• No results found

Project Management Planning

N/A
N/A
Protected

Academic year: 2021

Share "Project Management Planning"

Copied!
22
0
0

Loading.... (view fulltext now)

Full text

(1)

1.040/1.401

1.040/1.401

Project Management

Project Management

Spring 2007

Spring 2007

Planning

Planning

Dr. SangHyun Lee

Department of Civil and Environmental Engineering

Department of Civil and Environmental Engineering

Massachusetts Institute of Technology

(2)

Project Management Phase

Project Management Phase

FEASIBILITY DEVELOPMENT CLOSEOUT OPERATIONS

Fin.&Eval. Risk Estimating Planning Planning DESIGN DESIGN PLANNING PLANNING Organization

(3)

Outline

Outline

¾

¾

Planning

Planning

Hierarchical Project Structures

Hierarchical Project Structures

ƒ

ƒ Work Breakdown StructureWork Breakdown Structure ƒ

ƒ Organization Breakdown StructureOrganization Breakdown Structure

ƒ

(4)

Planning Components

Planning Components

„

„ What: Work Breakdown StructureWhat: Work Breakdown Structure

„

„ How: Plans and SpecificationsHow: Plans and Specifications

„

„ Who: Organization Breakdown StructureWho: Organization Breakdown Structure

„

„ How much: Cost Breakdown Structure (via estimate)How much: Cost Breakdown Structure (via estimate)

„

(5)

Outline

Outline

ƒ

ƒ

Planning

Planning

Hierarchical Project Structures

Hierarchical Project Structures

¾

¾Work Breakdown StructureWork Breakdown Structure ƒ

ƒ Organization Breakdown StructureOrganization Breakdown Structure

ƒ

(6)

Work Breakdown Structure

Work Breakdown Structure

„

„ A WBS is a deliverableA WBS is a deliverable--oriented grouping of project components oriented grouping of project components

that organizes and defines the total scope of the project

that organizes and defines the total scope of the project

„

„ Work not in the WBS is outside the scope of the projectWork not in the WBS is outside the scope of the project

„

„ WBS is usually an operative tool used by contractorsWBS is usually an operative tool used by contractors

„

„ First step towards constructing a scheduleFirst step towards constructing a schedule

„

(7)

WBS: Example

WBS: Example

Source: Shtub et al., 1994 different summary level

Project

Site-Work On-Site Utilities Buildings

Grading and

Drainage SurfacesPaving SystemWater UndergroundElectrical

Work

Package PackageWork PackageWork Office

Building MaintenanceBuilding WarehouseBuilding

Drives Parking Architectural

Foundation Shell

Structural Mechanical Electrical

Level I Major Facilities Level II Sub-Facilities Level III Work Item Level IV Tasks Level V Work Packages Denotes continued breakdown

Illustrative Work Breakdown Structure (WBS)

(8)

Work Package

Work Package

„

„ Lowest levelLowest level

„

„ Distinguish from OthersDistinguish from Others

„

„ Single Responsible OrganizationSingle Responsible Organization

„

„ Assigned Start and FinishAssigned Start and Finish

„

„ Assigned BudgetAssigned Budget

„

(9)

Types of WBS

Types of WBS

„

„ Project WBSProject WBS

„

„ Operative tool for monitoring and control contractor workOperative tool for monitoring and control contractor work

„

„ Contractual WBSContractual WBS

„

„ Defines the level of reporting that the seller will provide the Defines the level of reporting that the seller will provide the buyerbuyer

„

„ May include less detail than Project WBSMay include less detail than Project WBS

„

(10)

level 0 level 1 level 2 level 3 level 4 level 5

Functional

Functional

Approach

Approach

GAS-STEAM COMBINED POWER PLANT

MAIN FUNCTIONS OF PLANT

UNITS

GAS STEAM INTERFACES

TURBINE GENERATOR COMPRESSION STATION

COMPRESSORS GAS TREATMENT ENCLOSURE

SUB-UNITS WORK PACKAGES

ITEMS

COMPRESSOR 1 COMPRESSOR 2 FOUNDATIONS

(11)

Physical Space Approach

Physical Space Approach

„

„

Project

Project

„

„ Main buildingMain building

„ „ 1st floor1st floor „ „ StructuresStructures „ „ PlumbingsPlumbings „ „ ElectricalElectrical „ „ HVACHVAC „ „ 2nd floor2nd floor „

„ Service buildingService building

„ „ StructuresStructures „ „ PlumbingsPlumbings „ „ ElectricalElectrical „ „ HVACHVAC

(12)

Procedure Approach

Procedure Approach

„ „ ProjectProject „ „ FeasibilityFeasibility „ „ DesignDesign „ „ BasicBasic „ „ DetailDetail „

„ Bid documentsBid documents

„

„ Shop drawingsShop drawings

„

„ BidBid „

„ ConstructionConstruction

„

„ Foundations subcontractFoundations subcontract

„

„ Main buildingMain building „

„ PilesPiles

„

„ Concrete foundationsConcrete foundations

„

„ Service buildingService building „

„ PilesPiles

„

„ Concrete foundationsConcrete foundations

„

„ Steel erectionSteel erection

„

„ FinishingsFinishings

„

(13)

WBS: CSI Master Format

WBS: CSI Master Format

-

-

Example

Example

Source: Schaufelberger et al., 2002

1 Job Site General conditions 9 Finishes: 2 Site work: Drywall

Earthwork & Utilities Painting

Paving Acoustical Ceilings Walks & Miscellaneous Sitework Floor Covering: Carpet

3 Concrete: Floor Covering: Ceramic, Vinyl, Base Purchase Reinforcement Steel 10 Specialties

Foundations 11, 12, 13 Walls & Slabs

4 Masonry 14 Conveying Systems (Elevator) 5 Structural and Miscellaneous Metals 15 Mechnical Systems:

6 Wood & Plastic Plumbing Rough Carpentry Fire Protection Finish Carpentry / Wood Floors HVAC

7 Thermal & Moisture Protection Controls Insulation 16 Electrical Systems Roof & Accessories

Gutters & Downspouts 8 Doors, Windows, Glass

Doors

Windows & Storefront Door Hardware

Equipment, Furnishings, & Special Construction

NORTHWEST CONSTRUCTION COMPANY

1242 First Avenue, Cascade, Washington 98202 (206) 239-1422

CSI

Division Description

CSI

Division Description Work Breakdown Structure

Huna Office Building 7/15/2000

(14)

Outline

Outline

ƒ

ƒ

Planning

Planning

Hierarchical Project Structures

Hierarchical Project Structures

9

9Work Breakdown StructureWork Breakdown Structure ¾

¾Organization Breakdown StructureOrganization Breakdown Structure

ƒ

(15)

Organization Breakdown Structure

Organization Breakdown Structure

„

„ Decomposition of necessary resources to perform jobDecomposition of necessary resources to perform job

„

„ Identification & organization of the resources responsible with Identification & organization of the resources responsible with

carrying out activities associated with the project

carrying out activities associated with the project

„

„ Used to keep track of specific work assignments & resource Used to keep track of specific work assignments & resource

allocations

(16)

Organization Breakdown Structure

Organization Breakdown Structure

„

„ Project resourcesProject resources

„

„ Project management teamProject management team

„

„ Project managerProject manager

„

„ Construction superintendentConstruction superintendent

„

„ Field superintendentField superintendent

„

„ Office managerOffice manager

„

„ SchedulerScheduler

„

„ Accounter/controllerAccounter/controller

„

„ Field engineerField engineer

„

„ Construction forceConstruction force

„ „ WorkerWorker „ „ SubcontractorSubcontractor „ „ ElectricalElectrical „ „ PlumbingPlumbing „ „ InsulationInsulation „ „ TankageTankage „ „ RoadsRoads

(17)

OBS/WBS

OBS/WBS

Linkages

Linkages

Source: Shtub et al., 1994

Project People

WBS OBS

Major

Facility GroupMajor

Sub Facility or DepartmentSub Group

Work Item Discipline

Task 2

Task 1 Task 3 Engineer A Engineer B Engineer C

Work Package 1

Work Package 2

Work

Package 3 Denotes continuedbreakdown

Linking the WBS and OBS.

(18)

Outline

Outline

ƒ

ƒ

Planning

Planning

Hierarchical Project Structures

Hierarchical Project Structures

9

9Work Breakdown StructureWork Breakdown Structure 9

9Organization Breakdown StructureOrganization Breakdown Structure

¾

(19)

Cost Breakdown Structure (CBS)

Cost Breakdown Structure (CBS)

„

„ Breakdown of the costs of the various components of the Breakdown of the costs of the various components of the

structure including all work done by the subcontractors

structure including all work done by the subcontractors

„

„ Serves as a basis for subsequent monthly pay requests by the Serves as a basis for subsequent monthly pay requests by the

contractor

contractor

„

„ Used to continuously compare costs as they actually occur Used to continuously compare costs as they actually occur

with the budget

(20)

Cost Breakdown Structure (CBS)

Cost Breakdown Structure (CBS)

Source: Shtub et al., 1994

100 Clearing & Grubbing 245 Precast Concrete 101 Demolition 260 Concrete forms 102 Underpinning .01 footings 103 Earth Excavation .05 grade beams 104 Rock Excavation .07 slab on grade 105 Backfill .08 beams

115 Wood structural piles .10 slab 116 Steel structural piles .11 columns 117 Concrete structural piles .12 walls

121 Steel sheet piling 280 Structural Steel 240 Concrete poured 350 Masonry

.01 footings .01 8 in. block .05 grade beams .02 12 in. block .07 slab on grade .06 common brick .08 bcarns .20 face brick .10 slab on forms .60 glazed tile .11 columns 400 Carpentry .12 walls 440 Millwork

.16 stairs 500 Miscellaneous Metals .20 expansion joints .01 metal door frames .40 screeds .20 window sash .50 float finish .50 toilet partitions .51 trowel finish 560 Finish Hardware .60 rubbing 620 Paving

.90 curing 680 Allowance 685 Fencing Project Work Accounts .100 - .699

MASTER LIST OF PROJECT COST ACCOUNTS Subaccounts of General Ledger Account 80.000

(21)

Two Main Approaches

Two Main Approaches

„

„ CBS = WBSCBS = WBS

„

„ CBS is the project cost control structureCBS is the project cost control structure

„

„ CBS CBS ≠≠ WBSWBS

„

„ CBS is the corporate multiCBS is the corporate multi--project cost control structureproject cost control structure

„

(22)

Diverse Combinations

Diverse Combinations

„

„ WBS + OBS: Task assignmentsWBS + OBS: Task assignments

„

„ CBS + OBS: Budget monitoring of crews, etc.CBS + OBS: Budget monitoring of crews, etc.

„

„ OBS + Schedule: TimeOBS + Schedule: Time--specific crew assignmentsspecific crew assignments

„

References

Related documents

Checkpoint Tools and SMART Audit Suite • Powerful online resource—Checkpoint • Leading engagement management— Engagement CS and AdvanceFlow.. © 2013 Thomson Reuters/Tax

The effect of the extract on the kidney electrolyte after administration revealed no marked differences in the potassium levels while sodium, chloride and

The diurnal variation in aromatic VOC fluxes also suggested traffic and residential sources, though evaporative effects due to higher summer tempera- tures meant emissions were

And as you continue relaxing deeper, deeper and more deeply relaxed, I would like you to imagine all of the foods in your life which contain sugar, that’s right, just imagine

communities and an analysis on cost and benefit of PCD mechanism was done in three pairs. punctulatus, an inland vector became very rare with interventions),

and atomic data, was the same for all the abundance determinations. The logarithmic abundance gradients from this sample were computed and are presented in Table I, equal weight

• About two-thirds (65%) of the clients participating in the 1998 HICP identified as White, non-Hispanic. • African

For example, between 1950 and 1960, the average Social Security benefit rose from 57 to 81 percent of the poverty line (Smolensky, Danziger, and Gottschalk, 1988, p. Again,