FIRST COMMERCIAL PRODUCTION FACILITY – GARRAF FIELD DEVELOPMENT PROJECT
WEATHERFORD OIL TOOL MIDDLE EAST LTD.
FOR
PETRONAS CARIGALI IRAQ HOLDING BV
Document Title:
Document No.:
LP FLARE NETWORK CALCULATION
P10-1033-P-CA-0191
This document supersedes the LP Flare
Calculation cited in P10-1033-P-RE-0006
E0 21-06-2013 Issued for Construction PKM SY AM
REV DATE STATUS PREPARED
BY
CHECKED BY
APPROVED BY
Name Signature Title Date
CONTRACTOR CLIENT
PROJECT DOCUMENTS ARE CONTROLLED DOCUMENTS. REVISIONS ARE DENOTED
IN RIGHT HAND MARGINCLIENT:
PETRONAS CARIGALI IRAQ HOLDING BV
CLIENT REF:
CHO/2010/DPP/067
CONTRACTOR:
WEATHERFORD OIL TOOL MIDDLE EAST LTD
CONTRACTOR REF:
P10-1033
Resubmit for Approval
Resubmit for Review Approved with Comment Approved /Reviewed
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 2 of 18 Document1
TABLE OF CONTENTS
1
Introduction ... 3
2
Summary ... 3
2.1
Purpose ... 3
2.2
Definition of Standard and Normal Conditions ... 3
2.3
References ... 3
2.4
Assumptions... 4
2.5
Calculation Basis ... 4
2.6
Results and Conclusions ... 5
2.6.1 Backpressure ... 5
2.6.2 Mach No. & Rho V2 ... 6
2.6.3 NOISE ... 6
3
LP Flare ... 6
3.1
LP Flare Sources ... 6
3.2
LP Flare Network ... 7
3.3
LP Flare Relief Loads & Relief Gas Composition ... 8
3.3.1 1st Stage Separator (V-1010 / 1020) ... 8
3.3.2 2ND Stage Separator (V-1110 / 1120) ... 8
3.3.3 Dehydrator (V-1510 / 1520) & Desalter (V-1610 / 1620) ... 9
3.3.4 Produced Water Treatment Package (AQ-4210) ... 9
3.3.5 Fuel Gas Treatment Package (AQ-6020) ... 10
3.3.6 Power Plant Fuel Gas Conditioning Package (AQ-7501) ... 10
3.4
LP Flare Purge ... 10
3.5
LP Flare Knock Out Drum, V-6205 ... 11
3.6
LP Flare Stack (Smokeless Flaring) ... 11
3.7
LP Flare Tip... 11
4
LP Flare Scenarios ... 11
4.1
Scenario 1 ... 12
4.2
Scenario 2 ... 12
4.3
Scenario 3 ... 13
4.4
Scenario 4 ... 13
4.5
Scenario 5 ... 14
4.6
Scenario 6 ... 14
4.7
Scenario 7 ... 15
4.8
Scenario 8 ... 15
4.9
Scenario 9 ... 16
4.10
Scenario 10 ... 16
4.11
Scenario 11 ... 17
5
Relief Load In Various Scenarios ... 17
6
Basis For Aspen Flare System Analyzer Study ... 18
7
LP Flare Design Criteria ... 18
7.1
Header and Tailpipe ... 18
7.2
Noise Limitations ... 18
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 3 of 18 Document1
1
I
NTRODUCTIONThe LP Flare Network is an important part of FCP as it ensures the safe disposal of hydrocarbon releases from various pressurized sources. The 1st Stage and 2nd Stage separators of both trains are continuously relieving to LP flare header to maintain separator pressure. The following equipment / packages are also connected to the LP flare system for relief gas disposal: desalters, dehydrators, crude heater packages, fuel gas package, power plant fuel gas conditioning and produced water treatment packages.
The LP Flare source releases are estimated considering that each FCP Train is operating at the design production rate of 55000 bpd. Calculations produced in this document have been determined using Aspen Flare System Analyzer Version 7.3.
Once the various operating and relief scenarios that could occur are defined and the relief rates, venting rates and fluid properties are input into the flare system model, Aspen Flare System Analyzer performs numerous iterative calculations to size the LP flare network. Piping information i.e. layout, pipe lengths and fittings data are taken from piping isometrics in order to build the model.
2
S
UMMARY
2.1 Purpose
The purpose of this calculation is to identify relief scenarios and determine the relief loads directed to the LP flare system and to select the line sizes in the flare system.
2.2 Definition of Standard and Normal Conditions
The standard and normal conditions for volumetric measurement of gases and liquids are defined at pressure and temperature of:
Standard = 1.013 Bara and 15.6°C. Normal = 1.013 Bara and 0°C.
2.3 References
Sr No Documents Attachment No of Pages
1 Extract of PSV Datasheet sizing Doc No. :
P10-1033-P-DS-0003 Rev D2 (For Process Trains)
Attachment-A 4 2 1st Stage Separator – Total Flaring HYSYS
stream summary
Attachment-B 2
3 1st Stage Separator – Blocked outlet HYSYS
stream summary
Attachment-C 2
4 1st Stage Separator – Fire Case HYSYS stream
summary
Attachment-D 2 5 1st Stage & 2nd Stage Separator - Blowdown
Results
Attachment-E 4
6 2nd Stage Separator – Total Flaring HYSYS
stream summary
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 4 of 18 Document1
Sr No Documents Attachment No of Pages
7 2nd Stage Separator gas flow during 1st Stage
separator blocked outlet - HYSYS stream summary
Attachment-G 2
8 2nd Stage Separator- Gas blowby from 1st Stage separator - HYSYS stream summary
Attachment-H 2
9 2nd Stage Separator – Fire Case HYSYS stream
summary
Attachment-I 2
10 Dehydrator – Fire Case HYSYS stream
summary
Attachment-J 2
11 Desalter – Fire Case HYSYS stream summary Attachment-K 2
12 PW Treatment Package- PSV Data Attachment-L 2
13 Fuel Gas Package- PSV & BDV Data Attachment-M 3
14 Power Plant Fuel Gas Conditioning Package-
PSV & BDV Data
Attachment-N 3 15 Extract of Calculation for LP Flare KO Drum,
Doc No.: P10-1033-P-CA-0146
Attachment-O 1 16 Flare package data from Flare Industries Attachment-P 2
17 Purge gas calculation Attachment-Q 1
18 Fuel Gas Package H&M Balance Attachment-R 2
19 P&ID’s Attachment-S 17
20 Piping Isometrics Attachment-T 81
21 Pressure/flow summary (Results for scenarios 1-11) Attachment-U 11
2.4 Assumptions
1. Any operational contingency on one train will not affect the operation of other train. 2. Pipe lengths and fittings for the Fuel Gas Conditioning Package AQ-7501 and the
Produced Water Treatment Package AQ-4210 are assumed.
3. Thermal relief from piping and pig receivers are not considered in this calculation as flow rates are insignificant for this relief contingency.
4. The relief case for the Produced Water Package AQ-4210 is control valve failure based on nitrogen flow. This flow data is currently not available. However, as this flow is limited by an RO and insignificant relative to the governing case for the LP flare, the available data for the thermal relief case given in attachment L is used in the calculations.
2.5 Calculation Basis
1. Various relief loads to LP flare network is considering that both crude processing trains are operating at 55,000 bpd (Design Flow).
2. PSV rated flow is used as the relief load for all cases except fire.
3. For fire case, the required flow of relief valve is used as the relief load even if the governing case is the fire case as there are other mitigating devices in place to reduce the relief load e.g. blowdown and active fire protection. The fire case relief loads also do not govern the flare header sizing in this plant.
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 5 of 18 Document1
5. LP flare relief load for fire case scenario of any of these three equipments (2nd stage separator, desalter & dehydrator) is the same. As fire circle will cover all three equipments 2nd stage separator, desalter & dehydrator of the particular train.
6. During operational contingency on one train, it is considered that the feed to the fuel gas package AQ-6020, will be at normal user flow rate demand (i.e., 2 Crude heaters + LP &
ATM purge flows + Power Plant Fuel Gas Conditioning
Package=2x1591+3x80+3x55+7964=11551 kg/h) from the other normal operating train. Otherwise, the fuel gas package will be withdrawing equally from the 1st stage separators of trains 1 and 2 and the remaining gas is flared off.
7. During a fire scenario, the relief loads considered are for equipment located in the fire zone and the blowdown rates are from equipment outside the fire zone.
8. In the case of multiple working PSVs, the total relief load is distributed equally to the operating PSVs.
9. In normal operation, fuel gas is continuously purged at 3 locations into the flare header ends to prevent burn back in the flare tip.
10. For the determination of maximum backpressures for multiple PSVs, the farthest working PSVs from the flare stack are assumed to be relieving.
2.6 Results and Conclusions
Aspen Flare System Analyzer simulations are carried out for all scenarios & results are evaluated against the design criteria.
2.6.1 B
ACKPRESSUREMaximum back pressure for all scenarios (See attachment-U) is tabulated below.
Scenarios Maximum Back
Pressure, barg
Location PCV / Relief
Valve Scenario 1 0.24 Train 1- 2nd Stage Separator, V-1110 PCV-1110
Scenario 2 Note 2 Note 2 Note-2
Scenario 3 1.37 Train 1- 2nd Stage Separator, V-1110 PSV-1110C Scenario 4 1.40 Train 2- 2nd Stage Separator, V-1110 PSV-1120C
Scenario 5 1.14 Train 1- Dehydrator, V-1510 PSV-1510
Scenario 6 1.16 Train 2- Dehydrator, V-1520 PSV-1520
Scenario 7 0.40 Train 1- 1st
Stage Separator, V-1010 PSV-1010 C
Scenario 8 0.39 Train 2- 1st
Stage Separator, V-1020 PSV-1020 C
Scenario 9 1.79 Fuel Gas Package, AQ-6020 PSV-6000 A/B
Scenario 10 0.34 Power Plant Fuel Gas Conditioning Package, AQ-7501
PSV-6027/28
Scenario 11 0.15 AQ-4210, IGF PSV-4220/4221
Notes:
1- Maximum back pressure is observed at downstream of PSV-6000 A/B.
2- In scenario 2 (Total Blowdown), all BDV’s will be operating and BDV’s operation is independent of back pressure.
3- In scenarios 3 and 4, the maximum back pressures slightly exceed the allowable 30% back pressure, set in the simulation. However, as balanced bellows PSVs are used on 2nd stage separators and the rated flow is 30% higher than the required flow, there is no concern.
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 6 of 18 Document1
2.6.2 M
ACHN
O.
&
R
HOV2
In all scenarios, Mach No is significantly lower than 0.6 in all flare headers and sub-headers as well as Mach No. is lower than 0.5 downstream of all control valves (See Attachment U). In all scenarios, Rho V2 is significantly lower than 200000 kg/m/s2, therefore is no concern (See Attachment-U).
2.6.3 N
OISEIn all scenarios noise is significantly lower than 85 dB (A) thus there are no noise issues (See Attachment-U)
.
3
LP
F
LARE
3.1 LP Flare Sources
LP Flare sources are tabulated below
Source Name PCV / BDV / Relief Valve
V-1010 Train 1, 1st Stage Separator PCV-1011, BDV-1010, PSV-1010 A/B/C V-1110 Train 1, 2nd Stage Separator PCV-1110, BDV-1110, PSV-1110 A/B/C V-1510 Train 1, Dehydrator PSV-1510
V-1610 Train 1, Desalter PSV-1610
AQ-1111 Train 1, Crude Heater (Note 1) TSV-11101
V-1020 Train 2, 1st Stage Separator PCV-1020, BDV-1020, PSV-1020 A/B V-1120 Train 2, 2nd Stage Separator PCV-1120, BDV-1120, PSV-1120 A/B V-1520 Train 2, Dehydrator PSV-1520
V-1620 Train 2, Desalter PSV-1620
AQ-1112 Train 2, Crude Heater (Note 1) TSV-11201
AQ-6020 Fuel Gas Package (Note 2) PSV-6000 A/B, BDV-6001, BDV-6010 AQ-7501 Power Plant Fuel Gas
Conditioning Package (Note 2) PSV-6027/28, BDV-6001, BDV-6002 AQ-4210 Produced Water Treatment
Package
PSV-4210/4211, PSV-4220/4221
Note 1: Source modeled in Flare-Net but as this is a thermal relief case it is ignored in the simulations.
Note 2: Only the governing and blowdown sources that are modeled in Flare-Net are given here.
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 7 of 18 Document1
3.2 LP Flare Network
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 8 of 18 Document1
3.3 LP Flare Relief Loads & Relief Gas Composition
The LP flare sources have different relief loads in accordance with the overall relief scenario. The relief gas composition is dependent on the relieving scenario.
3.3.1 1
STS
TAGES
EPARATOR(V-1010
/
1020)
PCV / BDV / Relief Valve PCV-1011 /1021 PSV-1010 A/B/C / 1020 A/B/C PSV-1010 A/B/C / 1020 A / B /C BDV-1010 / 1020Scenario Total Flaring Blocked outlet Fire Adiabatic
Blowdown
Reference Attachment-B Attachment-A Attachment-A Attachment-E
Relief load, kg/h
36668.7
30713*
10637
4559
Pressure, barg
9.9
19.8
21.8
10.3
Temperature, oC
65.8
66.0
174.3
66
M.W.
24.2
22.8
34.8
24.2
Composition Attachment-B Attachment-C Attachment-D Attachment-B
For adiabatic blowdown, composition is considered similar to total flaring case. *Required flow given, the rated flow of 33654 kg/h for two operating PSVs is used in calculations.
3.3.2 2
NDS
TAGES
EPARATOR(V-1110
/
1120)
PCV / BDV / Relief Valve PCV-1011 /1021 PCV-1011 /1021 PSV-1110 A/B/C / 1120 A/B/C PSV-1010 A/B/C / 1020 A / B /CScenario Total Flaring During 1st Stage
Blocked outlet
Gas Blowby Fire
Reference Attachment-F Attachment-G Attachment-A Attachment-A
Relief load, kg/h 10545.9 12921 55556 8813
Pressure, barg
2.4
2.4
4.9
5.6
Temperature, oC
104.1
104.6
105.0
141.7
M.W.
38.3
42.6
25.6
37.8
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 9 of 18 Document1
2nd Stage Separator (V-1110 / 1120) During Blowdown
PCV / BDV / Relief Valve BDV-1110 / 1120 BDV-1110 / 1120 Scenario Adiabatic Blowdown Fire Case Blowdown
Reference Attachment-E Attachment-E
Relief load, kg/h 4354 6207
Pressure, barg
2.8
4.5
Temperature, oC
105
105
M.W.
38.3
38.3
Composition Attachment-F Attachment-F
For adiabatic & fire blowdown, composition is considered similar to total flaring case.
3.3.3 D
EHYDRATOR(V-1510
/
1520)
&
D
ESALTER(V-1610
/
1620)
PCV / BDV / Relief Valve PSV-1510 / 1520 PSV-1610 / 1620Scenario Fire Fire
Reference Attachment-A Attachment-A
Relief load, kg/h
15993
15991
Pressure, barg
20.5
20.5
Temperature, oC
199.3
199.3
M.W.
34.7
34.7
Composition Attachment-J Attachment-K
3.3.4 P
RODUCEDW
ATERT
REATMENTP
ACKAGE(AQ-4210)
PCV / BDV / Relief Valve PSV-4210 / 4211 PSV-4220 / 4221
Scenario Thermal Relief* Thermal Relief*
Reference Attachment-L Attachment-L
Relief load, kg/h
650
*650
*Pressure, barg
9.6
9.6
Temperature, oC
70
70
M.W.
24.2
24.2
Composition Attachment-R Attachment-R
*Thermal relief load used in calculations in the absence of actual data for control valve failure case. See section 2.4.
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 10 of 18 Document1
3.3.5 F
UELG
AST
REATMENTP
ACKAGE(AQ-6020)
Fuel Gas Treatment Package (AQ-6020) relief load is 63000 Kg/hr for the governing case. The PSV rated flow is limited to this required flow by the upstream train 1 and 2 control valve Cvs and system hydraulics.
Equipment V-6000 V-6000 S-6000 A/B
PCV / BDV / Relief
Valve PSV-6000A/B BDV-6000 BDV-6010
Scenario Control Valve
Failure
Adiabatic Blowdown
Adiabatic Blowdown
Reference Attachment-M Attachment-M Attachment-M
Relief load, kg/h
63000
331.5
932.6
Pressure, barg
15.1
8.6
8.0
Temperature, oC
60
60
75
M.W.
24.2
24.2
24.2
Composition Attachment-M&R Attachment-M&R Attachment-M&R
3.3.6 P
OWERP
LANTF
UELG
ASC
ONDITIONINGP
ACKAGE(AQ-7501)
Power Plant Fuel Gas Conditioning Package (AQ-7501) relief load is 8381 kg/hr for the governing case.
Equipment E-6006 V-6005 E-6001
PCV / BDV / Relief Valve
PSV-6027 /
6028 BDV-6002 BDV-6001
Scenario Tube Rupture Adiabatic
Blowdown Adiabatic Blowdown
Reference Attachment-N Attachment-N Attachment-N
Relief load, kg/h
8381*
705
1596
Pressure, barg
8.3
21.6
20.5
Temperature, oC
32.2
10.0
10.0
M.W.
24.0
24.0
24.0
Composition Attachment-N Attachment-N Attachment-N
*Required flow is used as the relief rate is limited by the supply of gas to this package.
3.4 LP Flare Purge
LP flare network is purged continuously with fuel gas through three locations (Train1 flare header, Train 2 flare header and fuel gas package, AQ-6020). Fuel gas purging requirement (for burnback prevention) is based on Flare Industries values and velocity criteria are adjusted to match the flow requirement. Purge gas flow rates are estimated based on a velocity of 0.092 m/s at flare tip.
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 11 of 18 Document1
During loss of fuel gas supply or during startup/shutdown, LP flare network is continuously purged with nitrogen through two locations (Train 1 Flare header, Train 2 Flare header). N2 purging requirement (for air-ingress prevention) is based on API velocity criteria (0.006-0.012 m/sec). Velocity of 0.012 m/sec is used for calculation and this is in close agreement with Flare Industries values. Refer to Attachment-Q for purge gas calculation.
3.5 LP Flare Knock Out Drum, V-6205
Calculated pressure drop across the LP flare KOD is approximately 10 mbar at the rated flow of 94400 kg/h. However, the actual pressure drop across the drum is likely to be higher because of the inlet device and sump pump obstruction to flow path. (Refer to Attachment-O, Calculation for LP Flare KO Drum P10-1033-P-CA-0146).
3.6 LP Flare Stack (Smokeless Flaring)
The LP flare stack assembly consists of a 36 inch inner flare gas riser and a 78 inch outer pipe. The dilution air is blown through the annulus between the riser and the outer pipe. The stack height is 45.7 m from ground level (see Attachment-P, LP Flare Package data from Flare Industries).
3.7 LP Flare Tip
The Flare Tip contains a dynamic seal. Its pressure drop is 25.77 mbar at the design flow (see Attachment-P, LP Flare package data from Flare Industries).
4
LP
F
LARE
S
CENARIOS
The following 11 scenarios are identified for the LP flare calculations. An individual scenario is selected to have maximum relief load in different parts of LP flare system or simultaneous maximum load in different area.
Various Scenarios are listed below:
Scenario 1 Total gas flaring Train 1 & 2
Scenario 2 Total Facility Blowdown
Scenario 3 2nd Stage Separator gas blowby, Train 1 Scenario 4 2nd Stage Separator gas blowby, Train 2
Scenario 5 Fire Case Train-1
Scenario 6 Fire Case Train-2
Scenario 7 Blocked outlet 1st Stage separator, Train-1 Scenario 8 Blocked outlet 1st Stage separator, Train-2
Scenario 9 FG Package control valve failure
Scenario 10 Power Plant Fuel Gas Conditioning Package
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 12 of 18 Document1
4.1 Scenario 1
Scenario 1 is maximum flaring of associated gas from both trains and each train is operating at design flowrate of 55000 bopd. Relief Loads from various sources are tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario V-1010 Train-1, 1st Stage Separator PCV-1011 36668.7 Total Flaring V-1110 Train-1, 2nd Stage Separator PCV-1110 10545.9 Total Flaring V-1020 Train-2, 1st Stage Separator PCV-1021 36668.7 Total Flaring V-1120 Train-2, 2nd Stage Separator PCV-1120 10545.9 Total Flaring
Total LP Flare Load 94429.3
4.2 Scenario 2
Scenario 2 is considering the total facility Blowdown e.g. during ESD. Relief Loads from various sources are tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario V-1010 Train-1, 1st Stage Separator BDV-1010 4559 Adiabatic Blowdown V-1110 Train-1, 2nd Stage Separator BDV-1110 4354 Adiabatic Blowdown V-1020 Train-2, 1st Stage Separator BDV-1020 4559 Adiabatic Blowdown V-1120 Train-2, 2nd Stage Separator BDV-1120 4354 Adiabatic Blowdown AQ-6020 Fuel Gas Package BDV-6000 331.5 Adiabatic Blowdown AQ-6020 Fuel Gas Package BDV-6010 932.6 Adiabatic Blowdown AQ-7501 Power Plant Fuel Gas
Conditioning Package BDV-6001 1596 Adiabatic Blowdown
AQ-7501 Power Plant Fuel Gas
Conditioning Package BDV-6002 705 Adiabatic Blowdown
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 13 of 18 Document1
4.3 Scenario 3
Scenario 3 is considering the Gas blowby from train 1, 2nd Stage Separator and gas from train 2 is under normal flaring. Relief Loads from various sources is tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario V-1110 Train-1, 2nd Stage Separator PSV-1110 B 27778.0 Gas Blowby V-1110 Train-1, 2nd Stage Separator PSV-1110 C 27778.0 Gas Blowby
V-1020 Train-2, 1st Stage Separator PCV-1021 25117.7 Total Flaring less Fuel Gas Consumption of 11551 kg/h V-1120 Train-2, 2nd Stage Separator PCV-1120 10545.9 Total Flaring
Purge Gas Flow 240.0 Total LP Flare Load 91459.6
4.4 Scenario 4
Scenario 4 is considering the Gas blowby from train 2, 2nd Stage Separator and gas from train 1 is under normal flaring. Relief Loads from various sources is tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario
V-1010 Train-1, 1st Stage Separator PCV-1011 25117.7 Total Flaring less Fuel Gas Consumption of 11551 kg/h V-1110 Train-1, 2nd Stage Separator PCV-1110 10545.9 Total Flaring
V-1120 Train-2, 2nd Stage Separator PSV-1120 B 27778.0 Gas Blowby V-1120 Train-2, 2nd Stage Separator PSV-1120 C 27778.0 Gas Blowby
Purge Gas Flow 240.0
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 14 of 18 Document1
4.5 Scenario 5
Scenario 5 is considering Train 1, 2nd stage separator is under fire and depressurized. Fire circle is spreading over desalter and dehydrator.1st stage separator is depressurized adiabatically. Train 2, Fuel gas Package & Power Plant Fuel Gas Conditioning Package is under adiabatic blowdown. Relief Loads from various sources is tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario V-1010 Train-1, 1st Stage Separator BDV-1010 4559 Adiabatic Blowdown V-1110 Train-1, 2nd Stage
Separator BDV-1110 6207 Fire Case Blowdown V-1510 Train-1, Dehydrator PSV-1510 15993 Fire Case
V-1610 Train-1, Desalter PSV-1610 15991 Fire Case
V-1020 Train-2, 1st Stage Separator BDV-1020 4559 Adiabatic Blowdown V-1120 Train-2, 2nd Stage
Separator BDV-1120 4354 Adiabatic Blowdown AQ-6020 Fuel Gas Package BDV-6000 331.5 Adiabatic Blowdown AQ-6020 Fuel Gas Package BDV-6010 932.6 Adiabatic Blowdown AQ-7501 Power Plant Fuel Gas
Conditioning Package BDV-6001 1596 Adiabatic Blowdown
AQ-7501 Power Plant Fuel Gas
Conditioning Package BDV-6002 705 Adiabatic Blowdown
Total LP Flare Load 55228.1
4.6 Scenario 6
Scenario 6 is considering Train 2, 2nd stage separator is under fire and depressurized. Fire circle is spreading over desalter and dehydrator.1st stage separator is depressurized adiabatically. Train 1, Fuel gas Package & Power Plant Fuel Gas Conditioning Package is under adiabatic blowdown. Relief Loads from various sources is tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario V-1010 Train-1, 1st Stage Separator BDV-1010 4559 Adiabatic Blowdown V-1110 Train-1, 2nd Stage Separator BDV-1110 4354 Adiabatic Blowdown V-1020 Train-2, 1st Stage Separator BDV-1020 4559 Adiabatic Blowdown V-1120 Train-2, 2nd Stage Separator BDV-1120 6207 Fire Case Blowdown V-1520 Train-2, Dehydrator PSV-1510 15993 Fire Case
V-1620 Train-2, Desalter PSV-1610 15991 Fire Case
AQ-6020 Fuel Gas Package BDV-6000 331.5 Adiabatic Blowdown AQ-6020 Fuel Gas Package BDV-6010 932.6 Adiabatic Blowdown AQ-7501 Power Plant Fuel Gas
Conditioning Package BDV-6001 1596 Adiabatic Blowdown
AQ-7501 Power Plant Fuel Gas
Conditioning Package BDV-6002 705 Adiabatic Blowdown
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 15 of 18 Document1
4.7 Scenario 7
Scenario 7 is considering that Train 1, 1st stage separator is under relieving under blocked outlet condition and Train 2 is normal flaring. Relief Loads from various sources is tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario V-1010 Train-1, 1st Stage Separator PSV-1010 C 16827 Blocked Outlet V-1010 Train-1, 1st Stage Separator PSV-1010 B 16827 Blocked Outlet V-1110 Train-1, 2nd Stage Separator PCV-1110 12921 Blocked Outlet of 1
st Stage
separator
V-1020 Train-2, 1st Stage Separator PCV-1021 25118 Total Flaring less Fuel Gas Consumption of 11551 kg/h V-1120 Train-2, 2nd Stage Separator PCV-1120 10545.9 Total Flaring
Purge Gas Flow 240.0
Total LP Flare Load 82478.9
4.8 Scenario 8
Scenario 8 is considering that Train 2, 1st stage separator is relieving under blocked outlet condition and Train 1 is total flaring. Relief Loads from various sources is tabulated below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario
V-1010 Train-1, 1st Stage Separator PCV-1011 25118 Total Flaring less Fuel Gas Consumption of 11551 kg/h V-1110 Train-1, 2nd Stage Separator PCV-1110 10545.9 Total Flaring
V-1020 Train-2, 1st Stage Separator PSV-1020 C 16827 Blocked Outlet V-1020 Train-2, 1st Stage Separator PSV-1020 B 16827 Blocked Outlet V-1120 Train-2, 2nd Stage Separator PCV-1120 12921 Blocked Outlet of 1
st stage
separator Purge Gas Flow 240
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 16 of 18 Document1
4.9 Scenario 9
In this scenario, the 1st Stage Separator fuel gas PCVs of both trains are wide open and the maximum flow through each PCV, assuming a hydraulically balanced system, is 63000 kg/h divided by 2 i.e. 31500 kg/h. Thus, the flare PCV flow from each 1st stage separator is equal to the total flaring load of 36668.7 kg/h less 31500 which equals 5168.7 kg/h. The 2nd stage separator flare PCV is maintaining its position and relieving 10545.9 kg/h. Relief loads for this scenario are given below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), Kg/Hr
Relief Scenario V-1010 Train-1, 1st Stage Separator PCV-1011 5168.7 1
st
Stage Separator fuel gas PCVs
V-1110 Train-1, 2nd Stage Separator PCV-1110 10545.9 Total Flaring V-1020 Train-2, 1st Stage Separator PCV-1021 5168.7 1
st Stage Separator fuel gas
PCVs V-1120 Train-2, 2nd Stage Separator PCV-1120 10545.9 Total Flaring AQ-6020 Fuel Gas Package PSV-6000
A/B 63000 Control Valve Failure
Total LP Flare Load 94429.3
4.10 Scenario 10
Scenario 10 is considering normal train operation with tube rupture occurring in the chiller exchanger in the Power Plant Fuel Gas Conditioning Package. Relief loads for this scenario are given below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario
V-1010 Train-1, 1st Stage Separator PCV-1011 30893 Total Flaring less half of 11551 kg/h
V-1110 Train-1, 2nd Stage Separator PCV-1110 10545.9 Total Flaring
V-1020 Train-2, 1st Stage Separator PCV-1021 30893 Total Flaring less half of 11551 kg/h
V-1120 Train-2, 2nd Stage Separator PCV-1120 10545.9 Total Flaring AQ-7501 Power Plant Fuel Gas
Conditioning Package PSV-6027/28 8381 Tube Rupture Purge Gas Flow 240
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 17 of 18 Document1
4.11 Scenario 11
Scenario 11 is considering normal train operation with the PWT Package fuel gas padding valve failing open. Relief loads for this scenario are given below.
Source Name PCV / BDV /
Relief Valve
Mass Relief Rate (Gas), kg/h
Relief Scenario
V-1010 Train-1, 1st Stage Separator PCV-1011 30893 Total Flaring less half of 11551 kg/h
V-1110 Train-1, 2nd Stage Separator PCV-1110 10545.9 Total Flaring
V-1020 Train-2, 1st Stage Separator PSV-1010 A 30893 Total Flaring less half of 11551 kg/h V-1120 Train-2, 2nd Stage Separator BDV-1120 10545.9 Total Flaring
AQ-4210 PW Treatment Package
PSV-4210/11 or
PSV-4220/21 650 Control Valve Failure
Purge Gas Flow 240
Total LP Flare Load 83768.3
5
R
ELIEF
L
OAD
I
N
V
ARIOUS
S
CENARIOS
LP flare relief load for various scenarios is tabulated below
Scenarios Relief Load , kg/h Relief Load, MMscfd
Scenario 1
94429.3
71.87
Scenario 221391.1
15.07
Scenario 391459.7
70.04
Scenario 491459.7
70.04
Scenario 555228.1
34.79
Scenario 655228.1
34.79
Scenario 782478.7
62.97
Scenario 882478.7
62.97
Scenario 994429.3
71.87
Scenario 1091498.8
69.64
Scenario 1183768.3
63.02
FIRST COMMERCIAL PRODUCTION FACILITY GARRAF FIELD DEVELOPMENT PROJECT Document No.: Revision: Page: P10-1033-P-CA-0191 E0 18 of 18 Document1
6
B
ASIS
F
OR
A
SPEN
F
LARE
S
YSTEM
A
NALYZER
S
TUDY
1. Calculation is carried out in the Rating Mode. 2. Pipe roughness used is 0.050 mm.
3. Calculation options assumed are as follows: VLE Method = Peng Robinson;
Enthalpy Method = Lee Kessler;
Pressure Drop Method = Beggs and Brill (Homogenous) Friction Factor Method = Chen
7
LP
F
LARE
D
ESIGN
C
RITERIA
7.1 Header and Tailpipe
Pipe Work Parameter Criteria Reference
Main Header / Sub header Mach No. <0.6 Process Design Philosophy, P10-1033-P-RE-0003
7.2 Noise Limitations
A. For emergency conditions the noise level not to exceed 115 dB(A). B. For normal operation noise levels not to exceed 85 dB(A).
8
R
ECOMMENDATIONS
The Power Plant Fuel Gas Conditioning Package (AQ-7501) PSV`s are currently conventional types. From the Flarenet simulations it is recommended to select balance bellow PSV`s to handle higher back pressures. It is also recommended for Petronas to revise the Flarenet model with final PSV relief loads and back pressures once the Power Plant Fuel Gas Conditioning Package vendor has finalized the design.