• No results found

What will it be; define the value

N/A
N/A
Protected

Academic year: 2021

Share "What will it be; define the value"

Copied!
7
0
0

Loading.... (view fulltext now)

Full text

(1)

Level 2 Frame

Facility: Greenfield Power Plant with Carbon Capture

All 6 Project Phases

All aspects for the relevant facility

Stage

Identify (Concept Study)

Evaluate (Pre-Feasibility Study) Define (Feasibility/FEED Study)

Execute

Operate

Closure

Description “What could it be” “Comparatively, what the cases might be, and

select the best one”

“What will it be; define the value”

Project Context and Opportunity Definition and Recommendation

Project sponsor to prepare a Draft Business Case that is developed to increasing levels of detail as the Project progresses through the various stages in its life-cycle

Assessment of project opportunities, rationale for investment, business plan, regulatory drivers, economic and technical viability of proposed project, assessment of appropriate capture technology

(pre/post/oxy).

Provide a recommendation that the opportunity does, or does not, warrant further funding to determine the likely economic and technical viability of the proposed opportunity.

Identify and agree project success criteria / high level requirements and secure funding to the Evaluate Stage activities

Detail the Business case

Benchmark conceptual data against base case options and overarching project criteria to rank and select most appropriate power plant and capture plant.

Provide a recommendation that the selected optimum case does, or does not, warrant further funding to determine the likely economic and technical viability of the proposed opportunity.

Secure funding for the FEED phase

Finalise the Business Case for Power Plant and Capture Plant.

Prepare Board Paper identifying: • Project Status

• Business Drivers

• Market tested project costs

• Remaining uncertainties / risks and mitigations

• Risk reduction trajectory / timing • Exit Strategy

• Key Financial metrics (NPV, IRR etc) • Future Work Plan Report

• Funding Recommendations • Recommendation to proceed /

terminate

Measure progress against business case on a periodic basis during the execute phase to ensure continued viability.

Revise business case to reflect the out-turn project performance. Prepare detailed annual operating plans on the basis of the updated business case.

Assessment of project closure opportunities and costs. Provide recommendation for preferred option. Project Development Approach

Outline a draft process development approach for capture plant requirements and key work streams for different technology options, commercial, project stakeholder engagement, HSE and consenting.

Outline management systems and proposed organisational responsibility structure.

Provide a statement as to whether (or not) the proposed project adheres to the proponent’s Business Expansion Policy.

Within the different work streams evaluate different capture processes, capacities, locations, and plant configuration scenarios Evaluate the technical and economic viability of the project for the overall plant life cycle (cradle to grave)

Select favoured option for development during ‘Define Stage’.

Provide an overview of the project

development approach. Describe the optimised selected business case. Advise the project structure, list all the alliances required whether commercial or technology based.

Implement the project execution and delivery strategy and revise / maintain a project execution plan.

n/a Outline process for

capture plant closure. Outline management systems and proposed organisational responsibility structure.

Site Selection Screening for appropriate power plant & capture plant location (depending on technology post/pre/oxy) for integrated new build capture plant, screening for most appropriate location for plant efficiency and minimal development constraints. Report any infrastructure and waste disposal structures.

Building upon screening undertake more detailed pre-feasibility analysis of site selection including to filter into the Feasibility/FEED (consider requirements for Site plot plan, Topographical survey, EIA, Air dispersion); nominate where all facilities are located and why the specific sites have been considered. Identify preferred site.

Undertake selected site survey Undertake topographical survey Soil investigation

Identify sensitive receptors (noise / visual impacts)

Negotiate and finalise site leasehold (including necessary easements), ready for execution Nominate where all the facilities are located and why the specific site has been considered.

n/a n/a Asset deconstruction

to achieved required decommissioned state (safely, on time, on budget and to scope & quality) Remediate asset site to required condition

Stakeholder and External

Relations

Identify an appropriate stakeholder register and engagement requirements with

Identify for each stakeholder if a specific report will be required and create a scope to be

Undertake community engagement, and other stakeholder engagement, according to

Interface / communicate with internal and external Stakeholders

Interface /

communicate with

Interface /

(2)

required regulatory bodies (i.e. HSE, Environmental Agency, Local Government, Transport, Public Authorities, District Network Operator)

Prepare stakeholder engagement strategy.

covered at feasibility stage. Identify any pre-qualification requirements for specialist consultancy requirements and if public consultations are required.

Revise Stakeholder engagement strategy (if necessary)

Develop stakeholder management plan.

Stakeholder Management Plan

Obtain key regulatory consents / approvals required to commence the execution of the project

• Planning Consent (Section 36 or similar) • Pollution Prevention & Control Permit

Application (or similar)

• Prepare Pre Construction Safety Report (or similar)

• Hazardous Substances consent • Construction Consent

• Water abstraction consent (if required) • Effluent discharge consent

involved with the project including Government and statutory

authorities and non Government agencies.

Obtain balance of regulatory approvals for completion of project

internal and external Stakeholders involved with the facility including Government and statutory

authorities and non Government agencies.

internal and external Stakeholders involved with the facility closure including Government and statutory authorities and non Government agencies.

Obtain balance of regulatory approvals for closure of facility.

Environment High level list of preliminary environmental impact possibilities and consultation procedures, outlining applicable project environmental permitting processes and timetable (based on professional

judgement, accessing knowledgeable local personnel and obtaining brief views, no detailed studies). Outline potential

unfavourable public responses to project’s environmental issues.

Initial review of the regulatory ‘landscape’ in project jurisdiction to identify where there are regulatory ‘gaps’ wrt carbon capture.

For all the alternatives considered describe all requirements, including a detailed timeline for environmental approvals. Undertake a more detailed environmental assessment study, identify impacts on regulatory consent to project time frame, understand cost

implications, and if environmental licenses will cause the project to be deferred or cancelled.

Undertake Surveys as identified by Environmental Regulator:

• Ecological Surveys • Wildlife Surveys • Flora &Fauna Surveys • Cultural Heritage Surveys • Background Nose Monitoring

Assessment

• Background Air Quality Assessment • Ground Survey

Undertake Environmental Impact Assessment and Report

Describe at summary level the status of all licensing activities and any licenses yet to be achieved.

Ensure environmental compliance for the Carbon Capture element of the project.

Carry out site decontamination works, i.e. asbestos removal if applicable

Ensure environmental compliance for the Carbon Capture element of the project.

Ensure

environmental compliance for the closure of the Carbon Capture facility.

Health and Safety High level review of HSE implications imposed by capture plant scale, location, operational conditions, materials handling and by-product disposal options.

Identify ‘gaps’ in the HSE regulations (if any) wrt carbon capture.

Scope out preliminary engagement plan with regulatory bodies.

Outline HSE systems that will be put in place and considered during FEED including

deliverables scope for studies to be included at FEED such as HAZID, HAZOP and ALARP. Engage with HSE authorities to progress regulation development.

H&S Management Study & Report Establish safety management team for construction and commissioning

Establish H&S procedures for site surveys. Provide a schedule nominating when H&S systems will need to be finalised.

Ensure H&S (CDM) statutory responsibilities are carried out. Establish H&S (CDM) duty holder roles (Client, Principle Contractor, Designer, CDM Co-ordinator). Focus on Contractor safety and engagement, for assurance of a well trained and safety motivated workforce.

Implement a design led hazard and risk mitigation process to design out (or mitigate) risks in advance of works. Design risk reviews should be a regular feature during the works, to ensure emergent design safety issues are addressed.

Ensure H&S compliance for the Carbon Capture element of the project.

Ensure H&S compliance for the closure of the Carbon Capture facility.

Fuel Supply Preliminary definition of fuel supply requirements and capture plant

implications. Any further onsite or off-site processing must be defined.

Undertake Feasibility analysis of fuel impacts on capture plant and overall CCS process. Consider requirements for power purchase agreements in relation to fuel. Note method of fuel transport and what products (waste or other) are likely to be generated or handled.

Negotiate and finalise all fuel supply contracts appropriate for the power plant (coal / gas / distillate fuel / biomass), ready for execution. Note the method of fuel transport and what products (waste or other) are likely to be generated or handled.

Execute fuel / consumable Contracts (for new build power station only).

Execute ongoing fuel / consumable Contracts

Terminate fuel / consumable Contracts

(3)

(including capture)

technologies and most likely options. Facility description and supporting design criteria, design basis and engineering deliverables to “block diagram” definition. Identify impacts of capture plant options on power plant, ensure technology work stream looks an optimal design option for concept stage. Initial process risk

assessment and mitigation strategies identified for potential and alternative core technologies.

process flow mapping (PFD level) of selected options, mass balance, equipment

requirements, ramp rate, capture plant integration, external interfaces and end to end design basis. Rank and select preferred options for FEED

studies, designing and costing the optimal power plant configuration to a completed point such that no material variations are required following Financial Investment Decision (FID) General site specific specifications to provide the basis of work to be conducted at the power plant (applicable to brown field site)

Produce Power plant & Capture Plant FEED deliverables

plant and capture plant.

Complete the detailed design for building the power plant with carbon capture asset including:

• Updated basis of design • P&ID Development • Equipment PDS’s • Civil Design • Structural / Architectural Design • HVAC

• Fire Detection and Protection Design • Piping Layout, Materials,

Stress and Supporting Design

• Fully functional 3D model with integrated plant engineering and clash modelling functionality. • Power Distribution System

Design

• Cable Routing Design • Grounding Design • Instrumentation Design • DCS Hardware and

Software Design

asset to comply with legislative regulatory changes & Best Available Techniques

to achieved required decommissioned state (safely, on time, on budget and to scope & quality) Remediate asset site to required condition

CO2 Product High level analysis the impacts of capture

technology on flue gas stream and the resulting composition (specification) of CO2 produced. Any further onsite or off-site processing must be defined.

Feasibility analysis on plant equipment selection and O&M. Feasibility analysis of CO2 composition (product specification) from capture plant selection on transport and storage costs and project implementation. Resulting impacts on transport (pipeline) design and specific impacts on storage dependent on geological requirements of selected site. Note what products (waste or other) are likely to be generated and handled.

Undertake Front End Engineering Design (FEED) studies, designing and costing the optimal compression / dehydration process

configuration to a completed point such that no material variations are required following Financial Investment Decision (FID). Note method of CO2 transport, and what products (waste or other) are likely to be generated or handled. Define CO2 product specification. Produce Compression & Dehydration Plant FEED deliverables

Negotiate CO2 reuse contracts, ready for

execution (if applicable) Produce FEED close out report

Complete the detailed design for building the CO2 compression and dehydration asset including:

• Updated basis of design • P&ID Development • Equipment PDS’s • Civil Design • Structural / Architectural Design • HVAC

• Fire Detection and Protection Design • Piping Layout, Materials,

Stress and Supporting Design

• Fully functional 3D model with integrated plant engineering and clash modelling functionality. • Power Distribution System

Design

• Cable Routing Design • Grounding Design • Instrumentation Design • DCS Hardware and

Software Design •

Modify the capture asset to comply with legislative regulatory changes & Best Available Techniques

Asset deconstruction to achieved required decommissioned state (safely, on time, on budget and to scope & quality) Remediate asset site to required condition

(4)

requirements for associated capture plant options (i.e. power, steam, land availability, other ancillaries)

Identification of potential constraints and the mitigation / costs.

feasibility deliverables required. Describe all criteria for the infrastructure for all the various options.

Agreement with network operator, ready for execution

Produce HV connection FEED deliverables

Produce Fuel Infrastructure Connection FEED deliverables

Water abstraction.

CO2 transportation

Describe all criteria for all required infrastructure.

requirements to enable the execution of the project. Let and manage any sub/contracts in a timely manor in order to achieve these requirements and avoid any delay to the project schedule.

to comply with legislative regulatory changes & Best Available Techniques

infrastructure and corridors to post-closure condition.

Project Delivery Initial high level implementation plan approaches to be defined, including manpower requirements, team disciplines required, draft deliverables scoped. Outline potential approaches to project delivery (i.e. EPC, EPCM, LSTK) that will form the proposed basis for implementing the project.

Select appropriate option for project delivery – linking into project development approach. Clearly scope out the phase gate approach to project implementation plan (PID) through the different cycles of the delivery and FEED contract to O&M. Describe what alternative strategies have been considered and the recommended delivery option.

Develop and manage a fully resourced and cost loaded FEED programme, optimise

implementation programme

Describe the project delivery status, and describe what strategies are recommended. Issue specification, and undertake tender negotiations with capture equipment suppliers and construction contractors. Outline status of significant procurement negotiations.

Negotiate and finalise contractual

arrangements with transport and storage partners (i.e. establish joint venture or similar contractual arrangement).

Develop procedures for interfaces between project partners.

Finalise project organisation structure for Execute Stage

Develop detailed site development plan

identifying activities and timing required for site enabling works.

Execute Capture Plant contract Build organisation to manage the execution of the Capture Plant Asset and deliver project governance, assurance and project controls.

Development and management of scope, schedule, budget,

performance, risk and expectations.

Manage a fully resourced and cost loaded execution programme covering project management / governance, engineering, procurement, manufacturing, construction, commissioning and acceptance testing. The

programme shall be fully logic linked to show the timing of all activities and to provide a comprehensive critical path. Order equipment, manufacture, FAT and delivery in line with the project programme requirements Place and manage Major Sub Contracts in line with project programme requirements

Build the Capture asset (safely, on time, on budget and to scope & quality)

Commission the Capture asset to operating state

Performance Testing

Execute Capture Plant contract for

modification to comply with legislative

regulatory changes & Best Available Techniques

Asset deconstruction to achieved required decommissioned state (safely, on time, on budget and to scope & quality) Remediate asset site to required condition

(5)

Capital / Operating Costs

Identify initial cost ranges for Capex plant equipment for potential technology selections, installation costs (+/- 30-35%), Opex for plant including power and ancillaries (+/-15-20%)

Study of equipment list options relating to cost variations and ranges, development of Capex cost model and initial engagement with major suppliers to improve cost estimation (+/- 20-25%). Further analysis of capture plant design on Opex (+/- 10-15%) prior to full cost modelling market analysis at ‘Define’ stage

Estimate order of magnitude costs of the capture plant (both capital (+/-10-15% accuracy) and operating (+/-5-10% accuracy))

Manage capital expenditure and project manpower budgets and optimise operating and

maintenance budgets. Finalise long term service agreement contracts with OEM’s.

Manage capital expenditure and project manpower budgets and optimise operating and maintenance budgets. Manage capital expenditure and project manpower decommissioning budgets.

Operations General assessment of effect of capture technology selection on power plant operations, efficiency, commissioning, start up, operation and CO2 transfer. Outline possible methods of establishing/increasing operations capability.

For the various options investigated provide descriptions of the organisation structure and strategy, industrial relations, employee relations strategy, and business start-up plan. Consider deliverables required from selected operational process at Feasibility/FEED stage.

Build organisation to commission and manage power and capture plant assets (recruitment of staff & negotiate long-term maintenance

agreements). For the selected option investigated provide descriptions of the organisation structure and strategy, industrial relations, employee relations strategy, and business start-up plan.

Develop the organisational structure and strategy and build organisation to commission and manage assets (recruitment of staff & negotiate long-term maintenance agreements)

Develop Asset Operation & Maintenance Procedures

Develop operations start up plan including industrial relations and employee relations strategy Handover to Operations and implement start up plan

Ramp-up operation of the capture asset to full performance

Operate capture asset to achieve required performance Maintenance of capture asset to achieve design life & performance

Control and manage plant modifications to achieve required performance Modify and operate the capture asset to realise identified opportunities

Operation of asset ceased

Management of post-closure asset (as required)

Revenue and Trading

Linking into financial analysis outline high level commercial forecasts for plant scale and energy price, impact of capture technology selections and associated carbon price mitigation depending on regulatory framework.

Undertake feasibility cash-flow analysis and sensitivity analysis to select most appropriate power plant & capture plant implementation considering information from conceptual stage and impact of any Clean Development Mechanism. Include the sale of power, sale of other by products, cost of waste disposal, carbon trading all of which is to include a revenue analysis and forecast.

Negotiate and finalise Power Purchase Agreement, ready for execution

Negotiate and finalise emissions trading strategy, ready for execution

Finalise forecast load plan (interface with financial model), identifying base-load, part load operating regimes, and outage schedules. Include the sale of power, sale of other by products, cost of waste disposal, carbon trading all of which is to include a revenue analysis and forecast.

Execute Power Purchase

Agreement and emissions trading strategy.

Manage Power Purchase Agreement and emissions trading strategy. Terminate Power Purchase Agreement and emissions trading strategy. Management Systems

Outline management systems and proposed organisational responsibility structure. Explain how the capture management will integrate with both the proposed transport and storage structure to ensure effective implementation of an overall CCS process. Including RACI level description of key project leads and contractors

Outline how the management system will operate in the project execution and

operation phases of the CCS project lifecycle. Identify any specific requirements to be further considered at the Feasibility/FEED stage and which (ISO) quality system the structure will be operating under.

For the selected option describe the Information Management Plan that is proposed to address the Execution and Operation phases.

Finalise partner agreements and have arrangements in place to create necessary investment vehicles ready for execution following FID.

Implement the Information Management Plan that is proposed to address the Operation phase.

Modify the Information Management Plan for the Operation phase.

Develop and implement the Information Management Plan for the Closure phase.

Ownership and Legal

Outline ownership and legal systems to be implemented for all project facets

Describe the framework for the ownership and legal systems for all facets of the project, including implementing any pre-feasibility legal contractual requirements between project team, sub-contractors, and partners

Describe the framework for the ownership and legal systems for all facets of the project.

Implement the framework for the ownership and legal systems

Modify the framework for the ownership and legal systems.

Modify the framework for the ownership and legal systems for the Closure phase.

(6)

IP Management Outline specific IP ownership for capture plant technologies under consideration. Identify any implications for project delivery

Map IP for specific parts of selected carbon capture plant development (i.e. if novel amine mixing process or membrane selection technology process). Ensure black box IP outlined to key development partners at project start up stage and cover in ownership/legal section.

Negotiate and finalise intellectual property rights of capture technology.

Develop procedures for secure management of IP information

Implement procedures for secure management of IP information

Modify procedures for secure management of IP information.

Modify procedures for secure

management of IP information for the Closure phase.

Financial Analysis Undertake high level financial analysis to outline project costs and commercial benefits of operation over plant lifetime. No sensitivity analysis for individual parameters. Potential up and downside cases around base case to demonstrate range of financial outcomes possible.

At Feasibility stage outline financial analysis in line with Capex and Revenue sections above. Simple form financial analysis, basis, methodology, key indicators and outcomes, describing range of possible outcomes. Describe sensitivity of financial outcomes to different parameters.

Where necessary need to understand the tax situation and potential risk sharing with partners / subs etc to secure the funding for the FEED.

Finalise discounted cash-flow model based on Total Plant Cost (TPC) and Total Capital Requirement (TCR), to calculate necessary parameters to make Financial Investment Decision.

• Net Present Value • Internal Rate of Return • Levelised Cost of Electricity • Operating & Maintenance Costs Describe range of possible outcomes. Describe sensitivity of financial outcomes to different parameters.

Make Final Investment Decision on Power Plant & Capture Plant

Optimise financial model in line with actual capital cost

information and operating / maintenance forecasts.

Need to update financial model with observed degradation rates, availability, reliability etc. Periodic / annual updates required. Update financial analysis for periodic changes in legislation affecting

decommissioning costs.

Risk Discussion of varying risks around possible project options. Risk management

structure to be implemented which considers initial risk ranking requirements through the project lifecycles. Should clearly link to initial site option selection and HSE study. Risk management process structured to provide guidance during Evaluate phase for key areas of study (including trade-off studies).

Identify perceived regulatory risks High level risk identification, scoping and where possible initial quantification. These are to be captured in a Project Risk

Register.

Feasibility study identifying and clearly ranking risks to projects such as operational, technical, and commercial. Identify potential mitigation strategies for varying design options and development of key risk register and ongoing management strategy to be implemented. Define any potential fatal flaws or extreme risks, with detailed responses to extreme and high risks. Include a summary of the Risk Register.

Where able, the financial / cost impact of the risks should be stated.

Develop Risk register that; utilises proponents Risk Management System, ranks all identified risks, defines all potential fatal flaws or extreme risks, and identifies mitigation actions generally, and which specifically has detailed mitigation responses to extreme or high risks. Define any potential fatal flaws. Include a summary of the Risk Register.

Development and management of the project risk register identifying and ranking all risks. Mitigation actions and response plans should be included along with risk post mitigation ranking.

The design risk register (identified in H&S section above) should be integrated into the overall project risk register.

Consider utilising advanced risk analysis tools to provide a comprehensive means of

determining confidence levels for project success through advanced Monte Carlo based cost and schedule analytics. This will give the means to provide an objective view of required contingency to account for cost and schedule uncertainty and also generate and analyse the cost effectiveness of risk response plans.

Management of the risk register identifying and ranking all risks. Mitigation actions and response plans should be included along with risk post mitigation ranking.

Management of the risk register

identifying and ranking all risks. Mitigation actions and response plans should be included along with risk post mitigation ranking.

(7)

Funding Outline of potential funding sources both commercial and via public sector

demonstration funding. Plus outline of options for project to meet funding requirements – sourcing via private equity partner options. Preliminary statement as to what extent and who could guarantee any of the project outcomes.

Identification of actual or potential funding partners.

Engagement with funding stakeholders via commercial work stream and any business plan development required to secure funding for Feasibility/FEED or full scale project implementation. Describe project ownership details and how the project is to be funded, list what guarantees are anticipated and pecuniary and statutory obligations this will realise.

Project to undergo financial due diligence as required

Describe project ownership details and how the project is to be funded, list what guarantees are anticipated and pecuniary and statutory

obligations this will realise.

Negotiate funding agreements with investment partners, ready for execution

Negotiate support funding agreement with government / NGO (if applicable), ready for execution

Establish project accounts / balance sheet

Operate project expenditure according to funding plan. Ongoing identification and management of financing / funding risks.

Maintain project accounts and operate within the annual operating budget.

n/a

Future Work Plan Description of developed scope statement and objectives for Feasibility study; state organisation and resources needed; outline cost estimate and time to conduct.

Clarify future work plan specifics in line with project development approach outlined above for Feasibility/FEED, listing all cost and schedule implications.

Schedule for the FEED Phase should be to level 3 detail.

Future Work Plan report for undertaking Execute Stage with:

• Scope statement and objectives

• Organisation and resources to complete • Cost estimate to complete

• Schedule to complete

Develop operating plan from business case and out-turn project performance.

Create and maintain annual operating plans for the project.

n/a

Status of Studies Include description of key learning

outcomes at concept stage around capture plan options and impacts

• Achieved progress and extent of evaluation achieved

• Significant issues / areas progress not achieved

• Any activities planned for Identify phase until next decision point

Identify specific requirements of pre-feasibility studies prior to Feasibility/FEED commencement in a phase gate approach to the project implementation. Advise what work/research is necessary to complete the study.

Commentary on overall status of study, proposed option; describe status of study. Advise what work / research necessary to complete study or approvals necessary to commence on-site works. Describe independent peer reviews undertaken and recommendations to date, also list scheduled peer review itinerary during construction phase.

Construction / execution phase learnings to be collated. Operational learning to be collated. Decommissioning learning to be collated.

References

Related documents

Using course web site report data, student grades, and redesigned course evaluations, we aimed to determine whether these modifications have led to increased interaction,

locations. Kodak Representative to provide asbestos surveys for demolition and renovation work. Kodak Representative to complete Appendix A, Chemical/Material/

import unit values inclusive of tariffs (import values divided by input quantities) for each tariff wave and for unaffected countries and products; proportional changes for each

In addition, approved B&B operators have been facing increasing competition from a reported growth in the number of homes without official approval offering guest

 It provides flight crews with Runway Visual Range (RVR) information for aerodromes during periods of low visibility  D-HZWX (Datalink – Hazardous Weather) Service.  It

A non-profit organization established to advocate open standards in cloud computing, announced its official launch at the OSCON 2011 Open Source Convention.. Its

The history of international human rights activism reveals that, historically, much of this work has involved transnational activist alliances working to define and

Innovation with quality assurance: online curriculum development for the University of New England‘s multi-institutional collaborative programs in German at UNE, James Cook