JOB HAZARD ANALYSIS WORKSHEET
Form 908 Version 3.2Uncontrolled When Printed Page 1 of 11
Company Name: Perkins Builders
JHA Development Team Trades Involved With Undertaking This Work Activity
Description of Work Activity: This JHA is submitted to Perkins Builders for:
Asbestos
PROJECT NAME:PROJECT No:
This JHA has been reviewed by the Perkins Builders site manager for its context, site requirements, and validated for the task/s being undertaken and considered appropriate.
Any changes to the scope of works shall be added to this document and signed off accordingly.
Perkins Builders Site Manager:
Name Signature Date
Person responsible for supervising and implementing, on the subcontractor’s behalf, the OHS controls associated with each step of this work activity.
Name Signature Date
Form 908 Version 3.2Uncontrolled When Printed Page 2 of 11
TYPE OF WORK TO BE UNDERTAKEN AND REQUIREMENTS
TYPE OF WORK PPE REQUIRMENTS
Please Tick
Please Tick
Asbestos
Isolation Practices
Barricading / Signs
Fire Blankets
Respirator
Confined Space
Mobile Plants
Coveralls
Gloves
Safety Harness
Crane / Rigging / Dogging
Scaffolding
Dust Masks
Hearing Protection
Spark Containment
Demolition
Temporary Propping
Electrical Safety
Height Safety
Specific Training Induction
Electrical
Tilt Panel / Pre cast concrete
Emergency Response
Material Safety Data Sheets
Sun / UV Protection
Excavation below 1.5m
Working at Height
Extinguishers
Monogoggles / Safety Glasses
Hot Work
Works in or around water catchments
Face Shield
Plant & Equipment Conditions Mobile Plant to be used:RISK RATING
LIKELIHOOD CONSEQUENCE 1 2 3 4 5
A Consequence is expected to occur in
most circumstances 1 Fatality or Disability.
High Cost Losses
E - Extreme H – High M – Medium L - Low
A E(1) E(2) E(4) H(7) H(11)
B Consequence will probably occur in many
circumstances 2 Lost time Injury.
Medium to high cost losses. B E(3) E(5) H(8) H(12) M(16)
C Consequence will probably occur is some
circumstances 3 Medical Treatment.
Medium to low cost losses C E(6) H(9) H(13) M(17) L(20)
D Consequence may occur in some
circumstances 4 First Aid Treatment
Minor Cost Losses. D H(10) H(19) M(18) L(21) L(23)
E Consequence may occur but only in
exceptional circumstances 5
Near-miss (near hit).
Possible minimal consequences E H(15) M(19) M(22) L(24) L(25)
JOB HAZARD ANALYSIS WORKSHEET
Form 908 Version 3.2Uncontrolled When Printed Page 3 of 11
NO.
JOB STEP
Break the job into steps or describe what work process are done
HAZARDS IDENTIFIED
What can harm you or others .g struck or hit by moving plant
INHERENT RISK
(Likelihood x Consequences)
JOB STEP CONTROL
Determine the controls to reduce risk to as low as responsibly practicable
RESIDUAL RISK
(Likelihood x Consequences)
RESPONSIBLITY
Person & Position Title to ensure controls are actioned
1.
PLANNING
➢ Inductions
➢ Register Updates
➢ Risk Assessment
➢ Workers
performing works involving asbestos not understanding Perkins hazard management practices and site- specific information
➢ Tickets and/or certifications not being checked and on file
➢ Unqualified and untrained workers performing works involving asbestos
➢ Removal
performed without WorkSafe
notification
➢ Unnecessary asbestos exposure
M(18)
➢ All workers that are to perform works on a Perkins site must at a minimum receive the site induction presentation and understand the practices and procedures that are to be followed on the work site.
➢ Safety Practice 90.02.19 to be read and understood by all personnel that are to undertake any task involving asbestos
➢ All workers that are to perform works involving asbestos are to have recent and up to date copies of all tickets and certifications relevant to asbestos removal and exposure
➢ No worker is to perform any tasks that they are not component or qualified in completing
➢ If applicable WorkSafe must be notified 10 days prior to asbestos removal
➢ A risk assessment must be completed prior to job commencement to determine if removal of asbestos is the best course of action
➢ If removal is required relevant code of practice must be on hand and referenced
M(22) Site Manager Workers
Form 908 Version 3.2Uncontrolled When Printed Page 4 of 11
➢ Licensing ➢ Untrained and incompetent personnel disposing of asbestos
(Safe Removal of Asbestos NOHSC2002:2005)
(Management and Control of Asbestos in Workplace NOHSC2018:2005)
➢ Over 10m2 of bonded (non-friable) asbestos requires an unrestricted
asbestos removal license which must be maintained and current
➢ All persons undertaking the removal of asbestos 10m2 or more must have undertaken a restricted asbestos removal training course delivered by a recognized training organization
➢ All subcontractors who perform asbestos removal or works relating must have up to date licenses and tickets on file
2.
JOB SET UP
➢ Fitness For Work
➢ Public Interaction
➢ Worker injury
➢ Worker under the influence of banned substances
➢ Asbestos exposure to public
➢ Wind conditions affecting airborne asbestos exposure
H(13)
➢ In line with Perkins Drug and Alcohol Policy all workers that are to perform any scope of works on Perkins sites shall adhere and follow the zero tolerance in relation to Drugs and Alcohol
➢ Workers must ensure where practicable that they are able to physically perform the task required
➢ Identify if any public areas have the risk of exposure and establish exclusion zones
➢ Ensure wind conditions are monitored throughout task ensuring task is ceased when conditions are detrimental
M(18) Site Manger Workers
JOB HAZARD ANALYSIS WORKSHEET
Form 908 Version 3.2Uncontrolled When Printed Page 5 of 11
➢ Surrounding Work Area Interaction
➢ Asbestos exposure to surrounding work groups
➢ Site Manager to ensure all other work groups are informed of works involving asbestos prior to job commencement
➢ Contractor overlapping where applicable to minimize work area exposure
➢ PPE worn at all times by all workers who are directly and indirectly exposed (P1 or P2 masks at a minimum)
➢ Exclusion zones and signage set up around work area
3.
CONDUCTING WORKS INVOLVING OR
REMOVAL OF ASBESTOS
➢ Method Determination
➢ In-adequate removal techniques exposing workers
E(3)
➢ Wet or Dry method determined when removing and/or handling materials containing asbestos
➢ Wet Method (Preferred) – A manually controlled, consistent low pressure, coarse spray, such as from an adjustable pistol- grip garden hose, is recommended for the purpose of wetting down work area
➢ The wetted down material involving asbestos should be removed in sections
➢ Material to be placed into waste containers and sealed to ensure correct disposal
➢ Dry Method (Least Preferred) – Dry method to only be used where wet method is not practical or safe (e.g. live electrical services or equipment present)
➢ The work area must be fully enclosed with the use of plastic sheeting
➢ All workers involved must wear a full-face mask with respirator at a minimum
➢ The material should be removed in small pre-cut sections with minimal disturbance to
M(18) Site Manager Workers
Form 908 Version 3.2Uncontrolled When Printed Page 6 of 11
➢ Monitoring ➢ Workplace exposure to asbestos not compliant
➢ Workforce exposure to asbestos not compliant
avoid generation of airborne asbestos disturbance
➢ Asbestos vacuum cleaners utilized if applicable
➢ All air clearance monitoring shall be conducted by an independent and competent person
➢ An Air Clearance Certificate must be received from the third-party representative before the removal of barriers, signs, and the re-occupation of the area can
commence
4.
DEMOBILISATION / CLEAN UP
➢ Equipment Storage
➢ Manual Handling
➢ Decontamination
➢ Equipment stored poorly causing damage
➢ Body strain or injury
➢ Poor access around work site
➢ Area contaminated with traces of exposure
H(13)
➢ All workers must ensure that all plant and equipment is correctly stored as per manufactures specifications to ensure integrity and condition
➢ Correct manual handling techniques used
➢ Accessways / pathways to remain clear of obstructions
➢ High level of housekeeping to be maintained throughout job and prior
➢ On completion of the removal work, the area immediately surrounding the removal area and the removal work area are to be vacuumed using a vacuum cleaner that
M(18) Site Manager Workers
JOB HAZARD ANALYSIS WORKSHEET
Form 908 Version 3.2Uncontrolled When Printed Page 7 of 11
➢ Clean Up and Disposal
➢ Personnel
contaminated with asbestos
➢ Asbestos
contamination left on site
➢ Asbestos disposal non-compliant
complies with the AS3544-2988 for use with asbestos
➢ All contaminated surfaces are to be wiped down with a damp cloth, paying attention to walls, ledges, fittings and furnishes if affected
➢ All personnel leaving the work area must follow and comply with decontamination procedure outlined in Perkins document 90.02.19
➢ Asbestos must be removed from site and Perkins Builders will ensure that clean-up is properly completed and that there is no contamination of asbestos left at a site
➢ All disposal of asbestos will be in
accordance with Section 9 of the Code of Practice for the Safe Removal of Asbestos 2nd edition [NOHSC: 2002(2005)
➢ Disposal can only be done after approval is given to dispose of asbestos at an
approved site and or the disposal activity is contracted to an approved licensed waste disposal contractor
Form 908 Version 3.2Uncontrolled When Printed Page 8 of 11
Read and Signed by Performers of Work on Site
Name Qualification or Training Position Signature Date
JOB HAZARD ANALYSIS WORKSHEET
Form 908 Version 3.2Uncontrolled When Printed Page 9 of 11
Please tick relevant box for construction tasks undertaken(more than one box can be ticked)
WA Acts and Regulations Dangerous Goods Safety Act 2004 Building Regulations 1989
Occupational Safety and Health Act 1984
Occupational Safety and Health Regulations1996 Electricity Act 1947
Electricity (Licensing ) Regulations 1991
WORKING AT HEIGHTSConstruction which involves a person being at risk of falling two metres or more
HAZARDOUS MATERIALConstruction work on or near chemical, fuel or refrigerant lines including the use of hazardous material Demolition, Scaffolding,
Concrete, Structural Steel Work, Formwork, Masonry, Hydraulics, Electrical Services, Mechanical Services, Lift installation, Aluminium Doors & Windows, Metalwork, Roofing, Carpentry, Plastering, Ceiling, Painting
Code of Practice: Prevention of Falls at Workplaces 2004 National Code of Practice of Falls in General Construction
Guidance Note: Preparing for Emergency Evacuations at the Workplace 2004 AS/NZS 4576 Guidelines for Scaffolding
AS/NZS 1892 Portable ladders 3.26 AS/NZS 1892.1 Metal
AS 1892.2 Timber AS/NZS 1576 Scaffolding
AS/NZS 1576.1 General requirements AS 1576.2 Couplers and Accessories
AS/NZS 1576.3 Prefabricated and Tube-and-Coupler Scaffolding AS 1576.4 Suspended Scaffolding
AS/NZS 1576.5 Prefabricated Split Heads and Trestles
AS/NZS 1576.6 Metal Tube-and-Coupler Scaffolding — Deemed to Comply With AS/NZS1576.3
Removing or Disturbing Asbestos, Termite Treatment, Concrete
National Code of Practice for the Control of Workplace Hazardous Substances[NOHSC:2007(1994)]
National Code of Practice for the Labelling of Workplace Substances [NOHSC:2012(1994)]
National Model Regulation for the Control of Workplace Hazardous Substances National Model Regulation for the Control of Scheduled Carcinogenic substances [NOHSC:1011(1995)]
Safe Removal of Asbestos 2nd Edition [NOHSC:2002(2005)]
Code of Practice for the Management and Control of Asbestos in the Workplace [NOHSC:2018(2005)]
Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres 2nd Edition [NOHSC:3003{2005)]
Code of Practice for the Control of Scheduled Carcinogenic Substances [NOHSC:2014(1995)]
Guidance Note: Provision of information of Hazardous Substances at Workplaces
Guidance Note: Occupational Safety and Health Management on Contaminated Sites Work 2005
EXCAVATIONConstruction involving excavation of 1.5 metres and below
ROADS AND RAILWAYSConstruction adjacent to roads and railways that are in use Demolition, Bulk earthworks,
Hydraulics, Electrical Services, Mechanical Services
Code of Practice: Excavation 2005 Code of Practice: Safe Design of Buildings and Structures 2008
National Standard for Construction Work [NOHSC: 1016 (2005)]
Form 908 Version 3.2Uncontrolled When Printed Page 10 of 11
CONFINED SPACESConstruction work involving a confined space
ELECTRICALConstruction work on or near energised electrical installations and lines (whether overhead or underground) Drainage Sumps, Sewerage
Sumps, Trenches, Swimming Pool Filters, Balance Tanks
Guidance Note: Working Alone 2009
AS 2865 Confined Spaces Powered Tools, Temporary
Power, Electricity, Electrical Services, Welding
Energy Safety Code of Practice : Safe Low Voltage Work Practices by Electricians Guidance Note: Electricity: Residual Current Devices
Guidance Note: Isolation of Plant 2006
Guidance Note: Gas Welding Safety Flashback Arrestors National Standard for Plant
Guideline for Work in the Vicinity of Overhead Powerlines
Guide to Testing and Tagging Portable Electrical Equipment and Residual Current Devices at Workplaces
AS 1674.1 Safety in Welding and Allied Processes – Fire Precaution AS 1674.2 Safety in Welding and Allied Processed - Electrical
AS/NZS 3000 Electrical Installations (known as Australian/New Zealand Wiring Rules) AS/NZS 3012 Electrical Installations – Construction and Demolition Sites
AS 3760 In Service Inspection and Testing of Electrical Equipment
DEMOLITIONConstruction work involving demolition
POWERED MOBILE PLANTConstruction involving movement of powered mobile plant Demolition Code of Practice: Occupational Safety and health Management and
contaminated sites
AS 2436 Guide to noise control on construction, maintenance and demolition sites
AS 2601 Demolition of structures
Demolition, Bulk earthworks, Landscaping, Concrete, Tilt Panel/Delta-Core panels, Steel Fixing, Structural Steel work, Formwork, Hydraulics, Lift, Metalwork, Roofing, Carpentry
Code of Practice: Safe Guarding of Machinery and Plant Code of Practice: Plant in the Workplace
Code of Practice: Powered Mobile Plant
Code of Practice: Safe Movement of Vehicles at Workplace Code of Practice: Working Safely with Forklifts
Machinery and Equipment Safety – An Introduction 1st Edition AS 4024.1 Series: Safety of Machinery
AS 1418 Set-Cranes, hoists and winches Set
AS 2550 Set- Cranes, hoists and winches – Safe Use Set AS/NZS 4431 Guidelines for Safe Working on New Lift Installations in New Constructions
JOB HAZARD ANALYSIS WORKSHEET
Form 908 Version 3.2Uncontrolled When Printed Page 11 of 11
TILT UP OR PRECASTConstruction work involving tilt-up or precast concrete
TEMPORARY SUPPORTSConstruction work involving alteration to a structure that requires the structure to be temporarily supported to prevent its collapse
Precast Concrete, Tilt Panel, Beams,
Delta Core Panels
National Code of Practice for Precast, Tilt- up and Concrete Elements in Building Construction (2008)
Code of Practice: Tilt- up and Precast Concrete Construction 2004 Code of Practice: Concrete and Masonry Cutting and Drilling 2004 AS 3850 Tilt-up Concrete Construction
AS 3610 Formwork for Concrete
AS 3610.1 Formwork for Concrete: Documentation and Surface
Demolition, Scaffolding, Concrete, Tilt Panel/ Delta Core Panels, Structural Steelwork, Masonry, Hydraulics, Electrical Services, Mechanical Services, Lift, Metalwork, Carpentry
Code of Practice: Safe Design of Buildings and Structures 2008 National Standard for Construction Work [NOHSC: 1016 (2005)]
ATMOSPHERIC CONTAMINATIONConstruction work in an area that may have a contaminated or flammable atmosphere
WATER OR OTHER LIQUIDSConstruction work in, over or adjacent to water or other liquids if there is a risk of drowning.
Carbon Monoxide, Asbestos Adopted National Exposure Standards for Atmospheric Contaminants in the Occupational Environment [NOHSC: 1003 (1995)]
Guidance Note on the Interpretation of Exposure Standards for Atmospheric Contaminants in the Occupational Environment 3rd Edition [NOHSC:
3008:1995)]
Guide to Hazardous or Combustible Dusts, Fumes and Fibres
Guidance Note: Prevention of Carbon Monoxide Poisoning from Petrol and Gas Powered Equipment 2008
Guidance Note: Occupational Safety and Health Management on Contaminated Sites Work 2005
Water, other liquids Code of Practice: Safe Design of Buildings and Structures 2008
National Standards for Construction Work [NOHSC: 1016(2005)]