• No results found

Factor for Construction Estimates

N/A
N/A
Protected

Academic year: 2021

Share "Factor for Construction Estimates"

Copied!
62
0
0

Loading.... (view fulltext now)

Full text

(1)

Proposed Two-Storey Residential Building with Roofdeck

I. Concreting Works II. Rebar Works

PRICE LIST PRICE LIST

MATERIAL PRICE MATERIAL

LAFARGE REPUBLIC PORTLAND PLUS 40KG

203.00 /bag 10 mm

WASHED SAND

600.00 /m³ 12 mm

CRUSHED GRAVEL 1"

850.00 /m³ 16 mm

Concreting of Column Footing

#16 G.I. WIRE

Total Volume of Column Footing (m³) 5.4 REINFORCEMENT BARS FOR COLUMN FOOTING (F1)

D IM EN SIO N S WIDTH 1.5

Total Length for of RSB for Column Footing (m)

LENGTH 1.5 HEIGHT/THICKNESS 0.2 D IM EN SIO N S NUMBER OF CF 12 CEMENT 48.6 TOTAL COST

12825.54

MATERIAL COST LABOR COST

9865.8

2959.74

2375.1 /m³ 16 mmØ x 6m REINFORCEMENT STEEL BAR

105.6 SAND

2.7 m³ of Washed Sand TOTAL COST MATERIAL COST

2106 LABOR COST

MATERIAL COST LABOR COST COST

1620

486

390 /m³ #16 G.I. WIRE

NUMBER OF INTERSECTIONS

GRAVEL NUMBER OF FOOTING

5.4 m³ of Crushed Gravel 1" TOTAL COST LENGTH OF TIE WIRE

5967 302.4

MATERIAL COST LABOR COST

4590

1377

1105 /m³ MATERIAL COST

LABOR COST

Concreting of Column

TOTAL COST

Total Volume of Column (m³) 11.56 ₱

REINFORCEMENT BARS FOR COLUMN FOOTING (F2)

D IM EN SIO N S WIDTH 0.25 LENGTH 0.4

Total Length for of RSB for Column Footing (m)

C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A

(2)

D IM EN SIO N S HEIGHT/THICKNESS 6.8

Total Length for of RSB for Column Footing (m)

NUMBER OF COLUMN 17 D IM EN SIO N S CEMENT 104.04 TOTAL COST

27456.156

MATERIAL COST LABOR COST

21120.12

6336.036

2375.1 /m³

16 mmØ x 6m REINFORCEMENT STEEL BAR SAND

9.9

5.78 m³ of Washed Sand TOTAL COST

4508.4 MATERIAL COST

MATERIAL COST LABOR COST LABOR COST

3468

1040.4

390 /m³ COST

#16 G.I. WIRE

GRAVEL NUMBER OF INTERSECTIONS

11.56 m³ of Crushed Gravel 1" TOTAL COST NUMBER OF FOOTING

12773.8 LENGTH OF TIE WIRE

MATERIAL COST LABOR COST

24.3

9826

2947.8

1105 /m³

MATERIAL COST

Concreting of Wall Footing

LABOR COST

Total Volume of Wall Footing (m³) 4.4925 TOTAL COST

₱ D IM EN SIO N S WIDTH 0.5

REINFORCEMENT BARS FOR COLUMN (C1)

THICKNESS 0.15

LENGTH OF WF1 59.9

Total Length for of RSB for Column (m) CEMENT 40.4325 TOTAL COST D IM EN SIO N S

10670.13675

MATERIAL COST LABOR COST

8207.7975

2462.33925

2375.1 /m³

16 mmØ x 6m REINFORCEMENT STEEL BAR

SAND 119.68

2.24625 m³ of Washed Sand TOTAL COST

1752.075 MATERIAL COST

MATERIAL COST LABOR COST LABOR COST

1347.75

404.325

390 /m³ COST #16 G.I. WIRE C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement

(3)

GRAVEL NUMBER OF LATERAL TIES

4.4925 m³ of Crushed Gravel 1" TOTAL COST NUMBER OF RSB

4964.2125 NUMBER OF COLUMN

MATERIAL COST LABOR COST LENGTH OF TIE WIRE

3818.625

1145.5875

1105 /m³ 1180.8

Concreting of Beam

MATERIAL COST

Total Volume of Beam (m³) 16.9425 LABOR COST

TOTAL COST D IM EN SIO N S WIDTH 0.5 ₱ THICKNESS 0.15

REINFORCEMENT BARS FOR COLUMN (C2)

LENGTH OF BEAMS 225.9

LENGTH OF FTB-1 34.95

Total Length for of RSB for Column (m)

LENGTH OF RCB-1 190.95 CEMENT DIM EN SIO N S 152.4825 TOTAL COST

40240.13175

MATERIAL COST LABOR COST

30953.9475

9286.18425

80480.2635 /m³ 16 mmØ x 6m REINFORCEMENT STEEL BAR

9.97 SAND

8.47125 m³ of Washed Sand TOTAL COST MATERIAL COST

6607.575 LABOR COST

MATERIAL COST LABOR COST COST

5082.75

1524.825

13215.15 /m³

LENGTH OF COLUMN LATERAL TIES (m)

GRAVEL PERIMETER OF COLUMN

16.9425 m³ of Crushed Gravel 1" TOTAL COST NUMBER OF COLUMN

18721.4625 NUMBER OF LATERAL TIES

MATERIAL COST LABOR COST NUMBER

14401.125

4320.3375

37442.925 /m³ SPACING

REMAINING LENGTH

Concreting of Slab (GF)

SPACING

Total Volume of Slab (m³) 14.3445 10 mmØ x 6m REINFORCEMENT STEEL BAR

166.12 D IM EN SIO N S THICKNESS 0.15

TOTAL AREA 95.63 MATERIAL COST

LABOR COST C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A

(4)

CEMENT COST

86.067 TOTAL COST #16 G.I. WIRE

22713.0813 NUMBER OF LATERAL TIES

MATERIAL COST LABOR COST NUMBER OF RSB

17471.601

5241.4803

1583.4 /m³ NUMBER OF COLUMN

LENGTH OF TIE WIRE SAND

98.4

7.17225 m³ of Washed Sand TOTAL COST

5594.355 MATERIAL COST

MATERIAL COST LABOR COST LABOR COST

4303.35

1291.005

390 /m³ TOTAL COST

GRAVEL

REINFORCEMENT BARS FOR WALL FOOTING

14.3445 m³ of Crushed Gravel 1" TOTAL COST

15850.6725 Total Length of RSB for Wall Footing (m)

MATERIAL COST LABOR COST

12192.825

3657.8475

1105 /m³ D IM EN SIO N S

Concreting of Slab (2F and RD)

Total Volume of Slab (m³) 35.23545

D IM EN SIO N S THICKNESS 0.15

TOTAL AREA 234.903 12 mmØ x 6m REINFORCEMENT STEEL BAR

32.95 CEMENT

317.11905 TOTAL COST MATERIAL COST

83687.717295 LABOR COST

MATERIAL COST LABOR COST COST

64375.16715

19312.550145

2375.1 /m³ 10 mmØ x 6m REINFORCEMENT STEEL BAR

18.49 SAND

17.617725 m³ of Washed Sand TOTAL COST MATERIAL COST

13741.8255 LABOR COST

MATERIAL COST LABOR COST COST

10570.635

3171.1905

390 /m³ #16 G.I. WIRE

NUMBER OF HOOP BARS

GRAVEL NUMBER OF RSB

35.23545 m³ of Crushed Gravel 1" TOTAL COST LENGTH OF TIE WIRE

40 kg./bag Portland Cement C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement

(5)

35.23545 m³ of Crushed Gravel 1"

38935.17225 180.6

MATERIAL COST LABOR COST

29950.1325

8985.03975

1105 /m³ MATERIAL COST

LABOR COST

Concreting of Stairs

TOTAL COST

Total Volume of Column (m³) 0.9 ₱

REINFORCEMENT BARS FOR CONCRETE BEAM (FTB-1)

D IM EN SIO N S WIDTH 1.5

LENGTH 0.2 Total Length of RSB for FTB-1

HEIGHT/THICKNESS 0.2 DIM EN SIO N S NUMBER OF STEPS 15 CEMENT 8.1 TOTAL COST

2137.59 12 mmØ x 6m REINFORCEMENT STEEL BAR

MATERIAL COST LABOR COST

41.94

1644.3

493.29

2375.1 /m³

MATERIAL COST

SAND LABOR COST

0.45 m³ of Washed Sand TOTAL COST COST

351 Total Length of Stirrups for FTB-1

MATERIAL COST LABOR COST

270

81

390 /m³ PERIMETER OF FTB-1

10 mmØ x 6m REINFORCEMENT STEEL BAR

GRAVEL 61.16

0.9 m³ of Crushed Gravel 1" TOTAL COST

994.5 MATERIAL COST

MATERIAL COST LABOR COST LABOR COST

765

229.5

1105 /m³ COST

#16 G.I. WIRE

NUMBER OF STIRRUPS NUMBER OF RSB LENGTH OF TIE WIRE 550.4625

MATERIAL COST LABOR COST

TOTAL COST

REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1)

C O N C R ET E M IX TU R E C LA SS A 40 kg./bag Portland Cement

(6)

REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1) Total Length of RSB for RCB-1

D IM EN SIO N S

16 mmØ x 6m REINFORCEMENT STEEL BAR

305.52

MATERIAL COST LABOR COST

COST

Total Length of Stirrups for RCB-1 PERIMETER OF RCB-1

10 mmØ x 6m REINFORCEMENT STEEL BAR 334.16 MATERIAL COST LABOR COST COST #16 G.I. WIRE NUMBER OF STIRRUPS NUMBER OF RSB LENGTH OF TIE WIRE 4009.95

MATERIAL COST LABOR COST

TOTAL COST

REINFORCEMENT FOR GROUND FLOOR SLAB

Total Length of RSB for GF Slab A

B

LENGTH OF RSB ALONG A ALONG B

(7)

12 mmØ x 6m REINFORCEMENT STEEL BAR 257.91 MATERIAL COST LABOR COST COST #16 G.I. WIRE NUMBER OR INTERSECTIONS

LENGTH OF TIE WIRE 1310.4

MATERIAL COST LABOR COST

TOTAL COST

REINFORCEMENT FOR 2F AND RD SLAB

NUMBER OF STEEL BARS AREA

12 mmØ x 6m REINFORCEMENT STEEL BAR 144.74

MATERIAL COST LABOR COST

COST

NUMBER OF STEEL BARS AREA

10 mmØ x 6m REINFORCEMENT STEEL BAR 144.74 MATERIAL COST LABOR COST COST #16 G.I. WIRE NUMBER OR INTERSECTIONS

LENGTH OF TIE WIRE Total Length of 12mmØ RSB

(8)

80.886

MATERIAL COST LABOR COST

TOTAL COST

(9)

II. Rebar Works III. Masonry Works

PRICE LIST PRICE LIST

MATERIAL PRICE MATERIAL

10 mm

125.00 /pc CONCRETE HOLLOW BLOCK 5" THK

12 mm

192.00 /pc CONCRETE HOLLOW BLOCK 4" THK

16 mm

315.00 /pc LAFARGE REPUBLIC PORTLAND PLUS 40KG

#16 G.I. WIRE

180.00 /kg WASHED SAND

REINFORCEMENT BARS FOR COLUMN FOOTING (F1) CRUSHED GRAVEL 1"

CONCRETE HOLLOW BLOCKS FOR WALL (EXTERIOR)

Total Length for of RSB for Column Footing (m) 633.6

LENGTH 3.3 NUMBER OF RSB

GROUND FLOOR

ALONG (B) 1.5 9 SECOND FLOOR

ALONG (L) 1.5 7

CONCRETE HOLLOW BLOCK 5" THK

NUMBER OF FOOTING (F1)

12

CEMENT MORTAR (CLASS C)

16 mmØ x 6m REINFORCEMENT STEEL BAR CEMENT

105.6 pcs TOTAL COST SAND

43243.2

PLASTERING @ 12mm THK (CLASS B)

MATERIAL COST

33264

AREA OF WALLS (TWO SIDES)

LABOR COST

9979.2

CEMENT

COST ₱ 19219.2 /m SAND

#16 G.I. WIRE TOTAL COST

NUMBER OF INTERSECTIONS 63 MATERIAL COST

NUMBER OF FOOTING 16 CHB 5" THK

LENGTH OF TIE WIRE 0.3 m CEMENT

302.4 meters 5.71 kg. SAND

CHB 5" THK

MATERIAL COST

1027.0188679245 CEMENT

LABOR COST

308.1056603774 SAND

TOTAL COST

1335.1245283019

CONCRETE HOLLOW BLOCKS FOR WALL (INTERIOR) 593.3886792453

REINFORCEMENT BARS FOR COLUMN FOOTING (F2)

Total Length for of RSB for Column Footing (m) 59.4 GROUND FLOOR

R EIN FO R C EM EN T B AR S 16 m m Ø x 6 m R E IN FO R C E M E N T S T E E L B A R

Total Area of Exterior Walls (m²)

/m²

Total Area of Interior Walls (m²)

16 m m Ø x 6 m R E IN FO R C E M E N T S T E E L B A R

(10)

Total Length for of RSB for Column Footing (m)

Total Length for of RSB for Column Footing (m) 59.4

SECOND FLOOR

LENGTH 3.3 NUMBER OF RSB CONCRETE HOLLOW BLOCK 4" THK

ALONG (B) 1.5 9 CEMENT MORTAR (CLASS C)

ALONG (L) 1.5 9 CEMENT

NUMBER OF FOOTING (F1)

1

SAND

PLASTERING @ 8mm THK (CLASS B)

16 mmØ x 6m REINFORCEMENT STEEL BAR AREA OF WALLS (TWO SIDES)

9.9 pcs TOTAL COST CEMENT

4054.05

SAND

MATERIAL COST

3118.5

TOTAL COST

LABOR COST

935.55

MATERIAL COST

COST ₱ 68.25 /m CHB 5" THK

#16 G.I. WIRE CEMENT

NUMBER OF INTERSECTIONS 81 SAND

NUMBER OF FOOTING 1 CHB 5" THK

LENGTH OF TIE WIRE 0.3 m CEMENT

24.3 meters 0.46 kg. SAND

Total Length of RSB for Vertical Bars

MATERIAL COST

82.5283018868

LABOR COST

24.758490566 TOTAL WIDTH OF WALLS

TOTAL COST

107.2867924528 SPACING

47.6830188679 LENGTH

REINFORCEMENT BARS FOR COLUMN (C1) 12 mmØ x 6m REINFORCEMENT STEEL BAR

67.5229166667

Total Length for of RSB for Column (m) 718.08

MATERIAL COST LENGTH OF COLUMN 6.8

12964.4 COST NUMBER OF RSB/COLUMN 6

Total Length of RSB for Horizontal Bars

NUMBER OF COLUMN 16

16 mmØ x 6m REINFORCEMENT STEEL BAR HEIGHT OF WALL

119.68 pcs TOTAL COST WIDTH

49008.96

10 mmØ x 6m REINFORCEMENT STEEL BAR

MATERIAL COST

37699.2

8.98

LABOR COST

11309.76

COST ₱ 68.25 /m MATERIAL COST

#16 G.I. WIRE LABOR COST

16 m m Ø x 6 m R E IN FO R C E M E N T S T E E L B A R /m² 16 m m Ø x 6 m R EIN FO R C EM EN T S TE EL BA R

(11)

NUMBER OF LATERAL TIES 41 COST

NUMBER OF RSB 6

NUMBER OF COLUMN 16

LENGTH OF TIE WIRE 0.3 /m

1180.8 meters 22.28 kg.

MATERIAL COST

4010.2641509434

LABOR COST

1203.079245283

TOTAL COST

5213.3433962264

766.6681465039 /m

REINFORCEMENT BARS FOR COLUMN (C2)

Total Length for of RSB for Column (m) 59.84

LENGTH OF COLUMN 6.8

NUMBER OF RSB/COLUMN 8

NUMBER OF COLUMN 1

16 mmØ x 6m REINFORCEMENT STEEL BAR

9.97 pcs TOTAL COST

4084.08

MATERIAL COST

3141.6

LABOR COST

942.48

COST ₱ 68.25 /m

LENGTH OF COLUMN LATERAL TIES (m) 996.71

PERIMETER OF COLUMN 1.3 m

NUMBER OF COLUMN 17

NUMBER OF LATERAL TIES 40.5

NUMBER 11

TOTAL NUMBER OF LATERAL TIES

SPACING 0.1

REMAINING LENGTH 5.7

41

SPACING 0.2

10 mmØ x 6m REINFORCEMENT STEEL BAR

166.12 pcs TOTAL COST

26994.2291666667

MATERIAL COST

20764.7916666667

LABOR COST

6229.4375

16 m m Ø x 6 m R EIN FO R C EM EN T S TE EL BA R

(12)

COST ₱ 27.0833333333 /m

#16 G.I. WIRE

NUMBER OF LATERAL TIES 41

NUMBER OF RSB 8

NUMBER OF COLUMN 1

LENGTH OF TIE WIRE 0.3 /m

98.4 meters 1.86 kg.

MATERIAL COST

334.1886792453

LABOR COST

100.2566037736

TOTAL COST

434.4452830189

63.8890122087 /m

REINFORCEMENT BARS FOR WALL FOOTING

Total Length of RSB for Wall Footing (m) 197.67

NUMBER OF RSB 3

LENGTH OF WALL FOOTING 59.9

Total Length of Hoop Bars (m) 110.92

SPACING OF HOOP BARS 0.3

WIDTH OF HOOP BARS 0.5

12 mmØ x 6m REINFORCEMENT STEEL BAR

32.95 pcs TOTAL COST

8223.072

MATERIAL COST

6325.44

LABOR COST

1897.632

COST ₱ 41.6 /m

10 mmØ x 6m REINFORCEMENT STEEL BAR

18.49 pcs TOTAL COST

3003.9930555556

MATERIAL COST

2310.7638888889

LABOR COST

693.2291666667

COST ₱ 27.0833333333 /m #16 G.I. WIRE

NUMBER OF HOOP BARS 200.67

NUMBER OF RSB 3

LENGTH OF TIE WIRE 0.3 m

12 m m Ø a nd 1 0 m m Ø R EIN FO R C EM EN T S TE EL B AR S

(13)

180.6 meters 3.41 kg.

MATERIAL COST

613.358490566

LABOR COST

184.0075471698

TOTAL COST

797.3660377358

13.3116199956 /m

REINFORCEMENT BARS FOR CONCRETE BEAM (FTB-1)

Total Length of RSB for FTB-1 251.64 m

NUMBER OF RSB 6

TOP BARS 3

BOTTOM BARS 3

TOTAL LENGTH OF FTB-1 34.95 m

12 mmØ x 6m REINFORCEMENT STEEL BAR

41.94 pcs TOTAL COST

10468.224

MATERIAL COST

8052.48

LABOR COST

2415.744

COST ₱ 41.6 /m

Total Length of Stirrups for FTB-1 366.975

PERIMETER OF FTB-1 1.2 m

10 mmØ x 6m REINFORCEMENT STEEL BAR

61.16 pcs TOTAL COST

9938.90625

MATERIAL COST

7645.3125

LABOR COST

2293.59375

COST ₱ 284.375 /m #16 G.I. WIRE NUMBER OF STIRRUPS 305.8125 NUMBER OF RSB 6

LENGTH OF TIE WIRE 0.3

550.4625 meters 10.39 kg.

MATERIAL COST

1869.4952830189

LABOR COST

560.8485849057

TOTAL COST

2430.3438679245

810.1146226415 /m

(14)

REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1) REINFORCEMENT BARS FOR CONCRETE BEAM (RCB-1)

Total Length of RSB for RCB-1 1833.12 m

WEB BARS 2

TOP BARS 3

BOTTOM BARS 3

TOTAL LENGTH OF RCB-1 190.95 m

16 mmØ x 6m REINFORCEMENT STEEL BAR

305.52 pcs TOTAL COST

125110.44

MATERIAL COST

96238.8

LABOR COST

28871.64

COST ₱ 68.25 /m

Total Length of Stirrups for RCB-1 2005.0

PERIMETER OF RCB-1 1.2 m

10 mmØ x 6m REINFORCEMENT STEEL BAR

334.16 pcs TOTAL COST

54301.40625

MATERIAL COST

41770.3125

LABOR COST

12531.09375

COST ₱ 284.375 /m #16 G.I. WIRE NUMBER OF STIRRUPS 1670.8125 NUMBER OF RSB 8

LENGTH OF TIE WIRE 0.3

4009.95 meters 75.66 kg.

MATERIAL COST

13618.6981132075

LABOR COST

4085.6094339623

TOTAL COST

17704.3075471698

92.7169811321 /m

REINFORCEMENT FOR GROUND FLOOR SLAB

Total Length of RSB for GF Slab 1547.46

7.05 m SPACING ALONG A 48

13.5 m 0.15 m ALONG B 91

LENGTH OF RSB 1289.55 m

ALONG A 648 m

(15)

12 mmØ x 6m REINFORCEMENT STEEL BAR 257.91 pcs TOTAL COST

64374.336

MATERIAL COST

49518.72

LABOR COST

14855.616

COST ₱ 14.7377142857 /m #16 G.I. WIRE NUMBER OR INTERSECTIONS 4368

LENGTH OF TIE WIRE 0.3 m

1310.4 meters 24.72 kg.

MATERIAL COST

4450.4150943396

LABOR COST

1335.1245283019

TOTAL COST

5785.5396226415

1.3245283019 /m

REINFORCEMENT FOR 2F AND RD SLAB

868.45

NUMBER OF STEEL BARS 3.221 m

AREA 269.62

12 mmØ x 6m REINFORCEMENT STEEL BAR

144.74 pcs TOTAL COST

36127.354432

MATERIAL COST

27790.27264

LABOR COST

8337.081792

COST ₱ 133.9936 /m 868.45

NUMBER OF STEEL BARS 3.221 m

AREA 269.62

10 mmØ x 6m REINFORCEMENT STEEL BAR

144.74 pcs TOTAL COST

23520.4130416667

MATERIAL COST

18092.6254166667

LABOR COST

5427.787625

COST ₱ 87.2354166667 /m #16 G.I. WIRE NUMBER OR INTERSECTIONS 269.62

LENGTH OF TIE WIRE 0.3 m

Total Length of 12mmØ RSB

Total Length of 10mmØ RSB

(16)

80.886 meters 1.53 kg.

MATERIAL COST

274.7071698113

LABOR COST

82.4121509434

TOTAL COST

357.1193207547

(17)

III. Masonry Works III. Formworks

PRICE LIST PRICE LIST

MATERIAL PRICE MATERIAL

CONCRETE HOLLOW BLOCK 5" THK

9.00 /pc Form Lumber 2" x 3" x 12' Coco Lumber CONCRETE HOLLOW BLOCK 4" THK

8.00 /pc Form Lumber 2" x 2" x 12' Coco Lumber

LAFARGE REPUBLIC PORTLAND PLUS 40KG

203.00 /bag 1/2"x4'x8' Ordinary Plywood WASHED SAND

600.00 /m³ FORMS FOR COLUMN

CRUSHED GRAVEL 1"

850.00 /m³ SIDES OF THE COLUMN

CONCRETE HOLLOW BLOCKS FOR WALL (EXTERIOR) SHORTER SIDE

LONGER SIDE 167.929

LATERAL PERIMETER OF THE COLUMN

GROUND FLOOR 85.3155 COLUMN HEIGHT

SECOND FLOOR 82.6135 NUMBER OF COLUMNS

CONCRETE HOLLOW BLOCK 5" THK 2099.1125 pcs. TOTAL AREA

1/2"x4'x8' Ordinary Plywood CEMENT MORTAR (CLASS C)

CEMENT 1601.62 bag TOTAL COST

SAND 177.17 MATERIAL COST

PLASTERING @ 12mm THK (CLASS B) LABOR COST

AREA OF WALLS (TWO SIDES) 335.86 m²

42.651

CEMENT 48.36 bag WOOD FRAME OF COLUMNS

SAND 4.03 m³

Form Lumber 2" x 2" x 12' Coco Lumber

TOTAL COST

601323.43

MATERIAL COST LABOR COST TOTAL COST

18892.0125

5667.60375 MATERIAL COST

334947.2370685

100484.17112055 LABOR COST

108717.23

32615.17038

29.000

CHB 5" THK

146.25 /m² SCAFFOLDING FOR COLUMNS

CEMENT

2592.94945 /m²

HORIZONTAL BRACES

SAND

841.62 /m²

CONCRETE HOLLOW BLOCKS FOR WALL (INTERIOR) VERTICAL BRACES

DIAGONAL BRACES 150.005

Form Lumber 2" x 2" x 12' Coco Lumber

GROUND FLOOR 65.2

Total Area of Exterior Walls (m²)

(18)

SECOND FLOOR 84.805 TOTAL COST

CONCRETE HOLLOW BLOCK 4" THK 1875.0625 pcs. MATERIAL COST

LABOR COST

CEMENT MORTAR (CLASS C)

1675.960

CEMENT 1430.67 bag

Form Lumber 2" x 3" x 12' Coco Lumber

SAND 158.26

PLASTERING @ 8mm THK (CLASS B) TOTAL COST

AREA OF WALLS (TWO SIDES) 300.01 m² MATERIAL COST

CEMENT 28.80 bag LABOR COST

SAND 2.40 m³

66.733

TOTAL COST

529966.92 FORMS FOR BEAM

MATERIAL COST LABOR COST PERIMETER OF TWO SIDES FORM

15000.5

4500.15 TWO SIDE FORMS

296273.1504425

88881.94513275 BOTTOM FORM

96393.21

28917.9639 LENGTH OF BEAM CHB 5" THK

130 /m² TOTAL AREA CEMENT

2567.61505 /m² 1/2"x4'x8' Ordinary Plywood SAND

835.38 /m²

Total Length of RSB for Vertical Bars 405.1375 m TOTAL COST

MATERIAL COST

TOTAL WIDTH OF WALLS 107.77 m LABOR COST

SPACING 0.8 m

42.651

LENGTH 3.00 m WOOD FRAME OF COLUMNS

12 mmØ x 6m REINFORCEMENT STEEL BAR

Form Lumber 2" x 3" x 12' Coco Lumber

67.5229166667 pcs. TOTAL COST

16853.72 TOTAL COST

MATERIAL COST LABOR COST MATERIAL COST

12964.4

3889.32 LABOR COST

₱ 156.3860072376 /m

55.126

Total Length of RSB for Horizontal Bars 53.885 m SCAFFOLDING FOR COLUMNS

HORIZONTAL BRACES

HEIGHT OF WALL 3

WIDTH 107.77 VERTICAL BRACES

10 mmØ x 6m REINFORCEMENT STEEL BAR

Form Lumber 2" x 2" x 12' Coco Lumber

8.98 pcs TOTAL COST

1459.3854166667

TOTAL COST

MATERIAL COST

1122.6041666667

MATERIAL COST

LABOR COST

336.78125

LABOR COST

(19)

₱ 27.0833333333 /m

47.165

Form Lumber 2" x 3" x 12' Coco Lumber TOTAL COST

MATERIAL COST LABOR COST

(20)
(21)
(22)
(23)
(24)
(25)

PRICE LIST

MATERIAL PRICE

Form Lumber 2" x 3" x 12' Coco Lumber

132.00 /pc Form Lumber 2" x 2" x 12' Coco Lumber

88.00 /pc

1/2"x4'x8' Ordinary Plywood

320.00 /pc

FORMS FOR COLUMN

SIDES OF THE COLUMN 0.65 m

SHORTER SIDE 0.25 m

LONGER SIDE 0.4 m

LATERAL PERIMETER OF THE COLUMN 1.5 m

COLUMN HEIGHT 6.8 m NUMBER OF COLUMNS 17 TOTAL AREA 173.4 m² 1/2"x4'x8' Ordinary Plywood 17.7780511811 pcs TOTAL COST

7395.67 MATERIAL COST

5688.98 LABOR COST

1706.69 42.651 /m²

WOOD FRAME OF COLUMNS

Form Lumber 2" x 2" x 12' Coco Lumber 43.956

pc s TOTAL COST

5028.59 MATERIAL COST

3868.15 LABOR COST

1160.44 29.000 /m²

SCAFFOLDING FOR COLUMNS

HORIZONTAL BRACES 2427.6 bd. F

t.

VERTICAL BRACES 809.2 bd. Ft.

DIAGONAL BRACES 1352.52 bd. F

t.

Form Lumber 2" x 2" x 12' Coco Lumber 2540.310

bd

. F

(26)

TOTAL COST

290611.46

MATERIAL COST

223547.28

LABOR COST

67064.18

1675.960 /m²

Form Lumber 2" x 3" x 12' Coco Lumber 67.433

bd . F t. TOTAL COST

11571.56 MATERIAL COST

8901.20 LABOR COST

2670.36 66.733 /m²

FORMS FOR BEAM

PERIMETER OF TWO SIDES FORM 0.95 m

TWO SIDE FORMS 0.25 m

BOTTOM FORM 0.35 m LENGTH OF BEAM 225.9 m TOTAL AREA 214.605 m² 1/2"x4'x8' Ordinary Plywood 22.003 pcs TOTAL COST

9153.10 MATERIAL COST

7040.85 LABOR COST

2112.25 42.651 /m²

WOOD FRAME OF COLUMNS

Form Lumber 2" x 3" x 12' Coco Lumber 68.942

bd . F t. TOTAL COST

11830.38 MATERIAL COST

9100.29 LABOR COST

2730.09 55.126 /m²

SCAFFOLDING FOR COLUMNS

HORIZONTAL BRACES 88.4775 bd. F

t.

VERTICAL BRACES 112.95 bd. Ft.

Form Lumber 2" x 2" x 12' Coco Lumber 88.478

pc

s

TOTAL COST

10121.83

MATERIAL COST

7786.02

(27)

47.165 /m²

Form Lumber 2" x 3" x 12' Coco Lumber 112.950

bd . F t. TOTAL COST

19382.22 MATERIAL COST

14909.40 LABOR COST

4472.82 90.316 /m²

(28)
(29)
(30)
(31)
(32)
(33)

TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK

BILL OF MATERIALS

I.D. NO DESCRIPTION UNIT

GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities

lot and Services/Demobilization/Permits

Sub-total 1.00 Earthworks

1.01 Clearing and Grubbing sq.m

1.02 Structural Excavation cu.m

1.03 Backfilling and Compaction cu.m

1.04 Gravel Bedding G-1 cu.m

1.05 Select Fill cu.m

1.06 Soil Poisoning sq.m

Sub-Total

2.00 Concreting Works Column Footing

2.01 Portland Cement bag

2.02 Crushed Gravel 1" cu.m

2.03 Washed Sand cu.m

Wall Footing

2.01 Portland Cement bag

2.02 Crushed Gravel 1" cu.m

2.03 Washed Sand cu.m

Column

2.01 Portland Cement bag

2.02 Crushed Gravel 3/4"" cu.m

2.03 Washed Sand cu.m

Beams

2.01 Portland Cement bag

2.02 Crushed Gravel 3/4"" cu.m

2.03 Washed Sand cu.m

Slab on Grade

2.01 Portland Cement bag

2.02 Crushed Gravel 1" cu.m

2.03 Washed Sand cu.m

(34)

2.01 Portland Cement bag

2.02 Crushed Gravel 1" cu.m

2.03 Washed Sand cu.m

Sub-total 3.00 Rebar Works Footings Column Footings 3.01 16 mm pc 3.02 #16 G.I. Wire kg Wall Footings 3.01 12 mm pc 3.02 10 mm pc 3.03 #16 G.I. Wire kg Column 3.01 16 mm pc 3.02 10 mm pc 3.03 #16 G.I. Wire kg

Roof beams & Tie beams

3.01 16 mm pc 3.02 12 mm pc 3.03 10 mm pc 3.04 #16 G.I. Wire kg Slabs 3.01 12 mm pc 3.02 10 mm pc 3.03 #16 G.I. Wire kg Sub-total

4.00 Forms and Scaffoldings Column form

4.01 Good lumber ( 2" x 2" x 12') pc

4.02 Plywood Ordinary, 1/4" x 4" x 8' pc

4.03 CWN, Assorted kg

Column & Roof beam Scaffolding

4.01 Vertical Support ( 2" x 3" x 12' Good lumber) pc

Horizontal Support (2" x 2" x 12' Good lumber) pc

Diagonal braces (2" x 2" x 12' Good lumber) pc

4.02 CWN, Assorted kg

Beam form

4.01 Good lumber ( 2" x 2" x 12') pc

(35)

4.03 CWN, Assorted kg Sub-total 5.00 Masonry Works Masonry wall 5.01 CHB 5" THK pcs. 5.02 CHB 4" THK pcs.

5.03 Portland Cement bag

5.04 Washed Sand cu.m

5.05 12mm x 6m RSB pc

5.06 #61 G.I. Tie wire kg

Plastering

5.01 Portland Cement bag

5.02 Washed Sand cu.m

Sub-total

6.00 Doors And Windows

6.01 set 6.02 set 6.03 set 6.04 set 6.05 set 6.07 set 6.08 set 6.09 set 6.1 set 6.12 set 6.13 set Sub-total 7.00 Electrical Works Roughing-ins

7.01 Electrical Conduit uPVC, 15mmØ pc

D-1, Double swing panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb

D-2, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb

D-3, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb

W-1, 12mm thk. bronze glass on powder coated aluminum frame

W-2, 6mm thk. bronze glass on powder coated aluminum frame

W-3, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-4, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-5, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-6, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-7, 12mm thk. bronze glass on powder coated aluminum frame

W-8, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs.

(36)

7.02 RSC 60mmØ pc

7.03

Entrance Cap 60mm dia.

pc

7.04

Junction Box , 4" x 4" G.I

pc

7.05

Utility Box, 2" x 4" x G.I

pc

7.06

Grounding Rod, 2.4m x 16mm dia.

pc Wires and Fixtures

7.01

3.5 mm2 THW wire , Stranded

box

7.02

Duplex C.O. with Plate

pc

7.03

3 Way Switch With Plate

pc

7.04

40 watts Flourescent Lamp

pc

7.05

Single Switch with Plate

pc

7.06

2-Gang Switch with Plate

pc

7.07 Incandescent Bulb 50W set

7.08 Panel Box, Flush Type, 4 Branches set

7.09 Circuit Breaker, 20A 2P set

7.10 Main Circuit Breaker, 175A 2P set

7.11 Electrical Tape pc

Sub-total 8.00 Plumbing Works

8.01 Water Closet 1.6gpf with Accessories set

8.02 Kitchen Sink set

8.03 Faucet , Hose Bibb , Brass 3/4"Ø pc

8.04 G.I Coupling, 3/4"Ø pc

8.05 G.I Tee, 3/4"Ø pc

8.06 G.I. Pipe 3/4" Sch.40 pc

8.07 G.I. Elbow 90° x 3/4"Ø pc

8.08 Gate Valve , 3/4"dia. pc

8.09 Check Valve , 3/4"dia. pc

8.10 S.S. Floor Drain 4' x 4" pc

(37)

9.00 Sanitary works

9.01 uPVC Sanitary Pipe 4"Ø x 10' pc

9.02 uPVC Wye 4" x 4" pc

9.03 uPVC Wye 4" x 2" pc

9.04 uPVC Sanitary Pipe 2"Ø pc

9.05 uPVC P-TRAP 2"Ø pc

9.06 uPVC P-TRAP 4"Ø pc

9.07 uPVC Elbow 45° x 4 "Ø pc

9.08 uPVC Cleanout 4" diameter pc

9.09 PVC Cement can

Sub-total 10.00 Painting Works

Concrete surfaces sq.m

10.01 Neutralizer qrt

10.02 Latex, Flat gal

10.03 Latex, Semi Gloss gal

10.04 Acri Color qrt

Sub-total 11.00 TileWorks

Wall

11.01 Unglazed Wall Tiles 20cm x 30cm T&B pc

11.02 Unglazed Wall Tiles 20cm x 20cm KITCHEN pc

11.03 Tile Trim 6mm. pc

11.04 Lining 2" X 20cm (T&B and KITCHEN) pc

11.05 Tile Adhesive 25kg/bag bag

11.06 Tile Grout 5 kg/bag bag

Flooring sq.m

11.01 Glazed Floor Tiles 20cmx 20cm(INTERIOR ) pc

11.02 Tile Adhesive 25kg/bag bag

11.03 Tile Grout 5 kg/bag bag

Sub-total

TOTAL BUILDING COST (LABOR AND MATERIAL)

PRICE FOR BIDDING

LABOR AND MATERIALS

(38)
(39)

TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK

BILL OF MATERIALS

QTY UNIT COST TOTAL COST

MATERIAL LABOR MATERIAL LABOR

1.00 30,000.00 9,000.00 30,000.00 9,000.00 140.00 0.00 50.00 0.00 7,000.00 75.80 0.00 250.00 0.00 18,950.00 50.00 150.00 50.00 7,500.00 2,500.00 5.00 850.00 255.00 4,250.00 1,275.00 13.00 150.00 45.00 1,950.00 585.00 140.00 50.00 15.00 7,000.00 2,100.00 48.60 203.00 66.00 9,865.80 3,207.60 5.40 850.00 255.00 4,590.00 1,377.00 2.70 600.00 180.00 1,620.00 486.00 40 203.00 66.00 8,120.00 2,640.00 2.25 850.00 255.00 1,912.50 573.75 4.5 600.00 180.00 2,700.00 810.00 105.00 203.00 66.00 21,315.00 6,930.00 11.56 850.00 255.00 9,826.00 2,947.80 5.78 600.00 180.00 3,468.00 1,040.40 153.00 203.00 66.00 31,059.00 10,098.00 16.94 850.00 255.00 14,399.00 4,319.70 8.47 600.00 180.00 5,082.00 1,524.60 417.00 203.00 66.00 84,651.00 27,522.00 50.85 850.00 255.00 43,225.90 12,967.77 25.40 600.00 180.00 15,240.60 4,572.18

(40)

8.00 203.00 66.00 1,624.00 528.00 0.90 850.00 255.00 765.00 229.50 0.45 600.00 180.00 270.00 81.00 164.00 315.00 10.00 51,660.00 1,640.00 4.28 180.00 10.00 770.40 42.80 33.00 192.00 10.00 6,336.00 330.00 18.50 125.00 10.00 2,312.50 185.00 3.41 180.00 10.00 613.80 34.10 130.00 315.00 10.50 40,950.00 1,365.00 167.00 125.00 10.00 20,875.00 1,670.00 24.14 180.00 10.00 4,345.20 241.40 306.00 315.00 10.50 96,390.00 3,213.00 41.94 192.00 10.00 8,052.48 419.40 395.00 125.00 10.00 49,375.00 3,950.00 86 180.00 10.00 15,480.00 860.00 403.00 192.00 10.00 77,376.00 4,030.00 144.74 125.00 10.00 18,092.50 1,447.40 26.25 180.00 10.00 4,725.00 262.50 44.00 88.00 26.40 3,872.00 1,161.60 18.00 320.00 96.00 5,760.00 1,728.00 30.00 80.00 24.00 2,400.00 720.00 180.38 132.00 39.60 23,810.16 7,143.05 209.67 88.00 26.40 18,450.96 5,535.29 112.71 88.00 26.40 9,918.48 2,975.54 35.00 80.00 24.00 2,800.00 840.00 69.00 88.00 26.40 6,072.00 1,821.60 22.00 320.00 96.00 7,040.00 2,112.00

(41)

30.00 80.00 24.00 2,400.00 720.00 2,100.00 9.00 2.55 18,900.00 5,355.00 1,875.00 8.00 2.55 15,000.00 4,781.25 3,032.00 203.00 57.00 615,496.00 172,824.00 275.43 600.00 168.00 165,258.00 46,272.24 76.50 192.00 9.60 14,688.00 734.40 20.00 180.00 19.50 3,600.00 390.00 77.16 203.00 54.00 15,663.48 4,166.64 56.32 600.00 168.00 33,792.00 9,461.76 1 10,800.00 3,240.00 10,800.00 3,240.00 5 4,500.00 1,350.00 22,500.00 6,750.00 3 2,495.00 748.50 7,485.00 2,245.50 1 8,700.00 2,610.00 8,700.00 2,610.00 9 7,500.00 2,250.00 67,500.00 20,250.00 6 7,000.00 2,100.00 42,000.00 12,600.00 7 5,625.00 1,687.50 39,375.00 11,812.50 2 5,500.00 1,650.00 11,000.00 3,300.00 5 4,200.00 1,260.00 21,000.00 6,300.00 1 3,145.00 943.50 3,145.00 943.50 1 3,000.00 900.00 3,000.00 900.00 50.00 58.00 14.50 2,900.00 725.00

(42)

11.00 1,000.00 250.00 11,000.00 2,750.00 11.00 80.00 20.00 880.00 220.00 34.00 20.00 5.00 680.00 170.00 12.00 20.00 5.00 240.00 60.00 14.00 200.00 50.00 2,800.00 700.00 12.00 3,750.00 937.50 45,000.00 11,250.00 14.00 108.00 27.00 1,512.00 378.00 4.00 250.00 62.50 1,000.00 250.00 10.00 150.00 37.50 1,500.00 375.00 10.00 68.00 17.00 680.00 170.00 13.00 108.00 27.00 1,404.00 351.00 14.00 40.00 10.00 560.00 140.00 3.00 320.00 80.00 960.00 240.00 4.00 350.00 87.50 1,400.00 350.00 1.00 3,000.00 750.00 3,000.00 750.00 35.00 25.00 6.25 875.00 218.75 4.00 4,500.00 1,125.00 18,000.00 4,500.00 2.00 600.00 150.00 1,200.00 300.00 7.00 250.00 62.50 1,750.00 437.50 11.00 17.00 4.25 187.00 46.75 11.00 17.00 4.25 187.00 46.75 13.00 370.00 92.50 4,810.00 1,202.50 8.00 17.00 4.25 136.00 34.00 5.00 360.00 90.00 1,800.00 450.00 12.00 300.00 75.00 3,600.00 900.00 4.00 200.00 50.00 800.00 200.00

(43)

11.00 525.00 131.25 5,775.00 1,443.75 11.00 160.00 40.00 1,760.00 440.00 14.00 97.00 24.25 1,358.00 339.50 14.00 205.00 51.25 2,870.00 717.50 11.00 50.00 12.50 550.00 137.50 17.00 110.00 27.50 1,870.00 467.50 8.00 97.00 24.25 776.00 194.00 5.00 110.00 27.50 550.00 137.50 6.00 120.00 30.00 720.00 180.00 646.52 8.62 130.00 32.50 1,120.60 280.15 21.55 450.00 112.50 9,697.50 2,424.38 22.00 440.00 110.00 9,680.00 2,420.00 4.20 123.00 30.75 516.60 129.15 168.00 40.00 10.00 6,720.00 1,680.00 45.00 32.00 8.00 1,440.00 360.00 21.00 50.00 12.50 1,050.00 262.50 54.00 25.00 6.25 1,350.00 337.50 8.00 270.00 67.50 2,160.00 540.00 8.00 165.00 41.25 1,320.00 330.00 431.39 15,530.00 13.00 3.25 201,890.00 50,472.50 134.00 270.00 67.50 36,180.00 9,045.00 134.00 185.00 46.25 24,790.00 6,197.50

TOTAL BUILDING COST (LABOR AND MATERIAL)

2,993,117.44

PRICE FOR BIDDING

(44)
(45)

TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK

TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK

BILL OF MATERIALS

COST (MATERIALS AND LABOR AND LABOR ONLY)

DETAILED ESTIMATES

GRAND TOTAL I.D. NO

39,000.00 39,000.00 1.00 7,000.00 1.01 18,950.00 1.02 10,000.00 1.03 5,525.00 1.04 2,535.00 1.05 9,100.00 1.06 53,110.00 2.00 13,073.40 2.01 5,967.00 2.02 2,106.00 2.03 10,760.00 2.01 2,486.25 2.02 3,510.00 2.03 28,245.00 2.01 12,773.80 2.02 4,508.40 2.03 41,157.00 2.01 18,718.70 2.02 6,606.60 2.03 112,173.00 2.01 56,193.67 2.02 19,812.78 2.03

(46)

2,152.00 2.01 994.50 2.02 351.00 2.03 303,686.45 3.00 53,300.00 3.01 813.20 3.02 6,666.00 3.01 2,497.50 3.02 647.90 3.01 42,315.00 3.02 22,545.00 3.03 4,586.60 99,603.00 3.01 8,471.88 3.02 53,325.00 3.03 16,340.00 3.01 81,406.00 3.02 19,539.90 3.03 4,987.50 417,044.48 3.01 3.02 5,033.60 3.03 7,488.00 3,120.00 3.01 3.02 30,953.21 3.03 23,986.25 12,894.02 3,640.00 3.01 3.02 7,893.60 9,152.00 3.01

(47)

3,120.00 3.02 107,280.68 3.03 4.00 24,255.00 19,781.25 4.01 788,320.00 4.02 211,530.24 4.03 15,422.40 3,990.00 4.01 19,830.12 43,253.76 4.02 1,236,783.45 4.01 14,040.00 4.02 29,250.00 4.03 9,730.50 11,310.00 5.00 87,750.00 54,600.00 5.01 51,187.50 5.02 14,300.00 5.03 27,300.00 5.04 4,088.50 5.05 3,900.00 5.06 307,456.50 5.01 5.02 3,625.00

(48)

13,750.00 6.00 1,100.00 6.01 850.00 6.02 300.00 6.03 3,500.00 6.04 6.05 56,250.00 6.07 1,890.00 6.08 1,250.00 6.09 1,875.00 6.1 850.00 6.12 1,755.00 6.13 700.00 1,200.00 7.00 1,750.00 3,750.00 7.01 1,093.75 7.02 95,488.75 7.03 7.04 22,500.00 7.05 1,500.00 7.06 2,187.50 233.75 7.01 233.75 7.02 6,012.50 7.03 170.00 7.04 2,250.00 7.05 4,500.00 7.06 1,000.00 7.07 40,587.50 7.08

(49)

7.09 7,218.75 7.10 2,200.00 7.11 1,697.50 3,587.50 8.00 687.50 8.01 2,337.50 8.02 970.00 8.03 687.50 8.04 900.00 8.05 20,286.25 8.06 8.07 8.08 1,400.75 8.09 12,121.88 8.10 12,100.00 645.75 9.00 26,268.38 9.01 9.02 9.03 8,400.00 9.04 1,800.00 9.05 1,312.50 9.06 1,687.50 9.07 2,700.00 9.08 1,650.00 9.09 252,362.50 10.00 45,225.00 10.01 30,987.50 10.02 346,125.00 10.03

2,993,117.44

10.04

PRICE FOR BIDDING

11.00

/m²

11.0111.02

11.03 11.04 11.05

(50)

11.06

11.01

11.02 11.03

(51)

TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK

DETAILED ESTIMATES

COST (MATERIALS AND LABOR AND LABOR ONLY)

DESCRIPTION COST

MATERIALS AND LABOR

GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities

Php 278.57

and Services/Demobilization/Permits

Earthworks

Php 379.36

Clearing and Grubbing

Php 50.00

Structural Excavation

Php 135.36

Backfilling and Compaction

Php 71.43

Gravel Bedding G-1

Php 39.46

Select Fill

Php 18.11

Soil Poisoning

Php 65.00

Concreting Works

Php 63,257.24

Concreting of Column Footing (F1)

Php 3,916.00

Portland Cement

Php 2,421.00

Crushed Gravel 1"

Php 1,105.00

Washed Sand

Php 390.00

Concreting of Wall Footing (WF1) Php 3,103.01

Portland Cement

Php 1,992.59

Crushed Gravel 1"

Php 460.42

Washed Sand

Php 650.00

Column (C1 & C2) Php 8,430.96 Portland Cement

Php 5,230.56

Crushed Gravel 3/4""

Php 2,365.52

Washed Sand

Php 834.89

Beams (FTB-1, RCB-1 & RFB-1) Php 12,311.54 Portland Cement

Php 7,621.67

Crushed Gravel 3/4""

Php 3,466.43

Washed Sand

Php 1,223.44

Slab on Grade (S-1) Php 34,848.05 Portland Cement

Php 20,772.78

Crushed Gravel 1"

Php 10,406.24

Washed Sand

Php 3,669.03

Stairs Php 647.69

(52)

Portland Cement

Php 398.52

Crushed Gravel 1"

Php 184.17

Washed Sand

Php 65.00

Rebar Works Php 8,162.37

Reinforcing Steel Bars in Footings Php 3,582.52 Column Footing (C1F1) Php 1,651.05 16 mm

Php 1,601.60

#16 G.I. Wire

Php 49.45

Column Footing (C2F1) Php 1,849.48 16 mm

Php 1,801.80

#16 G.I. Wire

Php 47.68

Wall Footings

Php 81.99

12 mm

Php 41.60

10 mm

Php 27.08

#16 G.I. Wire

Php 13.31

Reinforcing Steel Bars in Column Php 1,629.87

Column (C1F1) Php 731.87 16 mm

Php 450.45

10 mm

Php 233.51

#16 G.I. Wire

Php 47.91

Column (C2F1) Php 898.00 16 mm

Php 600.60

10 mm

Php 233.51

#16 G.I. Wire

Php 63.89

Reinforcing Steel Bars in Roof Beams

Php 1,686.46

FTB-1

Php 653.88

12 mm

Php 300.00

10 mm

Php 284.35

#16 G.I. Wire

Php 69.53

RCB-1 and RFB-2

Php 1,032.58

16 mm

Php 655.20

10 mm

Php 284.38

#16 G.I. Wire

Php 93.00

Reinforcing Steel Bars in Slabs

Php 1,263.52

Ground Floor Slab

Php 738.52

12 mm

Php 677.62

#16 G.I. Wire

Php 60.90

S-1

Php 525.00

(53)

10 mm

Php 174.87

#16 G.I. Wire

Php 75.00

Installation of Forms and Scaffoldings Php 15,776.57

Column form Php 2,300.24

Good lumber ( 2" x 2" x 12')

Php 740.24

Plywood Ordinary, 1/4" x 4" x 8'

Php 1,101.18

CWN, Assorted

Php 458.82

Column & Roof beam Scaffolding Php 10,510.81

Vertical Support ( 2" x 3" x 12' Good lumber)

Php 4,551.94

Horizontal Support (2" x 2" x 12' Good lumber)

Php 3,527.39

Diagonal braces (2" x 2" x 12' Good lumber)

Php 1,896.18

CWN, Assorted

Php 535.29

Beam form

Php 2,965.53

Good lumber ( 2" x 2" x 12')

Php 1,160.82

Plywood Ordinary, 1/4" x 4" x 8'

Php 1,345.88

CWN, Assorted

Php 458.82

Masonry Works

Php 3,690.59

Masonry wall Php 3,491.59 CHB 5" THK

Php 144.38

CHB 4" THK

Php 131.88

Portland Cement

Php 2,486.81

Washed Sand

Php 667.29

12mm x 6m RSB

Php 48.65

#61 G.I. Tie wire

Php 12.59

Plastering

Php 199.00

Portland Cement

Php 62.56

(54)

Installation of Doors And Windows

Php 3,236.38

D-1, Double swing panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb

Php 147.79

Php 307.89

Php 102.43

Php 119.05

Php 923.68

Php 574.74

Php 538.82

Php 150.53

Php 287.37

Php 43.04

Php 41.05

Electrical Works

Php 1,005.14

Installation of Roughing-ins

Php 243.42

Electrical Conduit uPVC, 15mmØ

Php 38.16

RSC 60mmØ

Php 144.74

Entrance Cap 60mm dia.

Php 11.58

Junction Box , 4" x 4" G.I

Php 8.95

Utility Box, 2" x 4" x G.I

Php 3.16

Grounding Rod, 2.4m x 16mm dia.

Php 36.84

Wires and Fixtures

Php 761.72

3.5 mm2 THW wire , Stranded

Php 592.11

Duplex C.O. with Plate

Php 19.89

3 Way Switch With Plate

Php 13.16

40 watts Flourescent Lamp

Php 19.74

Single Switch with Plate

Php 8.95

2-Gang Switch with Plate

Php 18.47

Incandescent Bulb 50W

Php 7.37

Panel Box, Flush Type, 4 Branches

Php 12.63

D-2, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb

D-3, Panel door with 2" x 6" wooden frame & 2" x 6" wooden door jamb

W-1, 12mm thk. bronze glass on powder coated aluminum frame

W-2, 6mm thk. bronze glass on powder coated aluminum frame

W-3, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-4, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-5, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-6, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs. W-7, 12mm thk. bronze glass on powder coated aluminum frame

W-8, 6mm thk. bronze glass on powder coated aluminum frame with open back, screen & lock accs.

(55)

Circuit Breaker, 20A 2P

Php 18.42

Main Circuit Breaker, 175A 2P

Php 39.47

Electrical Tape

Php 11.51

Plumbing Works

Php 427.24

Water Closet 1.6gpf with Accessories

Php 236.84

Kitchen Sink

Php 15.79

Faucet , Hose Bibb , Brass 3/4"Ø

Php 23.03

G.I Coupling, 3/4"Ø

Php 2.46

G.I Tee, 3/4"Ø

Php 2.46

G.I. Pipe 3/4" Sch.40

Php 63.29

G.I. Elbow 90° x 3/4"Ø

Php 1.79

Gate Valve , 3/4"dia.

Php 23.68

Check Valve , 3/4"dia.

Php 47.37

S.S. Floor Drain 4' x 4"

Php 10.53

Sanitary works

Php 213.54

uPVC Sanitary Pipe 4"Ø x 10'

Php 75.99

uPVC Wye 4" x 4"

Php 23.16

uPVC Wye 4" x 2"

Php 17.87

uPVC Sanitary Pipe 2"Ø

Php 37.76

uPVC P-TRAP 2"Ø

Php 7.24

uPVC P-TRAP 4"Ø

Php 24.61

uPVC Elbow 45° x 4 "Ø

Php 10.21

uPVC Cleanout 4" diameter

Php 7.24

PVC Cement

Php 9.47

Painting Works

Php 87.56

Concrete surfaces Neutralizer

Php 4.67

Latex, Flat

Php 40.41

Latex, Semi Gloss

Php 40.33

Acri Color

Php 2.15

TileWorks

Php 3,643.42

Wall

Php 184.74

Unglazed Wall Tiles 20cm x 30cm T&B

Php 88.42

Unglazed Wall Tiles 20cm x 20cm KITCHEN

Php 18.95

Tile Trim 6mm.

Php 13.82

Lining 2" X 20cm (T&B and KITCHEN)

Php 17.76

(56)

Tile Grout 5 kg/bag

Php 17.37

Flooring

Php 3,458.68

Glazed Floor Tiles 20cmx 20cm

Php 2,656.45

(INTERIOR )

Tile Adhesive 25kg/bag

Php 476.05

(57)

TWO STOREY RESIDENTIAL BUILDING WITH ROOFDECK

DETAILED ESTIMATES

COST (MATERIALS AND LABOR AND LABOR ONLY)

COST

MATERIALS AND LABOR

LABOR

Php 278.57

Php 64.29

Php 379.36

per m²

Php 231.50

per m²

Php 50.00

per m²

Php 50.00

per m²

Php 135.36

per m²

Php 135.36

per m²

Php 71.43

per m²

Php 17.86

per m²

Php 39.46

per m²

Php 9.11

per m²

Php 18.11

per m²

Php 4.18

per m²

Php 65.00

per m²

Php 15.00

per m²

Php 63,257.24

Php 15,393.39

Php 3,916.00

Php 1,174.00

Php 2,421.00

Php 594.00

Php 1,105.00

Php 255.00

Php 390.00

Php 90.00

Php 3,103.01

Php 745.14

Php 1,992.59

Php 488.89

Php 460.42

Php 106.25

Php 650.00

Php 150.00

Php 8,430.96

Php 2,021.89

Php 5,230.56

Php 1,283.33

Php 2,365.52

Php 545.89

Php 834.89

Php 192.67

Php 12,311.54

Php 2,952.28

Php 7,621.67

Php 1,870.00

Php 3,466.43

Php 799.94

Php 1,223.44

Php 282.33

Php 34,848.05

Php 8,344.81

Php 20,772.78

Php 5,096.67

Php 10,406.24

Php 2,401.44

Php 3,669.03

Php 846.70

Php 647.69

Php 155.28

per m² per m²

per m³

per m³

per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³ per m³

(58)

Php 398.52

Php 97.78

Php 184.17

Php 42.50

Php 65.00

Php 15.00

Php 8,162.37

per m²

Php 2,448.71

per m²

Php 3,582.52

per m²

Php 1,074.76

per m²

Php 1,651.05

per m²

Php 495.32

per m²

Php 1,601.60

per m²

Php 480.48

per m²

Php 49.45

per m²

Php 14.84

per m²

Php 1,849.48

per m²

Php 554.84

per m²

Php 1,801.80

per m²

Php 540.54

per m²

Php 47.68

per m²

Php 14.30

per m²

Php 81.99

per m

Php 24.60

per m²

Php 41.60

per m

Php 12.48

per m

Php 27.08

per m

Php 8.12

per m

Php 13.31

per m

Php 3.99

per m

Php 1,629.87

per m

Php 488.96

per m

Php 731.87

per m

Php 219.56

per m

Php 450.45

per m

Php 135.14

per m

Php 233.51

per m

Php 70.05

per m

Php 47.91

per m

Php 14.37

per m

Php 898.00

per m

Php 269.40

per m

Php 600.60

per m

Php 180.18

per m

Php 233.51

per m

Php 70.05

per m

Php 63.89

per m

Php 19.17

per m

Php 1,686.46

per m

Php 505.94

per m

Php 653.88

per m

Php 196.16

per m

Php 300.00

per m

Php 90.00

per m

Php 284.35

per m

Php 85.31

per m

Php 69.53

per m

Php 20.86

per m

Php 1,032.58

per m

Php 309.77

per m

Php 655.20

per m

Php 196.56

per m

Php 284.38

per m

Php 85.31

per m

Php 93.00

per m

Php 27.90

per m

Php 1,263.52

per m²

Php 379.06

per m²

Php 738.52

per m²

Php 221.56

per m²

Php 677.62

per m²

Php 203.29

per m²

Php 60.90

per m²

Php 18.27

per m²

Php 525.00

per m²

Php 157.50

per m²

Php 275.13

per m²

Php 82.54

per m²

per m³ per m³ per m³ per m³ per m³ per m³

(59)

Php 174.87

per m²

Php 52.46

per m²

Php 75.00

per m²

Php 22.50

per m²

Php 15,776.57

per m

Php 4,732.97

per m

Php 2,300.24

per m

Php 690.07

per m

Php 740.24

per m

Php 222.07

per m

Php 1,101.18

per m

Php 330.35

per m

Php 458.82

per m

Php 137.65

per m

Php 10,510.81

per m

Php 3,153.24

per m

Php 4,551.94

per m

Php 1,365.58

per m

Php 3,527.39

per m

Php 1,058.22

per m

Php 1,896.18

per m

Php 568.85

per m

Php 535.29

per m

Php 160.59

per m

Php 2,965.53

per m

Php 889.66

per m

Php 1,160.82

per m

Php 348.25

per m

Php 1,345.88

per m

Php 403.76

per m

Php 458.82

per m

Php 137.65

per m

Php 3,690.59

per m²

Php 1,107.18

per m²

Php 3,491.59

per m²

Php 1,047.48

per m²

Php 144.38

per m²

Php 43.31

per m²

Php 131.88

per m²

Php 39.56

per m²

Php 2,486.81

per m²

Php 746.04

per m²

Php 667.29

per m²

Php 200.19

per m²

Php 48.65

per m²

Php 14.60

per m²

Php 12.59

per m²

Php 3.78

per m²

Php 199.00

per m²

Php 59.70

per m²

Php 62.56

per m²

Php 18.77

per m²

Php 136.45

per m²

Php 40.93

per m²

(60)

Php 3,236.38

per m²

Php 970.92

per m²

Php 147.79

per m²

Php 44.34

per m²

Php 307.89

per m²

Php 92.37

per m²

Php 102.43

per m²

Php 30.73

per m²

Php 119.05

per m²

Php 35.72

per m²

Php 923.68

per m²

Php 277.11

per m²

Php 574.74

per m²

Php 172.42

per m²

Php 538.82

per m²

Php 161.64

per m²

Php 150.53

per m²

Php 45.16

per m²

Php 287.37

per m²

Php 86.21

per m²

Php 43.04

per m²

Php 12.91

per m²

Php 41.05

per m²

Php 12.32

per m²

Php 1,005.14

per m²

Php 301.54

per m²

Php 243.42

per m²

Php 73.03

per m²

Php 38.16

per m²

Php 11.45

per m²

Php 144.74

per m²

Php 43.42

per m²

Php 11.58

per m²

Php 3.47

per m²

Php 8.95

per m²

Php 2.68

per m²

Php 3.16

per m²

Php 0.95

per m²

Php 36.84

per m²

Php 11.05

per m²

Php 761.72

per m²

Php 228.52

per m²

Php 592.11

per m²

Php 177.63

per m²

Php 19.89

per m²

Php 5.97

per m²

Php 13.16

per m²

Php 3.95

per m²

Php 19.74

per m²

Php 5.92

per m²

Php 8.95

per m²

Php 2.68

per m²

Php 18.47

per m²

Php 5.54

per m²

Php 7.37

per m²

Php 2.21

per m²

Php 12.63

per m²

Php 3.79

per m²

(61)

Php 18.42

per m²

Php 5.53

per m²

Php 39.47

per m²

Php 11.84

per m²

Php 11.51

per m²

Php 3.45

per m²

Php 427.24

per m²

Php 128.17

per m²

Php 236.84

per m²

Php 71.05

per m²

Php 15.79

per m²

Php 4.74

per m²

Php 23.03

per m²

Php 6.91

per m²

Php 2.46

per m²

Php 0.74

per m²

Php 2.46

per m²

Php 0.74

per m²

Php 63.29

per m²

Php 18.99

per m²

Php 1.79

per m²

Php 0.54

per m²

Php 23.68

per m²

Php 7.11

per m²

Php 47.37

per m²

Php 14.21

per m²

Php 10.53

per m²

Php 3.16

per m²

Php 213.54

per m²

Php 64.06

per m²

Php 75.99

per m²

Php 22.80

per m²

Php 23.16

per m²

Php 6.95

per m²

Php 17.87

per m²

Php 5.36

per m²

Php 37.76

per m²

Php 11.33

per m²

Php 7.24

per m²

Php 2.17

per m²

Php 24.61

per m²

Php 7.38

per m²

Php 10.21

per m²

Php 3.06

per m²

Php 7.24

per m²

Php 2.17

per m²

Php 9.47

per m²

Php 2.84

per m²

Php 87.56

per m² Php 26.27 per m²

Php 4.67

per m²

Php 1.40

per m²

Php 40.41

per m²

Php 12.12

per m²

Php 40.33

per m²

Php 12.10

per m²

Php 2.15

per m²

Php 0.65

per m²

Php 3,643.42

per m²

Php 1,093.03

per m²

Php 184.74

per m²

Php 55.42

per m²

Php 88.42

per m²

Php 26.53

per m²

Php 18.95

per m²

Php 5.68

per m²

Php 13.82

per m²

Php 4.14

per m²

Php 17.76

per m²

Php 5.33

per m²

Php 28.42

per m²

Php 8.53

per m²

(62)

Php 17.37

per m²

Php 5.21

per m²

Php 3,458.68

per m²

Php 1,037.61

per m²

Php 2,656.45

per m²

Php 796.93

per m²

Php 476.05

per m²

Php 142.82

per m²

Php 326.18

per m²

Php 97.86

per m²

References

Related documents

§ 446 (2) If the probability of the insured risk increased due to a change effected by the policyholder without the consent of the insurer and the policyholder

Construction Services, LLC McManimon, Scotland & Baumann, LLC [email protected] Counsel to Official Committee of Unsecured Creditors of Hollister. Construction Services,

For the first research question, the data is obtained through observation during the learning class using the field note as a note during teaching and learning while the data for

In addition, systems engineers need the support of ALM and PLM tools so that they can improve design and development processes, and extend the V-model with iterative work

External type AISI-316L mechanical seal for highly corrosive fluids, static and rotating rings in SiC, spring and Polyester thermosetting powder coated power frame construction

Now I want to close out the series with three brief cases of companies using a JavaScript- based engine to develop and deploy web services to integrate CICS applications and

Such forward-looking statements include, but are not limited to, statements about: future projected or target production and the growth of production including the product mix of

Peer feedback : Of the peer companies we surveyed, 5% indicated offering supplemental key employee benefits was a high priority for them, and 19% indicated they would be