• No results found

Chapter-3 (1)

N/A
N/A
Protected

Academic year: 2021

Share "Chapter-3 (1)"

Copied!
110
0
0

Loading.... (view fulltext now)

Full text

(1)

Exercise

9

Solving Linear Programming

(2)

incorrect statement.

______1. An iterative process is a procedure, which is repeated over and over following a random pattern.

______ 2. An inequality relationship may be converted into an equality by the addition of a slack variable.

______ 3. An infeasible solution is characterized as one where at least one constraint is violated.

______ 4. The Cj column in a maximization simplex table indicates the profit per unit for only those variables in the product mix.

______ 5. The significance of the quantity column in the simplex table is that it always shows the right hand side values of the constraints.

______ 6. Artificial, slack, and surplus variables are added to inequality constraints in order to convert them to equalities. Artificial variables are also added to constraints which were equalities to begin with.

(3)

incorrect statement.

______ 7. There are always more variables in a simplex problem than there are constraints.

______ 8. If an artificial variable appears in the product mix of a table, which is optimal, it is likely that somebody has defined two or more

incompatible constraints.

______ 9. Shadow prices are identified with variables, which are included in the product mix.

______ 10. For any basic variable in the product mix of a simplex table, the value of Cj – Zj in the column headed by the basic variables will always be negative in a maximization problem and positive in a minimization problem.

(4)

incorrect statement. (Answer is in red letter)

______1. An iterative process is a procedure, which is repeated over and over following a random pattern. True

______ 2. An inequality relationship may be converted into an equality by the addition of a slack variable. True

______ 3. An infeasible solution is characterized as one where at least one constraint is violated. True

______ 4. The Cj column in a maximization simplex table indicates the profit per unit for only those variables in the product mix. True

______ 5. The significance of the quantity column in the simplex table is that it always shows the right hand side values of the constraints. True

______ 6. Artificial, slack, and surplus variables are added to inequality constraints in order to convert them to equalities. Artificial variables are also added to constraints which were equalities to begin with. True

(5)

incorrect statement.

______ 7. There are always more variables in a simplex problem than there are constraints. False

______ 8. If an artificial variable appears in the product mix of a table, which is optimal, it is likely that somebody has defined two or more

incompatible constraints. False

______ 9. Shadow prices are identified with variables, which are included in the product mix. True

______ 10. For any basic variable in the product mix of a simplex table, the value of Cj – Zj in the column headed by the basic variables will always be negative in a maximization problem and positive in a minimization problem. True

(6)

______ 1. Which of the following is not true for the simplex procedures? a. Each iteration results a new solution, which is as good as or better than

the previous solution.

b. The procedure indicates when the optimum solution has been reached. c. The procedure ensures that the optimum solution is reached in the

minimum

number of iteration.

d. All of the above choices are correct.

______ 2. If for a given solution, a slack variable is equal to zero then, a. the solution is not feasible

b. the solution is optimal

c. the entire amount of resource has been used d. all of the above choices are correct

(7)

______ 3. A variable, which is not included in the product mix column for a given solution is:

a. always equal to zero b. never equal to zero c. called a basic variable

d. none of the above choices are correct

______ 4. With simplex, the initial solution contains only: a. slack variable in the product mix

b. artificial variables in the product mix

c. slack and artificial variables in the product mix d. real variables in the product mix

______ 5. The procedure for solving a minimization problem with simplex is exactly the same as solving a maximization problem but with one exception, which is:

a. the identification of the replaced row b. the identification of the optimum column c. the computation of the Cj – Zj values

(8)

just two resources (2 slack variables), then the combination that will yield the optimal profit is: a. produce all 100 products if both resources are used to full capacity

b. produce, at most 2 products c. produce only one product

d. none of the above choices are correct

______ 7. In converting > constraint to equality one will a. add an artificial variable

b. add a slack variable

c. subtract a surplus variable and add an artificial variable d. subtract a surplus variable

______ 8. In solving maximization problem using simplex method, the optimum column is obtained by getting the column with

a. the largest positive value in the Cj – Zj row b. the largest negative value in the Cj – Zj row c. zero value in the Cj – Zj row

(9)

______ 9. Which of the following in a simplex table indicates that an optimal solution for maximization problem has been formed?

a. All the Cj – Zj values are negative or zero. b. All the Cj – Zj values are positive or zero.

c. There are no more slack variables in the product mix. d. All the Cj – Zj values are zeros.

______ 10. Which of the following must equal to zero? a. Basic variables

b. Solution mix variables c. Non-basic variables

(10)

__b____ 1. Which of the following is not true for the simplex procedures? a. Each iteration results a new solution, which is as good as or better than

the previous solution.

b. The procedure indicates when the optimum solution has been reached.

c. The procedure ensures that the optimum solution is reached in the minimum number of iteration.

d. All of the above choices are correct.

__c____ 2. If for a given solution, a slack variable is equal to zero then, a. the solution is not feasible

b. the solution is optimal

c. the entire amount of resource has been used d. all of the above choices are correct

(11)

__d____ 3. A variable, which is not included in the product mix column for a given solution is:

a. always equal to zero b. never equal to zero c. called a basic variable

d. none of the above choices are correct

__c____ 4. With simplex, the initial solution contains only: a. slack variable in the product mix

b. artificial variables in the product mix

c. slack and artificial variables in the product mix d. real variables in the product mix

__d____ 5. The procedure for solving a minimization problem with simplex is exactly the same as solving a maximization problem but with one exception, which is:

a. the identification of the replaced row b. the identification of the optimum column c. the computation of the Cj – Zj values

(12)

__d___ 6. In solving a problem where 100 different products (100 real variables) are produced using just two resources (2 slack variables), then the combination that will yield the optimal profit is:

a. produce all 100 products if both resources are used to full capacity b. produce, at most 2 products

c. produce only one product

d. none of the above choices are correct

___C___ 7. In converting > constraint to equality one will a. add an artificial variable

b. add a slack variable

c. subtract a surplus variable and add an artificial variable d. subtract a surplus variable

__b____ 8. In solving maximization problem using simplex method, the optimum column is obtained by getting the column with

a. the largest positive value in the Cj – Zj row b. the largest negative value in the Cj – Zj row c. zero value in the Cj – Zj row

(13)

___a___ 9. Which of the following in a simplex table indicates that an optimal solution for maximization problem has been formed?

a. All the Cj – Zj values are negative or zero. b. All the Cj – Zj values are positive or zero.

c. There are no more slack variables in the product mix. d. All the Cj – Zj values are zeros.

___d___ 10. Which of the following must equal to zero? a. Basic variables

b. Solution mix variables c. Non-basic variables

(14)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

1. Maximize: Z = 4x1 + 5x2 subject to: 3x1+ 6x2 ≤ 36 4x1 + 2x2 ≤ 36 x1 + x2 ≤ 8 x1,x2 ≥ 0 2. Maximize: Z = 6x + 3y subject to: 2x+ 4y ≤ 30 4x + 2y ≤ 30 2x + 3y ≥ 18 x1,x2 ≥ 0

(15)

C. Adding the appropriate slack, surplus, and artificial

variables.

1. Maximize: Z = 4x1 + 5x2 subject to: 3x1+ 6x2 ≤ 36 4x1 + 2x2 ≤ 36 x1 + x2 ≤ 8 x1,x2 ≥ 0 Z = 4x1 + 5x2 + 0S1 + 0S2 + 0S3 3x1+ 6x2 + 1S1 + 0S2 + 0S3= 36 4x1 + 2x2 + 0S1 + 1S2 + 0S3 = 36 x1 + x2 + 0S1 + 0S2 + 1S3 = 8

(16)

C. Adding the appropriate slack, surplus, and artificial variables.

2. Maximize: Z = 6x + 3y ubject to: 2x+ 4y ≤ 30 4x + 2y ≤ 30 2x + 3y ≥ 18 x1,x2 ≥ 0 Z = 6x + 3y + 1S1 + 0S2 + 0S3 + 10A 2x+ 4y + 1S1 + 0S2 + 0S3 + 0 A3 =30 4x + 2y + 0S1 + 1S2 + 0S3 + OA3 = 30 2x + 3y + 0S1 + 0S2 - 1S3 +1A3 = 18

(17)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

3. Minimize: C = 8x + 4y

subject to: 10x+ 25y ≥ 100 y ≤ 4 x,y ≥ 0 4. Minimize: C = 4x + 5y subject to: x+ 6y = 12 x ≤ 4 y≤ 8 y ≥ 5 x,Y ≥ 0

(18)

C. Adding the appropriate slack, surplus, and artificial variables.

3. Minimize: C = 8x + 4y

subject to: 10x+ 25y ≥ 100 y ≤ 4 x,y ≥ 0 C = 8x + 4y + 0S1 + 0S2 + 10 A1 10x+ 25y + 1S1 + 0S2 + 1A1 = 100 0x + y - 0S1 + 1S2 + 0A1 = 4

(19)

C. Adding the appropriate slack, surplus, and artificial variables.

4. Minimize: C = 4x + 5y subject to: x+ 6y = 12 x ≤ 4 y≤ 8 y ≥ 5 x,Y ≥ 0 C = 4x + 5y + 0S2 + 0S3 + 0S4 +10A1 +10A4 x+ 6y + 0S2 + 0S3 + 0S4 +1A1 + 0A4 = 12 x + 0y + 1S2 + 0S3 + 0S4 +0A1 + 0A4 = 4 0x + y + 0S2 + 1S3 + 0S4 +0A1 + 0A4 = 8 0x + y + 0S2 + 0S3 - 1S4 +0A1 + 1A4 = 5

(20)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

5. Minimize: C = 0.05x + 0.06y subject to: 5x+ 25y ≥ 50

25x + 10y ≥ 100 10x + 10y ≥ 60 36x + 20y ≥ 180 x,y ≥ 0

6. Maximize: Z = 4A + 5B subject to: 3A+ 4B ≤ 150 A+2B ≤ 60 A ≥ 25 A,B ≥ 0

(21)

C. Adding the appropriate slack, surplus, and artificial variables.

5. Minimize: C = 0.05x + 0.06y subject to: 5x+ 25y ≥ 50 25x + 10y ≥ 100 10x + 10y ≥ 60 36x + 20y ≥ 180 x,y ≥ 0

C = 0.05x + 0.06y + 0S1 +0S2 + 0S3 + 0S4 +10A1 + 10A2 + 10A3 +10A4 5x+ 25y - 1S1 +0S2 + 0S3 + 0S4 +1A1 + 0A2 + 0A3 +0A4 = 50

25x + 10y + 0S1 -1S2 + 0S3 + 0S4 +0A1 + 1A2 + 0A3 +0A4 = 100 10x + 10y + 0S1 +0S2 - 1S3 + 0S4 +0A1 + 0A2 + 1A3 +0A4 = 60

(22)

C. Adding the appropriate slack, surplus, and artificial variables.

6. Maximize: Z = 4A + 5B subject to: 3A+ 4B ≤ 150 A+2B ≤ 60 A ≥ 25 A,B ≥ 0 Z = 4A + 5B +

0S

1

+0S

2

+ 0S

3 + 10A 3A+ 4B +

1S

1

+0S

2

+ 0S

3

+ 0A =

150 A+ 2B +

0S

1

+ 1S

2

+ 0S

3

+ 0A =

60 A + 0B +

0S

1

+0S

2

- 1S

3

+ 1A =

25

(23)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

7. Minimize: C = 2x1 + 5x2 subject to: 3x1+ 2x2 = 30 x1 ≤ 5 x2 ≥ 10 x1,x2 ≥ 0 8. Minimize: C = 2x1 + 5x2 + 9x3 subject to: 2x1+ 2x2 + x3 = 20 2x1+ 4x2 + 5x3 ≤ 20 x1 + 2x2 ≥ 6 x2 ≥ 10 x1,x2, x3 ≥ 0

(24)

C. Adding the appropriate slack, surplus, and artificial variables.

7. Minimize: C = 2x1 + 5x2 subject to: 3x1+ 2x2 = 30 x1 ≤ 5 x2 ≥ 10 x1,x2 ≥ 0 C = 2x1 + 5x2 3x1+ 2x2 -1S1 +0S2 + 0S3 + 1A1

+ 0A

3 = 30 x1 + 0x2 +0S1 +1S2 + 0S3 + 0A1

+ 0A

3 = 5 0x1 + x2 +0S1 +0S2 - 1S3 + 0A1 + 1A3 = 10

(25)

C. Adding the appropriate slack, surplus, and artificial variables.

8. Minimize: C = 2x1 + 5x2 + 9x3 subject to: 2x1+ 2x2 + x3 = 20 2x1+ 4x2 + 5x3 ≤ 20 x1 + 2x2 ≥ 6 x2 ≥ 10 x1,x2, x3 ≥ 0

C = 2x1 + 5x2 + 9x3 + 0S2 + 0S3 + 0S4 + 10A1 + 10A3 + 10A4 2x1+ 2x2 + x3 + 0S2 + 0S3 + 0S4 + 1A1 + 0A3 + 0A4 = 20

2x1+ 4x2 + 5x3 + 1S2 + 0S3 + 0S4 + 0A1 + 0A3 + 0A4 = 20 x1 + 2x2 +0x3 + 0S2 - 1S3 + 0S4 + 0A1 + 1A3 + 0A4 = 6

(26)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

9. Maximize: Z = 8x1 + 6x2 + 2x3 subject to: 3x1+ 2x2 + 6 ≤ 24 4x1+ 3x2 + 6x3 = 48 x1,x2, x3 ≥ 0 10. Minimize: C = 4x + 5y+ 3z subject to: 4x+ 2y + 3z= 100 x≥ 20 y ≤ 6 z ≥ 8 x,y, z ≥ 0

(27)

C. Adding the appropriate slack, surplus, and artificial variables.

9. Maximize: Z = 8x1 + 6x2 + 2x3 subject to: 3x1+ 2x2 + 6 ≤ 24 4x1+ 3x2 + 6x3 = 48 x1,x2, x3 ≥ 0 Z = 8x1 + 6x2 + 2x3 + 0S1 + 10A2 3x1+ 2x2 + 6 + 1S1 + 0A2 = 24 4x1+ 3x2 + 6x3 + 0S1 + 1A2 = 48

(28)

C. Adding the appropriate slack, surplus, and artificial variables.

C = 4x + 5y + 3z + 0S2 + 0S3 + 0S4 + 10A1 +10A2 +10A4 4x + 2y + 3z + 0S2 + 0S3 + 0S4 + 1A1 + 0A2 + 0A4 = 100 1x + 0y + 0z- 1S2 + 0S3 + 0S4 + 0A1 +1A2 +0A4 = 20 0x + 1y + 0z+ 0S2 + 1S3 + 0S4 + 0A1 +0A2 +0A4 = 6 0x + 0y + 1z+ 0S2 + 0S3 - 1S4 + 0A1 +0A2 +1A4 = 8 10. Minimize: C = 4x + 5y+ 3z subject to: 4x+ 2y + 3z= 100 x≥ 20 y ≤ 6 z ≥ 8 x,y, z ≥ 0

(29)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

11. Minimize: C = 6x1 + 16x2 subject to: x1+ x2 = 400 x1= 150 x2 ≥ 200 x1,x2, ≥ 0 12. Minimize: C = 1000x + 1500y subject to: 20x+ 20y ≥ 160 30x+ 60y ≥ 300 x ≥ 2 x,y, ≥ 0

(30)

C. Adding the appropriate slack, surplus, and artificial variables.

C = 6x1 + 16x2 + 0S3 + 10A1 + 10A2 + 10A3 1x1+ 1x2 + 0S3 + 1A1 + 0A2 + 0A3 = 400 1x1+ 0x2 + 0S3 + 0A1 + 1A2 + 0A3 = 150 0x1+ 1x2 - 1S3 + 0A1 + 0A2 + 1A3 = 200 11. Minimize: C = 6x1 + 16x2 subject to: x1+ x2 = 400 x1= 150 x2 ≥ 200 x1,x2, ≥ 0

(31)

C. Adding the appropriate slack, surplus, and artificial variables.

C = 1000x + 1500y+ 0S1 + 0S2 + 0S3 + 10A1 +10A2 +10A3 20x + 20y - 1S1 + 0S2 + 0S3 + 1A1 +0A2 +0A3 = 160

30x + 60y + 0S1 - 1S2 + 0S3 + 0A1 +1A2 +0A3 = 300

1x + 0y + 0S1 + 0S2 - 1S3 + 0A1 +0A2 +1A3 = 2 12. Minimize: C = 1000x + 1500y

subject to: 20x+ 20y ≥ 160 30x+ 60y ≥ 300 x ≥ 2 x,y, ≥ 0

(32)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

13. Minimize: C = 10x1 + 20x2 subject to: x1+ x2 ≥ 10 3x1 + x2 ≤ 12 x1,x2, ≥ 0 14. Minimize: C = 120x1 + 100x2 subject to: 2x1+ x2 ≤ 18 5x1+ 4x2 ≥ 60 x1,x2, ≥ 0

(33)

C. Adding the appropriate slack, surplus, and artificial variables.

C = 10x1 + 20x2 + 0S1 + 0S2 + 10A1 1x1+ 1x2 - 1S1 + 0S2 + 1A1 = 10 3x1+ 1x2 + 0S1 + 1S2 + 0A1 = 12 13. Minimize: C = 10x1 + 20x2 subject to: x1+ x2 ≥ 10 3x1 + x2 ≤ 12 x1,x2, ≥ 0

(34)

C. Adding the appropriate slack, surplus, and artificial variables.

C = 120x1 + 100x2 + 0S1 + 0S2 + 10A2 1x1+ 1x2 + 1S1 + 0S2 + 0A2 = 18 3x1+ 1x2 + 0S1 - 1S2 + 1A2 = 60 14. Minimize: C = 120x1 + 100x2 subject to: 2x1+ x2 ≤ 18 5x1+ 4x2 ≥ 60 x1,x2, ≥ 0

(35)

C. Add the appropriate slack, surplus, and artificial variables.

Use the value of 10 for the objective function coefficient of

artificial variables. Do not solve.

15. Minimize: Z = 2x1 + 1x2 subject to: 2x1+ 3x2 ≥ 12 3x1+ 4x2 ≤ 21 6x1+ 5x2 ≤ 30 x1,x2, ≥ 0

(36)

C. Adding the appropriate slack, surplus, and artificial variables.

Z = 2x1 + 1x2 + 0S1 + 0S2 + 0S3 + 10A1 1x1+ 1x2 - 1S1 + 0S2 + 0S3 + 1A1 = 12 1x1+ 0x2 + 0S1 + 1S2 + 0S3 + 0A1 = 21 0x1+ 1x2 + 0S1 + 0S2 + 1S3 + 0A1 = 30 15. Minimize: Z = 2x1 + 1x2 subject to: 2x1+ 3x2 ≥ 12 3x1+ 4x2 ≤ 21 6x1+ 5x2 ≤ 30 x1,x2, ≥ 0

(37)

D. Solve the following problems using simplex method:

1. Ignacio Furniture Co. makes two types of playhouses: a standard model and a deluxe model. The playhouse are sold to the independent dealers at a profit of P200/standard and P300/ deluxe. A standard requires 30 man-hours for assembly, and 20 man-hours for painting and finishing and 10 man-hours for inspecting. A deluxe requires 75 hours for assembly, 25 man-hours for painting and finishing, and five (5) man-man-hours for inspecting. A production run generally has 15000 man-hours available for assembly, 6500 man-hours available for painting and finishing and 2500 man-hours for inspecting. Determine the maximum profit and optimal values of the decisions and slack variables.

(38)

Z = 200x1 + 300x2 + 0S1 + 0S2 + 0S3 30x1+ 75x2 + 1S1 + 0S2 + 0S3 = 15,000 20x1+ 25x2 + 0S1 + 1S2 + 0S3 = 6,500 10x1+ 5x2 + 0S1 + 0S2 + 1S3 = 2,500 1 Maximize: Z = 200x1 + 300x2 subject to: Assembly 30x1+ 75x2 ≤ 15,000 Painting/finishing 20x1+ 25x2 ≤ 6,500 inspecting 10x1+ 5x2 ≤ 2,500 x1,x2, ≥ 0

D. Solve the following problems using simplex method:

Let x1 = standard model x2 = deluxe model

(39)

Initial Tableau

200 300 0 0 0

Cont. Soln. Qty. X1 X2 S1 S2 S3 ETR

0 S1 15,000 30 75 1 0 0

0 S2 6,500 20 25 0 1 0

0 S3 2,500 10 5 0 0 0

Zj 0 0 0 0 0 0

(40)

Initial Tableau

200 300 0 0 0

Cont. Soln. Qty. X1 X2 S1 S2 S3 ETR

0 S1 15,000 30 75 1 0 0 200

0 S2 6,500 20 25 0 1 0 260

0 S3 2,500 10 5 0 0 0 500

Zj 0 0 0 0 0 0

(41)

Second Tableau

200 300 0 0 0

Cont. Soln. Qty. X1 X2 S1 S2 S3 ETR

300 X1 200 2/5 1 1/75 0 0

0 S2 1,500 10 0 -1/3 1 0

0 S3 1,500 8 0 -1/15 0 0

Zj 60,000 120 300 4 0 0

(42)

Second Tableau

200 300 0 0 0

Cont. Soln. Qty. X1 X2 S1 S2 S3 ETR

300 X1 200 2/5 1 1/75 0 0 500

0 S2 1,500 10 0 -1/3 1 0 150

0 S3 1,500 8 0 -1/15 0 0 187.5

Zj 60,000 120 300 4 0 0

(43)

Third (Final) Tableau

200 300 0 0 0

Cont. Soln. Qty. X1 X2 S1 S2 S3 ETR

300 X1 140 0 1 11/75 -1/25 0

200 X1 150 1 0 -1/30 1/10 0

0 S3 300 0 0 13/5 -1/80 0

Zj 72,000 200 300 112/3 8 0 Cj - Zj -72,000 0 0 -112/3 -8 0

The solution is optimal: X

2

= 140 Max Z = 200x

1

+ 300x

2

X

1

= 150 = 72,000

(44)

D. Solve the following problems using simplex method:

2. To make one unit of product x requires three (3) minutes in Dept. I and one (1) minute in Dept. II. One unit of product y requires four (4) minutes in Dept.I and two (2) minutes in Dept.II. Profit contribution is P5/unit of x and P8/unit of y. It is required that at least 25 units of x be made to maximize profit if Dept.I and II have 150 and 160 minutes available respectively. What is the maximum profit?

(45)

Z = 5x + 8y + 0S1 + 0S2 + 0S3 + 10A3 3X+ 4Y + 1S1 + 0S2 + 0S3 +0 A3 = 150 1X+ 2Y + 0S1 + 1S2 + 0S3 + 0A3 = 160 1X+ 0Y + 0S1 + 0S2 - 1S3 + 1A3 = 25 2 Maximize: Z = 5x + 8y subject to: time in dept. 1 3x+ 4y ≤ 150 time in dept .2 1x+ 2y ≤ 160 capacity x ≥ 25 x,y ≥ 0

(46)

Initial Tableau

5 8 0 0 0 10

Cont. Soln. Qty. X Y S1 S2 S3 A3 ETR

0 S1 150 3 4 1 0 0 0

0 S2 160 1 2 0 1 0 0

10 A3 25 1 0 0 0 -1 1

Zj 250 10 0 0 0 -10 10

(47)

Initial Tableau

5 8 0 0 0 10

Cont. Soln. Qty. X Y S1 S2 S3 A3 ETR

0 S1 150 3 4 1 0 0 0 50

0 S2 160 1 2 0 1 0 0 160

10 A3 25 1 0 0 0 -1 1 25

Zj 250 10 0 0 0 -10 10

(48)

Second (Final) Tableau

5 8 0 0 0 10

Cont. Soln. Qty. X Y S1 S2 S3 A3 ETR

0 S1 75 0 4 1 0 -3 -3

0 S2 135 0 2 0 1 1 -1

5 X 25 1 0 0 0 -1 1

Zj 125 5 0 0 0 -5 5

Cj - Zj -125 0 8 0 0 5 5

The solution is optimal: X = 25 Max Z = 5X + 8Y

Y= 0 = 125

(49)

D. Solve the following problems using simplex method:

3. A manufacturer of commercial chemical has an order for a certain mixture containing of three ingredients x1, x2, x3, which costs P8, P7, and P4 per kilo, respectively. The following are specifications: a. It cannot contain more than 35 kilos of x.

b. It must contain at least 15 kilos of x2.

c. It cannot contain more than 40 kilos of X3. d. The weight of the mixture must be 120 kilos.

Find a mixture of the three ingredients, which satisfies his customer’s requirements and still yields the minimum total cost of raw materials.

(50)

Z = 8x1 + 7x2 + 4x3 + 0S1 + 0S2 + 0S3 + 10A2 + 10A4 1x1+ 1x2 + 1x3 + 1S1 + 0S2 + 0S3 + 0A2 +0A4 = 35 0x1+ 1x2 + 0x3 + 0S1 - 1S2 + 0S3 +1A2 +0A4= 15 0x1+ 0x2 + 1x3 + 0S1 + 0S2 + 1S3 +0A2 + 0A4 = 40 1x1+ 1x2 + 1x3 + 0S1 + 0S2 + 0S3 +0A2 + 1A4 = 120 3. Minimize: Z = 8x1 + 7x2 + 4x3 subject to: content of X x1+ x2 + x3 ≤ 35 content of X2 x2 ≥ 15 content of X3 x3 ≤ 40 weight x1+ x2 + x3 = 120 x1,x2, x3≥ 0

(51)

Initial Tableau

8 7 4 0 0 0 10 10

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 A2 A4 ETR

0 S1 35 1 1 1 1 0 0 0 0 10 A2 15 0 1 0 0 -1 0 1 0 0 S3 40 0 0 1 0 0 1 0 0 10 A4 120 1 1 1 0 0 0 0 1 Zj 1350 10 20 10 0 -10 0 10 10 Cj - Zj -1350 -2 -13 -6 0 10 0 0 0

(52)

Initial Tableau

8 7 4 0 0 0 10 10

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 A2 A4 ETR

0 S1 35 1 1 1 1 0 0 0 0 35 10 A2 15 0 1 0 0 -1 0 1 0 15 0 S3 40 0 0 1 0 0 1 0 0 0 10 A4 120 1 1 1 0 0 0 0 1 120 Zj 1350 10 20 10 0 -10 0 10 10 Cj - Zj -1350 -2 -13 -6 0 10 0 0 0

(53)

Second Tableau

8 7 4 0 0 0 10 10

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 A2 A4 ETR

0 S1 20 1 0 1 1 2 0 -1 0 7 X2 15 0 1 0 0 -1 0 1 0 0 S3 40 0 0 1 0 0 1 0 0 10 A4 105 1 0 1 0 1 0 -1 1 Zj 1155 10 7 10 0 3 0 -3 10 Cj - Zj -1155 -2 0 -6 0 -3 0 7 0

(54)

Second Tableau

8 7 4 0 0 0 10 10

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 A2 A4 ETR

0 S1 20 1 0 1 1 2 0 -1 0 20 7 X2 15 0 1 0 0 -1 0 1 0 0 0 S3 40 0 0 1 0 0 1 0 0 40 10 A4 105 1 0 1 0 1 0 -1 1 105 Zj 1155 10 7 10 0 3 0 -3 10 Cj - Zj -1155 -2 0 -6 0 -3 0 7 0

(55)

Third (Final) Tableau

8 7 4 0 0 0 10 10

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 A2 A4 ETR

4 X3 20 1 0 1 1 2 0 -1 0 7 X2 15 0 1 0 0 -1 0 1 0 0 S3 20 1 0 0 -1 -2 1 1 0 10 A4 85 0 0 0 -1 -1 0 0 1 Zj 1035 4 7 4 -6 -9 0 3 10 Cj - Zj -1035 4 0 0 6 9 0 7 0

The solution is optimal: X3 = 20 X1 = 0 Min Z = 8X1 + 7X2 + 4X3 + 10A4 X2= 15 A4 = 85 = 1035

(56)

D. Solve the following problems using simplex method:

4. The Jay Gee Bull Ranch has plans to sell cattle to a large meat packaging plant. The manager of the ranch believes that each cattle should receive a minimum of 240 oz. of nutritional ingredients A and a minimum of 150 oz. of nutritional ingredients B each week. There are two grains available which contain both types of nutritional ingredients. One bag of grain 1 contains 12 oz of ingredients A and 25 oz of ingredients B and costs P140/bag; one bag of grain 2 contains 20 oz of ingredients A and five (5) oz. of ingredients B and costs P120/bag. Determine the optimum mixture of grains and the associated minimum cost.

(57)

Z = 140x + 120y + 0S1 + 0S2 + 1000A1 + 1000A2 12x + 20y -1S1 + 0S2 + 1A1 + 0A2 = 35 25x + 5y + 0S1 - 1S2 + 0A1 + 1A2 = 35 4. Minimize: Z = 140x + 120y subject to: Ingredients A 12X + 20Y ≥ 240 Ingredients B 25X + 5Y ≥ 150 x,y ≥ 0

D. Solve the following problems using simplex method:

Let X = grain 1 Y = grain 2

(58)

Initial Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR

1000 A1 240 12 20 -1 0 1 0

1000 A2 150 25 5 0 -1 0 1

Zj 390000 37000 25000 -1000 -1000 1000 1000 Cj - Zj -390000 -36860 -24880 1000 1000 0 0

(59)

Initial Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR

1000 A1 240 12 20 -1 0 1 0 20

1000 A2 150 25 5 0 -1 0 1 6

Zj 390000 37000 25000 -1000 -1000 1000 1000 Cj - Zj -390000 -36860 -24880 1000 1000 0 0

(60)

Second Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR 1000 A1 168 0 88/5 -1 12/25 1 -12/25

140 X 6 1 1/5 0 -1/25 0 1/25

Zj 168840 140 18300 -1000 4794.4 1000 -4794.4 Cj - Zj -168840 0 -18180 1000 -4794.4 0 5794.4

(61)

Second Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR 1000 A1 168 0 88/5 -1 12/25 1 -12/25 840/88

140 X 6 1 1/5 0 -1/25 0 1/25 30

Zj 168840 140 18300 -1000 4794.4 1000 -4794.4 Cj - Zj -168840 0 -18180 1000 -4794.4 0 5794.4

(62)

Third Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR 120 Y 105/11 0 1 -5/88 3/110 5/88 -3/110

140 X 45/11 1 0 1/88 -1/22 -1/88 1/22 Zj 1145.45 140 120 5.23 -3.09 5.23 -4794.4 Cj - Zj -1145.55 0 0 -5.23 3.09 994.8 6.36

(63)

Third Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR 120 Y 105/11 0 1 -5/88 3/110 5/88 -3/110 -168

140 X 45/11 1 0 1/88 -1/22 -1/88 1/22 360 Zj 1145.45 140 120 5.23 -3.09 5.23 -4794.4

(64)

Fourth Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR

120 Y 30 5 1 0 -22/110 0 22/110

0 S2 360 88 0 1 -4 -1 4

Zj 3,600 600 120 0 -24 0 24

(65)

Fourth Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR

120 Y 30 5 1 0 -22/110 0 22/110 0

0 S2 360 88 0 1 -4 -1 4 4.09

Zj 3,600 600 120 0 -24 0 24

(66)

Fifth (Final) Tableau

140 120 0 0 1000 1000

Cont. Soln. Qty. X Y S1 S2 A1 A2 ETR 120 Y 105/11 0 1 -5/88 3/110 -5/88 -3/110

140 X 45/11 1 0 1/88 -4/88 1/88 4/88 Zj 1718.18 140 120 -5.23 -3.09 5.23 3.09 Cj - Zj -1718.18 0 0 5.23 3.09 994.77 996.91

The solution is optimal: Y = 105/11 Min Z = 140X + 120Y X= 45/11 = 1718.18

(67)

D. Solve the following problems using simplex method:

5. A manufacturer makes two products; picnic tables and benches, which must be processed through two machine centers. MC1 has up to 60 hours available. MC2 can handle up 48 hours of work. Each picnic table requires four (4) hours in MC1 and two (2) hours in MC2. Each bench takes two (2) hours in MC1 and four(4) hours in MC2. If profit is P80/picnic table and P60/bench, determine the best possible contribution of picnic tables and benches to produce and sell in order to realize the maximum profit.

(68)

Z = 80x + 60y + 0S1 + 0S2 4X+ 2Y + 1S1 + 0S2 = 60 2X+ 4Y + 0S1 + 1S2 = 48 5. Maximize: Z = 80x + 60y subject to: MC 1 4x+ 2y ≤ 60 MC 2 2x+ 4y ≤ 48

D. Solve the following problems using simplex method:

Let X = picnic table Y = bench

(69)

Initial Tableau

80 60 0 0

Cont. Soln. Qty. X Y S1 S2 ETR

0 S1 60 4 2 1 0

0 S2 48 2 4 0 1

Zj 0 0 0 0 0

(70)

Initial Tableau

80 60 0 0

Cont. Soln. Qty. X Y S1 S2 ETR

0 S1 60 4 2 1 0 15

0 S2 48 2 4 0 1 24

Zj 0 0 0 0 0

(71)

Second Tableau

80 60 0 0

Cont. Soln. Qty. X Y S1 S2 ETR

80 X 15 1 1/2 1/4 0

0 S2 18 0 3 -1/2 1

Zj 1200 80 40 20 0

(72)

Second Tableau

80 60 0 0

Cont. Soln. Qty. X Y S1 S2 ETR

80 X 15 1 1/2 1/4 0 7.5

0 S2 18 0 3 -1/2 1 6

Zj 1200 80 40 20 0

(73)

Third Tableau

80 60 0 0

Cont. Soln. Qty. X Y S1 S2 ETR

80 X 4 1 0 1/3 -1/6

60 Y 8 0 1 -1/6 1/3

Zj 800 80 60 16.67 6.67 Cj - Zj -800 0 0 -16.67 -6.67

The solution is optimal: X = 4 Max Z = 80X + 60Y y = 8 = 800

(74)

D. Solve the following problems using simplex method:

6. Mr. Winston Pe can produce in his shop any mix of three products x,y, and z. The prices and variable cost per unit are:

Product Price/unit Variable cost/unit X P20 P11

Y 12 8 Z 8 6

Winston processes three product in each of the three departments I, II, III. The time requirements per department are as follows:

80 hours per day is available at each of the department. Develop the set of constraints and the objective function to maximize profit. How much is the maximum profit?

(75)

Z = 9x + 4y + 2z + 0S1 + 0S2 + 0S3 2X+ 4Y + 3z + 1S1 + 0S2 + 0S3 = 80 X+ 6Y + 5z + 0S1 + 1S2 + 0S3 = 80 7X+ 2Y + 9z + 0S1 + 0S2 + 1S3 = 80 6. Maximize: Z = 9x + 4y + 2z subject to: Dept. 1 2x+ 4y + 3y ≤ 80 Dept. 2 x+ 6y + 5y ≤ 80 Dept. 3 7x + 2y + 9z ≤ 80

(76)

Initial Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 80 2 4 3 1 0 0

0 S2 80 1 6 5 0 1 0

0 S2 80 7 2 9 0 0 1

Zj 0 0 0 0 0 0 0

(77)

Initial Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 80 2 4 3 1 0 0 40

0 S2 80 1 6 5 0 1 0 80

0 S2 80 7 2 9 0 0 1 11.43

Zj 0 0 0 0 0 0 0

(78)

Second Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 400/7 0 24/7 3/7 1 0 -2/7 0 S2 480/7 0 40/7 26/7 0 1 -1/7

9 X 80/7 1 2/7 9/7 0 0 1/7

Zj 102.86 9 2.57 11.57 0 0 1.29 Cj - Zj -102.86 0 1.43 -9.57 0 0 -1.29

(79)

Second Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 400/7 0 24/7 3/7 1 0 -2/7 133.3 0 S2 480/7 0 40/7 26/7 0 1 -1/7 18.46

9 X 80/7 1 2/7 9/7 0 0 1/7 8.89

Zj 102.86 9 2.57 11.57 0 0 1.29 Cj - Zj -102.86 0 1.43 -9.57 0 0 -1.29

(80)

Third Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 160/3 -1/3 10/3 0 1 0 -1/3 0 S2 4940/63 -26/9 308/63 0 0 1 -35/63

2 Z 80/9 7/9 2/9 1 0 0 1/9

Zj 17.78 1.56 0.44 2 0 0 0.22 Cj - Zj -17,78 7.44 3.56 0 0 0 -0.22

(81)

Third Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 160/3 -1/3 10/3 0 1 0 -1/3 -160 0 S2 4940/63 -26/9 308/63 0 0 1 -35/63 -27.25

2 Z 80/9 7/9 2/9 1 0 0 1/9 11.43 Zj 17.78 1.56 0.44 2 0 0 0.22

(82)

Fourth Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 1200/21 0 72/21 3/7 1 0 -6/21

0 S2 40 0 360/63 26/7 0 1 -9/63

9 X 80/7 1 2/7 9/7 0 0 1/7

Zj 102.86 9 2.57 11.57 0 0 1.29 Cj - Zj -102.86 0 1.43 -9.57 0 0 -1.29

(83)

Fourth Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 1200/21 0 72/21 3/7 1 0 -6/21 21.05

0 S2 40 0 360/63 26/7 0 1 -9/63 7

9 X 80/7 1 2/7 9/7 0 0 1/7 31.5

Zj 102.86 9 2.57 11.57 0 0 1.29 Cj - Zj -102.86 0 1.43 -9.57 0 0 -1.29

(84)

Fifth (Final) Tableau

9 4 2 0 0 0

Cont .

Soln. Qty. X Y Z S1 S2 S3 ETR

0 S1 232/7 0 0 -9/5 1 -3/5 -13/35

4 Y 7 0 1 13/20 0 7/40 -1/40

9 X 66/7 1 0 11/7 0 -1/20 19/140

Zj 112.85 9 4 16.74 0 0.25 1.12 Cj - Zj -112.86 0 0 -14,74 0 -0.25 -1.12 The solution is optimal: Y= 7 Max Z = 9X + 4Y + 2Z = 112.86 X = 66/7

(85)

D. Solve the following problems using simplex method:

7. The poultry farmer must supplement the vitamins in the feeds he buys. He is considering two supplements, each of which contains the feed required but in different amounts. He must meet or exceed the minimum vitamin requirements.

The vitamin content per gram of the supplements is given in the following table:

Vitamin Supplement 1 supplement 2 1 2 1

2 2 9 3 2 3

Supplement 1 costs P5 per gram and supplement 2 costs P4 per gram. The feed must contain at least 12 units of vitamin 1, 36 units of vitamin 2, and 24 units of vitamin 3. Determine the combination that has the minimum cost.

(86)

Z = 5x + 4y + 0S1 + 0S2 + 0S3 +10A1 + 10A2 + 10A3 2X + 1Y - 1S1 + 0S2 + 0S3 +1A1 + 0A2 + 0A3 = 12 2X + 9Y + 0S1 - 1S2 + 0S3 +0A1 + 1A2 + 0A3 = 36 2X + 3Y + 0S1 + 0S2 - 1S3 +0A1 + 0A2 + 1A3 = 24 7. Minimize: Z = 5x + 4y subject to: vita 1 2x+ 1y ≥ 12 vita 2 2x+ 9y ≥ 36 vita 3 2x + 3y ≥ 24

D. Solve the following problems using simplex method:

Let X = supplement 1 Y = supplement 2

(87)

Initial Tableau

5 4 0 0 0 10 10 10

Con t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

10 A1 12 2 1 -1 0 0 1 0 0 12 10 A2 36 2 9 0 -1 0 0 1 0 4 10 A3 24 2 3 0 0 -1 0 0 1 8 Zj 720 60 130 -10 -10 -10 10 10 10 Cj - Zj -0 -55 -126 10 10 10 0 0 0

(88)

Second Tableau 5 4 0 0 0 10 10 10 Cont. Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR 10 A1 8 16/9 0 -1 1/9 0 1 -1/9 0 4 Y 4 2/9 1 0 -1/9 0 0 1/9 0 10 A3 12 4/3 0 0 1/3 -1 0 -1/3 1 Zj 216 32 4 -10 4 -10 10 -4 10 Cj - Zj -216 -27 0 10 -4 10 0 14 0

(89)

Second Tableau 5 4 0 0 0 10 10 10 Co nt. Sol n. Qty. X Y S1 S2 S3 A1 A2 A3 ETR 10 A1 8 16/9 0 -1 1/9 0 1 -1/9 0 4.5 4 Y 4 2/9 1 0 -1/9 0 0 1/9 0 18 10 A3 12 4/3 0 0 1/3 -1 0 -1/3 1 9 Zj 216 32 4 -10 4 -10 10 -4 10 Cj - Zj -216 -27 0 10 -4 10 0 14 0

(90)

Third Tableau

5 4 0 0 0 10 10 10

Con t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

5 X 9/2 1 0 -9/16 1/16 0 9/16 -1/16 0 4 Y 3 0 1 1/8 -1/8 0 -1/8 1/8 0 10 A3 6 0 0 3/4 1/4 -1 -3/4 -1/4 1 Zj 94.5 5 4 0.188 2.31 -10 -5.19 -2.31 10 Cj - Zj -94.5 0 0 -0.188 -2.31 10 15.19 12.31 0

(91)

Third Tableau

5 4 0 0 0 10 10 10

Con t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

5 X 9/2 1 0 -9/16 1/16 0 9/16 -1/16 0 72 4 Y 3 0 1 1/8 -1/8 0 -1/8 1/8 0 -24 10 A3 6 0 0 3/4 1/4 -1 -3/4 -1/4 1 24 Zj 94.5 5 4 0.188 2.31 -10 -5.19 -2.31 10 Cj - Zj -94.5 0 0 -0.188 -2.31 10 15.19 12.31 0

(92)

Fourth Final Tableau 5 4 0 0 0 10 10 10 Cont. Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR 5 X 3 1 0 -3/4 0 1/4 3/4 0 -1/4 4 Y 6 0 1 1/2 0 -1/2 -1/2 0 1/2 0 S2 24 0 0 3 1 -4 -3 -1 4 Zj 39 5 4 -1.75 0 -0.75 1.75 0 0.75 Cj - Zj -39 0 0 1.75 0 0.75 8.25 0 9.25

The solution is optimal: Y= 6 Min Z = 5X + 4Y = 39 X = 3

(93)

D. Solve the following problems using simplex method:

8. The Ajax Manufacturing Company makes three products, x1, x2, and x3. The profit per unit for each is as follows: x1, P2; x2, P4; and x3, P3. The three products pass through three manufacturing centers as part of the manufacturing process. Product x1 requires 3 hours in center 1, two (2) hours in center 2, and one (1) hour in center 3; and product x2 requires 4 hours in center 1, 1 hour in center 2, and 3 hours in center 3; and product x3 requires 2 hours in each of the 3 centers. Each center has time available as follows; center 1, 60 hours; center 2, 40 hours; and center 3, 80 hours. Determine the optimum product mix for next week production schedule.

(94)

Z = 2x1 + 4x2 + 3x3 + 0S1 + 0S2 + 0S3 3x1+ 4x2 + 2x3 + 1S1 + 0S2 + 0S3 = 60 2x1+ 1x2 + 2x3 + 0S1 + 1S2 + 0S3 = 40 1x1+ 3x2 + 2x3 + 0S1 + 0S2 + 1S3 = 80 8. Maximize: Z = 2x1 + 4x2 + 3x3 subject to: Center 1 3x1+ 4x2 + 2x3 ≤ 60 Center 2 2x1+ 1x2 + 2x3 ≤ 40 Center 3 1x1+ 3x2 + 2x3 ≤ 80 x1,x2, x3≥ 0

(95)

Initial Tableau

2 4 3 0 0 0

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 ETR

0 S1 60 3 4 2 1 0 0

0 S2 40 2 1 2 0 1 0

0 S3 80 1 3 2 0 0 1

Zj 0 0 0 0 0 0 0

(96)

Initial Tableau

2 4 3 0 0 0

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 ETR

0 S1 60 3 4 2 1 0 0 15

0 S2 40 2 1 2 0 1 0 40

0 S3 80 1 3 2 0 0 1 26.67

Zj 0 0 0 0 0 0 0

(97)

Second Tableau

2 4 3 0 0 0

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 ETR 4 X2 15 3/4 1 2/4 1/4 0 0

0 S2 25 1/4 0 2/4 -1/4 1 0 0 S3 35 -5/4 0 2/4 -3/4 0 1

Zj 60 3 4 2 1 0 0

(98)

Second Tableau

2 4 3 0 0 0

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 ETR 4 X2 15 3/4 1 2/4 1/4 0 0 30 0 S2 25 1/4 0 2/4 -1/4 1 0 50 0 S3 35 -5/4 0 2/4 -3/4 0 1 70

Zj 60 3 4 2 1 0 0

(99)

Third (Final) Tableau

2 4 3 0 0 0

Cont. Soln. Qty. X1 X2 X3 S1 S2 S3 ETR 3 X3 30 3/2 2 1 1/2 0 0

0 S2 10 -1/2 -1 0 -1/2 1 0

0 S3 20 -2 -1 0 -1 0 1

Zj 90 4.5 6 3 1.5 0 0 Cj - Zj -90 -2.5 -2 0 -1.5 0 0

The solution is optimal: X3= 30 Max Z = 2X1 + 4X2 + 3X3 = 90 S2 = 10

(100)

D. Solve the following problems using simplex method:

9. The dean of the university, College of B.A, plans the course offerings for the second semester. Student demands make it necessary to offer at least 30 undergraduate and 20 graduate courses in the term. Faculty contracts also dictate that at least 60 courses be offered in total. Each undergraduate course taught costs the college an average of P2,500,000 in faculty wages, and each graduate course costs P3,000,000. How many undergraduate and graduate courses should be taught in the second semester so that total faculty salaries are kept to a minimum?

(101)

Z = 2.5Mx + 3My + 0S1 + 0S2 + 0S3 +10MA1 + 10MA2 + 10MA3 1X + 0Y - 1S1 + 0S2 + 0S3 +1A1 + 0A2 + 0A3 = 30 0X + 1Y + 0S1 - 1S2 + 0S3 +0A1 + 1A2 + 0A3 = 20 1X + 1Y + 0S1 + 0S2 - 1S3 +0A1 + 0A2 + 1A3 = 60 9. Minimize: Z = 2.5Mx + 3My subject to: Course offerings x ≥ 30 y ≥ 20 x + y ≥ 60

D. Solve the following problems using simplex method:

Let X = undergraduate Y = graduate

(102)

Initial Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

10M A1 30 1 0 -1 0 0 1 0 0 10M A2 20 0 1 0 -1 0 0 1 0 10M A3 60 1 1 0 0 -1 0 0 1 Zj 1100M 20M 20M -10M -10M -10M 10M 10M 10M Cj - Zj -1100M -17.5M -17M 10M 10M 10M 0 0 0

(103)

Initial Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

10M A1 30 1 0 -1 0 0 1 0 0 30 10M A2 20 0 1 0 -1 0 0 1 0 0 10M A3 60 1 1 0 0 -1 0 0 1 60 Zj 1100M 20M 20M -10M -10M -10M 10M 10M 10M Cj - Zj -1100M -17.5M -17M 10M 10M 10M 0 0 0

(104)

Second Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

2.5M X 30 1 0 -1 0 0 1 0 0 10M A2 20 0 1 0 -1 0 0 1 0 10M A3 30 0 1 1 0 -1 -1 0 1 Zj 575M 2.5M 20M 7.5M -10M -10M -7.5M 10M 10M Cj - Zj -575M 0 -17M -7.5M 10M 10M 2.5M 0 0

(105)

Second Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

2.5M X 30 1 0 -1 0 0 1 0 0 0 10M A2 20 0 1 0 -1 0 0 1 0 20 10M A3 30 0 1 1 0 -1 -1 0 1 30 Zj 575M 2.5M 20M 7.5M -10M -10M -7.5M 10M 10M Cj - Zj -575M 0 -17M -7.5M 10M 10M 2.5M 0 0

(106)

Third Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

2.5M X 30 1 0 -1 0 0 1 0 0 3M Y 20 0 1 0 -1 0 0 1 0 10M A3 10 0 0 1 1 -1 -1 -1 1 Zj 235M 2.5M 3M 7.5M 7M -10M -7.5M -7M 10M Cj - Zj -235M 0 0M -7.5M -7M 10M 17.5M 17M 0

(107)

Third Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

2.5M X 30 1 0 -1 0 0 1 0 0 -2.5 3M Y 20 0 1 0 -1 0 0 1 0 0 10M A3 10 0 0 1 1 -1 -1 -1 1 10 Zj 235M 2.5M 3M 7.5M 7M -10M -7.5M -7M 10M Cj - Zj -235M 0 0M -7.5M -7M 10M 17.5M 17M 0

(108)

Fourth Tableau

2.5M 3M 0 0 0 10M 10M 10M Con

t.

Soln. Qty. X Y S1 S2 S3 A1 A2 A3 ETR

2.5M X 40 1 0 0 1 -1 0 -1 1 3M Y 20 0 1 0 -1 0 0 1 0 0 S1 10 0 0 1 1 -1 -1 -1 1 Zj 160M 2.5M 3M 0 -0.5M -2.5M 0 0.5M 2.5M Cj - Zj -160M 0 0 0 0.5M 2.5M 10M 9.5M 7.5M

The solution is optimal: X= 40 Min Z = 2.5MX + 3MY = 160M Y = 20 Where: M= million pesos

References

Related documents

Results suggest that the probability of under-educated employment is higher among low skilled recent migrants and that the over-education risk is higher among high skilled

The main optimization of antichain-based algorithms [1] for checking language inclusion of automata over finite alphabets is that product states that are subsets of already

Aptness of Candidates in the Pool to Serve as Role Models When presented with the candidate role model profiles, nine out of ten student participants found two or more in the pool

role of Women in Development (WID) as an important component of EIA studies for major projects, as well as other aspects of environment related work undertaken by Newtech included

Field experiments were conducted at Ebonyi State University Research Farm during 2009 and 2010 farming seasons to evaluate the effect of intercropping maize with

The samples of adherend for each variant of bonded joints were subjected to 3 methods of surface treatment: mechanical treatment with the P120 grain size abrasive paper and degreas

Customer relationship has been regarded as the most important issue of the firms, so that an attempt is made to develop customer relationships and their comments on quality and