• No results found

COMMODITIZING THE DATA CENTER MARKET

N/A
N/A
Protected

Academic year: 2021

Share "COMMODITIZING THE DATA CENTER MARKET"

Copied!
8
0
0

Loading.... (view fulltext now)

Full text

(1)

CENTRALCOLO LLC COPYRIGHT 2014

“COMMODITIZING THE DATA CENTER MARKET”

Site Summary

The building at 1360 Kifer Road has approximately 94,500 SF of server and support space and is currently divided into two independent data center areas. Data Center Area A consists of about 48,500 SF of 24 inch raised floor space and Area B, consists of about 26,000 SF of raised floor space and a total of 39,327 rentable square feet. The building is an integrated and redundant Tier III data center and has approximately 6.5 MW of available IT load with an N+1 architecture.

(2)

CENTRALCOLO LLC COPYRIGHT 2014 EXISTING EQUIPMENT

PHASE 1 SITE “B” ELECTRICAL ( south area only )

3- 3,000 amp Switchboards branch panels / PDU

diesel generators -- 4- 2mw gens for area B (Caterpillars) fuel tanks -- 2 - 4,000 gallon tanks plus 4 – 500 gallon belly tanks

automatic transfer switch ATS Bus system

load bank ( Avron system ) exercises generators freestanding switch ( allows for rollup generator )

6 - 750kva UPS units

UPS matching battery cabinets – 5 strings per UPS (VRLA batteries) DC plant for telco related power for north use

all power and electrical distribution under raised floor

Fire Suppression system ( manual pulls with heat/smoke detectors throughout) Vesda early warning detection system throughout facility

security system ( keypad access & surviellance cameras )

MECHANICAL ( south area only )

main floor HVAC cooling delivered by thirty four 35 ton units CRAH units - 1,190 tons raised floor cooling 24"

chiller plant -- (4) 353 ton air cooled chillers

water pumps (4) 20hp pumps and (8) 30hp secondary pumps Electrical room cooling (2) 5-ton units and (1) 10-ton unit

UPS room cooling (2) 35-ton units Monitoring of all systems through NOC

TECHNOLOGY

MDF ( aggregation point for all fiber connectivity ) two separate paths into 1360 MDF crossconnects extend out to cage-cabinet-room customers

OSP delivers fiber from 1380 through conduits and fiber vaults fiber conduits between 1380 and 1360

(3)
(4)
(5)

CENTRALCOLO LLC COPYRIGHT 2014

Geographic Description

The interior of the facility consists of two independent data centers (A and B) along with additional shared infrastructure including MDF, shipping and receiving and storage. The office and lounge area are located in area B and consists of private offices, conference rooms, kitchen area and network operations center (“NOC”). There is ample parking for customers and deliveries. The shipping and receiving areas provide for delivery, storage, staging, and direct access to raised floor areas.

Property Due Diligence:

The site has been fully operational and maintained to high standards by Level 3 Communications since its commissioning back in 2002. The CentralColo team has consulted mechanical, electrical and technology infrastructure consultants who are familiar with the site and, in many cases, have been involved in maintaining the existing equipment. In general, the equipment was found to be well maintained and in good condition. The facility has two independent mechanical and electrical systems, which allow this facility to be demised into two separate data center areas. The exception is the existing technology fiber infrastructure. Although it does have diverse points of entry into the building it is currently routed through carrier gear located in 1380 Kifer Rd. and lands on a central MDF in 1360 Kifer Road.

List of Fiber Providers available includes; 1. Level 3 2. CenturyLink 3. ATT 4. Verizon 5. Zayo 6. Cogent 7. Time Warner 8. Silicon Valley Power 9. Comcast

(6)

CENTRALCOLO LLC COPYRIGHT 2014 The following is a detailed description of the key infrastructure systems for data center Area B:

Electrical Power System

Electrical power for the data center is provided by Pacific Gas & Electric Company via two 12.47KV feeders. The power is distributed through an IEM substation on the end of the building. The electrical distribution system inside the building is completely separated between Area A (north) and Area B (south). Area B is fed by three 2500 KVA transformers feeding three main 3000 amp switchboards that are paralleled in a 2N distribution system. The 2N system means that every electrical piece of gear, from transformers down to branch panels, has a matching fully redundant piece of gear. This “parallel redundant” electrical distribution system qualifies as a Tier 3 level system which is very reliable.

Connectivity Building is currently designed with a centralized Main Distribution Frame (MDF) area located near the center of the building. This MDF area is used as the aggregation point for all fiber connectivity. The building is served by multiple fiber feeders distributed in two separate pathways, both originating from building 1380. This fiber infrastructure delivers all Telco Services being used by tenants in this facility. From the MDF, cross connects are then extended to customer cage areas for their individual use.

Service Providers have the option to deliver services directly to building 1360 through a dedicated Outside Plant (OSP) conduit infrastructure providing direct pathways from the street vaults/manholes to 1360 directly.

Cooling Facility area “B” has over 1,190 tons of cooling delivered by thirty four (34) 35-ton, down-flow, chilled water CRAH units installed on the 24” high raised floor, which also recirculate air through the open space by supplying cold air to below the raised floor and returning warm air via openings at the top of the units. Cold air is supplied to server cabinets through perforated floor tiles located at the front of the cabinets. The chiller plant that provides chilled water to the CRAH units consists of four (4) 353-ton air-cooled chillers that supply water into a single, common header.

UPS System Area B operates six 750KVA-rated UPS units with matching 5-string battery cabinets consisting of 32 batteries per string for a total of 960 batteries. The units are secured in two separate rooms located in the southeast corner of the building.

Generators Area B has four (4) 2MW 2500KVA standby Caterpillar diesel generators. The generators have belly tanks sized for 500 gallons of diesel fuel each. In addition, there are two above ground remote tanks holding 4,000 gallons of fuel. The generators are paralleled to a single emergency bus which in turn is connected

(7)

CENTRALCOLO LLC COPYRIGHT 2014 to the switchboards via ATS’s. In the event of a generator failure the load will

automatically be shifted to the remaining generators.

Fire Protection The fire alarm system is a Firelite system. There is also a Vesda early warning smoke detection system throughout the facility.

Structural All power and communications are distributed under the raised floor, which doubles as an air plenum. The lighting system provides adequate illumination and is generally provided by two lamp fluorescent fixtures in both areas.

Electrical System Detail

Component Capacity Quantity Installed Capacity

Redundancy Usable Capacity

Transformers 2,500 kVA 3 7,500 kVA 2,500 kVA 5,000 kVA Generators 2,500 kVA 4 10,000 kVA 2,500 kVA 7,500 kVA

UPS 750 kVA 6 4,500 kVA 0 4,500 kVA

PDUs 200 kVA 12 2,400 kVA 0 2,400 kVA(1)

(2,160 kW) (1) PDU distribution is limiting factor for usable capacity.

(8)

CENTRALCOLO LLC COPYRIGHT 2014

CentralColo is at the epicenter of Silicon Valley’s Data Center activity

1360 K ife r Road 138 0 Ki fe r R oa d Le ve l 3 T el x SC L2 Sa nt a C la ra Que st S un ny va le 2 2403 W al sh S tr ee t D ig ita l R ea lty SVC OL O Sa nt a C la ra vXc hn ge Sa nt a C la ra 800 C en tr al E xpr es swa y D ig ita l R ea lty 3011 La fa ye tte S tr ee t D ig ita l R ea lty T el x SC L1 Sa nt a C la ra T at a C om m uni ca tio ns Sa nt a C la ra 1550 Spa ce P ar k D ig ita l R ea lty 3105 Al fr ed R oa d So ftL ay er 3080 R ay m on d St La ye r 42 3705 R ay m on d St Sy po te c 3115 Al fr ed R oa d D ig ita l R ea lty

References

Related documents

a) Free Cooling Project at Central Heating and Cooling Plant #1 – The Water Side Economizer provided over 3,912,254 ton-hours of free cooling this fiscal year, an estimated

Which pillar of education is being strengthened by a teacher who provides learning opportunities for his/her students to develop their social skills and capacities to work with

was “Does a seated position characterized by the con- ventions of functional seating increase the frequency of  accurate selection and speed of accurate target selection on a

 Data center clients that require larger chilled water distribution are able to connect to the main and distribute chilled water as necessary to accommodate their cooling demand..

SECURITY APPLICATION SERVICES Existing databases AUTHORIZED USERS Entirely searchable & scalable NTSS database SECURITY AUDITING AND MONITORING DATA.. CLUSTERPOINT NTS

171 tons (N+1) cooling data center 675kW (IT loads) data center 9 tons (N) cooling electrical room 11 tons (N+1) cooling cross-connect room 40kW (IT Loads) cross-connect room

■ The overall HVAC system will be, for example, a raised floor design, in-line cooling approaches, common or individual rack chimneys, dedicated cooling units for racks, ceiling

The engineering simulation allows you to model any type of data center configuration whether it’s raised floor, slab, overhead cooling, in-row cooling, etc.. Modern free-cooling