A Specific Effort Estimation Method Using Function Point

BINGCHIANG JENG1,*, DOWMING YEH2, DERON WANG3, SHU-LAN CHU2 AND CHIA-MEI CHEN1

1

Department of Information Management National Sun Yat-sen University

Kaohsiung, 804 Taiwan

2

Department of Software Engineering National Kaohsiung Normal University

Kaohsiung, 802 Taiwan

3

Department of Information System China Steel Corporation

Kaohsiung, 812 Taiwan

Software estimation provides an important tool for project planning; whose quality and accuracy greatly affect the success of a project. Despite a plethora of estimation models, practitioners experience difficulties in applying them because most models attempt to in-clude as many influential factors as possible in estimating software size and/or effort. This research suggests a different approach that simplifies and tailors a generic function point analysis model to increase ease of use. The proposed approach redefines the function type categories in the FPA model, on the basis of the target application’s characteristics and system architecture. This method makes the function types more suitable for the particular application domain. It also enables function point counting by the programmers themselves instead of by an expert. An empirical study using historical data establishes the regression model and demonstrates that its prediction accuracy is comparable to that of a FPA model.

Keywords: effort estimation, function point analysis, empirical model, project management, size measurement

1. INTRODUCTION

Size and effort of a software system are two different but correlated terms; size meas-ures how large the system is while effort specifies how much endeavor requires to create it. Given a same size task, the effort required from different teams may vary a lot because their productivities are different. Thus, it is the effort that provides more useful reference for project cost estimation, schedule planning, and so on [1, 2]. However, effort estimation in practice usually rely on human domain experts, who offer estimations based on their experiences with similar projects in past, and estimation quality thus depends on personal experiences and subjective judgments, which tend to result in unstable or even poor esti-mation accuracy.

Algorithmic estimation models address this problem by trying to capture the influence factors to estimate software size and/or effort using predefined equations [3-7]. Yet practi-tioners experience difficulties with these models due to hidden factors such as team’s pro-ductivity that affect development effort differently but are not fully reflected in the mod-els [8-11]. In addition, most existing modmod-els are complicated and difficult to implement, Received November 9, 2009; revised March 12, 2010; accepted June 10, 2010.

(2)

which further hinders their acceptance among practitioners [12, 13].

Given this situation, a more sophisticated model to cover ever more factors seems in-appropriate since existing ones already take effort to implement [12, 13]. Besides, some factors are inherent to a domain and may not be easy to generalize. An alternative approach might be necessary to face with these problems.

This paper presents a new type of estimation approach that is created solely for a specific organization, using its historical project data and some metrics pertaining to the application type and system architecture. It inherits the spirit from function point analysis (FPA) [3, 4, 15] but is much simplified. FPA analysis process usually relies on experts who judge and estimate the various aspects of a software system [13], which makes it dif-ficult for a common project team to adopt. In addition, the new approach generates esti-mated effort only, without the intermediate step of size estimation, which further simplifies the process.

The remainder of this article is organized as follows: Section 2 briefly introduces the related methods of size and effort estimations and FPA. The new model and a redefinition of function points appear in section 3. A regression process establishes the model in sec-tion 4, and then an empirical study applies the created model to a real example and com-pares its result with FPA in section 5. The final section concludes with some implications and further research directions.

2. RELATED ESTIMATION METHODS

2.1 Estimation Methods

Effort (and size) estimations are critical to the success of a software project [16]. Of the different techniques presented in prior literature [6-9, 17], the most popular include algorithmic and parametric models, expert judgment, and reasoning by analogy [18]. Ac-cording to Heemstra’s survey, 29 different software-based cost models have been pro-posed since 1966 [6].

Most effort estimation models rely on empirical derivation, using regression analy-sis of a collection of historical project data. These models usually take a software size as input to estimate its development effort, where the size measurement can be either lines of code (LOC) or function points. The LOC-based models are mostly nonlinear, and their estimated effort is at least quadratic to the size. Other models based on function points are not; the effort relates linearly to the function points, e.g., the one proposed by Albrecht and Gaffney [4]. A possible explanation to this is that the generation process of counting function points already involves nonlinear computation.

Machine learning models for size and/or effort estimation are rather more recent; they include case-based reasoning [20], fuzzy logic [21], neural network [22], and many others [23]. Most such approaches report results that are comparable to those of other techniques [9]. However, because the data needed by these models usually are not available at the start of a software project, most can be applied only during the later stages of the software development process.

(3)

2.2 Function Point Analysis

FPA denotes a family of algorithmic methods for size estimation. This method sepa-rately evaluates two classes of the attributes of a software system: size factors and influ-ence factors. The first version of FPA, invented by Albrecht at IBM in 1979 [3], proposed a new metric (i.e., function point) for software size rather than lines of code. The Interna-tional Function Point User Group (IFPUG) adopted a revised method [4], defining a func-tion point as a means to “measure software size by quantifying the funcfunc-tionality provided to the user based solely on logical designs and functionality specifications” [24]. Because the functionality of a software system, from the user’s perspective, usually emerges early in a project, FPA offers the unique advantage of being applicable during the early stage, when other approaches to size measurement are not appropriate.

A FPA model classifies the functions of a software system into five types: external inputs (EI), which refer to the unique user data or control inputs that add to or change the data; external outputs (EO), which are the unique user data or control outputs that fall out-side the boundaries of the system; external inquiries (EQ), which are the unique input that generates immediate output; internal logical files (ILF), which are internally maintained, logical groups of data; and external interface files (EIF) that are passed or shared among applications. Furthermore, IFPUG groups these functions into either data functions (ILFs and EIFs) or transactional functions (EIs, EOs, and EQs). Each category consists of dif-ferent function elements. For example, the data function category consists of data element type (DET), which refers to a user-recognizable field from a business perspective that par-ticipates in a transaction or is stored on a logical data file, and record element type (RET), which refers to a user-recognizable subgroup of data elements within ILF or EIF only.

The suggested steps for FPA, according to the IFPUG, are as follows: (1) identify the function elements in each prescribed function; (2) assign each function a ranking level of simple, medium, or complex according to the number of function elements found; (3) cal-culate an initial function point count; (4) determine the total degree of influence exerted on the general system characteristics; and (5) calculate the final function points on the basis of the initial point count and the influence adjustment factor.

Although the description of the first step is simple, it takes effort to identify and count the function elements (i.e., DET, RET, and so on) that occur in each of the five categories. Based on the findings, a user function is then ranked with simple, medium, or complex ac-cording to the complexity ranking table defined for each category. This rank equates with a numeric value in the complexity weighting factor table, ranging from 3 to 15. These nu-meric values sum together to generate the initial count of unadjusted function points, as described in the third step of the process.

Because FPA is designed to apply across different organizations, the next step con-siders fourteen environmental factors and their influences. Depending on the degree of influence, each characteristic receives a value from 0 to 5. The summation of the fourteen factors’ values, multiplied by 0.01 and then added to a constant of 0.65, generates the value adjustment factor (VAF). The previous unadjusted function point count multiplied by this VAF equals the final count.

Various other FPA models exist as well. Since the first revision of FPA in 1984, varia-tions and extensions have altered the original model. For example, Symons introduced Mark II Function Point in 1991 [11], and Abran et al. considered Full Function Point in

(4)

1997 [25]. Other related models include COSMIC, Object Point Analysis, and Feature Point Model [26]; the IFPUG’s version 4.2.1 is the most recent.

Although FPA is well known, it is difficult to adopt in modern software environments, which has been the impetus for various extensions [11]. The coefficients in the complexity weighting factor table also must be justified before implementation, as noted by Kitchen-ham [14]. The determination of the influence adjustment factor is another problem; em-pirical studies show that each estimator demands different considerations regarding the influence factor of the general system characteristics, and the final function points may vary by as much as 30% within an organization and even more across organizations when they are based on different estimators [10, 15].

In a specific application domain, with historical project data available, a simpler ap-proach might avoid or at least alleviate these problems. In particular, the FPA model might be made to be specific to the domain, which could mitigate existing concerns, as well as the variance of subjective judgments regarding the influence adjustment factor.

3. TAILORED FUNCTION POINT ANALYSIS

The proposed approach consists of three steps. First, it reduces the gap between the classification of function types in FPA and the classification contained in a real applica-tion. The five basic function types and function elements from FPA usually cannot match well the functional complexity of a modern application. In addition, counting the function elements requires some expertise. Therefore, the first step redefines the basic function types with respect to the application domain and upgrades the classification to a higher level of meaningful indicators.

Second, general system characteristics get incorporated into the function points to reduce possible subjective bias. Our goal here is not to develop a generic model, as FPA does, so there is no need to separate the consideration of function complexity into two parts. Both Kemerer [23] and Low and Jeffery [27] show that size predictions based on raw function points are just as accurate as predictions based on adjusted function points, and Kitchenham [14] supports the abandonment of adjustments. This second step therefore does nothing but set the value of the influence adjustment factor equal to 1.

Third, it requires a readjustment of the complexity weighting factor table in FPA ac-cording to the system characteristics of different applications. Because the first step has modified the basic function types, which requires updating the weighting table, the third step consists of a regression process that recreates the complexity weighting factor table and determines its coefficients on the basis of historical data.

3.1 Function Type Reclassification

Although the five function types in FPA are useful in size estimation, within a spe-cific application domain and developer team, other factors may better reflect the complex-ity and effort of the task. The application domain entails an information department in a large steel company whose information systems mainly feature mainframe computers run-ning the third-generation language COBOL. This case provides an effective experimental target for two reasons. First, the department keeps good records of its historical project

(5)

data, and second, it experiences a low turnover rate among software engineers, which helps reduce the effect of the human factor in evaluating the accuracy of the estimation model. In the formalized software development process, most software engineers per-form their work according to the schedule assigned by the project.

Our study case is a set of On Line Transaction Processing (OLTP) applications run-ning in this company, and interviews with their senior engineers reveal six influential factors that affect their daily programming jobs, namely,

1. Intercommunication parameter sets: As a common feature of the company’s OLTP pro-grams, many programs call one another to complete a specific task. These programs usually exchange complicated parameters during their communication. Thus, it is a complexity indicator reflecting the complexity of the task that a program performs. 2. Connected subsystems: Depending on its business purpose, a program might be

con-nected to the sales management, production management, logistic and data warehouse, equipment management, administration, and/or financial management systems. The more subsystems involved, the greater is the functional complexity. At the least, engi-neers need more time to study the connected systems and their internal data elements. 3. Updated files: As a good standard practice, business application programs keep logs of

inserted, deleted, or modified data for failure recovery purposes or auditing trails. These logs provide good indicators of the workload and complexity of a program.

4. User departments involved: A special characteristic of the systems in this study is that most of the applications have similar user interfaces. The more user departments are involved, the more complicated a user interface is. In addition, more user departments imply more complicated function requirements.

5. Utility programs: Utilities are programs that implement code tables, data checking and validation, or certain business rules. The more utilities are invoked, the greater pro-gram’s execution of the data transformation functions.

6. Subroutines (or subprograms): Similar to a utility program, a subroutine performs vari-ous jobs. Again, the more subroutines a program calls, the more complicated it is.

Table 1 summarizes the new function categories compared to the original ones. As the table reveals, the spirit of the new function categories follows the FPA’s original classi-fication, except that the levels of emphasis differ. In addition, the proposed categories are more natural and easier for project team members to use, because they refer to familiar topics.

Table 1. Comparison between basic function types and proposed classification.

Categories Equivalent to FPA Inter-communication parameter sets Internal logical files, external interface files

Connected subsystems Data communications, distributed functions, complex processing, multiple sites. Updated files Internal logical files

User departments External inputs, external outputs, external inquiries Utility programs External interface files

(6)

An example illustrates the point: According to the FPA’s rules, one cannot update an external file directly but instead must assume an (virtual) external interface with another program that can handle the processing between the application program and the file. The proposed function category is more direct and does not suffer from such a problem. In ad-dition, counting function elements is much easier. Because the new function types are al-ready the most basic elements that provide meaning, there is no need to divide them further to identify the function elements.

These factors reflect the specific characteristics for effort estimation under this study. To derive factors for other domain, one may follow a similar procedure. Namely, collect possible factors from senior engineers, consolidates them to preferably no more than seven factors. Too many factors would complicate the estimation model. It is best to compare these factors with the original function point classification to note for possible biases or even pretermission of important aspects.

3.2 Creating the Complexity Weighting Factor Table

In FPA, the complexity weighting factor table helps generate the function points of each individual function. Redefining the basic function types according to the application domain requires rebuilding the table and determining its coefficients, using a regression analysis of the historical data. Start with the equation for function point computing:

1 , n i i FP UFP VAF = =

where n is the number of function types, and UFPi is the unadjusted function points for

the ith function type. In line with the preceding discussion, VAF equals 1 and thus may be ignored hereafter. The total function point is the sum of function points in each classified function type. Assume Xi denotes the function points for the ith function type in a program,

W is the ratio of person-day per function point, and C is the physical person-days of a programming task. The rewritten equation becomes:

1 . n i i X W C = ⋅ =

(1)

The calculation of Xi requires a complexity weighting factor table similar to that of

FPA and multiply the number of functions, Ni, by the corresponding weight in that

cate-gory, i.e., Xi = NiWi.If treating the weights for the low, medium, and high complexity

lev-els of a function type as independent, 3n variables must be determined. In contrast, in the current FPA, the weight factors for the low, medium, and high complexity levels roughly follow the ratio of 3:4:6. So the proposed model introduces another variable πi and rewrites

Xi = (N1iA1i + N2iA2i + N3iA3ii, where Aji denotes the ratio for different complexity levels,

assigned constant value of 3, 4, or 6, and πi is the factor to be determined by the relative

weight over the different function types. When πiW = Wi, the equation simplifies to: 3 1 1 ( ) . n j j i i i i j N A W C = = × =

∑ ∑

(2)

(7)

This equation is ready for regression. Substitution the historical data into it will determine the best values for Wi. Assume the initial solution be represented by Wi′, in which case the

equation becomes 3 1 1 ( ) . n j j i i i i j N A W C e = = ′ × = +

∑ ∑

(3)

The next step minimizes the summation of the squared errors for m number of training data to find Wi′: 2 1 . m j j s e = =

(4)

The converging criterion restricts the difference between the largest and smallest Wi

to less than 5% (which can be adjusted). Alternatively, the smallest Wi′ can divide all Ai

Wi′ and reveal a new set of Ai, which, when substituted into Eq. (3), generates a new set of

Wi′. The iteration process terminates when the criterion is satisfied.

4. REGRESSION MODELS

The software team under study develops new functions for existing systems in re-sponse to daily requests from other departments in the company. To simplify the data analysis, this investigation applies effort estimation to the last two phases of software de-velopment, namely, implementation and testing, when the function requirements and over-all design of programs are already known so that counting function points is easier and more certain. The analysis can be extended to the whole life cycle, if necessary, in that the effort expended during these two phases exhibits roughly a constant ratio with total de-velopment effort, with minor variance.

Table 2. Test data profiles.

System Number of Programs Total Lines of Code Effort (person-day)

A 6 10230 32

B 21 23318 126

C 20 30548 95

D 20 13458 122

E 5 3330 23

The regression analysis includes program data from five historical projects, as Table 2 shows. For each system, the programs are sorted according to their complexity in each classified function category. A program earns a low complexity rank in a function category if its complexity falls below 30% on the spectrum, a medium rank if it appears greater than 30% but less than 70%, and a high rank otherwise.

During the regression process, sensitivity analysis reveals the strength of different factors that contribute to development effort; factors with smaller values disappear from

(8)

Table 3. Sensitivity analyses of function categories. Complexity Weights Intercommunication Parameter Sets Connected Subsystems User Departments Called Subroutines Connected Utility Programs Updated Files (3, 4, 5) 0.2667 0.6260 0.1705 0.0148 0.4187 0.1418 (3, 4, 6) 0.2969 0.5298 0.1904 − 0.0074 0.3860 0.1627 (7, 10, 15) 0.3128 0.5401 0.2054 − 0.0109 0.1410 0.1660

Table 4. Convergences of weight control factors.

Model 1 Model 2 Model 3 Model 4 Model 5

Category Wi Ai Wi Ai Wi Ai Wi Ai Wi Ai Inter-communication parameter sets 0.167 6/8/12 0.1506 14/18/27 0.166 3/4/6 0.0123 5/6/10 0.1612 5/6/10 Connected subsystems 0.1924 10/13/19 0.1613 5/7/11 0.1595 10/13/20 0.0112 127/170/255 0.1529 11/15/22 User departments 0.1472 5/7/11 0.1604 4/6/9 0.1326 6/7/11 0.0116 12/16/24 0.1416 3/4/6 Connected utility programs 0.1746 4/5/8 0.1405 4/5/8 0.1579 7/9/14 0.0113 178/238/357 0.1669 7/9/13 Updated files 0.1762 3/4/6 0.1393 4/5/8 0.1675 5/6/9 0.0113 63/84/125 0.1589 4/6/9

the function category. The test indicates that the “called subroutines” function category attained too much emphasis, in that its related value is far less than that of others, as Table 3 displays. This category therefore joins the similar category of “connected utility pro-grams.”

An iteration of the regression analysis process determines the best values for Withat

lead to the total error summation in Eq. (4) within the threshold value, 5%. The initial val-ues of Aiare 3, 4, and 6, respectively. If the error summation after the regression fails to

reach the threshold value, the values of Ai require adjustment, by multiplying

correspond-ing Wi, dividing by the minimum value of Wi, and iterating the regression analysis.

The evaluation of the generated regression models employs a five-fold cross-vali-dation process; in each run of the process, data from four out of the five projects serve to train the model, and then data from the remaining project test it. The five repetitions of this process produce the results in Table 4.

One of the basic assumptions of multiple regression analysis is that the error eiof

in-dependent variables should not be related. The Durbin-Watson (DW) test can examine this assumption. The DW values in all five runs are close to 2. This result implies there are no significant relations in the model and that its predictions are reliable. Another test to ex-amine the validity of the overall regression model is the analysis of variance (ANOVA). The test results demonstrate that all p-values are less than 0.05, in support of the linear relationship in the proposed model.

5. EXPERIMENTAL RESULTS AND MODEL EVALUATION This section describes the physical test of the effectiveness of the proposed new mod-els and compares their estimation accuracies with those obtained by standard FPA. For easy comparisons, all the results are shown in the commonly used measure of the mean value of the magnitude of relative error (MMRE) [9, 16, 22]. The magnitude of relative

(9)

error (MRE) is a normalized measure of the variance between actual values (VA) and pre-dicted values (VF): | | . A F A V V MRE V − =

5.1 Estimation Accuracy of the Tailored Models

The tests of the five regression models established in the previous section return the average estimation accuracies in Table 5. The mean error of the new estimation method based on the five-fold test is 25.91% in MMRE, with 13.37% variance − not very good but comparable to other known studies [19, 22].

Table 5. New models’ effort estimation (by application systems).

Reference Projects Tested Project MRE

A, B, C, D E 49.55% A, B, C, E D 21.52% A, B, D, E C 18.75% A, C,D, E B 17.36% B, C, D, E A 22.39% MMRE 25.91% Standard deviation 13.37%

Table 6. New models’ effort Estimation (by random partition).

Reference Groups Tested group MRE

V, W, X,Y Z 13.06% V, W, X, Z Y 17.67% V, W,Y, Z X 25.00% V, X, Y, Z W 15.86% W, X, Y, Z V 9.12% MMRE 16.14% Standard deviation 5.91%

Yet the experiment is not perfect. Model quality depends on the regression analysis of historical project data, and these models are not trained with a sufficient number of pro-jects. If different projects vary greatly in their characteristics, the proposed model is less reliable, as indicated by the large standard deviation in MRE. Another experiment there-fore trained the models using the program, rather than the system, units. This experiment breaks down the application systems’ boundaries and randomly assigns each program from the five projects into five groups so that the application characteristics from the five sys-tems distribute evenly into these groups. After a random partitioning, the five groups con-tained 14, 16, 17, 13, and 12 programs.

The same process applied to these groups creates five new models. Estimation accu-racies in this test are better (see Table 6). These experimental outcomes appear closer to

(10)

the real evaluation of the new approach, because the models derive from more random data items, and the standard deviation of MRE declines greatly.

5.2 Comparison with Standard FPA

Another way to evaluate the new approach is to compare the estimation results with those from standard FPA. Table 7 shows the function points and person-days per function point for each of the five applications using the standard FPA method.

Table 7. Function points and person-days conversion.

Application A B C D E

Adjusted function points 111 400 389 368 78

Actual person-days 32 126 95 122 23

Person-days per function point 0.2883 0.3150 0.2442 0.3315 0.2949

Table 8. FPA’s effort estimation (by application systems).

Reference projects Average MD/FP Tested Project MRE

A, B, C, D 0.2957 E 0.28% A, B, C, E 0.2822 D 14.88% A, B, D, E 0.3166 C 29.64% A, C,D, E 0.2875 B 8.73% B, C, D, E 0.2964 A 2.84% MMRE 11.28% Standard deviation 11.72%

A similar experimental process uses four of the five projects as the historical data to compute an average number of person-days per function point, which then serves as an estimation of the effort for the last project. For example, the average person-days per func-tion point from projects A, B, C, and D is (32 + 126 + 95 + 122)/(111 + 400 + 389 + 368) = 0.2957. This value, multiplied by 78, is the estimated effort for project E, which equals 23.0646. Compared with the actual value for person-day 23, the estimation accuracy is 0.28% in MMRE.

Table 8 shows the estimation results of this experiment. The surprisingly high estima-tion accuracies of some models indicate that the standard FPA has physical support, which likely explains its persistent popularity. The only shortcoming is its stability, which varies up to 29% in terms of accuracy from the best to the worst.

The large variation indicates that the intrinsic characteristics of these applications vary greatly across different projects in the experiment. Thus another experiment, similar to the second one in the last subsection, follows, and its estimation outcomes appear in Table 9. The statistics in this table, however, are not as reliable as those in Table 9, be-cause the standard deviation of MRE increases. That is, FPA prefers to estimate using a whole project’s data rather than randomized data. This experiment does not represent the usual way in using FPA, because the VAF factors in the final process to adjust function points are designed to evaluate a whole system, not programs.

(11)

Table 9. FPA’s effort estimation (by random partition).

Reference Groups Average MD/FP Tested Group MRE

V, W, X,Y 0.2074 Z 9.80% V, W, X, Z 0.199 Y 26.31% V, W,Y, Z 0.232 X 44.33% V, X, Y, Z 0.2103 W 3.73% W, X, Y, Z 0.2125 V 2.13% MMRE 17.26% Standard deviation 17.90%

6. DISCUSSION AND CONCLUSION

Although effort estimation is a critical step for the success of a software project, in practice, many projects still use ad hoc methods to conduct this task. This phenomenon may result because most of the generic algorithmic estimation models are difficult to be adopted, in that they require the collection of many detailed items that may affect the size (and effort) associated with an application. This research presents a different approach that trades “generic” with “specific” and greatly simplifies the estimation model to enable com-mon programmers to use it.

Although the new approach may not be as formal as a normal estimation model, it does reduce the difficulties of using it by giving programmers a method to build their own model, which captures more of a given application domain’s characteristics and is easier to use. The demonstration of this approach offers an unique benefit in that it makes the func-tion classificafunc-tion more suitable for a particular applicafunc-tion domain so that funcfunc-tion point counting can be conducted by programmers themselves instead of by a certified FPA ex-pert.

We believe such an approach should be applicable to domains when FPA works since it still stays with the FPA spirit. However, it may shares the limitations of FPA also. To verify its usefulness, it is no doubt that more experimental data from a wider range of ap-plication domains and environments should be collected to deepen the investigation into the trade-off between generic versus specific. At least two research directions exist. First, studies could evaluate whether the tailored FPA model always fits a business application domain and still maintains comparable estimation accuracy. Second, the ideas presented herein might be adopted to another estimation model and determine how it performs. Each direction will lead to more detailed research findings.

REFERENCES

1. K. Molokken and M. Jorgensen, “A review of software surveys on software effort es-timation,” in Proceedings of International Symposium on Empirical Software

Engi-neering, 2003, pp. 223-230.

2. J. S. Osmundson, J. B. Micheal, M. J. Machniak, and M. A. Grossman, “Quality man-agement metrics for software development,” Information and Management, Vol. 40, 2003, pp. 799-812.

(12)

3. A. J. Albrecht, “Measuring application development productivity,” in Proceedings

of IBM Applications Development Symposium, 1979, pp. 83-92.

4. A. J. Albrecht and J. E. Gaffney Jr., “Software function, source lines of code, and de-velopment effort prediction: A software science validation,” IEEE Transactions on

Software Engineering, Vol. 9, 1983, pp. 639-648.

5. B. W. Boehm, Software Cost Estimation with Cocomo II, Prentice Hall, New Jersey, 2000.

6. A. L. Lederer and J. Prasad, “A causal model for software cost estimating error,” IEEE

Transactions on Software Engineering, Vol. 24, 1998, pp. 137-148.

7. F. Walkerden and R. Jeffery, “An empirical study of analogy-based software effort estimation,” Empirical Software Engineering, Vol. 4, 1999, pp. 135-158.

8. N. E. Fenton and M. Neil, “Software metrics: success, failures and new directions,”

Journal of Systems and Software, Vol. 47, 1997, pp. 149-157.

9. A. R. Gray and S. G. MacDonell, “A comparison of techniques for developing pre-dictive models of software metrics,” Information and Software Technology, Vol. 39, 1997, pp. 425-437.

10. D. Garmus and D. Herron, Function Point Analysis: Measurement Practices for

Suc-cessful Software Projects, Addison-Wesley, Boston, MA, 2001.

11. C. R. Symons, Software Sizing and Estimating MkII FPA (Function Point Analy-sis), John Wiley and Sons, Chichester, U.K., 1991.

12. J. J. Dolado, “On the problem of the software cost function,” Information and

Soft-ware Technology, Vol. 43, 2001, pp. 61-72.

13. A. Abran and P. N. Robillard, “Function points analysis: An empirical study of its measurement processes,” IEEE Transactions on Software Engineering, Vol. 22, 1996, pp. 895-909.

14. B. Kitchenham, “The problem with function points,” IEEE Software, Vol. 14, 1997, pp. 29-31.

15. R. Jeffery and J. Stathis, “Function point sizing: Structure, validity and applicability,”

Empirical Software Engineering, Vol. 1, 1996, pp. 11-30.

16. M. Jorgensen and D. I. K. Sjoberg, “Impact of effort estimates on software project work,” Information and Software Technology, Vol. 43, 2001, pp. 939-948.

17. C. Gencel and O. Demirors, “Functional size measurement revisited,” ACM

Transac-tions on Software Engineering and Methodology, Vol. 17, 2008, pp. 1-36.

18. B. Barry, C. Abts, and S. Chulani, “Software development cost estimation approaches

− A survey,” Annals of Software Engineering, Vol. 10, 2000, pp. 177-205.

19. L. H. Putnam and W. Myers, Measures for Excellence: Reliable Software on Time,

within Budget, Yourdon Press, Englewood Cliffs, NJ, 1992.

20. R. Bisio and F. Malabocchia, “Cost estimation of software projects through case-base reasoning,” in Proceedings of Case-Based Reasoning Research and Development, 1995, pp. 11-22.

21. O. D. Lima, P. M. Farias, and A. D. Belchior “Fuzzy modeling for function points analysis,” Software Quality Journal, Vol. 11, 2003, pp. 149-166.

22. J. Hakkarainen, P. Laamamen, and R. Rask, “Neural networks in specification level software size estimation,” in P. K. Simpson, ed., Neural Network Applications, IEEE

Technology Update Series, 1993, pp. 887-895.

(13)

estimat-ing software development effort,” Information and Software Technology, Vol. 44, 2002, pp. 911-922.

24. R. Boehm, “Frequently asked questions,” http://www.ifpug.org, 2002.

25. A. Abran, M. Maya, J. M. Desharnais, and D. St-Pierre, “Adapting function points to real-time software,” American Programmer, Vol. 10, 1997, pp. 32-43.

26. C. Jones, Applied Software Measurement: Assuring Productivity and Quality, McGraw- Hill, New York, 2008.

27. G. C. Low and D. R. Jeffery, “Function points in the estimation and evaluation of the software process,” IEEE Transactions on Software Engineering, Vol. 16, 1990, pp. 64-71.

Bingchiang Jeng (鄭炳強) joined in the National Sun Yat-

Sen University as an Associate Professor in 1990 and became a full Professor in 1998. He is currently the department chair of Infor-mation Management and the graduate director of Communication Management. Hereceived B.S. in Computer Science and Informa-tion Engineering from NaInforma-tional Chiao Tung University, and Ph.D. in Computer Science from New York University. His current re-search interests include software testing, model checking, and com- puter-aided instruction in programming.

Dowming Yeh (葉道明) is a Professor in the Department of

Software Engineering at the National Kaohsiung Normal Univer-sity, Taiwan, R.O.C. He received his Ph.D. in Computer Science from the University of Utah in U.S.A. Before assuming his cur-rent post, he was an Associate Professor in the Department of Management Information System at the National Pingtung Uni-versity of Science and Technology and a manager at the Institute for Information Industry in Taiwan. His research interest includes software reengineering, e-learning, web engineering, program analy-sis, and human computer interaction. Dr. Yeh is a member of IEEE and ACM.

Deron Wang (王德榮) joined in the China Steel

Corpora-tion as a system engineer in 1978 and became a secCorpora-tion manager of Information System Department in 1989. Hereceived M.S. in In-formation Management from National Sun Yat-Sen University in 2003. His working interests include ERP consulting, downsizing migration, data center management and network security.

(14)

Shu-Lan Chu (祝淑蘭) is presently employed as an Associ-ate Technical Specialist in the Southern Regional Regulatory De-partment of National Communications Commission. Shereceived Master of Education in Information and Computer Education In-stitute, from National Kaohsiung Normal University in 2006.

Chia-Mei Chen (陳嘉玫) joined in the National Sun Yat-

Sen University as an Associate Professor in 1996 and became a full professor in 2004. In addition, she is Section Chef of Network Division, Office of Library and Information Services. Shereceived B.S. in Computer Science and Information Engineering from Na-tional Chiao Tung University, and Ph.D. in Computer Science from the University of Maryland, College Park. She serves as a coordi-nator of TWCERT/CC (Taiwan Computer Emergency Response Team/Coordination Center) since 1998 and continues working for the network security society. Her current research interests include mobile networks, multimedia systems, and network security.

References

Related documents

Discuss the steps in the buying process or merchandising cycle Identify the types of fashion retailers Discuss buying motives Explain the steps in the personal-selling process

A consequence of this perspective of woman directors being appointed as part of the symbolic management of the independence of the board is that, when these directors lose

The exclusion of sports and activities in the General Exclusions is deleted only with respect to cover under Medical and Other Expenses Section and under Curtailment Section

of wheat production in Iran: A case study from Ardabil province. Eco-efficiency analysis by BASF: The method. Life Cycle Assess. Energy flow and ecological sustainability in

• Best Entrepreneurial Social Enterprise or Charity based in Liverpool • Best Young Entrepreneur (under 25 years old).. • Best New Business Idea by a

In Religious Freedom, Human Rights, and Peaceful Coexistence, Professor Leslie Griffin emphasizes the magnitude of John Courtney Murray’s ecclesial achievement,

Further, by showing that v τ is a modular unit over Z we give a new proof of the fact that the singular values of v τ are units at all imaginary quadratic arguments and obtain

◦ Open Problems in Lattice Algorithms and Theory, Student Discrete Math Seminar, UC Davis, Davis, CA, October 2011.. ◦ New Interactions between Asymptotic Convex Geometry and