Jackson Park Elementary School Replacement
Design Development Approval Presentation
1 October 10, 2012
Jackson Park Elementary School Replacement
Project Expenditures/Revenue
Projected Expenditures
CPL Plan
Schematic
Design
Construction $19,603,377 $19,603,377 $19,603,377 Soft Costs $ 4,509,400 $ 4,954,400 $ 4,975,262 Project Reserves $ 1,261,049 $ 816,049 $ 795,187
Total Expenses $25,373,826 $25,373,826 $25,373,826
Projected Revenue
CPL Plan
Schematic
Design
Local Funds $11,997,526 $11,997,526 $11,997,526 State Funds $ 4,500,000 $ 5,400,000 $ 7,200,000 Federal Funds $ 8,876,300 $ 8,876,300 $ 8,876,300 Total Revenue $25,373,826 $26,273,826 $28,073,826 2 Presented 9/26/12
Jackson Park Elementary School Replacement
Design Development Considerations
•
Covered Play Area
Recommendation – Construct 3,400 Sq. Ft. Covered Play Area (+$370,000)•
Storm Water Retention
Recommendation – Construct Underground Stormwater Stor. (+$290,000)•
Building 106 Warehouse
Recommendation – Demolish Building 106 (+$130,000)•
Building Envelope Options
Proposed Design – Smooth‐faced CMU to 9’‐6”/Hardi‐Plank Siding Above Option – Smooth‐faced CMU to 9’‐6”/Metal Siding Above (+$270,000) Option – Smooth‐faced CMU to 9’‐6”/Brick Above (+$510,000) Option – Brick Full Height (+$590,000)•
Multi‐Purpose Room Options
Proposed Design ‐ Combined Multi‐Purpose Room/Gymnasium Option – Separate Multi‐Purpose Room and Gymnasium (+$1,135,000) 3 Presented 9/26/12Jackson Park Elementary School Replacement
SITE PLAN
4 50yd x 75yd U‐11
Soccer Field Shown
Jackson Park Elementary School Replacement SITE PLAN Recommended Option -Underground Stormwater Storage 60yd x 95yd U‐13 Soccer Field Shown 5 Presented 9/26/12
Jackson Park Elementary School Replacement
FLOOR PLANS – First Floor
6 Presented 9/26/12
Jackson Park Elementary School Replacement
FLOOR PLANS – Second Floor
7 Presented 9/26/12
Jackson Park Elementary School Replacement
Building Envelope Options
Initial Options Considered September 26, 2012 Proposed Design – Smooth‐faced CMU to 9’‐6”/Hardi‐Plank Siding Above Option – Smooth‐faced CMU to 9’‐6”/Metal Siding Above (+$270,000) Option – Smooth‐faced CMU to 9’‐6”/Brick Above (+$510,000) Option – Brick Full Height (+$590,000) Additional Options Identified since September 26, 2012 Option – Smooth‐faced CMU to 16’‐0”/Hardi‐Plank Siding Above (+$90,000) Option – Smooth‐faced CMU to 21’‐0”/Hardi‐Plank Siding Above (+$160,000) Option – Brick to 16’‐0”/Hardi‐Plank Siding Above (+$250,000) Option – Brick to 21’‐0”/Hardi‐Plank Siding Above (+$350,000) Presented 10‐10‐12 8Jackson Park Elementary School Replacement
Building Envelope Options/Life Cycle Analysis
9 Capital Fund Initial Cost Maintenance Cost at 15 Years Maintenance Cost at 60 Years Initial Investment Order Maintenance Investment Order Total Life Cycle Investment Order Evaluation Total A Proposed Design ‐ CMU 9.5'/ Hardi‐Plank Siding Above $0 $235,600 $942,400 $942,400 1 8 4 13 4 1 B CMU 9.5'/Metal Above $270,000 $161,182 $644,728 $914,728 5 3 3 11 2 8 D CMU 9.5'/Brick Above $510,000 $142,842 $571,368 $1,081,368 7 2 6 15 6 4 E Brick Full Height $590,000 $107,132 $428,528 $1,018,528 8 1 8 17 7 5 F CMU 16'/Hardi Above $90,000 $202,770 $811,080 $901,080 2 7 1 10 1 2 G CMU 21'/Hardi Above $160,000 $186,588 $746,352 $906,352 3 6 2 11 2 3 H Brick 16'/Hardi Above $250,000 $184,538 $738,152 $988,152 4 5 5 14 5 6 I Brick 21'/Hardi Above $350,000 $163,637 $654,548 $1,004,548 6 4 7 17 7 7 Architect's Aesthetic Order General Fund Ranking Options Life Cycle Cost at 60 Years Rank OrderJackson Park Elementary School Replacement
Multi‐Purpose Room Addition
•
New schools greater percentage with Multi‐Purpose Rooms
•
4 of 12 CKSD elementary schools currently have Multi‐Purpose
Rooms
•
Enhances learning activities in large schools (> 500 students)
(specifically Physical Education, Lunch and Performances)
•
Increases flexibility for Learning Spaces
•
Decreases maintenance on moveable wall
•
Decreases impact to custodian and PE staff (set up and clean
up)
•
Extends the life of chairs, table and PE equipment
Presented 10‐10‐12 10CMU 9’ 6” Option A CMU to 16’ Option F CMU 21’ Option G Brick Above CMU 9’6” Option D
Include Covered Play Area Current $ Current $ Current $ Current $
Include Underground Stormwater Storage $290,000 $290,000 $290,000 $290,000 Include Removal of Building 106 (Warehouse) $130,000 $130,000 $130,000 $130,000 Include Multi‐purpose Room $1,135,000 $1,135,000 $1,135,000 $1,135,000 Include Building Envelope Finish $0 $90,000 $160,000 $510,000 Total $1,555,000 $1,645,000 $1,715,000 $2,065,000 Additional Revenue from Tracyton $1,800,000 $1,800,000 $1,800,000 $1,800,000 Total Remaining $245,000 $155,000 $85,000 ($265,000)
Jackson Park Envelope Options and
Recommendation
11Jackson Park Elementary School Replacement
Design Development MACC/Budget Adjustments
MACC Budget Project Budget
56,000 Sq. Ft. Facility $16,631,392 $25,373,826 Add Off‐Site Work $ 560,000 $ 0 (Costs Included in CPL Levy add to A/E Contract) Subtotal 56,000 Sq. Ft. Facility $17,191,392 $25,373,826 Add 3,400 Sq. Ft. Covered Play Area $ ‐ $ ‐ (Costs Included in Design Development Submittal) Add Underground Storm Water $ 213,000 $ 290,000 Add Demolition Building $ 97,350 $ 130,000 Add Smooth‐Faced CMU to 16’‐0” $ 60,000 $ 90,000 Add 3,000 Sq. Ft. M.P. Room $ 841,000 $ 1,135,000 Revised 60,700 Sq. Ft. Facility $18,402,742 $27,018,826 (OSPI – Covered Play Area Sq. Ft./2) 12
Presented 10‐10‐12 13 JP Funded July 2013 No Cash Flow Issues JP Funded July 2014 No Cash Flow Issues JP Funded July 2015 Cash Flow Issues Building Envelope Options Includes Multipurpose Room CMU 9'5" Hardi‐Plank Above $6.1 M @ 20 months CMU 9'5" Metal Above $6.4 M @ 22 months CMU 9'5" Brick Above $6.7 M @ 24 months Brick Full Height $6.8 M @ 25 months CMU 16' Hardi‐Plank Above $6.2 M @ 20 months CMU 21' Hardi‐Plank Above $6.3 M @ 21 months Brick 16' Hardi‐Plank Above $6.4 M @ 22 months Brick 21" Hardi‐Plank Above $6.5 M @ 23 months JP Funded July 2013 No Cash Flow Issues JP Funded July 2014 No Cash Flow Issues JP Funded July 2015 Cash Flow Issues
Viable Options Cost Impact School Support Levy
Delay the Bid of JP to Spring 2014 3% of JP = $480,000 Lost Enrollment = $200,000 Off Schedule Off Budget Bid Project after SSL 2014 Seek A Line of Credit (Non‐Voted Debt) Up To $6,200,000 3% * 20 mo * $6.2 M = $310,000 Stay on Schedule Smaller Budget Increase NVD vs Cash Flow JP Under Construction Freeze Projects Scheduled for Summer 2014 Up to $6,475,321 3% of Delayed 2014 Proj= 194,260 Stay on JP Schedule Smallest $$ Increase Off Budget on Delay Proj Delay of Scheduled Projects JP Under Construction Additional Option Impact to Cash Flow for 2015 Funding Only