Transportation Improvement Program (TIP) Amendment

FY 2021/22- 2025/26

Downtown Interchange Safety & Operations Adjustments, Westshore Interchange Reconstruction Preliminary Phase, and

Traffic Congestion Management Technology Technical Advisory Committee October 2021

p l a n h i l l s b o r o u g h . o r g

(2)

• Aesthetics planned as part of the DTI improvements include

• Cut back slopes with gravity walls and widened sidewalks at Palm Avenue, 14th Street and 15th Street

• Upgraded lighting at all underpasses

• Aesthetics along 14thStreet and 15th Street to match existing

• Landscaping and lighting along the shared use path

• Contractor will design landscaping for areas identified for potential landscape opportunities

Aesthetics

Cut back slope with gravity wall example

(3)

Aesthetics – Lighting

• New roadway lighting will match the existing poles

• Existing lighting that will remain will be upgraded to LED

• Underdeck lighting will be upgraded to LED wall

packs

(4)

• New LED lighting will be installed on the widened bridges over 14th and 15th

• Bridge beam lights will be upgraded to LED lighting

• Ybor five-globe lights along 14th and 15th lights will be replaced with patented

versions used within the historic district

• New five-globe lights will be installed along the south side of Nebraska Avenue, the southside of 14th Street and the southside of 15th Street

• Shared use path (SUP) solar lights will be installed

Aesthetics – Specialty Lighting

(5)

Aesthetics – Signing

• Monotube structure signs

• Ground mount single post signs

(6)

• Noise barriers will aesthetically match the existing noise barriers

• New noise barriers will replace the existing noise barriers and be 8’ shoulder mounted

• New exit ramp location to 14th/15th Streets will have an 8’ barrier

Aesthetics – Noise Barrier and Visual Barrier

(7)

Brick X Patterned Texture

Aesthetics – MSE Wall Patterns

Shell /Florida Native Limestone Texture

MSE wall patterns will match the current pattern at the existing locations

(8)

• Mesh/Wire Welded Fencing will be installed at grade

• Black Vinyl-Coated Chain Link Fencing will be installed on slopes

Aesthetics – Fencing

Mesh Wire Welded Fencing Black Vinyl-Coated Chain Link Fencing

(9)

• Patterned Pavement Crosswalks

• Hex Patterned Stamped Concrete Crosswalks

• Brick Intersections

• Hex Paver Sidewalks

• Brick Sidewalks

Aesthetics – Specialty Pavement

(10)

Thank You

(11)

Transportation Improvement Program (TIP) Amendment

FY 2021/22- 2025/26

Downtown Interchange Safety & Operations Adjustments, Westshore Interchange Reconstruction Preliminary Phase, and

Traffic Congestion Management Technology Technical Advisory Committee October 2021

p l a n h i l l s b o r o u g h . o r g

(12)

Amendments

p l a n h i l l s b o r o u g h . o r g

• 14 Amendments requested by Florida Department of Transportation (FDOT) to add funds to the year 2022

Downtown Interchange Safety

& Operations Adjustments

3 Amendments ~$154 million

Westshore Interchange Reconstruction

Preliminary Phase

5 Amendments ~$80 million

Traffic Congestion Management Technology

6 Amendments ~$24 million

(13)

Downtown Interchange Safety &

Operations Adjustments

p l a n h i l l s b o r o u g h . o r g

(14)

Stacking along I-275 SB to exit to flyover ramp to EB I-4

I-275/I-4 Interchange

Existing Conditions

Existing single-lane flyover ramp to EB I-4

(15)

I-275/I-4 Interchange

2. Westbound I-4 to Southbound I-275 (FPID 445056-2)

• Widen 2-lane ramp from I-4 to SB I-275 to 3 lanes

• Widen shoulders on SB I-275 from Palm Ave. to Jefferson St.

• Downtown exit ramp shifted to the west

1. Westbound I-4 to Northbound I-275 (FPID 445056-1)

• Widen existing 1 lane ramp from I-4 to NB I-275 to 2 lanes

• Additional merge lanes on NB I-275 from the interchange to the Dr. MLK Jr., Blvd exit

3. Southbound I-275 to Eastbound I-4 (FPID 445057-1)

• Widen existing 1 lane flyover ramp to EB I-4 to 2 lanes

• Modify exit ramps to Ybor City/East Tampa from 21st/22nd Streets to 14th/15th Streets

• Widen EB I-4 existing frontage road to 2 lanes

Safety and Operational Improvements

Safety and operational improvements to the I-275/I-4 interchange

(16)

p l a n h i l l s b o r o u g h . o r g

Downtown Interchange Safety & Operations Adjustments

• “Quick Fix” Safety and Operations Adjustments will:

• Reduce lane weaving and speeding

• Reduce congestion in lining up for exit

• Improve access to exits to the

local network

(17)

I-275/I-4 Interchange

Safety and Operational Improvements

DTI Safety & Operational Improvements Benefits

• 25% crash reduction on I-275

• 9% crash reduction on I-4

• 48% crash reduction for serious injury crashes and 47% crash reduction for fatal injury crashes along I-275

• Reduce multiple-vehicle crashes along I-275 by 30% and along I-4 by 10%

• 14% reduction of traffic on Palm Avenue between 21st/22nd Streets and 14th/15th Streets

(18)

Trail Network

(19)

14

th

Street Improvements

14th Street from Columbus Drive to 14th Avenue

• Add speed limit signs

• Add curb bulb-outs at side street intersections

• Reduce lane widths

• Add high emphasis crosswalk markings

14th Street from 14th Avenue to 13th Avenue

• Add new traffic signals a 14th Avenue and 13th Avenue

• Add high emphasis crosswalk markings

• Reduce lane widths

• Add SB left turn lane to EB 13th Avenue

(20)

14

th

and 15

th

Street Improvements

15th Street Typical Section 14th Street Typical Section

FDOT will continue working with the City of Tampa on the roadway typical section for 14thStreet

(21)
(22)
(23)
(24)
(25)

Westshore Interchange

Reconstruction Preliminary Phase

p l a n h i l l s b o r o u g h . o r g

(26)

WB SR 60 from N of Spruce Street to Memorial Highway

FPID 447107-1

Boy Scout Blvd at Lois Ave Right Turn Lane Addition

FPID 447976-4

SR 60/Kennedy Blvd at SR 60/Memorial Hwy Turn Lane Improvements

FPID 447976-2 Cypress St at LaSalle St

Intersection Reconfiguration FPID 447614-1

Causeway Seawall, Trail and SB I-275 FPID 447534-1

Tampa’s Westshore Interchange

Early Works Projects

(27)

Westbound SR 60 Veteran’s Connection

• The project will construct one lane along

westbound SR 60 from the George Bean Pkwy ramp to the Courtney Campbell Causeway

• A new westbound SR 60 braided ramp connection will provide access from the

general use lanes to Independence Parkway

• Improvements will accommodate the future construction of general-purpose lanes

along westbound SR 60 with connections to Courtney Campbell Causeway and the Veterans Expressway

• The improvements will help facilitate traffic movement during interstate construction

WB SR 60 from N of Spruce Street to Memorial Highway

FPID 447107-1

(28)

p l a n h i l l s b o r o u g h . o r g

(29)

• This project will extend a new seawall and construct an

adjacent shared use path along the north side of the I-275

causeway

• Improvements include paving SB I-275 within project area

Causeway Seawall, Trail and SB I-275

Causeway Seawall, Trail and SB I-275 FPID 447534-1

(30)

p l a n h i l l s b o r o u g h . o r g

(31)

• This project will widen and realign the Cypress Street and W LaSalle Street intersection

• The improvement will enhance traffic operations, mobility and

safety during interstate construction

Cypress Street at LaSalle Street Intersection

Cypress St at LaSalle St Intersection Reconfiguration

FPID 447614-1

(32)

p l a n h i l l s b o r o u g h . o r g

(33)

SR 60/Kennedy Blvd at SR 60/Memorial Hwy Turn Lane Improvements

FPID 447976-2

Kennedy Boulevard at Memorial Highway

• The project will add a third right turn lane from

eastbound Kennedy Boulevard to eastbound SR 60/Kennedy Boulevard

• Improvements will also add a third left turn lane from

westbound SR60/Kennedy Boulevard to westbound Kennedy Boulevard

• This improvement will help to facilitate traffic and mobility during interstate construction

(34)

p l a n h i l l s b o r o u g h . o r g

(35)

• Project will add a right turn lane from eastbound Boy Scout Boulevard to southbound Lois Avenue

• This improvement will help to facilitate traffic and mobility during interstate construction

Boy Scout Boulevard at Lois Avenue

Boy Scout Blvd at Lois Ave Right Turn Lane Addition

FPID 447976-4

(36)

p l a n h i l l s b o r o u g h . o r g

(37)

Traffic Congestion Management Technology/

Integrated Corridor Management (ICM)

p l a n h i l l s b o r o u g h . o r g

(38)

Tampa’s Westshore Interchange ICM Projects

Integrated Corridor Management (ICM) projects:

• Will allow FDOT to actively manage traffic flow based on near real time traffic conditions

• Will maintain traffic along diversion routes during interstate construction

• Will upgrade technology along key corridors to reduce delays, improve travel time reliability, and enhance safety

US 41 (Nebraska Ave)

FPID 443444-3 US 41(Tampa St/Florida Ave)

FPID 443444-2 Hillsborough Ave

FPID 443445-4

Boy Scout Blvd FPID 443445-5

Dr. MLK Jr Blvd FPID 443445-3

Kennedy Blvd FPID 443445-2

(39)

Traffic Congestion Management Technology

p l a n h i l l s b o r o u g h . o r g

Known as Integrated Corridor Management (ICM)

• Goals

• Make work zones safer

• Reduce delay among key corridors

• Improve travel time reliability through advanced live-monitoring technology

• What are ICM Systems?

• Signal Upgrades

• New controllers

• Bluetooth sensors

• Roadside units

• Advanced detection

• Dynamic message signs

• CCTV

• Additional fiber-optic connections

(40)
(41)

p l a n h i l l s b o r o u g h . o r g

(42)
(43)
(44)

p l a n h i l l s b o r o u g h . o r g

(45)

p l a n h i l l s b o r o u g h . o r g

(46)

Public Participation

p l a n h i l l s b o r o u g h . o r g

(47)

p l a n h i l l s b o r o u g h . o r g

Preliminary Survey Results through June 30th, 2019

✓ Highest star-rating overall

✓ Supported or unopposed by most zip codes

Low Star Rating High Star Rating

✓ 5200+ responses to

“It’s TIME survey!

(48)

Community Input Has Led to FDOT Action

2017

2018

2019

Launched Tampa Bay Next

Community & Neighborhood Events

Hillsborough MPO TIP Hearing – June 13, 2017 Community Working Groups

Citizens Transportation Academy

Neighborhood & Stakeholder Presentations SEIS Public Workshop #1

Community & Neighborhood Events Community Working Groups

Hillsborough MPO TIP Hearing – June 12, 2018 Neighborhood & Stakeholder Presentations

Community & Neighborhood Events

Neighborhood & Stakeholder Presentations SEIS Public Workshop #2

Hillsborough MPO TIP Hearing – June 11, 2019 I-275/I-4 Operational Improvements

2020

Community & Neighborhood Events

Neighborhood & Stakeholder Presentations SEIS Public Hearing

Hillsborough MPO TIP Hearing – June 30, 2020 2021 Community & Neighborhood Events

Neighborhood & Stakeholder Presentations

Hillsborough MPO Board Approved DTI ROW TIP Amendment – May 12, 2021 Hillsborough MPO TIP Hearing – June 9, 2021

(49)

Public Outreach for the TIP Amendment

p l a n h i l l s b o r o u g h . o r g

• Four Outreach Efforts:

• Press Release

• 30 Media Outlets

• 100+ Neighborhood Associations and Community Groups

• Social Media Outreach

• Signs Posted

• Webpage for more information

(50)

Public Outreach for the TIP Amendment

p l a n h i l l s b o r o u g h . o r g

(51)

p l a n h i l l s b o r o u g h . o r g

Clerical Corrections

• Amendment 13

• Change from third left turn lane from eastbound Kennedy Boulevard to eastbound SR 60/Kennedy Boulevard to third right turn lane

• Amendment 19

• Changes in west project limits from I-275 to Veterans Expressway

(52)

Approve the Amendments to the FY

2021/22 TIP and recommend approval to the TPO Board

Recommended Action…

p l a n h i l l s b o r o u g h . o r g

(53)

Mary Lou Godfrey, FDOT:

[email protected] Connor MacDonald, TPO:

[email protected]

Contact Information

p l a n h i l l s b o r o u g h . o r g

(54)

Comments/ Questions?

p l a n h i l l s b o r o u g h . o r g

References

Related documents

 Install a three phase traffic signal on East Genesee Street at the proposed main site driveway including a protected/permitted eastbound left turn phase with a southbound right

Traffic Impact: Florida Power and Light Improvements in Oakland Park: one eastbound lane and one westbound lane of W Oakland Park Boulevard from NW 31st Avenue to State Highway 9

Every second year the Hidalgo County MPO in coordination with the Texas Department of Transportation and other interested parties prepares a Metropolitan Transportation

Staff is seeking a recommendation from the Technical Committee to the Board of Directors to approve an amendment to the 2020-2024 Transportation Improvement Program (TIP)..

Motorists traveling westbound on Gateway Boulevard will be detoured via Congress Avenue and the I-95 northbound entrance ramp from Hypoluxo Road.. Eastbound Gateway Boulevard

The Florida Department of Transportation (FDOT) and MPOs must coordinate when selecting Highway Safety measures (PM1), Pavement and Bridge Condition measures (PM2), and System

The City of Virginia Beach requests an amendment to the FY 2021-2024 HRTPO Transportation Improvement Program (TIP) to both amend and expand the scope of UPC 108955 Corridor

Percent of NHS Bridges in Good ≥ 60% NHS in Good condition as a percentage of total Condition NHS bridge deck are Percent of NHS Bridges in Poor ≤ 10% NHS in Poor Condition condition