Prepared by: Karin Nilsson
14 July 2009
Prepared for:
Eraring Energy
Document Number: ERAPOW\12-B177
Revision B
PO Box 248 Berowra Heights NSW 2082 Telephone: [02] 9985 1056 Facsimile: [02] 9427 7851 Email: [email protected]HAZOP STUDY REPORT OF THE
TURBINE HYDRAULIC POWER UNIT,
BOILER UPGRADE AND LOW NO
X
BURNERS AS PART OF THE ERARING
ENERGY POWER STATION UPGRADE
PROJECT
Acknowledgment
The author would like to thank the HAZOP review team and in particular Ian
O’Brian, Phil Fenney, Steve Shawcross, Graeme Hankin and Frank Mieszala
for organising the HAZOP Studies and providing input and reviews of minutes
and report.
Disclaimer
This report was prepared by Planager Pty Ltd (Planager) as an account of work
for Eraring Energy. The material in it reflects Planager's best judgement in the
light of the information available to it at the time of preparation. However, as
Planager cannot control the conditions under which this report may be used,
Planager and its related corporations will not be responsible for damages of any
nature resulting from use of or reliance upon this report. Planager's
responsibility for advice given is subject to the terms of engagement with
Eraring Energy.
HAZOP Study Report of the Turbine Hydraulic Power
Unit, Boiler Upgrade and Low NOx Burners as Part of
the Eraring Energy Power Station Upgrade Project
Rev Date Description Prepared By Authorised By A 19/06/2009 Draft for Comment Karin Nilsson Frank Mieszala
C
ONTENTS
1
I
NTRODUCTION... 6
1.1
Background ... 6
1.2
Aim of This Report ... 6
1.3
Location of EPS ... 7
1.4
Project Description ... 7
1.5
Scope of HAZOP Study ... 7
1.5.1
Boiler Upgrade ... 8
1.5.2
Turbine Hydraulic Power Supply ... 8
1.5.3
Low NO
xBurners ... 8
2
M
ETHODOLOGY... 9
2.1
Introduction ... 9
2.2
Details of the HAZOP Study Procedure ... 9
2.3
HAZOP Study Guidewords ... 10
2.4
Risk Ranking Tools ... 12
3
R
ESULTS ANDR
ECOMMENDATIONS... 13
3.1
Presentation of Risk Results ... 13
3.2
Risk Levels of the Boilers Design ... 14
3.2.1
Level 4 Risks Boilers ... 14
3.2.2
Level 3 Risks Boilers ... 15
3.2.3
Level 2 and Level 1 Risks Boilers ... 18
3.3
Risk Levels of the Turbine Hydraulic Power Unit Design ... 18
3.3.1
Level 4 Risks Hydraulic Power Unit ... 18
3.3.2
Level 3 Risks Hydraulic Power Unit ... 18
3.4
Risk Levels of the Low NO
xBurner Design ... 19
3.4.1
Level 4 Risks Low NO
xBurners ... 19
3.4.2
Level 3 Risks Low NO
xBurners ... 19
3.4.3
Level 2 and Level Low NO
xBurners ... 19
3.5
Risk Profile of Plant Assuming HAZOP Recommendations in
Place ... 20
4
C
ONCLUSION... 21
5
R
EFERENCES... 222
L
IST OF
A
PPENDICES
Appendix 1 – HAZOP Study Minutes
Appendix 2 – Approval as HAZOP Leader
Appendix 3 – Eraring Energy Risk Tools
R
EPORT
PROJECT TITLE:
Power Station Upgrade Project
LOCATION:
Eraring Energy Power Station.
HAZOP MINUTES:
Appendix 1
HAZOP Leaders:
Karin Nilsson (DoP Approved)
Mark Wyburn (Eraring Energy, second
half
day
of
Boiler
HAZOP.
Methodology
used
and
outcome
reviewed by Karin Nilsson)
HAZOP SCOPE AND DATES FOR STUDY:
-
Boiler Upgrade
8 April and 5 May 2009 (1½ days)
-
Turbine Hydraulic Power Supply 23 March 2009 (one day)
-
Low NO
xBurners
22 April 2009 (one day)
RECORD OF ATTENDANCE
Name
Company
Position
Boiler Upgrade
Ian O’Brian
Eraring Energy
Project Manager, Boiler
Upgrade Project
Ray Ansell
Eraring Energy
Senior Tradesman
Chris Brucki
Eraring Energy
Boiler Team Leader and Asset
Management
Shaun Edwards
Eraring Energy
Project Change Manager
Gary Craig
Eraring Energy
Project Manager, CCP Project
Phil Fenney
Eraring Energy
Project Manager, Low NO
xBurners
Mark Wyburn (part
time)
Eraring Energy
Chemical Asset Team Leader
RECORD OF ATTENDANCE
Turbine Hydraulic Power Unit
Steve Shawcross
Eraring Energy
Project Manager Turbine
Upgrade Project
Graham Hankin
Eraring Energy
Turbine Asset
Phil McWilliam
PPI – DPPA Rep
Project Manager
Daniel McNally
Eraring Energy
E&I Technician
Keith Clark
Eraring Energy
Operator
Ian Dawson
Eraring Energy
Projects Engineer
Steve Wheeler
Eraring Energy
Operations Team Leader
Steve Gambrill (part
time)
Eraring Energy
Environment
Gemma Keith
Eraring Energy
Secretarial Support
Low NO
xBurner
Phil Fenney
Eraring Energy
Project Manager, Low NO
xBurners
Steve Wheeler
Eraring Energy
Operations Engineer
Chris Brucki
Eraring Energy
Boiler Team Leader and Asset
Management
John Harris
Eraring Energy
Plant Owner
Tarkel Larson
Siemens
Field Services Manager
Kenneth Tichy
Siemens
Project Manager, Low NO
xBurners
1
I
NTRODUCTION
1.1 B
ACKGROUND
The
Energy Directions Green Paper
(Ref 1) prepared by the NSW Government
identified that if the current trend of increased electricity demand continues,
additional generation capacity or demand management would be required by
2010.
Eraring Energy (EE), one of three State-Owned Corporations that manages a
diverse set of electricity-generating assets located throughout NSW operates a
coal-fired power station (at Eraring), known as Eraring Power Station (EPS).
EE has put forward a proposal to undertake capacity increase and performance
improvements to the existing EPS to increase the capacity of each of the four
660 MW generating units (which are capable of generating at an equivalent
rating of around 700 MW) to enable the units to operate up to a maximum
continuous rating of 750 MW.
EE has obtained Project Approval, subject to a number of Consent Conditions,
for the capacity increase project under section 75J of the EP&A Act in
accordance with the provisions of Part 3A of the EP&A Act. The Minister for
Planning is the approval authority for the application.
One of these Consent Conditions requires a HAZOP Study to be undertaken for
the proposed development, as follows:
...a Hazard and Operability Study (HAZOP) for the power station
upgrade, chaired by an independent, qualified person or team. The
independent person or team shall be approved by the
Director-General. The Study shall be carried out in accordance with the
Department’s publication Hazardous Industry Planning Advisory
Paper No. 8
– HAZOP report. If the Proponent intends to defer the
implementation of a recommendation, justification must be included.
1.2 A
IM OF
T
HIS
R
EPORT
Eraring Energy has commissioned Planager Pty Ltd to lead a multidisciplinary
team through the
HAZOP Study
of a number of sub-projects which form part of
the EPS’ Upgrade Project.
Planager’s principal risk engineer, Karin Nilsson, has received approval from
the Department of Planning to lead the HAZOP Study. The letter of approval for
Karin Nilsson as HAZOP study leader is included in Appendix 2.
The aim of the HAZOP study is to review a design of a technological system to
identify hazards or significant obstacles to operability, which could arise,
particularly through deviations from the design intent.
1.3 L
OCATION OF
EPS
EPS’s site comprises approximately 1,200 hectares of land and is located in a
natural dip on the western shore of Lake Macquarie. The site falls within the
Lake Macquarie Local Government Area, near the township of Dora Creek,
within the Morisset Planning District. The power station and associated
infrastructure covers a footprint of approximately 150 hectares, with the
remaining area including the CCP management facility, water canals, and
ancillary power station facilities.
The surrounds of the EPS consist largely of natural vegetated areas with
development dedicated primarily to the extractive industries, such as coal
mining. Some semi-rural areas exist to the south on the shores of Lake
Macquarie.
1.4 P
ROJECT
D
ESCRIPTION
The key objective of the project is to upgrade the infrastructure at EPS. By
replacing existing aging components of plant and equipment within the EPS
operating units, EE would be able to maintain operational capacity and the
replacement/renewal program would enable improved efficiency of operations
and the environmental and safety performance of EPS.
The upgrade would allow the four existing 660 MW generating units to operate
at a MCR of up to 750MW. This improved performance would be used to meet
the increasing demands of the NEM, particularly during peak periods.
Aged components of the Boiler and Turbine Generating Plant would be
refurbished to achieve a MCR of 750 MW generated at a Power Factor of 0.9 at
rated conditions (Generator 833 MVA rating). This would include:
“Steam Path Upgrade” of high pressure, intermediate pressure and low
pressure stages of the turbine;
Upgrade of generator;
Upgrade of generator transformer cooling system;
Additional tubing inside boiler;
Replacement of 28 boiler burners with low NOx burners; and
Other miscellaneous work.
1.5 S
COPE OF
HAZOP
S
TUDY
EE has identified the following three operations which would benefit from a
HAZOP Study:
Boiler Upgrade
Turbine Hydraulic Power Supply
Low NO
xBurners
The HAZOP study sessions were all carried out
By Difference
with the existing
plant operation, i.e. the HAZOP focussed on the implication of the changes to
plants and processes which result from the proposed changes to boilers,
hydraulic unit and burners. As such, the HAZOP did not attempt to cover the
whole of the Power Station operation and design. The scope of each HAZOP
study is as follows:
1.5.1 Boiler Upgrade
Included:
The scope of the Boiler HAZOP includes the design and
operation of the actual boilers.
Excluded:
The scope excludes the new (Low NO
xBurners, see below),
including the burner management, flame stability and wind box.
1.5.2 Turbine Hydraulic Power Supply
Included:
The scope includes the design and operation of pumps, fans,
piping, valving, instrumentation etc. which form part of the hydraulic
power unit.
Excluded:
The scope excludes the control system and the main oil
pump and the auxiliary pump. The Emergency Trip Device is also
outside the scope of this HAZOP. Further, outside the scope is the
extractor relay dump valve operation, the Turbine protection and control
module, the mechanical steam path upgrade.
Note that at the time of the HAZOP the exact composition of the
hydraulic oil was not known (it was believed to be some type of
phosphate ester). The HAZOP team took into account that it could be
potentially hazardous to people handling the material. As such the
HAZOP of the turbine hydraulic power unit is regarded as a
Preliminary
HAZOP
and further engineering investigation will be required (whether it
be in the form of supplementary HAZOP studies or other risk
management techniques).
1.5.3 Low NO
xBurners
Included:
The scope of the Burner HAZOP included the new Low NO
xBurners, including burner management, flame stability and wind box.
2
M
ETHODOLOGY
2.1 I
NTRODUCTION
The HAZOP study is based on engineering line diagrams (P&ID's) and outline
operating procedures. The consequences and deviations are identified, the
existing safeguards are highlighted and, where necessary, appropriate
corrective actions initiated.
A HAZOP study is a form of design review which concentrates on how the plant
will cope with abnormal conditions, rather than on how it will perform under
normal conditions. The study comprises consideration of each process line and
vessel, examining for each the possible causes and consequences of a wide
range of process abnormalities. While some of the postulated abnormalities
may be inapplicable for a particular process line, they are all probed with the
objective of identifying any significant route to a process upset, operating
problem or hazardous incident. It is, in effect, a very thorough but mainly
qualitative approach.
HAZOP is the method recommended for identifying hazards and problems
which prevent efficient operation of a processing plant. It is a technique which
provides opportunities for people to think creatively and examine all possible
ways in which hazards or operating problems might arise. To reduce the
chance that something is missed it is done in a systematic way - each pipeline
and each type of hazard being considered in turn. The study is carried out by a
team so that they can stimulate each other and build on each other’s ideas.
The results of a HAZOP depend more upon the experience and attitudes of the
participants and on the leadership style adopted, than on the procedures
themselves. The participants were selected to provide the necessary
experience, knowledge, skills and authority to approve the actions decided
upon. The Study leader needs to be very experienced in HAZOP studies and
Hazard Analysis techniques and capable of performing as an independent and
unbiased leader. This person needs to be familiar with other related techniques
and to know when other techniques would be beneficial compared to the
HAZOP technique.
2.2 D
ETAILS OF THE
HAZOP
S
TUDY
P
ROCEDURE
The HAZOP study was conducted according to ICI's traditional HAZOP
methodology, corresponding to established engineering practices. The study of
each step in the operation of the plant followed the pattern outlined below:
A brief outline of the purpose of the step in the operation and of the lines
involved with the operation is provided by one of the team members (usually
by the designer). The lines are highlighted on the P&ID with dotted lines
The purpose, design features, operating conditions, fittings, etc, are
explained.
Any general questions about the lines are then answered.
The detailed "line by line" study commences at this point. The discussion
leader takes the group through a series of guide words set out in a book
(see Section 2.3). Each card has a guide word or prompt on it, such as
"FLOW - HIGH", which identifies a deviation from normal operating
conditions. This is used to prompt discussion of the possible effects of flow
at an undesirably slow speed, and of the possible causes. If in the opinion
of the meeting, the combination of the consequences and the likelihood of
occurrence are sufficient to warrant action, then the combination is regarded
as a "problem" and minuted as such. Potential incidents with severe
consequences where the team judges that the risk management techniques
already designed into the process are sufficient are also minuted in order to
provide a record of the safeguards to be installed. Further, if a particular
item was subject to discussions then it would be minuted to record the
outcomes of these discussions.
For major risk areas the need for action is assessed quantitatively. For less
important risks the need for action can be based on experience and
judgement. The person responsible for defining the corrective action is also
nominated.
It should always be remembered that the main aim of the meeting is to find
problems needing solution, rather than determine actual solutions. If the
group becomes tied down by trying to resolve a problem it is better to
continue the discussion at a later date and proceed with the study.
When each guide word requires no more consideration, the chairperson
turns that card down revealing the next guide word.
Discussion for each guide word is confined to the line marked, the vessels or
other major equipment at each end and any equipment such as pumps or
heat exchangers in between. Any changes agreed at the meeting are
minuted, and where possible, marked on the P&I diagram or layout with red
pen.
When all guide words have been covered, the line is fully highlighted
(instead of with a dotted line) to show that it has been covered, and the next
line is chosen.
When all the lines in a plant sub-section have been reviewed, additional
guide words are used for review (overview) of the P&ID as a whole (see
below).
2.3 HAZOP
S
TUDY
G
UIDEWORDS
The guidewords applicable for continuous operations were used for the most of
the designs under review. If the operation has critical sequencing conditions,
such as for the Low NO
xBurner project, then the continuous operation
guidewords were complemented with batch guidewords as listed below.
Line-By-Line Guidewords - Continuous Process
High Level / High Flow
Low Level / Low Flow
Zero Flow / Empty
Reverse Flow
High Pressure - Venting, relief rate
Low Pressure - Venting, relief rate
High Temperature
Low Temperature
Impurities - gaseous, liquid, solid
Change in concentration / Change in composition / Two phase flow /
Reactions
Testing - equipment / product
Plant Items - operable / maintainable
Instruments - sufficient for control / too many / correct location
Overview Guidewords
Toxicity
Commissioning
Start-up
Shutdown (isolation, purging)
Breakdown (including services failure)
Effluent
Fire and Explosion
Safety Equipment
Noise
Materials of Construction
Services required
Electrical: area classification / isolation / earthing
Quality and Consistency
Output - reliability and bottlenecks
Efficiency – losses
Simplicity
Line-By-Line Guidewords - Batch Process
Timing – start too early/late; stop too early/late
Flow High / Low
Level High / Low
Zero Flow / Empty
Reverse Flow
None
Density High / Low
Viscosity High / Low
Static
Effects on Existing Equipment
Concentration High / Low
Contamination / Extra Phase
Duration – Delayed / Omitted
Out of Sequence / Wrong Operation
Not Complete
Duplication
Testing - equipment / product
Plant Items - operable / maintainable
Instruments - sufficient for control / too many / correct location
Overview Guidewords
Operator Health
Environment
Electrical
Services
Materials of Construction
Non-routine Conditions - Start-up/ Shutdown / Maintenance / Cleaning /
Commissioning
Fire and Explosion
Safety Equipment
Quality and Consistency
Output - reliability and bottlenecks
Simplicity & Efficiency
2.4 R
ISK
R
ANKING
T
OOLS
The HAZOP Study was complemented with a formal risk ranking of each
scenario using Eraring Energy’s risk ranking tool (Ref 2) presented in Appendix
3. This is as per Eraring Energy’s requirements for risk reviews of their
projects.
3
R
ESULTS AND
R
ECOMMENDATIONS
3.1 P
RESENTATION OF
R
ISK
R
ESULTS
Items were recorded on the HAZOP Study Record Sheets, which may be seen
in Appendix 1. The 3.5 days HAZOP generated a total of 115 issues and
recommendations.
As per the methodology, entries were made on the record sheets as follows:
Where a hazard or an operational problem was recognised as requiring
further risk or operations controls;
Where the potential consequences of an incident were severe even
though the management of the risk considered acceptable.
Where a particular item was discussed in detail during the study and
hence required minuting to record the final outcome of these discussions.
HAZOPs are focussed on the engineering design of a particular plant or
equipment. Hence, trip, slip and fall type incidents were not recorded nor were
they discussed. These are better discussed in a Job Safety Assessment (or
similar) type forum.
The table in Appendix 1 shows the following columns:
Risk Number,
Guideword,
Causes,
Consequences
Controls in place (a listing of the controls currently in place and approved
as part of the present project),
Current risk rating (rating of the risk with the controls which are currently
in place or approved),
Mitigating actions (further risk reduction recommendations aiming to
reduce the risk to ALARP
1levels),
Residual risk rating (the risk rating of the scenario with the recommended
mitigating actions (above) in place,
Below is provided a listing of Levels 4 and 4 risk scenarios as identified and
evaluated for the existing design. The resultant risk level once the
recommendations arising out of the HAZOP Study have been implemented is
also discussed for each scenario. The table in Section 3.5 below presents the
risk profile of the systems under study assuming all recommendations have
been implemented successfully.
3.2 R
ISK
L
EVELS OF THE
B
OILERS
D
ESIGN
Below are listed the risk scenarios for each Risk Level (as per Eraring Risk
definition) for the Boiler Design. These risk levels are as per current design
without
the additional risk reduction recommendations arising from the HAZOP
implemented.
3.2.1 Level 4 Risks Boilers
A. Risk of increased copper transportation (Scenario 5)
Increased copper transportation has largely got a financial effect to EE. Copper
would eventually carry-over through to turbine blades, reducing the efficiency of
the turbine operation and hence output capacity. It may cause flow restrictions
in superheater tubes and lead to a decreased life on low pressure heaters. The
copper transportation issue will require a change in the manner in which
maintenance is carried out on the superheaters and turbine rotors.
Current controls include ongoing routine copper transportation survey; a
Strategy Review which is being conducted on the merits of chemically cleaning
the superheaters versus foam clean of turbine; a review of the procedures for
boiler tube repairs have been reviewed; and new boiler chemical controls being
installed to reduce copper transportation from LP heaters.
Recommended additional controls are as follows:
Option a: Successful chemical clean carried out on super heaters which will be
carried out there-after as required need to review sliding pressure operation.
This would reduce the consequences of this event resulting in reducing the
overall risk level to a Level 3 risk.
Option b: Replacement of LP heaters to allow oxygenated treatment of the
boiler feed water. This would reduce the risk level to 1.
NB: Eraring Energy has engaged a contractor to complete superheater tube
cleaning commencing with unit four in November 2009.
B. Insufficient power supplies or access for operation during
construction (Scenarios 51 and 52)
Insufficient power supplies for construction purposes and insufficient access for
operations such as cranage due to other works (e.g. bottom ash hopper
crushing plant and boiler upgrade crane location) would lead to delays in
meeting program. The likelihood of such delays is seen as Very High leading to
a Level 4 risk.
It is recommended to place these risk scenarios on the Electrical Project Teams
(#51) and Site Operations Managers (#51 and #52) agenda. This would reduce
the risk to a Level 1 and Level 2 for scenarios 51 and 52 respectively.
3.2.2 Level 3 Risks Boilers
A. Flow accelerated corrosion due to increase in normal operational
flow (Scenario 1)
Flow accelerated corrosion (FAC) is a temperature dependent corrosion
mechanism normally occurring after a bend or in a straight pipe after a flow
disturbance e.g. thermocouple probe, orifice plate etc. It may lead to pipe
failure and loss of containment of high pressure water, injury from burns,
possible fatalities. Existing controls are confirmation of adequate thickness of
piping etc. (thickness survey already conducted); planned thickness surveys 4
years after start up and the fact that there is no change in geometry as a result
of the project.
Further recommendations are to determine high risk areas in terms of FAC and
to perform thickness survey at targeted areas at first Combined Maintenance
Outage Program (CMOP
2) outage on units 4 and 2 and correlate to the duration
above the original design flow. It is also recommended to record the extent of
flow above the original design (for use in thickness survey mentioned above)
and to confirm that FAC study by contractor has been completed and is valid for
current design.
Implementation of these recommendations would reduce the likelihood from a
Moderate to a Low. It would however not reduce the overall risk rating, which
remains a Level 3 risk due to the relatively High consequence rating.
B. Failure of new pressure parts (Scenarios 7, 15, 19, 26, 50)
Failure of new pressure parts for a number of reasons may lead to pipe failure
and loss of containment of high pressure steam / water, injury from burns, and
possible fatalities.
Current and approved controls include the fact that the design and construction
will adhere to Australian Standards including inspection; 100% radiography on
all site tube welds; all other site welds to be NDT in compliance with Australian
Standards; testing, including Non Destructive Testing (NDT); Asset Strategy
defined field test for creep life of welds.
Provided that these controls are successfully implemented and maintained the
team concluded that the risk of these scenarios are
As Low As Reasonably
2
Practicable
(ALARP) and no further risk control measures were identified. The
risk scenarios remain however at Level 3 risk due to the relatively High
consequence should they occur even though the likelihood is considered as low
as reasonably practicable.
C. Increased
maximum
flow
exceeds
maximum
capacity
of
superheater safety valves (Scenario 14)
An increase in the maximum flow may exceed the maximum relieving capacity
of superheater safety valves. This would result in over pressurisation of the
superheater leading to pipe failure and loss of containment of high pressure
water, injury from burns, possible fatalities.
Current controls include the review carried out by contractors in this regards
which provides advice on the safe operation of safety valves.
Recommendations are to establish actual flows for overload and revise plant
control limits if necessary and to include (in the amended plant operating
manuals) the established plant limitation. This would have the effect of
minimising the likelihood of this event. However, due to the relatively High
consequence of the scenario the risk level remains 3.
NB: Review of flow rates from boiler designer indicates that operation to 750
MW will be achievable with installed safety valves. It is not expected that safety
valve replacement will be required however it will be assessed post upgrade.
D. Increase of velocities (Scenario 36)
Boiler operation at higher loads increases average flue gas velocity which
increases grit erosion. This could lead to tube failures and reduced boiler tube
life and would increase maintenance/costs.
Current and approved controls include Combined Maintenance Outage
Program (CMOP) inspections and shielding, as identified in surveys for current
known high wear area; existing baffling along the wall sections; and acoustic
detectors to minimise damage in the event of a failure. Further, tube wall
thickness design takes into account exposure to erosion and new economiser
panels have all bends enclosed out of gas flow.
Further recommendations from the HAZOP are for the design process to
evaluate the need for baffling, shielding and soot blower locations in primary
superheater and Reheater backpasses; the review to include rear wall
penetration and seal boxes as now in an area of historical high risk. Prior to
warranty expiration (12 months) take unit out of service for grit erosion survey
on new design items; cold air flow testing and smoke bombs to identify high
velocity areas and record high flow areas for targeted inspection - adjust baffling
or shielding as required; perform inspections on previously un exposed areas
while elements are removed during upgrade; and modify the boiler strategy to
reflect concerns and learnings from inspections.
Provided these recommendations are implemented the risk level of this
scenario is reduced to a Level 2.
E. Higher gas temperatures in the backpass (superheater and
Reheater passes) (Scenario 42)
Higher flue gas temperatures after the air heater exit and attemperation point
will cause fabric filter bag failures due to excessive shrinkage. This could lead
to cell isolations and potential breach of the environmental licence if EPS load
not reduced. The failure may require long time to implement repairs if a stock
holding of replacement bags is not available due to long lead time (3-6 months)
on bags.
The risk exposure exists until 2015 when all PAN filter bags would have been
replaced. Currently EPS has excellent bag life with 6 to 7 year bag replacement
cycle.
Current and approved safeguards are using experience with this potential risk
(which exists also in the existing plant); the new attemperating air system which
initiates at 125 deg C, a High Alarm at 135 deg C and a High High Alarm at 140
deg C - for load reduction. Boiler flue gas design brief is 135 deg C at air
heater exit at 720 MW with a 32 degree ambient air temperature. Fabric filter
bag supply contract requires 8 cells of bags on site
Further recommendation are for documentation to be produced to implement an
operating limit of 135 deg C to manage bag life, with a nominal operating target
of less than 130 deg C; adjustment of operating limit down on subsequent units
if rapid multi cell failures occur; evaluating the need of attemperating air spray
system if operating need exists; stock holding costs versus risk to be assessed;
and investigation of stock holding limits with contracted supplier.
If the recommendation above are implemented the risk is reduced to a Level 2
(possibly to a Level 1 depending on the rigour of implementation).
F. Poor Access To Bottom Bank Reheater Tubes (Scenario 46)
Poor access to bottom bank Reheater tubes may mean that in the event of a
tube failure the outage may need to be extended to gain access to carry out
repairs.
There are currently no controls for this scenario (apart from a trained workforce
with adequate operating procedures and PPE).
Recommendation is if for a review to achieve workable access for maintenance.
Provided this is workable access is achieved adequately the risk of this scenario
is reduced to a Level 2.
G. Change in boiler components (Scenario 53)
Change in boiler components would result in change in load distribution.
Currently structural review is being undertaken by contractor which also
includes earthquake and wind load code compliance. Further action is to
ensure that action resulting from design study to reflect latest Australian
Standards and Codes. This would result in a Level 1 risk scenario.
H. Changes to existing job sheets for boiler start up and shut down
(Scenario 56 and 57)
Changes to existing job sheets for boiler start up and shut down leading to plant
damage or injury. Current controls are that boiler project team work scope
includes procedural review. A tight control of the completion of plant
modification process would result in a Level 1 risk.
3.2.3 Level 2 and Level 1 Risks Boilers
There are a number Level 2 and Level 1 risks that were identified. These are
detailed in Appendix 1.
3.3 R
ISK
L
EVELS OF THE
T
URBINE
H
YDRAULIC
P
OWER
U
NIT
D
ESIGN
3.3.1 Level 4 Risks Hydraulic Power Unit
There are not Level 4 risks identified.
3.3.2 Level 3 Risks Hydraulic Power Unit
A. Removal of Pump MRP
Removal of Pump MRP causes Safety issue with 11MPa. Current controls are
primary isolation valve and the pressure gauge.
Recommended further controls are to ensure positive isolation to allow stand-by
pump removal and to ensure the main isolation valves can be locked out.
Provided these recommendations are implemented the risk level for this
scenario is reduced to a Level 2 risk.
B. Impact on fluid trip drain from valves back to tank causes pinching
Impact on fluid trip drain from valves back to tank causes pinching resulting in
an inability to trip turbine. This may, in adverse operating conditions, cause a
burst of drain pipe over 1.4MPa with injury potential to personnel from high
pressure event.
Current and approved controls are the appropriate layout of piping (very short
pipe) and protection of pipe between structures.
Further recommendations are to review the layout of drainpipe to rule out
impact; consult with contractor as to implications of a blocked drain line on
operation; and to ensure EE field surveillance officer approves pipe line layout
with attention to mechanical damage and weld inspection. The target is to
ensure that this scenario becomes incredible.
3.3.3 Level 2 and Level 1 Risks Hydraulic Power Unit
There are a number Level 2 and Level 1 risks that were identified. These are
detailed in Appendix 1.
3.4 R
ISK
L
EVELS OF THE
L
OW
NO
XB
URNER
D
ESIGN
3.4.1 Level 4 Risks Low NO
xBurners
There are not Level 4 risks identified.
3.4.2 Level 3 Risks Low NO
xBurners
A. Pressure controller has been disabled or the Atomising air pressure
is high (Scenario 12)
If the pressure controller has been disabled or the atomising air pressure is high
while atomising air to the ignitor it is possible for the unit to fail to ignite causing
an operational upset and loss of power generation. Note that this is not a safety
concern.
It is recommended to review air pressure requirements with designers and
respond appropriately. This would reduce the risk of this scenario to a Level 2.
B. Inability to remove oil gun and spark rod on D level (Scenario 13)
New burner layout may result in an inability to remove oil gun and spark rod on
D level.
Provided the design change to relocate oil gun to allow removal this scenario is
reduced to a Level 1 risk.
3.4.3 Level 2 and Level Low NO
xBurners
There are a number Level 2 and Level 1 risks that were identified. These are
detailed in Appendix 1.
3.5 R
ISK
P
ROFILE
The risk profile of the part of the plant assessed, assuming that the risk
reduction measures recommended during the HAZOP Studies are all
implemented successfully, is as follows:
Table 1 – Levels of Risk With HAZOP Recommendations Implemented
Risk Level
Risk Scenario
Boilers
Level 4
No scenarios identified remain at Level 4
Level 3
FAC due to increase in normal operational flow (scenario 1)
Financial effect only: Risk of increased copper transportation
(scenario 5). Reduced to a Level 1 based on feasibility study.
Failure of new pressure parts (scenario 7, 15, 19, 26, 50)
Increased maximum flow exceeds maximum capacity of
superheater safety valves (Scenario 14). Reduced to a Level 1
based on commissioning data and plant control settings.
Level 2
Detailed in HAZOP Minute sheets in Appendix 1
Level 1
Detailed in HAZOP Minute sheets in Appendix 1
Turbine Hydraulic Power Unit
Level 4
No scenarios identified remain at Level 4
Level 3
No scenarios identified remain at Level 3
Level 2
Detailed in HAZOP Minute sheets in Appendix 1
Level 1
Detailed in HAZOP Minute sheets in Appendix 1
Low NO
xBurners
Level 4
No scenarios identified remain at Level 4
Level 3
No scenarios identified remain at Level 3
Level 2
Detailed in HAZOP Minute sheets in Appendix 1
4
C
ONCLUSION
The formal HAZOP review process for major project
is part of EE’s multilevel
risk management strategy and represents a clear commitment by EE as to the
management of risks for the business and for safety, health and environment.
This type of process allows for input by a number of experienced and senior
representatives from operations, design, maintenance, safety etc. at a defined
number of stages throughout the life of the project, from early conception
through to detailed design and to final operation.
It provides an opportunity for a multidisciplinary team to formally review a
proposal and to use their experience and corporate memory to improve this
proposal and wherever possible avoid any repeat of errors or issues that may
have occurred in the past.
The team that took part in the HAZOP reviews which are presented in the
present report participated freely and with a high degree of expertise.
This is apparent from the results from these HAZOP Study reviews which
provides for a solid understanding as to the risks associated with the projects.
c:\erapow\12-b177\HAZOP Report Upgrade Project Rev B.Doc Revision B 14 July, 2009 A1.1
HAZOP Study Report Of The Turbine Hydraulic Power Unit, Boiler Upgrade And Low Nox Burners As Part Of The Eraring Energy Power Station Upgrade Project
Appendix 1
HAZOP Minutes
Burner HAZOP
Turbine Hydraulic Power HAZOP
Low NO
x
Burner HAZOP
HAZOP Study Report of the Turbine Hydraulic
Power Unit, Boiler Upgrade and Low NOx Burners
as Part of the Eraring Energy Power Station
Upgrade Project
BOILER HAZOP
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng 1 General - -
Line: Feedwater from economiser inlet through to drum and furnace.
2 High Flow FAC due to increase in normal
operational flow.
May lead to pipe failure and loss of containment of high pressure water, injury from burns, possible fatalities
Thickness survey already conducted. Planned thickness survey 4 years after start up,
No change in geometry
4 2 3 a. Determine high risk areas in terms of FAC. Perform Thickness survey at targeted areas at first CMOP outage on units 4 and 2 and correlate to duration above original design flow.
b. Record the extent of flow above original design (for use in thickness survey mentioned in action 1a above)
c. Confirm that FAC study by CW has been completed and is valid for current design.
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng
3 High Flow Inability of drum to effectively separate water from steam at higher flow rates of upgraded design.
If drum unable to effectively separate water form steam, the possibility of carryover of water to superheater. Deposition of chemicals and erosion of turbine blades
Design 2 2 2 Perform carry over test at commissioning of unit 4 and if carryover found engineer out (i.e. replacement separators)
1 1 1
4 High Flow Increased maximum flow exceeds maximum capacity of drum safety valves. Over pressurisation of drum may cause failure. May lead to pipe failure and loss of containment of high pressure water, injury from burns, possible fatalities.
Design review carried out by Connell Wagner and the safety valves on the drum have been confirmed to be adequate. (10% margin above 750MW flow rate.) With this safeguard in place this scenario has
effectively been eliminated.
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng 5 High Pressure Risk of increased copper transportation Eventually carry-over of copper through to turbine blades. Copper affects the efficiency of the turbine and may cause blockage in superheater tubes. The copper
transportation issue will also require a change in manner of which maintenance is carried out on superheaters. Decrease life on LP heaters. Ongoing routine copper transportation survey.
Strategy Review being conducted on merits of chemically cleaning the superheaters versus foam clean of turbine.
Procedures for boiler tube repairs have been reviewed.
New boiler chemical controls are being installed to reduce copper transportation from LP heaters. Improved start up and shut down procedures.
4 4 4 a. Successful chemical clean carried out on super heaters and turbine. Carry out routinely if cannot stop copper transportation. brevier sliding pressure characteristic.
c. Replacement of LP heaters to allow
oxygenated treatment (this option is being considered).
2 1 4 1 3 1
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng
6 Low Flow Imbalance of flow between front and back pass
economisers
Flow may be too low in front pass
encroaching in steaming margin. May cause pipe damage and level stability issues in drum (so called drum swell). Mixing at T-piece may be unstable.
Design review carried out. Regular operational inspections to confirm design review outcomes. Hazard warning through noise. 1 1 1 Install thermocouples on each outlet header of economisers.
1 1 1
7 Low Flow Failure of new pressure parts
May lead to pipe failure and loss of containment of high pressure water, injury from burns, possible fatalities.
Design and constructed to standards including inspection, testing and NDT.
4 1 3 No further action identified. 4 1 3
8 Low Temperature Design will lower economiser duty by 35% Lowering of the feedwater temperature to the drum which leads to higher gas flows and increased risk of erosion.
Parameters have been given to designers as part of design scope and outcomes have been reviewed and accepted by Eraring.
1 1 1 No further action identified. 1 1 1
9 Impurities Construction debris left in system. Blockages, tube starvation and failure. Financial effect. Impact on human Safety low.
Construction
methodology including flush processes. Visual inspections, ITP's
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng 10 Reaction Cooler temperatures in economiser Possible reduced effectiveness of chemical dosing regime (particularly at start up) Tube samples at outages. Continuous chemical monitoring. Upgrade of Chemical Control Room (CCR) with respect to instrumentation. 1 2 1 Issue to be reviewed by Chemical Team. 1 1 1
11 Operability New operating parameters
Potential mal operation impacting life and viability of equipment.
Training requirements 1 2 1 New performance data sheets to be compiled. 1 1 1 12 Operability/ maintaina-bility Obstruction to galleries from new economiser feed pipe to drum.
Poor access around and into boiler
Ensure adequate access around boiler
1 1 1 No further action identified. 1 1 1
13 Instrumenta-tion inadequate information of plant condition Failure to understand plant condition Existing instrumentation will be a guide to
requirements for new equipment.
1 1 1 Refer to action No.6 w.r.t. thermocouples
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng
Line: Steam from the Heat Recovery Area outlet header through the Superheaters to the Main Steam Outlet
14 High Flow Increased maximum flow exceeds maximum capacity of superheater safety valves. Over pressurisation of superheater may cause failure. May lead to pipe failure and loss of
containment of high pressure water, injury from burns, possible fatalities.
Designer review carried out by CW. Relieving capacity reduced from IHI design of 155.6 to 139.4 kg/s. Minimum Aust Standard code requirements (20% of steam flow relieving) equates to max steam flow rate of 695kg/s, hence steady state 750MW flow
conditions of 624kg/s within this margin. Original design assessment allowed for discharging 25% of steam flow rate through superheaters and under this basis 622 kg/s is maximum steam flow under original IHI design or 557 kg/s under revised CW capacity.
4 2 3 a. Establish actual flows at commissioning for overload and revise plant limits if necessary
b. Plant limitation to be included in amended plant operating manuals.
c. Based on findings in (a) determine need to install larger size safety valves to allow achievement of additional overload above 633 kg/sec (being 22% of the revised CW relieving capacity). 4 1 1 1 3 1
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng
15 Low Flow Failure of new pressure parts
May lead to pipe failure and loss of containment of high pressure water, injury from burns, possible fatalities.
Design and constructed to standards including inspection, testing and NDT.
4 1 3 No further action identified. 4 1 3
16 High Temperature Higher steam temperatures resulting in more frequent use of spray water
Potential for thermal fatigue failure of spray water system
Original design and material selection. 12-yearly inspections of spray water systems.
3 2 2 Increase frequency of inspections of spray water system (currently 12-yearly). 3 1 2 17 High Temperature Insufficient capacity of spray water to control superheater steam temperatures. Accelerated creep life usage. Material Failure. Design parameter reviewed and accepted by Eraring Energy. Metal temperature operational limits and alarms (except SSH).
1 1 1 No further action identified. 1 1 1
18 High Temperature Accelerated creep life consumption of headers Reduced life of headers Software system to monitor header life (ODAS).
Field testing -
replication of headers
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng 19 High Temperature Reduced creep life of welds
Pressure part weld failure. Loss of containment of steam internal of boiler, could be external to boiler. Burns.
Asset Strategy defined field test for creep life of welds
4 1 3 No further action identified. 4 1 3
20 High Temperature Burner replacement Higher or lower temperatures To be covered in burner HAZOP - - - To be covered in burner HAZOP - - - 21 High Temperature Increased primary superheater surface area Higher steam temperature for stages 1,2 and 3 resulting in higher metal temperatures causing metallurgical failure.
Design review has indicated that
materials are suitable for duty
1 1 1 No further action identified. 1 1 1
22 Impurities Increased flow rate increases demand on polishing plant, particularly during periods of salt leaks
Salt leak tolerance reduced due to lack of polishing plant capacity. Load reduction, boiler damage Reduce load as operating procedure. Polishing plant capacity review is carried out by CW
1 3 2 a. Implement actions from CW review on polishing plant capacity.
OR
b. Review the turbine condenser life strategy
1 1 1 1 1 1
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng 23 Impurities Increased exfoliation of internal stable oxide layer due to the increase flow rate and heat fluxes
Blocked super heater tubes or solid particle erosion of HP turbine
Not an issue at current operating conditions.
2 2 2 Desk top review of
superheater metallurgy and susceptibility to the phenomena 2 1 1 24 Instrumentati on Inadequate information of plant condition Failure to understand plant condition
TBA 1 1 1 Review instrumentation when it becomes available from designers
1 1 1
Line: Steam from superheater outlet valve through the Reheater to IP Turbine
25 High Flow Increased maximum flow exceeds maximum capacity of Reheater safety valves. Over pressurisation of Reheater may cause failure. See No. 1 above.
Design review carried out and confirmed. Maximum Reheater flowrate of 646kg/s for existing safety valves. Hence superheater safety valves are the first high flow limitation with respect to boiler safety valves.
1 1 1 No further action identified. 1 1 1
High Flow Increased design flow and additional surface area increases DP across the Reheater Reduced IP turbine inlet pressure which may lead to reduced output
Boiler turbine matching review completed with outcome for boiler designer to advise of Reheater DP
No Guide Word Causes Consequences Safeguards (Existing and Approved) Imp
ac t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Imp ac t Lik elih oo d R aw R isk R ati ng
26 Low Flow Failure of new pressure parts
May lead to pipe failure and loss of containment of high pressure water, injury from burns, possible fatalities.
Design and constructed to standards including inspection, testing and NDT.
4 1 3 No further action identified. 4 1 3
27 High Temperature Increased surface area enabling Reheater to exceed design temperatures Metallurgical failure of tubing resulting in loss of generation and revenue. Reduced Creep life on hot Reheater header.
Temperature control with back pass dampers. ODAS system for creep life monitoring. Field replications as per strategy.
Note: Existing spray water is
decommissioned
2 2 2 Implement alarms on hot reheat steam outlet temperature. Implement appropriate training. 2 1 1 28 High Temperature Tube failure of hot Reheater elements due to achieving design temperatures
Tube failure unit out of service, loss of revenue
Material review carried out by designers
No Guide Word Causes Consequences Safeguards (Existing and Approved) Impac
t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Impac t Lik elih oo d Ta rg et R ati ng
Line: Furnace Area/gas side - from Ash hopper throat to furnace rear wall screen tubes.
29 High Flow Increased firing Increased gas flow causing increased vibration/movement on superheater pendants leading to tube failure. Outage inspections/condition monitoring, acoustic detectors will limit the impact.
2 2 2 No further actions 2 2 2
30 High Flow No erosion issues identified
- - - No further actions - - - 31 High Pressure Upgrade not
affecting existing
- - - No further actions - - -
32 Low Pressure Upgrade not affecting existing - - - No further actions - - - 33 High Temperature Refer to Low NOx Burner HAZOP Slagging No further actions
No Guide Word Causes Consequences Safeguards (Existing and Approved) Impac
t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Impac t Lik elih oo d Ta rg et R ati ng 34 High Temperature Increased time at higher metal temperatures on superheaters. Increased rate of creep life consumption requiring early replacement.
CMOP inspection for gap between pendants and nose
1 1 1 Furnace flue gas temperature measurements to confirm design expectations. Consider metal temperature instrumentation on SSH if flue gas temperatures high. 1 1 1 35 High Temperature Increased temperatures on superheaters leading to increased metal temperatures Increased rate of creep life consumption requiring early replacement.
CMOP inspection for gap between pendants and nose
No Guide Word Causes Consequences Safeguards (Existing and Approved) Impac
t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Impac t Lik elih oo d Ta rg et R ati ng
Line: Backpass (superheater and Reheater passes)
36 High Flow Overall average velocity increases with reduced bias from front to rear pass - specifically higher flow in the superheater compared to previously. High flow causes grit erosion Tube failures, increased maintenance/costs, shorter life
CMOP inspections and shielding as identified in surveys for current known high wear areas.
Existing baffling along the wall sections. Acoustic detectors to minimise damage in the event of a failure. Tube wall thickness design takes into account exposure to erosion. New economiser panels have all bends enclosed out of gas flow.
3 3 3 a) Design process to consider baffling,
shielding and soot blower locations in primary superheater and Reheater.
b) Review to include rear wall penetration and seal boxes as now in an area of historical high risk. c) Prior to warranty expiration (12 months) take unit out of service for grit erosion survey on new design items.
d) Cold air flow testing and smoke bombs to identify high velocity areas and record high flow areas for targeted inspection - adjust baffling or shielding as required. e) Perform inspections on previously un exposed areas while elements are removed during upgrade. f) Modify the boiler strategy to reflect concerns and learnings from inspections.
No Guide Word Causes Consequences Safeguards (Existing and Approved) Impac
t Lik elih oo d R aw R isk R ati ng Further Mitigating Actions Impac t Lik elih oo d Ta rg et R ati ng
37 High Flow Overall average velocity increases with reduced bias from front to rear pass - specifically higher flow in the superheater compared to previously. High flow causes grit erosion Possible increased grit erosion on dampers, with increased maintenance costs - damper failure loss of temperature control
CMOP inspections to confirm if problem has increased from current
1 1 1 Inspect at 12 month warranty survey
1 1 1
38 Low Pressure Higher DP across finned economiser.
ID fan capacity margin is reduced which may lead to forced load limitation particularly in summer.
Soot Blowing 2 2 2 Review ID fan cut back set point with regards to the risk of duct implosion limits.
2 1 1
39 Low Pressure Higher DP across finned economiser.
More soot blowing to control dust build up in finn tubes, potentially causing higher rates of soot blower steam erosion on tubes leading to tube failure.
Shield soot blower steam impact areas.