber 2" x 2" x 12' Coco Lumber
8.98 pcs TOTAL COST
₱
1459.3854166667
TOTAL COSTMATERIAL COST
₱
1122.6041666667
MATERIAL COSTLABOR COST
₱
336.78125
LABOR COST₱ 27.0833333333 /m
₱
47.165Form Lumber 2" x 3" x 12' Coco Lumber TOTAL COST
MATERIAL COST LABOR COST
PRICE LIST
MATERIAL PRICE
Form Lumber 2" x 3" x 12' Coco Lumber
₱
132.00 /pc Form Lumber 2" x 2" x 12' Coco Lumber₱
88.00 /pc1/2"x4'x8' Ordinary Plywood
₱
320.00 /pcFORMS FOR COLUMN
SIDES OF THE COLUMN 0.65 m
SHORTER SIDE 0.25 m
LONGER SIDE 0.4 m
LATERAL PERIMETER OF THE COLUMN 1.5 m
COLUMN HEIGHT 6.8 m NUMBER OF COLUMNS 17 TOTAL AREA 173.4 m² 1/2"x4'x8' Ordinary Plywood 17.7780511811 pcs TOTAL COST
₱
7395.67 MATERIAL COST₱
5688.98 LABOR COST₱
1706.69 42.651 /m²WOOD FRAME OF COLUMNS
Form Lumber 2" x 2" x 12' Coco Lumber 43.956
pc s TOTAL COST
₱
5028.59 MATERIAL COST₱
3868.15 LABOR COST₱
1160.44 29.000 /m²SCAFFOLDING FOR COLUMNS
HORIZONTAL BRACES 2427.6 bd. F
t.
VERTICAL BRACES 809.2 bd. Ft.
DIAGONAL BRACES 1352.52 bd. F
t.
Form Lumber 2" x 2" x 12' Coco Lumber 2540.310
bd
. F
TOTAL COST
₱
290611.46MATERIAL COST
₱
223547.28LABOR COST
₱
67064.181675.960 /m²
Form Lumber 2" x 3" x 12' Coco Lumber 67.433
bd . F t. TOTAL COST
₱
11571.56 MATERIAL COST₱
8901.20 LABOR COST₱
2670.36 66.733 /m²FORMS FOR BEAM
PERIMETER OF TWO SIDES FORM 0.95 m
TWO SIDE FORMS 0.25 m
BOTTOM FORM 0.35 m LENGTH OF BEAM 225.9 m TOTAL AREA 214.605 m² 1/2"x4'x8' Ordinary Plywood 22.003 pcs TOTAL COST
₱
9153.10 MATERIAL COST₱
7040.85 LABOR COST₱
2112.25 42.651 /m²WOOD FRAME OF COLUMNS
Form Lumber 2" x 3" x 12' Coco Lumber 68.942
bd . F t. TOTAL COST
₱
11830.38 MATERIAL COST₱
9100.29 LABOR COST₱
2730.09 55.126 /m²SCAFFOLDING FOR COLUMNS
HORIZONTAL BRACES 88.4775 bd. F
t.
VERTICAL BRACES 112.95 bd. Ft.
Form Lumber 2" x 2" x 12' Coco Lumber 88.478
pc
s
TOTAL COST
₱
10121.83MATERIAL COST
₱
7786.0247.165 /m²
Form Lumber 2" x 3" x 12' Coco Lumber 112.950
bd . F t. TOTAL COST
₱
19382.22 MATERIAL COST₱
14909.40 LABOR COST₱
4472.82 90.316 /m²TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK
BILL OF MATERIALS
I.D. NO DESCRIPTION UNIT
GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
lot and Services/Demobilization/Permits
Sub-total 1.00 Earthworks
1.01 Clearing and Grubbing sq.m
1.02 Structural Excavation cu.m
1.03 Backfilling and Compaction cu.m
1.04 Gravel Bedding G-1 cu.m
1.05 Select Fill cu.m
1.06 Soil Poisoning sq.m
Sub-Total
2.00 Concreting Works Column Footing
2.01 Portland Cement bag
2.02 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Wall Footing
2.01 Portland Cement bag
2.02 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Column
2.01 Portland Cement bag
2.02 Crushed Gravel 3/4"" cu.m
2.03 Washed Sand cu.m
Beams
2.01 Portland Cement bag
2.02 Crushed Gravel 3/4"" cu.m
2.03 Washed Sand cu.m
Slab on Grade
2.01 Portland Cement bag
2.02 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
2.01 Portland Cement bag
2.02 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Sub-total 3.00 Rebar Works Footings Column Footings 3.01 16 mm pc 3.02 #16 G.I. Wire kg Wall Footings 3.01 12 mm pc 3.02 10 mm pc 3.03 #16 G.I. Wire kg Column 3.01 16 mm pc 3.02 10 mm pc 3.03 #16 G.I. Wire kg
Roof beams & Tie beams
3.01 16 mm pc 3.02 12 mm pc 3.03 10 mm pc 3.04 #16 G.I. Wire kg Slabs 3.01 12 mm pc 3.02 10 mm pc 3.03 #16 G.I. Wire kg Sub-total
4.00 Forms and Scaffoldings Column form
4.01 Good lumber ( 2" x 2" x 12') pc
4.02 Plywood Ordinary, 1/4" x 4" x 8' pc
4.03 CWN, Assorted kg
Column & Roof beam Scaffolding
4.01 Vertical Support ( 2" x 3" x 12' Good lumber) pc
Horizontal Support (2" x 2" x 12' Good lumber) pc
Diagonal braces (2" x 2" x 12' Good lumber) pc
4.02 CWN, Assorted kg
Beam form
4.01 Good lumber ( 2" x 2" x 12') pc
4.03 CWN, Assorted kg Sub-total 5.00 Masonry Works Masonry wall 5.01 CHB 5" THK pcs. 5.02 CHB 4" THK pcs.
5.03 Portland Cement bag
5.04 Washed Sand cu.m
5.05 12mm x 6m RSB pc
5.06 #61 G.I. Tie wire kg
Plastering
5.01 Portland Cement bag
5.02 Washed Sand cu.m
Sub-total
6.00 Doors And Windows
6.01 set 6.02 set 6.03 set 6.04 set 6.05 set 6.07 set 6.08 set 6.09 set 6.1 set 6.12 set 6.13 set Sub-total 7.00 Electrical Works Roughing-ins
7.01 Electrical Conduit uPVC, 15mmØ pc
D-1, Double swing panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb
D-2, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb
D-3, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb
W-1, 12mm thk. bronze glass on powder coated aluminum frame
W-2, 6mm thk. bronze glass on powder coated aluminum frame
W-3, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-4, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-5, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-6, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-7, 12mm thk. bronze glass on powder coated aluminum frame
W-8, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs.
7.02 RSC 60mmØ pc
7.03
Entrance Cap 60mm dia.
pc
7.04
Junction Box , 4" x 4" G.I
pc
7.05
Utility Box, 2" x 4" x G.I
pc
7.06
Grounding Rod, 2.4m x 16mm dia.
pc Wires and Fixtures
7.01
3.5 mm2 THW wire , Stranded
box
7.02
Duplex C.O. with Plate
pc
7.03
3 Way Switch With Plate
pc
7.04
40 watts Flourescent Lamp
pc
7.05
Single Switch with Plate
pc
7.06
2-Gang Switch with Plate
pc
7.07 Incandescent Bulb 50W set
7.08 Panel Box, Flush Type, 4 Branches set
7.09 Circuit Breaker, 20A 2P set
7.10 Main Circuit Breaker, 175A 2P set
7.11 Electrical Tape pc
Sub-total 8.00 Plumbing Works
8.01 Water Closet 1.6gpf with Accessories set
8.02 Kitchen Sink set
8.03 Faucet , Hose Bibb , Brass 3/4"Ø pc
8.04 G.I Coupling, 3/4"Ø pc
8.05 G.I Tee, 3/4"Ø pc
8.06 G.I. Pipe 3/4" Sch.40 pc
8.07 G.I. Elbow 90° x 3/4"Ø pc
8.08 Gate Valve , 3/4"dia. pc
8.09 Check Valve , 3/4"dia. pc
8.10 S.S. Floor Drain 4' x 4" pc
9.00 Sanitary works
9.01 uPVC Sanitary Pipe 4"Ø x 10' pc
9.02 uPVC Wye 4" x 4" pc
9.03 uPVC Wye 4" x 2" pc
9.04 uPVC Sanitary Pipe 2"Ø pc
9.05 uPVC P-TRAP 2"Ø pc
9.06 uPVC P-TRAP 4"Ø pc
9.07 uPVC Elbow 45° x 4 "Ø pc
9.08 uPVC Cleanout 4" diameter pc
9.09 PVC Cement can
Sub-total 10.00 Painting Works
Concrete surfaces sq.m
10.01 Neutralizer qrt
10.02 Latex, Flat gal
10.03 Latex, Semi Gloss gal
10.04 Acri Color qrt
Sub-total 11.00 TileWorks
Wall
11.01 Unglazed Wall Tiles 20cm x 30cm T&B pc
11.02 Unglazed Wall Tiles 20cm x 20cm KITCHEN pc
11.03 Tile Trim 6mm. pc
11.04 Lining 2" X 20cm (T&B and KITCHEN) pc
11.05 Tile Adhesive 25kg/bag bag
11.06 Tile Grout 5 kg/bag bag
Flooring sq.m
11.01 Glazed Floor Tiles 20cmx 20cm(INTERIOR ) pc
11.02 Tile Adhesive 25kg/bag bag
11.03 Tile Grout 5 kg/bag bag
Sub-total
TOTAL BUILDING COST (LABOR AND MATERIAL)
PRICE FOR BIDDING
LABOR AND MATERIALS
TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK
BILL OF MATERIALS
QTY UNIT COST TOTAL COST
MATERIAL LABOR MATERIAL LABOR
1.00 30,000.00 9,000.00 30,000.00 9,000.00 140.00 0.00 50.00 0.00 7,000.00 75.80 0.00 250.00 0.00 18,950.00 50.00 150.00 50.00 7,500.00 2,500.00 5.00 850.00 255.00 4,250.00 1,275.00 13.00 150.00 45.00 1,950.00 585.00 140.00 50.00 15.00 7,000.00 2,100.00 48.60 203.00 66.00 9,865.80 3,207.60 5.40 850.00 255.00 4,590.00 1,377.00 2.70 600.00 180.00 1,620.00 486.00 40 203.00 66.00 8,120.00 2,640.00 2.25 850.00 255.00 1,912.50 573.75 4.5 600.00 180.00 2,700.00 810.00 105.00 203.00 66.00 21,315.00 6,930.00 11.56 850.00 255.00 9,826.00 2,947.80 5.78 600.00 180.00 3,468.00 1,040.40 153.00 203.00 66.00 31,059.00 10,098.00 16.94 850.00 255.00 14,399.00 4,319.70 8.47 600.00 180.00 5,082.00 1,524.60 417.00 203.00 66.00 84,651.00 27,522.00 50.85 850.00 255.00 43,225.90 12,967.77 25.40 600.00 180.00 15,240.60 4,572.18
8.00 203.00 66.00 1,624.00 528.00 0.90 850.00 255.00 765.00 229.50 0.45 600.00 180.00 270.00 81.00 164.00 315.00 10.00 51,660.00 1,640.00 4.28 180.00 10.00 770.40 42.80 33.00 192.00 10.00 6,336.00 330.00 18.50 125.00 10.00 2,312.50 185.00 3.41 180.00 10.00 613.80 34.10 130.00 315.00 10.50 40,950.00 1,365.00 167.00 125.00 10.00 20,875.00 1,670.00 24.14 180.00 10.00 4,345.20 241.40 306.00 315.00 10.50 96,390.00 3,213.00 41.94 192.00 10.00 8,052.48 419.40 395.00 125.00 10.00 49,375.00 3,950.00 86 180.00 10.00 15,480.00 860.00 403.00 192.00 10.00 77,376.00 4,030.00 144.74 125.00 10.00 18,092.50 1,447.40 26.25 180.00 10.00 4,725.00 262.50 44.00 88.00 26.40 3,872.00 1,161.60 18.00 320.00 96.00 5,760.00 1,728.00 30.00 80.00 24.00 2,400.00 720.00 180.38 132.00 39.60 23,810.16 7,143.05 209.67 88.00 26.40 18,450.96 5,535.29 112.71 88.00 26.40 9,918.48 2,975.54 35.00 80.00 24.00 2,800.00 840.00 69.00 88.00 26.40 6,072.00 1,821.60 22.00 320.00 96.00 7,040.00 2,112.00
30.00 80.00 24.00 2,400.00 720.00 2,100.00 9.00 2.55 18,900.00 5,355.00 1,875.00 8.00 2.55 15,000.00 4,781.25 3,032.00 203.00 57.00 615,496.00 172,824.00 275.43 600.00 168.00 165,258.00 46,272.24 76.50 192.00 9.60 14,688.00 734.40 20.00 180.00 19.50 3,600.00 390.00 77.16 203.00 54.00 15,663.48 4,166.64 56.32 600.00 168.00 33,792.00 9,461.76 1 10,800.00 3,240.00 10,800.00 3,240.00 5 4,500.00 1,350.00 22,500.00 6,750.00 3 2,495.00 748.50 7,485.00 2,245.50 1 8,700.00 2,610.00 8,700.00 2,610.00 9 7,500.00 2,250.00 67,500.00 20,250.00 6 7,000.00 2,100.00 42,000.00 12,600.00 7 5,625.00 1,687.50 39,375.00 11,812.50 2 5,500.00 1,650.00 11,000.00 3,300.00 5 4,200.00 1,260.00 21,000.00 6,300.00 1 3,145.00 943.50 3,145.00 943.50 1 3,000.00 900.00 3,000.00 900.00 50.00 58.00 14.50 2,900.00 725.00
11.00 1,000.00 250.00 11,000.00 2,750.00 11.00 80.00 20.00 880.00 220.00 34.00 20.00 5.00 680.00 170.00 12.00 20.00 5.00 240.00 60.00 14.00 200.00 50.00 2,800.00 700.00 12.00 3,750.00 937.50 45,000.00 11,250.00 14.00 108.00 27.00 1,512.00 378.00 4.00 250.00 62.50 1,000.00 250.00 10.00 150.00 37.50 1,500.00 375.00 10.00 68.00 17.00 680.00 170.00 13.00 108.00 27.00 1,404.00 351.00 14.00 40.00 10.00 560.00 140.00 3.00 320.00 80.00 960.00 240.00 4.00 350.00 87.50 1,400.00 350.00 1.00 3,000.00 750.00 3,000.00 750.00 35.00 25.00 6.25 875.00 218.75 4.00 4,500.00 1,125.00 18,000.00 4,500.00 2.00 600.00 150.00 1,200.00 300.00 7.00 250.00 62.50 1,750.00 437.50 11.00 17.00 4.25 187.00 46.75 11.00 17.00 4.25 187.00 46.75 13.00 370.00 92.50 4,810.00 1,202.50 8.00 17.00 4.25 136.00 34.00 5.00 360.00 90.00 1,800.00 450.00 12.00 300.00 75.00 3,600.00 900.00 4.00 200.00 50.00 800.00 200.00
11.00 525.00 131.25 5,775.00 1,443.75 11.00 160.00 40.00 1,760.00 440.00 14.00 97.00 24.25 1,358.00 339.50 14.00 205.00 51.25 2,870.00 717.50 11.00 50.00 12.50 550.00 137.50 17.00 110.00 27.50 1,870.00 467.50 8.00 97.00 24.25 776.00 194.00 5.00 110.00 27.50 550.00 137.50 6.00 120.00 30.00 720.00 180.00 646.52 8.62 130.00 32.50 1,120.60 280.15 21.55 450.00 112.50 9,697.50 2,424.38 22.00 440.00 110.00 9,680.00 2,420.00 4.20 123.00 30.75 516.60 129.15 168.00 40.00 10.00 6,720.00 1,680.00 45.00 32.00 8.00 1,440.00 360.00 21.00 50.00 12.50 1,050.00 262.50 54.00 25.00 6.25 1,350.00 337.50 8.00 270.00 67.50 2,160.00 540.00 8.00 165.00 41.25 1,320.00 330.00 431.39 15,530.00 13.00 3.25 201,890.00 50,472.50 134.00 270.00 67.50 36,180.00 9,045.00 134.00 185.00 46.25 24,790.00 6,197.50
TOTAL BUILDING COST (LABOR AND MATERIAL)
2,993,117.44
PRICE FOR BIDDING
TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK
TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK
BILL OF MATERIALS
COST (MATERIALS AND LABOR AND LABOR ONLY)
DETAILED ESTIMATES
GRAND TOTAL I.D. NO
39,000.00 39,000.00 1.00 7,000.00 1.01 18,950.00 1.02 10,000.00 1.03 5,525.00 1.04 2,535.00 1.05 9,100.00 1.06 53,110.00 2.00 13,073.40 2.01 5,967.00 2.02 2,106.00 2.03 10,760.00 2.01 2,486.25 2.02 3,510.00 2.03 28,245.00 2.01 12,773.80 2.02 4,508.40 2.03 41,157.00 2.01 18,718.70 2.02 6,606.60 2.03 112,173.00 2.01 56,193.67 2.02 19,812.78 2.03
2,152.00 2.01 994.50 2.02 351.00 2.03 303,686.45 3.00 53,300.00 3.01 813.20 3.02 6,666.00 3.01 2,497.50 3.02 647.90 3.01 42,315.00 3.02 22,545.00 3.03 4,586.60 99,603.00 3.01 8,471.88 3.02 53,325.00 3.03 16,340.00 3.01 81,406.00 3.02 19,539.90 3.03 4,987.50 417,044.48 3.01 3.02 5,033.60 3.03 7,488.00 3,120.00 3.01 3.02 30,953.21 3.03 23,986.25 12,894.02 3,640.00 3.01 3.02 7,893.60 9,152.00 3.01
3,120.00 3.02 107,280.68 3.03 4.00 24,255.00 19,781.25 4.01 788,320.00 4.02 211,530.24 4.03 15,422.40 3,990.00 4.01 19,830.12 43,253.76 4.02 1,236,783.45 4.01 14,040.00 4.02 29,250.00 4.03 9,730.50 11,310.00 5.00 87,750.00 54,600.00 5.01 51,187.50 5.02 14,300.00 5.03 27,300.00 5.04 4,088.50 5.05 3,900.00 5.06 307,456.50 5.01 5.02 3,625.00
13,750.00 6.00 1,100.00 6.01 850.00 6.02 300.00 6.03 3,500.00 6.04 6.05 56,250.00 6.07 1,890.00 6.08 1,250.00 6.09 1,875.00 6.1 850.00 6.12 1,755.00 6.13 700.00 1,200.00 7.00 1,750.00 3,750.00 7.01 1,093.75 7.02 95,488.75 7.03 7.04 22,500.00 7.05 1,500.00 7.06 2,187.50 233.75 7.01 233.75 7.02 6,012.50 7.03 170.00 7.04 2,250.00 7.05 4,500.00 7.06 1,000.00 7.07 40,587.50 7.08
7.09 7,218.75 7.10 2,200.00 7.11 1,697.50 3,587.50 8.00 687.50 8.01 2,337.50 8.02 970.00 8.03 687.50 8.04 900.00 8.05 20,286.25 8.06 8.07 8.08 1,400.75 8.09 12,121.88 8.10 12,100.00 645.75 9.00 26,268.38 9.01 9.02 9.03 8,400.00 9.04 1,800.00 9.05 1,312.50 9.06 1,687.50 9.07 2,700.00 9.08 1,650.00 9.09 252,362.50 10.00 45,225.00 10.01 30,987.50 10.02 346,125.00 10.03
2,993,117.44
10.04PRICE FOR BIDDING
11.00/m²
11.0111.0211.03 11.04 11.05
11.06
11.01
11.02 11.03
TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK
DETAILED ESTIMATES
COST (MATERIALS AND LABOR AND LABOR ONLY)
DESCRIPTION COST
MATERIALS AND LABOR
GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
Php 278.57
and Services/Demobilization/Permits
Earthworks
Php 379.36
Clearing and Grubbing
Php 50.00
Structural Excavation
Php 135.36
Backfilling and Compaction
Php 71.43
Gravel Bedding G-1
Php 39.46
Select Fill
Php 18.11
Soil Poisoning
Php 65.00
Concreting Works
Php 63,257.24
Concreting of Column Footing (F1)
Php 3,916.00
Portland Cement
Php 2,421.00
Crushed Gravel 1"
Php 1,105.00
Washed Sand
Php 390.00
Concreting of Wall Footing (WF1) Php 3,103.01
Portland Cement
Php 1,992.59
Crushed Gravel 1"Php 460.42
Washed SandPhp 650.00
Column (C1 & C2) Php 8,430.96 Portland CementPhp 5,230.56
Crushed Gravel 3/4""Php 2,365.52
Washed SandPhp 834.89
Beams (FTB-1, RCB-1 & RFB-1) Php 12,311.54 Portland CementPhp 7,621.67
Crushed Gravel 3/4""Php 3,466.43
Washed SandPhp 1,223.44
Slab on Grade (S-1) Php 34,848.05 Portland CementPhp 20,772.78
Crushed Gravel 1"Php 10,406.24
Washed SandPhp 3,669.03
Stairs Php 647.69Portland Cement
Php 398.52
Crushed Gravel 1"
Php 184.17
Washed Sand
Php 65.00
Rebar Works Php 8,162.37
Reinforcing Steel Bars in Footings Php 3,582.52 Column Footing (C1F1) Php 1,651.05 16 mm
Php 1,601.60
#16 G.I. WirePhp 49.45
Column Footing (C2F1) Php 1,849.48 16 mmPhp 1,801.80
#16 G.I. WirePhp 47.68
Wall FootingsPhp 81.99
12 mmPhp 41.60
10 mmPhp 27.08
#16 G.I. WirePhp 13.31
Reinforcing Steel Bars in Column Php 1,629.87
Column (C1F1) Php 731.87 16 mm
Php 450.45
10 mmPhp 233.51
#16 G.I. WirePhp 47.91
Column (C2F1) Php 898.00 16 mmPhp 600.60
10 mmPhp 233.51
#16 G.I. WirePhp 63.89
Reinforcing Steel Bars in Roof Beams
Php 1,686.46
FTB-1
Php 653.88
12 mmPhp 300.00
10 mmPhp 284.35
#16 G.I. WirePhp 69.53
RCB-1 and RFB-2Php 1,032.58
16 mmPhp 655.20
10 mmPhp 284.38
#16 G.I. WirePhp 93.00
Reinforcing Steel Bars in Slabs
Php 1,263.52
Ground Floor Slab
Php 738.52
12 mm
Php 677.62
#16 G.I. Wire
Php 60.90
S-1
Php 525.00
10 mm
Php 174.87
#16 G.I. Wire
Php 75.00
Installation of Forms and Scaffoldings Php 15,776.57
Column form Php 2,300.24
Good lumber ( 2" x 2" x 12')
Php 740.24
Plywood Ordinary, 1/4" x 4" x 8'
Php 1,101.18
CWN, Assorted
Php 458.82
Column & Roof beam Scaffolding Php 10,510.81
Vertical Support ( 2" x 3" x 12' Good lumber)
Php 4,551.94
Horizontal Support (2" x 2" x 12' Good lumber)
Php 3,527.39
Diagonal braces (2" x 2" x 12' Good lumber)
Php 1,896.18
CWN, Assorted
Php 535.29
Beam formPhp 2,965.53
Good lumber ( 2" x 2" x 12')Php 1,160.82
Plywood Ordinary, 1/4" x 4" x 8'Php 1,345.88
CWN, AssortedPhp 458.82
Masonry WorksPhp 3,690.59
Masonry wall Php 3,491.59 CHB 5" THKPhp 144.38
CHB 4" THKPhp 131.88
Portland CementPhp 2,486.81
Washed SandPhp 667.29
12mm x 6m RSBPhp 48.65
#61 G.I. Tie wire
Php 12.59
Plastering
Php 199.00
Portland Cement
Php 62.56
Installation of Doors And Windows
Php 3,236.38
D-1, Double swing panel door with 2" x 6" wooden frame & 2" x 6" wooden door jambPhp 147.79
Php 307.89
Php 102.43
Php 119.05
Php 923.68
Php 574.74
Php 538.82
Php 150.53
Php 287.37
Php 43.04
Php 41.05
Electrical WorksPhp 1,005.14
Installation of Roughing-insPhp 243.42
Electrical Conduit uPVC, 15mmØ
Php 38.16
RSC 60mmØ
Php 144.74
Entrance Cap 60mm dia.
Php 11.58
Junction Box , 4" x 4" G.I
Php 8.95
Utility Box, 2" x 4" x G.I
Php 3.16
Grounding Rod, 2.4m x 16mm dia.
Php 36.84
Wires and Fixtures
Php 761.72
3.5 mm2 THW wire , Stranded
Php 592.11
Duplex C.O. with Plate
Php 19.89
3 Way Switch With Plate
Php 13.16
40 watts Flourescent Lamp
Php 19.74
Single Switch with Plate
Php 8.95
2-Gang Switch with Plate
Php 18.47
Incandescent Bulb 50W
Php 7.37
Panel Box, Flush Type, 4 Branches
Php 12.63
D-2, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb
D-3, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb
W-1, 12mm thk. bronze glass on powder coated aluminum frame
W-2, 6mm thk. bronze glass on powder coated aluminum frame
W-3, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-4, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-5, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-6, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-7, 12mm thk. bronze glass on powder coated aluminum frame
W-8, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs.
Circuit Breaker, 20A 2P
Php 18.42
Main Circuit Breaker, 175A 2P
Php 39.47
Electrical Tape
Php 11.51
Plumbing Works
Php 427.24
Water Closet 1.6gpf with Accessories
Php 236.84
Kitchen Sink
Php 15.79
Faucet , Hose Bibb , Brass 3/4"Ø
Php 23.03
G.I Coupling, 3/4"Ø
Php 2.46
G.I Tee, 3/4"Ø
Php 2.46
G.I. Pipe 3/4" Sch.40
Php 63.29
G.I. Elbow 90° x 3/4"Ø
Php 1.79
Gate Valve , 3/4"dia.
Php 23.68
Check Valve , 3/4"dia.
Php 47.37
S.S. Floor Drain 4' x 4"
Php 10.53
Sanitary works
Php 213.54
uPVC Sanitary Pipe 4"Ø x 10'
Php 75.99
uPVC Wye 4" x 4"
Php 23.16
uPVC Wye 4" x 2"
Php 17.87
uPVC Sanitary Pipe 2"Ø
Php 37.76
uPVC P-TRAP 2"Ø
Php 7.24
uPVC P-TRAP 4"Ø
Php 24.61
uPVC Elbow 45° x 4 "Ø
Php 10.21
uPVC Cleanout 4" diameter
Php 7.24
PVC Cement
Php 9.47
Painting WorksPhp 87.56
Concrete surfaces NeutralizerPhp 4.67
Latex, FlatPhp 40.41
Latex, Semi Gloss
Php 40.33
Acri Color
Php 2.15
TileWorks
Php 3,643.42
Wall
Php 184.74
Unglazed Wall Tiles 20cm x 30cm T&B
Php 88.42
Unglazed Wall Tiles 20cm x 20cm KITCHEN
Php 18.95
Tile Trim 6mm.
Php 13.82
Lining 2" X 20cm (T&B and KITCHEN)
Php 17.76
Tile Grout 5 kg/bag
Php 17.37
Flooring
Php 3,458.68
Glazed Floor Tiles 20cmx 20cm
Php 2,656.45
(INTERIOR )Tile Adhesive 25kg/bag
Php 476.05
TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK
DETAILED ESTIMATES
COST (MATERIALS AND LABOR AND LABOR ONLY)
COST