TABLE OF CONTENTS
3
OnSite Energy & Power
4
Comprehensive Energy Master Planning
6
Feature Project:
Critical Service Central Plant
8
Demand-Side Energy Savings
10
Central Utility Plants and District Energy
12
Thermal Energy Storage
14
Feature Project:
Central Plant Master Plan
16
Combined Heat and Power
18
Regulatory Compliance
20
Electrical Distribution and Substations
22
Feature Project:
Biomedical District Steam Plant
24
Thermal Distribution Systems
26
Construction, Startup, Commissioning and Facility Operations
28
About Burns & McDonnell
On
Site
ENERGY & POWER
Campus environments — universities,
airports, hospitals — require individual utility
solutions. A one-size-fits-all approach won’t
deliver the systems that will prepare your
institution for growth.
The dedicated Burns & McDonnell OnSite
Energy & Power Group brings the extensive
experience of more than 140 professionals
to bear on the master planning, design,
construction and commissioning needs of
your campus.
This team specializes in energy planning and
design, having led such projects for more
than $2 billion in infrastructure development
and demand side initiatives over the past
10 years. We have led more than 30 energy
master plans and have worked on more than
60 large health care and institutional utility
systems.
COMPREHENSIVE
MASTER PLANNING
Your energy master plan is a sustainable
road map to guide you in decisions about
maintaining and expanding campus
infrastructure. It can enable environmental
compliance, energy efficiency, growth
capacity, reliability, redundancy, flexibility
and the lowest life cycle system cost.
Looking at your utility requirements for the
next 15 to 30 years, your energy master plan
considers cost-benefit analyses of equipment
performance, alternative energy sources,
demand-side management and infrastructure
optimization to reduce environmental impact
and operating costs.
Our team will develop your base case load
profile and analyze your future load growth
using complex computer simulations.
Then, the team can reverse engineer the
infrastructure upgrades, associated capital
costs and efficiency effects to create
your master plan — your road map — to
prioritize projects informed by an accurate
financial picture that includes expansions,
maintenance and replacements.
Burns & McDonnell updated Texas A&M’s utility and energy management master plan and assisted with compliance and reporting. The master plan extends efficiency beyond the utility infrastructure into building standards and aids in securing funding and approval for upgrades over the next 30 years of planned campus expansion. Recommendations — including thermal energy storage and a heat pump chiller — involve $170 million in utility capital projects with $33 million in life cycle savings. Burns & McDonnell secured a $10 million U.S. Department of Energy grant for the university.
This comprehensive infrastructure master plan prepares Ohio State to meet growing campus energy demands for the next 40 years. The plan includes load projections, energy production and distribution requirements, analysis of centralized versus localized plant assets, and a life cycle cost analysis. Recommendations include thermal energy storage, combined heat and power, and condensing economizers. In total, the plan could save the university more than $40 million throughout its term.
Purdue University sought to meet its efficient energy management goals by creating a comprehensive energy master plan. Burns & McDonnell developed a plan focused on the efficient production of electricity, chilled water and steam in the campus utility plants. Analysis of the chilled water and steam distribution system, as well as building electricity, domestic water, chilled water and steam consumption led to equipment modifications that provided immediate annual savings in excess of $1 million.
UTILITY AND ENERGY MANAGEMENT MASTER PLAN
Texas A&M University
College Station, Texas
INFRASTRUCTURE MASTER PLAN
Ohio State University
Columbus, Ohio
COMPREHENSIVE ENERGY MASTER PLAN
Purdue University
Providing reliable power and protection from grid outages, the new Parkland central utility plant features 13,750 tons of cooling, 1,000 tons of heat pump chilling, 200,000 pounds per hour of steam and 17.5 MW of emergency power. The plant supports 2.5 million square feet of hospital and medical office buildings, and it can provide emergency electricity and thermal utilities for at least 36 hours during a grid outage — known as operating in “island mode.”
Reliability was a crucial design factor for the hospital, which serves 1,600 primary care patients daily, including 500 in the Emergency Department. It also houses the second-largest civilian burn unit in the country. When operating in island mode, an 850,000-gallon water storage tank can keep the hospital’s cooling tower functional and fulfill demand for water in faucets, sterilization equipment and other systems.
The project focused on sustainability, with an eye on water scarcity in the future. The heat pump chiller is expected to save 15 million gallons of water annually and pay for itself in four to six years. The system is also designed for flexibility, with room for a sixth chiller, seventh boiler and another generator to accommodate demand growth. There’s also a spare equipment bay ready for future technology needs, and other systems are easily converted to new uses or designed for easy movement of equipment.
A strong client connection was critical. The project was completed on schedule and within budget, and plans were adjusted throughout the timeline to support other initiatives. One example: Selected utility installations were expedited to enable work to progress on the new hospital. “Their team moved seamlessly into design and developed top-notch documents for construction,” said Maria Dierking, who served as Parkland’s senior program manager for the hospital replacement program. “Throughout the process, they worked closely with the entire hospital staff and design team and helped us to maximize the value
CRITICAL SERVICE
CENTRAL PLANT
Parkland Health & Hospital System
Dallas
Energy analysis and detailed design
The energy-efficient CUP contributes to potential LEED Silver certification for the campus, meeting Parkland’s strategic sustainability goals.
The plant was built to last for up to 100 years, matching the expected life span of the hospital.
FEA
TURE PR
O
JE
C
T
DEMAND-SIDE
ENERGY SAVINGS
Rising utility costs and programs to reduce
energy use are among your top concerns.
The Burns & McDonnell team can take you
through an energy audit and advise you in
developing the business case for energy
efficiency measures. Your solution will
incorporate your financial models, reliability
requirements, maintenance structure and
corporate investment strategies.
This U.S. Department of Energy voluntary program engages participants in identifying energy-saving strategies and reducing consumption through facility improvements. The University of Utah intends to reduce campus energy use by 20 percent by 2020. As program manager, Burns & McDonnell is evaluating and developing energy efficiency projects, following with design and construction administration over the six-year, five-phase implementation for 12 million square feet of campus building space.
This comprehensive energy management program (EMP) provides a sustainable system based on a plan-do-check-act strategy, modeled after the ISO 50001 guidelines and the Environmental Protection Agency’s Energy Star initiative. Burns & McDonnell led the development and implementation of the EMP, which uses a holistic energy management approach covering awareness, efficiency measure identification and implementation, standards and best practices implementation, progress monitoring and validation, performance reviews, and continuous improvement.
This audit included detailed surveys of all buildings, analysis and modeling of a comprehensive list of conservation measures, and associated cost estimates. Because of security issues in sensitive reseach and development areas, the Burns & McDonnell team worked with Boeing to manage and schedule all audit activities. The audit also provided detailed analyses of program costs, capital versus operating expenses, and multiple financing alternatives.
BETTER BUILDING CHALLENGE
University of Utah
Salt Lake City
ENERGY MANAGEMENT PROGRAM
Confidential Food Manufacturer
North America
INVESTMENT GRADE ENERGY AUDIT
The Boeing Co.
CENTRAL UTILITY
PLANTS AND
DISTRICT ENERGY
A central utility plant cost-effectively
consolidates your energy conversion
equipment into one location, giving
you advantages in efficiency, reliability,
maintainability and redundancy. Our team
analyzes, optimizes, retrofits and expands
plants and district energy systems, drawing
on decades of experience assessing and
incorporating emerging technologies.
A continuing assessment of emerging
technologies helps us integrate the most
effective solutions into your central utility
plant or district energy system, optimizing
your energy efficiency and minimizing your
environmental impact. Our analysis considers
the issues that drive utility use within your
buildings, providing critical input in the
development of design standards to optimize
performance of new facilities. Our processes
integrate power generation with HVAC
demand, load planning and savings goals.
As the university expands into a new medical district requiring a new, expandable cooling and heating facility, Burns & McDonnell provided energy analysis to establish the concepts for plant design, including thermal energy storage and heat pump chillers. The plant will integrate with existing campus chilled water systems and will be the first hot water plant on the campus. The project features 15,000 tons of variable speed chillers, 1,200 tons of heat pump chillers, more than 5.6 million gallons of thermal energy storage and 113,000 MBH (thousands of BTUs per hour) of heating equipment. The plant puts the campus on the leading edge of reliable, energy-efficient facilities.
Burns & McDonnell performed an energy analysis and detailed design for a central utility plant (CUP) for Parkland’s new hospital in Dallas. The plant features 13,750 tons of cooling, 1,000 tons of heat pump chilling, 200,000 pounds per hour of steam and 17.5 MW of emergency power to support 2.5 million square feet of hospital and medical office buildings. The CUP’s energy efficiency will help Parkland obtain LEED Silver certification for the $1.2 billion campus and provide emergency electricity and thermal utilities for at least 36 hours in the event of a utility grid outage.
The Airbus Powerhouse project provides a centralized source of heating and cooling for the new Airbus A320 assembly plant. It included more than 4,200 tons of chilled water capacity, 44,000 MBH of hot water capacity, and domestic water, compressed air and sanitary sewer services for the full complex. Burns & McDonnell provided design-build services on a fast-track schedule, with design completed in about two months, just 13 months after the signing of the initial contract. Burns & McDonnell also provided support for Federal Aviation Administration
CENTRAL CHILLING STATION #7
University of Texas
Austin, Texas
CRITICAL SERVICE CENTRAL PLANT
Parkland Health & Hospital System
Dallas
AIRBUS POWERHOUSE
Honeywell
THERMAL ENERGY
STORAGE
Few on-site energy options deliver as
powerful a combination of lower capital costs
and lower energy costs as a thermal energy
storage (TES) system. TES allows large
cooling systems to generate cooling energy
(chilled water or ice) for storage during
off-peak electrical periods, when rates are lower
and the system operates most efficiently.
Stored cooling energy is then used during
peak hours, when electrical demand is
higher, saving money and wear on expensive
equipment. With an installed cost lower than
new chillers and associated equipment, it’s
hard to beat.
A TES system can also reduce the risk of
electric grid overload by helping to manage
power demand through peak demand
reduction and ramping up or down in
response to grid load changes. When linked
with a combined heat and power system,
TES generates additional savings. Burns &
McDonnell has the experience to help you
find the right TES solution for your campus,
which could lead to millions in saved
operating expenses.
A TES tank installation is improving the reliability and efficiency of mission-critical services at Texas A&M. The system provides the capacity to shift chilled water production to off-peak hours, allowing the university to reduce electricity consumption during peak demand periods and increasing system capacity and operational flexibility. Potential annual savings
are $395,000.
An 8.8 million-gallon TES tank at the Texas Medical Center provides 76,000 ton-hours of storage capacity, enough to defer running electric centrifugal chillers during expensive peak demand times. In August 2011, the tank saved TECO more than $500,000 in energy costs, while providing increased redundancy and reliability. It works in combination with TECO’s combined heat and power system. The tallest TES tank worldwide at construction, it was named Steel Tank of the Year by the Steel Tank Institute and was honored with the ASHRAE Technology Award.
Thermal energy storage at this corporate headquarters and home of the F-16 Fighting Falcon and the F-35 Lightning II increases system capacity, efficiency and flexibility. The chilled water system responds directly to the dynamic nature of manufacturing loads. Pumps quickly modulate to meet large load swings while chillers remain at their most efficient setting.
UTILITY PLANT PRODUCTION UPGRADE
Texas A&M University
College Station, Texas
THERMAL ENERGY STORAGE
Thermal Energy Corp. (TECO)
Houston
THERMAL ENERGY STORAGE
Lockheed Martin Aeronautics
Fort Worth, Texas
Shortly after it was commissioned and placed into service in 2010, the 48-MW combined heat and power (CHP) system supplying the Texas Medical Center campus with steam and chilled water faced one of the hottest August days on record. TECO didn’t pull a single watt of electricity from the grid that day. The CHP system didn’t miss a beat. Combined with 32,000 tons of new chiller capacity and a thermal energy storage (TES) tank, the largest district energy cooling system in the U.S. is a model of sustainability, operating at 80 percent efficiency. Environmental emissions also were cut by an estimated 302,000 tons in the system’s first year of operation, equivalent to taking 52,000 cars off the road. The district energy system has also been part of an initiative to bolster TECO’s service reliability in the face of natural disasters like the hurricanes that struck in 2005 and 2008.
The required growth of this CUP didn’t come with the ability to double the size of the site. Bordered by a waterway, busy roadways and an established medical campus, the site presented a challenging, constrained space to accommodate major construction, staging areas, major equipment lifts and more than 400 subcontractor personnel. Design-build project delivery enabled the tight coordination necessary to accomplish the task.
“The only way TECO could do this project is to have design (and) construction under one roof. We recognized that we needed to identify a firm that could come in and do the design, that could do construction administration, could do the procurement in between, and Burns & McDonnell brought that expertise in all of those (areas). There’s no question that there’s an efficiency in everything — from time, dollars, effort — when you have one point of contact,” says Steve Swinson, CEO and president of TECO.
The efficiencies in operation translate into financial advantages for TECO and its customers. The master plan implementation is expected to save more than $200 million over its first 15 years in operation. TECO was able to reduce its customer rates by 2 percent and
CENTRAL PLANT
MASTER PLAN
Thermal Energy Corp. (TECO)
Houston
Architecture, engineering, procurement and construction
The 8.8 million-gallon TES tank saved TECO more than $500,000 in energy costs in a single month, all while providing increased reliability and redundancy. A heat recovery steam generator recovers waste heat via conductive heat transfer to produce steam.
FEA
TURE PR
O
JE
C
T
COMBINED HEAT
AND POWER
Combined heat and power (CHP) can
cost-effectively provide 100 percent of a facility’s
day-to-day electric and thermal energy needs,
simultaneously satisfying all or a portion of
backup generation requirements. That’s why
the Department of Energy (DOE) considers
it one of the most promising options in the
U.S. energy portfolio: lower greenhouse gas
emissions, high energy efficiency, potential
for nationwide implementation, and ability to
relieve the burden on the electrical grid.
Burns & McDonnell is recognized by the
DOE as an industry leader, and our team has
experience designing, building, permitting
and interconnecting CHP plants as large
as 200 MW and as small as 500 kW for
universities, hospitals, large office buildings,
data centers, corporate and government
campuses, and international airports. We can
develop financial and economic cost models,
prepare grant applications and arrange utility
partnerships to help offset the costs of
your system.
The GRU South Energy Center on the University of Florida campus provides electrical power, chilled water, steam and medical gasses for the Shands Cancer Center. The workhorse of this $45 million facility is a 4.3-MW, natural gas-fired combustion turbine with low emissions. The ultra-high-efficiency generator can run 24/7 and normally operates in parallel with one of two utility feeds from separate substations. The LEED Gold-certified energy center can generate all of the hospital’s and its own power needs on site. The plant, designed to keep the hospital operational even in the midst of a hurricane-driven grid outage, produces 4,200 tons of cooling and 30,000 pounds per hour of steam.
This complete design-build project provided an efficient, natural gas-fired CHP system that generates 48 MW of power and 330,000 pounds of steam per hour. It can operate as a base load system to serve 100 percent of the plant’s peak electrical load and TECO’s customers’ peak process and space-heating loads. Exceeding 80 percent efficiency, the CHP system saves an estimated 0.75 trillion Btu annually over separate electrical and steam generation and reduces carbon dioxide emissions by more than 300,000 tons per year. It also enables TECO to provide uninterrupted energy services in the event of a grid outage.
Burns & McDonnell conducted a Level II CHP study that investigated potential alternatives for expansion of CHP capabilities at Harvard’s historic Blackstone. The initial screening-level phase analyzed six options at Blackstone and six options for a new standalone CHP facility sited elsewhere on campus. The study examined several options and developed detailed performance characteristics for each, which were then subjected to a dispatch model to develop a plan for the most effective use of both existing assets and proposed additions.
HOSPITAL CAMPUS CHP ENERGY CENTER
Gainesville Regional Utilities
Gainesville, Fla.
48-MW CHP PLANT AT TEXAS MEDICAL CENTER
Thermal Energy Corp. (TECO)
Houston
CHP ADDITION
Harvard University
Cambridge, Mass.
REGULATORY
COMPLIANCE
Central utility plants face a challenging
regulatory landscape. At the forefront for
many is the National Emission Standard
for Hazardous Air Pollutants for Industrial,
Commercial and Institutional Boilers and
Process Heaters — commonly known as
the Industrial Boiler MACT Rule — and the
National Ambient Air Quality Standards
(NAAQS). Boiler MACT requires compliance
by 2015, and facilities may have
to concurrently demonstrate compliance
with NAAQS.
The situation is unique for every facility.
Planning now is critical. Compliance
planning (testing and preliminary studies and
permitting) can take six to 12 months, and
air pollution control retrofits or new boiler
installations can take 12 to 30 months. Burns
& McDonnell can help you determine
your facility’s compliance status and select
appropriate measures to move you forward
with a comprehensive solution.
To identify air pollution control modifications to comply with Boiler MACT and other regulations, Purdue hired Burns & McDonnell to conduct a study and provide detailed design for
recommended changes to its Wade Utility Plant. The firm evaluated alternatives that allowed continued operation and assessed the ability of the existing plant auxiliary systems to support retrofits. Detailed design included new fabric filter and dry scrubber systems, which were retrofitted to the existing boiler.
To comply with the Boiler MACT rule, Penn State decided to eliminate coal as a fuel in its system, converting the boilers to fire gas with oil as a backup. To help analyze the options and design the selected solution, the university hired Burns & McDonnell to complete a boiler conversion study and a new steam generation study, as well as provide cost estimates and schedules for compliance. When the selection is made, Burns & McDonnell will provide detailed design and installation services.
Burns & McDonnell replaced three coal-fired stoker boilers with three new natural gas/oil-fired package boilers and made modifications to the remaining circulating fluidized bed boilers for compliance with the Boiler MACT rule. Services included environmental permitting, substation upgrades, demolition and remediation, prepurchase packages, and a building addition. The boiler replacement includes a new oil storage and distribution system, which allows Iowa State to continue operations during a gas curtailment. The new boilers interface with
BOILER MACT COMPLIANCE
Purdue University
West Lafayette, Ind.
BOILER MACT COMPLIANCE
Pennsylvania State University
University Park, Pa.
BOILER REPLACEMENT
Iowa State University
ELECTRICAL
DISTRIBUTION
AND SUBSTATIONS
As a recognized leader in the transmission
and distribution industry, Burns & McDonnell
has broad experience engineering a wide
variety of projects. Our analysis and
design experience ranges from small
4.16-kV projects to multimillion-dollar
500-kV efforts. We have designed
customer-owned substations for both private- and
public-sector clients, including transmission
interconnection configurations for CHP
systems and full analysis and design of
relay equipment. In some cases, installing a
customer-owned substation can pay for itself
in less than five years.
Such a facility provides improved reliability
and avoids outages more common with utility
distribution systems. In addition, our detailed
analysis and review of a campus electric
distribution system will show opportunities
to harden your system and provide the
dependable and consistent power required
for today’s complex and demanding facilities.
This project features six large pump stations with loads from 20 to 46 MVA along a 150-mile pipeline route. Burns & McDonnell assisted TRWD in determining if the local utility or water district should construct and own the transmission line extension and substation that would serve each pump station. After consulting multiple utilities and electric cooperatives to determine interconnection requirements and delivery tariffs and after performing life cycle cost analyses for each option, Burns & McDonnell recommended TRWD own the equipment and employ a standardized substation design.
The medium-voltage electrical distribution system on the Clemson campus requires a significant upgrade to continue safe and reliable operation. Substation and distribution switchgear
equipment are reaching the end of their useful lives, and the university plans to migrate away from the 5-kV system in favor of a more reliable and efficient 15-kV system. Burns & McDonnell is developing a detailed upgrade and replacement plan and preparing associated design and construction documents to modernize the electrical distribution system.
The Air Force Plant 4 substation equipment and 5-kV distribution feeder cables are nearing the end of their useful life. Burns & McDonnell estimated the life cycle cost for multiple replacement and upgrade options. Transmission service with a phased design and installation proved the most economic and reliable option, with Lockheed constructing a new substation adjacent to the existing one. The radial 5-kV distribution system will be replaced with a looped system to improve reliability and maintainability. Multiple radial feeders will be combined and connected
HIGH-VOLTAGE UTILITY ENGINEERING
Tarrant Regional Water District (TRWD)
Tarrant County, Texas
SUBSTATION AND DISTRIBUTION UPGRADES
Clemson University
Clemson, S.C.
SUBSTATION AND DISTRIBUTION REPLACEMENT
Lockheed Martin Aeronautics
The Downtown New Orleans district energy system provides steam and chilled water services to numerous customers, including the Louisiana State University (LSU) Medical Center. Burns & McDonnell is the design-builder for the new Biomedical District Energy Plant, which will replace an existing boiler plant providing critical services to the Level I trauma center at LSU.
As the sole source of steam to critical and noncritical facilities, the plant must deliver reliability and availability in the face of potential hurricane wind loads, as well as house critical equipment above the flood plain-plus margin. The medical center is required to maintain operations for up to seven days in the event of a disruption in electrical, natural gas or water utility service in the district. Both nonpotable water and fuel oil will be stored on-site to support the critical steam load of 50,000 pounds per hour for that seven-day period. The urban area and constrained available footprint create construction and design challenges, requiring careful scheduling and equipment staging.
BIOMEDICAL DISTRICT
STEAM PLANT
Enwave USA
New Orleans
Design-build delivery
Dual-fuel boilers deliver flexibility and reliability in a hurricane- prone region.
The plant provides up to 900 kW of power and 210,000 pounds per hour of steam at peak capacity.
FEA
TURE PR
O
JE
C
T
THERMAL
DISTRIBUTION
SYSTEMS
The power quality and thermal distribution
systems on your campus are critical.
They also present specialized needs.
Burns & McDonnell has extensive experience
with campus-level system analysis and
design, whether the concern is a deteriorated
tunnel, failed pipe supports or leaking
expansion joints. We develop complex steam,
hot water and chilled water distribution
models calibrated to existing conditions and
referencing GPS information and campus
maps. Once calibrated, the models simulate
growth, determine optimal routes and sizing,
and provide extensions to utility distribution
systems that enable flexibility and growth.
Any proposed alternatives and system
changes factor in construction phasing and
sequencing options to minimize short- and
long-term interruption of utilities. Those
phasing and sequencing requirements are
defined and incorporated in all construction
documents to keep your campus operating
and focused on education.
The Mayo Clinic expects to double in size over the next 30 years, growing along with the aging U.S. population. The existing infrastructure must grow as well. Burns & McDonnell analyzed multiple chilled water and steam distribution solutions and verified suitable sites for new production. Recommendations from the analysis included improvements to existing system efficiencies and a new utility/pedestrian subway system that can both feed utilities to new facilities and provide comfortable campus access for patients, visitors and medical staff.
Upgrades to about 1,200 feet of 1970s-era walkable distribution tunnels will increase the well-lit, maintainable space, improving conditions for university staff and boosting overall performance. Renovations and revitalizations will include: new high pressure steam and stainless steel condensate piping; structural repairs to existing tunnel piping support structures; buried, high-density polyethylene natural gas piping; tunnel ventilation shafts; and upgrades to the lighting and power systems.
A planned campus expansion study laid the groundwork for expansion of the chilled water distribution system and the conversion of the steam system to a distributed hot water system. Burns & McDonnell developed a utility master plan and recommended incorporation of distributed heating and cooling infrastructure that is reliable and economical. The systems would also be flexible and expandable to meet future growth in demand. Comprehensive flow analysis and system modeling software were used to analyze the hot and chilled water piping
THERMAL DISTRIBUTION SYSTEM EXPANSION
Mayo Clinic
Rochester, Minn.
STEAM SYSTEM REHABILITATION
Ohio State University
Columbus, Ohio
THERMAL DISTRIBUTION MODELING AND DESIGN
Auburn University
CONSTRUCTION, STARTUP,
COMMISSIONING AND
FACILITY OPERATIONS
The depth and breadth of Burns & McDonnell facility design
and construction experience brings advantages to every
project. Our Construction/Design-Build Group builds more
than $1 billion in projects each year, across a range of
industries and facility types. That means your project
benefits from skilled staff who know how to maintain
schedules and budgets.
Our commissioning team has experience with a spectrum
of project types, including governmental, institutional,
educational, health care, labs, central utility plants, and
combined heat and power facilities. The commissioning
process begins in pre-design and sets performance goals
early. Rigorous function testing and inspections validate
system performance and help train your operations staff,
as well as provide documentation for ongoing operations.
The commissioning process can improve the reliability and
performance of your new or renovated system, and when your
team takes over, it’s trained to work effectively and efficiently.
When your facility is complete, Burns & McDonnell subsidiary
Facility Operation Services (FOS) can provide qualified
management and staff to operate and maintain your plant
for a contracted period, or consult on a limited basis.
FOS complements our design, engineering and construction
services, rounding out the entire facility capital asset
Burns & McDonnell provided commissioning, including technical design review, as a subconsultant to Honeywell Building Solutions, on this $213 million central utility plant expansion at the FDA’s White Oak campus. The expansion features a 24.5-MW CHP plant with three gas combustion turbine generators, three 2,500-ton electric chillers, 2 million gallons of thermal energy storage, three heat recovery steam generators, an auxiliary boiler and two emergency diesel generators. Burns & McDonnell is helping the project meet U.S. General Services Administration P100 and LEED Silver standards.
Enwave owns and operates the Downtown New Orleans district energy system providing steam and chilled water services to the Louisiana State University (LSU) Medical Center. Burns & McDonnell, as the design-builder for the new $27.2 million Biomedical District Energy Plant, will help Enwave meet expected growth on the campus. The center must be able to operate continuously for up to seven days during a disruption in electrical, natural gas or water utility service. To meet this requirement, both nonpotable water and fuel oil will be stored on-site to support the critical steam load.
Since 2005, FOS has operated and maintained utility service for the Kansas City International Airport aircraft overhaul base. FOS provides capable management and skilled labor personnel to reliably and efficiently serve the steam, chilled water and compressed air needs of this large complex. Besides stewardship of the CUP assets, FOS cares for distribution systems and customer-side equipment.
CHP SYSTEM COMMISSIONING
U.S. Food & Drug Administration (FDA)
Silver Spring, Md.
BIOMEDICAL DISTRICT BOILER PLANT
Enwave USA
New Orleans
CUP OPERATIONS AND MAINTENANCE
Kansas City Aviation Division
ABOUT BURNS & MCDONNELL
Founded in 1898, Burns & McDonnell is a 100 percent employee-owned, full-service engineering,
architecture, construction, environmental and consulting solutions firm. Burns & McDonnell ranks in
the upper 5 percent of
Engineering News-Record
’s Top 500 Design Firm and is among the leaders
in many service categories. With the multidisciplinary experience of 4,500 professionals in more
than 30 offices in the United States, Burns & McDonnell plans, designs, permits, constructs and
manages facilities worldwide with one mission in mind — to make our clients successful.
COMPANY SERVICES
• Air quality control
• Architecture
• Aviation
• Business consulting
• Commissioning
• Construction
• Electrical transmission and distribution
• Energy services
• Environmental
• Environmental studies and permitting
• Facilities design
• Federal and military
• Food and consumer products
• Health care and research facilities
• Industrial
• Information technology
• Laboratories and clean rooms
• Manufacturing and facility solutions
• On
Site Energy & Power
• Oil and gas
• Power generation
• Process design
• Program management
• Security and compliance
• Sustainability
• Telecommunications
• Transportation
• Water
FROM
ENGINEERING NEWS-RECORD
2013
#1 Designer of the Year (
ENR Midwest
)
#13 in Top 50 Program Management Firms
#13 in Top 100 Construction Management-for-Fee Firms
#15 in Top 100 Green Design Firms
#18 in Top 500 Design Firms (2014)
#20 in Top 100 Design-Build Firms
#42 in Top 100 Construction Management-at-Risk Firms
INDUSTRY-SPECIFIC LISTS (
ENR
2013)
#2 in Transmission and Distribution
#3 in Electronic Assembly
#4 in Power (2014)
#6 in Aerospace
#8 in Cogeneration
#12 in Airports
#12 in Commercial Offices
#15 in Government Offices
#19 in Manufacturing (2014)
#21 in Industrial Process
#40 in General Building
FOUNDED IN
1898
100%
EMPLOYEE-OWNED
4,500
PROFESSIONALS
UPPER
5%
TOP 500
DESIGN FIRMS
MORE THAN35
U.S. OFFICES
www.burnsmcd.com/onsite
E n g i n e e r i n g , A r c h i t e c t u r e , C o n s t r u c t i o n , E n v i r o n m e n t a l a n d C o n s u l t i n g S o l u t i o n s
Client success is our mission.
How can we help
you
succeed?
For more information, contact:
Scott Clark
Principal,
On
Site Energy & Power
817-233-1540
Tim Burkhalter
Business Development,
On
Site Energy & Power
816-289-8519