• No results found

Part 2 - Assessment Outcomes

N/A
N/A
Protected

Academic year: 2021

Share "Part 2 - Assessment Outcomes"

Copied!
25
0
0

Loading.... (view fulltext now)

Full text

(1)
(2)

Part 2 - Assessment Outcomes

Table 2.1 – Assessment Details

Name of entity

St Lucia Campus

Total energy use in the last financial year 430,982 GJ

Total percentage of energy use assessed 10.38% %

Description of the way in which the entity carried out its assessment

The main campus of The University of Queensland (UQ) is located on a large bend in the Brisbane River at St Lucia about 10km from the CBD.  The St  Lucia Campus has over 33 major buildings with GFA greater than 5000m2 and over 60 smaller buildings.  A wide range of teaching, research, 

recreational and cultural activities are conducted on this campus.    

During 2010/11 energy efficiency consultants conducted Level 1 energy audits on nine buildings at St Lucia and a Level 2 energy audit on one  building, J D Story Building.  The audits resulted in a large number of recommendations to improve energy use.  Most covered lighting.  In two of  these buildings, the Queensland Biosciences Precinct and the Queensland Brian Institute, facility management personnel are exclusively assigned to  the buildings and therefore they had sufficient local knowledge to start the process of retrofitting new lighting. 

 

A data base system consisting of lighting technology surveys, detailing of specific opportunities (scopes of work) and implementation was developed.  A full scale trial retrofit was conducted at the JD Story Building during 2011/12 to prove this system.  This was followed by light technology surveys  and retrofitting of 8 buildings at St Lucia, namely, the Richards, Forgan Smith, Priestley, Hartley Teakle, Goddard and Steel Buildings, the Faculty of  Sciences Building 69 and the Human Movement Studies Building.  As well as changing light fittings and/or lamps, retrofit work at St Lucia has also  included  installation of passive infrared (PIR) and photoelectric (PE) sensors to turn off lights when not needed in toilets and meeting rooms.   

 As part of a continuing lighting technology survey program Plan at the St Lucia Campus, surveys were also conducted during 2011/12 of the Sir  William McGregor, Mansergh Shaw, General Purpose South and Sir Llew Edwards Buildings. 

 

During 2010/11 the University commissioned an energy and comfort audit of the UQ Centre.  The UQ Centre is the main graduation venue for the  University.  Students, their parents, relatives and friends, senior academic staff and dignitaries attend graduations and this provides an opportunity  to showcase the University.  For a number of years parts of the UQ Centre have, however, been uncomfortably hot at times during summer.  The  consultants recommended a multipronged strategy to reduce heat loads and improve comfort: improved lighting to reduce internal heat loads;  window film for the eastern windows to block out solar heat gain; and better maintenance of the air conditioning systems to enhance energy  efficiency and service delivery.  This work was successfully completed in 2011/12.

(3)

 

Towards the end of the 2011/12 year, tender documents were prepared for Level 2 energy audits of 12 major buildings on the St Lucia Campus and  associated reviews of the metering and BMS systems in these buildings. The buildings covered by the tender were Building 69, General Purpose  North 3, Hawken Engineering, Sir James Foot, Sir William MacGregor, Goddard, Mansergh Shaw, General Purpose South, Chamberlain, Sir Llew  Edwards, Hartley Teakle and Forgan Smith Buildings.  The contract for this work was awarded and work started before the end of the 2011/12 year. 

 

Air conditioning at St Lucia is provided using chilled water produced in central chiller stations.  St Lucia has 12 chiller stations serving multiple‐

building precincts and two stand alone installations – chillers that serve just a single building.  Presently the largest chilled water precinct, the Central  Precinct, has 12 buildings served by a single chiller station.  Understanding the production, distribution and use of chilled water at St Lucia, is 

essential to identifying efficiency opportunities.   

During 2010/11, a building control company installed temporary metering to monitor the performance of selected chillers in the three of the largest  chiller stations.  As a result of this exercise a decision was taken to install permanent electrical and chilled water metering on each chiller in the three  chiller stations (eight chillers in total) and create a network to monitor real time performance.  The meter installation was completed in 2011/12 and  the creation of a monitoring network commenced.  In the same year, scopes of works were prepared for the retrofit installation of chilled water  meters on chillers at two other precinct chiller stations, namely Human Movement Studies and Computer Sciences precinct stations.  Scopes of work  were also prepared for the installation of chilled water meters on three buildings; the Chancellery, the Learning Innovation Building and the 

Chamberlain Building.  Installation will occur during 2012/13. As part of the University’s CAPEX (new building) program, chilled water meters were  also installed in the chillers serving the new Centre for Advanced Imaging Building during 2011/12.  

 

A major review of electrical metering at St Lucia was conducted during 2011/12. Existing meters were identified and their location and other  attributes were entered into an asset management database. Single line diagrams were prepared showing the location of meters in the electrical  reticulation system. This work enabled strategic gaps in the present metering system to be identified. During 2011/12 approximately 30 new  electrical meters were installed at St Lucia to cover many of these gaps. This work is ongoing with the objective that by the end of 2012/13 it will be  possible to accurately monitor the electricity use in all 33 major buildings at the campus.  Electrical meters were also installed on chiller motors,  pumps and cooling towers as part of the work to establish a system to monitor energy consumed in the production distribution and use of chilled  water for air conditioning; the overall point of all this new metering is to enable energy use to be monitored, opportunities for improvement to be  identified and progress to be tracked. 

 

During 2011/12 opportunities to improve the operation of the Central Chiller Station and its precinct were identified (Figure 1).  A proposal was  developed to improve the operation of the chillers and their integration with the cooling towers.  A project to install an optimisation package on the  chillers station plant was developed.  This project is scheduled for implementation during 2012/13. Energy savings of around 20% are anticipated.   

       

(4)

 

Each building on the Central Chiller Precinct has one and in some cases two chilled water pumps.  Pumps motors are long lived and those on the  Central precinct were thought to pre‐date the availability of highly efficient models.  Over 95% of the lifecycle cost of a water pump is electricity  supply to the pump motor.  High efficiency motors can save so much electricity that it can make sense to swap out old motors (and recycle their  components) even if they still have plenty of life left in them.  A detailed audit of the pumps was conducted during 2011/12 and this confirmed that  opportunities exist to retrofit more efficient pump motors.  This work is planned for 2012/13. 

 

  Figure 1: Central Chiller Precinct at St Lucia (orange fill) [PP & SP = Primary and Secondary Pumps] 

(5)

Name of entity

Gatton Campus

Total energy use in the last financial year 61,582 GJ

Total percentage of energy use assessed 1.85% %

Description of the way in which the entity carried out its assessment

The UQ Gatton Campus is located adjacent to the Warrego highway at Gatton approximately 90km west of Brisbane.  The main activities at Gatton  are teaching and research associated with veterinary and agricultural science disciplines, food production and environmental management.  Gatton  has residential colleges to house students and accommodation for visiting staff.  It also has administration, teaching and research buildings, a  veterinary hospital and farm facilities such as a dairy, calf rearing sheds, piggery units and equine facilities.  

 

During 2010/11, consultants conducted a Level 1 energy audit of the Centre for Advanced Animal Science (CAAS), a complex of buildings at Gatton.   CAAS is a joint venture between the Queensland Department of Primary Industries and The University of Queensland.  The CAAS complex comprises  24 buildings ranging from containment laboratories through to animal sheds.  CAAS is a relatively new complex and possibly as a consequence, no  energy efficiency opportunities with paybacks of less than 4 years were identified by the audits. 

 

Two of the audit report‘s recommendations concerned hot water heating.  Recommendations were made to replace electric resistance storage  heaters with heat pumps or to augment the systems with solar collectors.  Retrofitting the relatively new existing equipment at CAAS was not  considered cost effective, but the University thought there that retrofitting hot water plant close to end of life would be viable. As a consequence  during 2011/12 the University reviewed how water is heated at Gatton and noted other opportunities for improvement, such as converting the  electric hot water heaters at the Halls of Residence to solar electric and heat pump water heating. Using heat recovery from refrigeration to heat  water was another opportunity noted. 

 

A detailed survey was undertaken of the hot water systems at the Halls of Residence. The Halls can accommodate around 450 people and provide  hot water for showers and clothes washing.   They have some LPG water heating systems but most of hot water demand is met via electric storage  heaters.  The total installed capacity is just over 180kW.  Detailed retrofit plan based on these surveys are now developed.   

 

The expansion of the dairy herd at Gatton revealed shortcomings in the system used to supply hot water for washing down and equipment flushing.  Electric resistance heating was used to provide this water.  Like most dairies the one at Gatton had a large refrigeration unit to cool the milk holding  vat.  During 2011/12 a project was developed to use the waste heat from the refrigeration unit to preheat the water needed for washing and 

(6)

transferred to the atmosphere via a radiator and a fan. This project was completed during 2011/12. It is expected to save approximately 15,000 kWh  in electricity per year or about $1,500 in running costs. 

 

During 2011/12 the University investigated an opportunity at Gatton to treat piggery and other waste streams via anaerobic digestion to produce  methane.   Solar thermal and photovoltaic power opportunities were also investigated at Gatton during 2011/12. It may be possible to integrate  these opportunities with other energy service proposals under investigation at Gatton in a way that reduces energy consumption overall.  This  possibility will be investigated further in 2012/13.  

 

An electrical meter documentation exercise, similar to that carried out at the St Lucia campus, was completed at Gatton during 2011/12. Meter  locations and other attributes were entered into an asset management data base and single line diagrams showing the campus electrical reticulation  and meter positions were drawn up.  This work will assist with the identification of energy efficiency opportunities in future years. 

                                     

(7)

Name of entity

Ipswich Campus

Total energy use in the last financial year 15,226 GJ

Total percentage of energy use assessed 16.32% %

Description of the way in which the entity carried out its assessment  

The UQ Ipswich Campus is located at Ipswich, approximately 40km west of Brisbane.  The campus was established in 1999 on the site of an historic  mental health facility.  The campus consists of a mix of heritage buildings and relatively modern facilities.  At Ipswich the University provides  teaching, research and clinical activity in the Health Sciences, but also offers programs in the Arts and Education. 

 

During 2010/11 two energy related initiatives took place at Ipswich.  The production and distribution of chilled water was reviewed by consultants in  the context of developing a chilled water master plan.  The local electricity distribution company, Energex, requested the University also explore the  potential for peak load reduction in the course of developing the master plan.  Subsequently, a chilled water thermal energy storage (TES) proposal  was developed for the Ipswich Campus.  The TES project had the potential to save energy as well as shift load to off‐peak periods.  The cost to the  University of a TES system turned out to be very high and a decision was taken not to proceed with the project.   Experience with this project has,  however, encouraged the University to explore a similar concept at its Gatton Campus were a number of factors may make TES more viable.    

During 2011/12 the university conducted a detailed light technology survey of all the interior lighting at the Ipswich campus.  The type, number and  location of all fittings and lamps were recorded in an Access database.  This information was then assessed to identify energy efficiency retrofit  opportunities based on replacing lamps, de‐lamping and installation of sensor controls, etc.   The retrofit projects are planned for 2012/13.   

Outdoor lighting was also reviewed at Ipswich.  There are over 200 pole mounted outdoor lights at Ipswich each containing a 70W sodium lamp.   Trials were conducted where the sodium lamp was replaced with a 24W compact fluorescent lamp.  Light levels remained satisfactory so this retrofit  is now being rolled out.    

 

An electrical meter documentation exercise, similar to that carried out at the St Lucia campus, was completed at the Ipswich campus during 2011/12.  Meter locations and other attributes were entered into an asset management data base and single line diagrams showing the campus electrical  reticulation and meter positions were drawn up.  This work will assist with the identification of energy efficiency opportunities in future years.

(8)

Name of entity

Moreton Bay Research Station

Total energy use in the last financial year 1,203 GJ

Total percentage of energy use assessed 0 %

Description of the way in which the entity carried out its assessment  

UQ’s Moreton Bay Research Station (MBRS) is located at Dunwich on North Stradbroke Island which is on the eastern side of Moreton Bay and about  45km east of Brisbane.  The MBRS is used to conduct marine research, to provide teaching facilities for University and secondary school students and  it is also used as a conference venue. 

 

In view of the high cost of electricity supplied to the MBRS, consultants were engaged to examine the feasibility of using renewable energy sources,  namely solar hot water heating and PV to supply some of the Station’s needs.  During 2010/11, the University also engaged with consultants and the  local electricity distribution company, Energex, to study peak load reduction opportunities at the MBRS.  These studies improved our knowledge of  the MBRS load profile and energy distribution across end uses and also indicated some general opportunities for energy efficiency improvements.       

One general opportunity related to lighting retrofits. Subsequently the University conducted a detailed survey of the lighting at the MBRS and drew  up a scope of work for improvements, which mainly consisted of replacing T8 fluorescent tubes withT5 tubes and the use of voltage controllers.  The  work is scheduled for completion early 2012/13. 

 

Another opportunity related to water heating.  The hot water system at MBRS is based on electric resistance storage cylinders and a pumped  circulation loop.  The existing shower heads were replaced with super low flow heads which lowered hot water use by almost 15%.  The circulation  pump was placed on a timer and this has reduced heat losses from the long pipe network.  The pipe insulation was also improved.  Finally a solar  collectors and storage tanks were installed. 

 

Solar heat gain through north to part of the MBRS is substantial and adds to the air conditioning load. During 2011/12 an opportunity was recognised  to address this issue through installation of reflective window film.  This work is scheduled for completion in 2012/13. 

 

The renewable energy feasibility study mentioned above has led to a 40kW PV installation on the roof of the MBRS, completed in November 2011.   While this does not qualify as an opportunity in terms of EEO legislation, the panels themselves create a secondary efficiency gain; they provide  significant shade to the research station roofs thus, reducing solar heat gain and load on air conditioning equipment.  It is difficult to quantify this  benefit at present but it is the subject of research at the University.   The renewable energy feasibility and load reduction studies also revealed that  energy management at the MBRS would be improved by the installation of sub‐meters and a power quality meter.  This work was completed during  2011/12 and is now assisting with the identification of further energy efficiency opportunities at the MBRS.

(9)

Name of entity

Heron Island Research Station

Total energy use in the last financial year 1,732 GJ

Total percentage of energy use assessed 0 %

Description of the way in which the entity carried out its assessment

Heron Island is located 72km NE of Gladstone, off the central Queensland coast.  The island has the Delaware North Heron Island Resort, a  Queensland Parks and Wildlife Service Ranger Station and the University’s Heron Island Research Station (HIRS).   

 

During 2010/11 Wide Bay Water Corporation managed a Commonwealth Government Green Precincts Project which was designed to improve  energy efficiency, reduce water use and reduce the carbon footprint of activities on this World Heritage Site. Wide Bay Water Corporation arranged  a comprehensive audit by external consultants of energy and water use at the HIRS.  Subsequently Wide Bay Water Corporation worked with UQ to  action many of the audit recommendations.  The University funded around two thirds of the cost of implementation and the balance came from the  Green Precincts program.  

 

One of the key Green Precincts projects, a 54kW photovoltaic installation, does not qualify itself as an EEO project, but the presence of solar panels  on the roofs of the research Station is thought to reduce solar heat load and thus reduce electricity used for air conditioning.  

 

Super low flow shower heads were installed resulting in energy savings of around 15% from the need to heat less hot water.  Water on the island  comes from the Resort’s desalination plant, so such water efficiency measures reduce the diesel consumption of the Resorts generators.  This saving  has not been attributed to UQ in this EEO report.   

 

The key projects that saved energy at the HIRS were: installing a variable speed (VS) drives; improved control on the HIRS seawater pump that  supplies water to the teaching and research aquariums; placing timers on the air conditioning equipment so that it switches off when people are not  present; improving the controls on food cold‐rooms and freezers; and making improvements to lighting.  These were all completed in 2010/11.     

During 2011/12 an opportunity was identified to replace an existing compressor on the island with a more energy efficient model. The compressor in  question was used to provide air to an ongoing climate change experiment.  This experiment runs 24 hours a day, every day, so the compressor’s  duty cycle is high and the potential energy saving from a more efficient model is considerable.  The replacement is scheduled for the first half of  2012/13. 

 

During 2011/12 in order to facilitate identification of further opportunities, a complete inventory was created of all the plant equipment and lighting  at the Research Station. The type of equipment, its location and rated load were noted in a database. This information will be reviewed during  2012/13 and viable energy efficiency opportunities will be implemented.  

(10)

Name of entity

Long Pocket

Total energy use in the last financial year 2,981 GJ

Total percentage of energy use assessed 10.83% %

Description of the way in which the entity carried out its assessment

The Queensland State Government made facilities at its Long Pocket site available to the University after the January 2011 Brisbane River flood. The  site is near Indooroopilly and about ten minutes by shuttle bus from the main campus at St Lucia. Prior to its use by UQ, the site was used by State  Government land, natural resource and environmental agencies (DERM and DEEDI).  Only part of the site was occupied by UQ in 2011/12 with the  rest lying largely vacant. Discussions between UQ and the State Government will determine the long term role for UQ at the Long Pocket site.  Walk through audits in late 2010/11 and 2011/12 in advance of UQ occupying given floor areas indicated that opportunities existed for the lighting  to be improved by retrofitting more efficient lamps or installing occupancy sensors. These opportunities were implemented during 2011/12. Once  the long term future of the site is determined UQ will be able to review other energy services such as the air conditioning systems. 

                                 

(11)

Name of entity

Indooroopilly Mine

Total energy use in the last financial year 3,707 GJ

Total percentage of energy use assessed 17.04% %

Description of the way in which the entity carried out its assessment

The University of Queensland Experimental Mine is located at Indooroopilly a suburb of Brisbane.  It is situated on a moderately steep slope  bordering Witton Creek some 200m from the Brisbane River. The site has a mining history dating back to 1918 when silver/lead mineralisation was  discovered.  It now has a number of surface office, teaching and maintenance buildings as well as subsurface mine features.  

The UQ School of Mechanical and Mining Engineering operate out of the site. The Julius Kruttschnitt Minerals Research Centre (JKMRC), now part of  the UQ Sustainable Minerals Institute (SMI), also shares surface infrastructure at the site. 

During 2011/12 the university surveyed the lighting in the surface buildings at the Mine site. Information on fitting and lamp locations, type, number  and control were recorded in an Access database.  This has revealed a number of retrofit opportunities which will be reviewed and where 

appropriate developed into scopes of work for implementation during 2012/13.                               

(12)

Table 2.2 - Energy efficiency opportunities identified in the assessment

St Lucia

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 27 2 23 3 123 22 795 941 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 60 14 433 9 86 37 1,407 1,927 Under Investigation 41 7 356 8 588 26 4,104 5,049 Not to be Implemented 33 1 9 0 0 32 762 771 Outcomes of

assessment Total Identified 161 24 821 20 798 117 7,068 8,687

Please note that Corporate Groups are not required to report opportunities with a payback greater than 4 years. Reporting this data is voluntary.

Gatton

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 1 0 0 1 54 0 0 54 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 0 0 0 0 0 0 0 0 Under Investigation 1 0 0 0 0 1 124 124 Not to be Implemented 3 0 0 0 0 3 200 200 Outcomes of

assessment Total Identified 5 0 0 1 54 4 324 378

(13)

Ipswich

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 0 0 0 0 0 0 0 0 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 1 0 0 1 145 0 0 145 Under Investigation 0 0 0 0 0 0 0 0 Not to be Implemented 1 0 0 0 0 1 1,260 1,260 Outcomes of

assessment Total Identified 2 0 0 1 145 1 1,260 1,405

Please note that Corporate Groups are not required to report opportunities with a payback greater than 4 years. Reporting this data is voluntary.

Moreton Bay Research Station

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 0 0 0 0 0 0 0 0 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 4 0 0 4 45 0 0 45 Under Investigation 0 0 0 0 0 0 0 0 Not to be Implemented 0 0 0 0 0 0 0 0 Outcomes of

assessment Total Identified 4 0 0 4 45 0 0 45

(14)

Heron Island Research Station

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 7 0 0 2 203 5 73 276 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 15 0 0 0 0 15 96 96 Under Investigation 0 0 0 0 0 0 0 0 Not to be Implemented 0 0 0 0 0 0 0 0 Outcomes of

assessment Total Identified 22 0 0 2 203 20 169 372

Please note that Corporate Groups are not required to report opportunities with a payback greater than 4 years. Reporting this data is voluntary.

Long Pocket

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 6 2 152 1 1 3 18 171 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 0 0 0 0 0 0 0 0 Under Investigation 0 0 0 0 0 0 0 0 Not to be Implemented 0 0 0 0 0 0 0 0 Outcomes of

assessment Total Identified 6 2 152 1 1 3 18 171

(15)

Indooroopilly Mine Site

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ Business Response Implemented 0 0 0 0 0 0 0 0 Implementation Commenced 0 0 0 0 0 0 0 0 To be Implemented 6 0 0 0 0 6 71 71 Under Investigation 0 0 0 0 0 0 0 0 Not to be Implemented 0 0 0 0 0 0 0 0 Outcomes of

assessment Total Identified 6 0 0 0 0 6 71 71

(16)

Table 2.3 - Details of significant opportunities identified in the assessment

Corporate Groups are required to provide at least 3 examples of significant opportunities for improving the energy efficiency of the group that have been identified in assessments.

Opportunity

 

1

 

 

Metering,

 

Meter

 

Inventory,

 

Prioritization

 

and

 

Expansion

Voluntary Information

A comprehensive, readily accessible metering system is a vital tool for identifying energy efficiency  opportunities, analysing these and  then monitoring the results of subsequent efficiency projects.  A good  metering system will also facilitate public communication and education through such means as website or  building foyer displays of real time energy use and comparisons with benchmarks or the performance of  other buildings.  

 

At July 2010, UQ was thought to have a substantial electrical sub‐metering network but details of the system  were not consistently documented and interrogating the system to analyse energy patterns was time 

consuming.  A program to systematically address these issues was rolled out during 2010/11 and continued in  2011/12:  

 

Key Opportunities realised:    

• Digital Power Meters were Documented and an Asset  Management  Database was created; 

• A Strategic Review was undertaken to Identify Priority Meters and Metering  Gaps 

• Chilled Water Energy Meters and Power Meters were installed on Chillers. 

• A software application was procured to enable the meters to be monitored in real time.   

Metering schematics were prepared showing the position of meters on the high voltage and low voltage  networks and hence the loads or sub‐ networks metered.  The schematics contain a communication layer so  that it is possible to visualise the relationship of meters to the IT network.  Accurate metering schematics  have enabled the identification of opportunities to create virtual meters and to cover gaps in the network.   The schematics have been organised into a library linked directly to the meter management database  (outlined shortly).  Users can toggle between meter attributes in the management database and a  visualisation of meter location and IT arrangements.  Figure 2 shows an example of metering schematic.    

Electrical power meters have a range of attributes that are important both for asset management and meter  interrogation.  Key attributes are: the IP address of the gateway that connects the meter to the LAN; the  physical location of the meter; and the nature of the load monitored by the meter (its location and type ‐  chiller, cooling tower, building light and power etc.).  The Microsoft access database enables reports to be run  on existing meters and allows new meters to properly documented and added to the system.   It also plays an 

Equipment Type Business Response Energy saved (GJ) Greenhouse gas abated (CO2-e) $s saved Payback period

(17)

consumption and trends from specific meters.  The database contains meters that measure on‐site power  production as well as consumption.  Figure 3 shows an extract from a report resulting from a search for all  meters at the St Lucia Campus that measure PV output. 

 

The metering schematics, the management data base and other information have enabled a strategic  overview of metering at UQ and the subsequent identification of gaps.  The UQ St Lucia campus for example  has 33 buildings with GFA greater than 5,000m2.  Of these buildings almost half – 15 buildings – do not have  sufficient metering to enable a determination of the electrical consumption of the building.  During 2011/12  scopes of work were developed to roll out enough meters to cover these gaps and most of the necessary  meters were installed. 

(18)

Air conditioning at UQ is mainly provided via chilled water networks serving air handling units or fan coil  units.  The central plant produces chilled water which is then distributed to buildings within the chiller  precinct.  In one case, 13 buildings are served by a single chiller station with three chillers.  The energy  consumed in the production of chilled water can represent 30% or more of the energy consumed in a 

building.  Accounting for this energy is important when benchmarking buildings and monitoring changes in AC  scheduling, adjustment of space set‐points or making other improvements.  At the start of 2010/11 the  production and distribution of chilled water “energy” was not metered a UQ.    

 

A program of works has been established to meter the production of chilled water from individual chillers and  also to separately meter the electrical input to chillers, pumps and cooling towers.  At the end of 2010/11 the  University started to install thermal meters on chillers and building chilled water off‐takes and continued this  work through 2011/12. To date meters have been installed on seven chiller stations and three buildings.    

 As a result:    

1. The efficiency of metered chillers (COP) can now be monitored to identify opportunities for changes  in maintenance or operation to improve energy efficiency; and  

 

2. The total electrical input to the production of chilled water can be determined and expressed as kWh  per litre of chilled water per oC – or as kWh per GJ of heat rejected. 

 

Most buildings already have flow meters that measure the amount of chilled water diverted to the building.   Where suitable these flow meters will be converted progressively to chilled water energy meters by the  addition of suitable temperature sensors.  If the flow meter is not suitable it will eventually be replaced with  one that is suitable for energy monitoring. Once this is done it will be possible to assign a share of the  electrical energy used to produce and circulate chilled water through particular buildings.  As mentioned  earlier, this will facilitate better energy management of the buildings.  Figure 3 shows an extract from the  schematic for the Central Chiller Station metering schematic showing the chilled water thermal meter  (CWM)  the electrical meter monitoring the chiller motor (DPM) and a virtual meter that monitors the chiller 

coefficient of performance (COP).   

At the start of the EEO cycle UQ had a system of data acquisition, retrieval and rendering that enables tables  and graphs of energy consumption and trends to be produced using metering data.  A considerable amount  of manual handling of data was needed, however, to get good results.  

     

(19)

During 2011/12, UQ trialled a new software front end that creates a user friendly reporting system – a system  that can be readily used by students, researchers, facilities engineers and consultants.  UQ intends to roll out  the system during 2012/13. This will improve overall visibility of energy use patterns and this in turn is  expected to lead to identification of a greater number of energy efficiency opportunities than is presently  possible.  

 

 

(20)

   

Figure 4: Chilled Water Metering Schematic ‐ Example             

(21)

Opportunity

 

2

 

 

Lighting

 

Surveys,

 

Data

 

Management

 

and

 

Retrofits

Voluntary Information

Building audits conducted during 2010 revealed a common theme; opportunities were present to  improve lighting through a range of measures: 

 

• Retrofitting T5 fluorescent tubes in suitable T8 fittings (those with electromagnetic ballasts); 

• Swapping 50W dichroic lamps with 35W high efficiency infrared coating (IRC) lamps; 

• Replacing 50W lamps with LEDs where existing  light levels were higher than needed; 

• De‐lamping – removing one tube from a twin fitting where light levels were high; and 

• Fitting voltage controllers to T8 magnetically ballasted fluorescent lighting circuits 

•  Installing passive infrared (PIR) occupancy sensors and piezoelectric (PE) daylight sensors to  turn lights off when not needed. 

 

The challenge faced by UQ was to develop a cost effective way of realising these opportunities without  creating unintended consequences now, or maintenance problems down the track.  The following  strategy was adopted: 

 

1. Conduct trials to identify pro and cons of each approach and develop scopes of work;  2. Establish some rules of thumb to identify the characteristics of cost effective opportunities;  3. Create a light technology survey methodology and data management system; 

4. Prove the survey and management system through a whole building trial   5. Progressively retrofit the lighting groups of buildings with efficient lighting. 

Installing PIR sensors in multi‐cubicle toilet blocks can, for example, create a problem if lights switch off  while people are still present, but are not detected by a sensor.  A solution was successfully trialled:   installation of low wattage light‐emitting diode (LED) pilot lights that remain on when the main lights  are turned off by the PIR.  This solution provides a good balance of energy efficiency, OH&S and  personal security.  Through various trials the limitations of each approach were discovered and  necessary mitigation measures were established. 

 

Lighting audits often recommend generic upgrades (replace T8 fluorescent tubes with T5 tubes), but  any given opportunity may not be cost effective in a particularly situation.  On the other hand, the cost  of doing a detailed financial analysis for every case creates an overhead that can counter the benefits of  a particular proposal.  This issue is usually dealt with by using rules of thumb – generalisations about  the scale or thresholds within which a type of project remains cost effective.  Rules of thumb are easy 

Equipment Type Business Response Energy saved (GJ) Greenhouse gas abated (CO2-e) $s saved Payback period

(22)

 

UQ, like other universities, is an expensive place to carry out retrofit work.  Meanwhile as a mixed  blessing, as a bulk purchaser, UQ is able to obtain electricity on very favourable terms.  This means that  standard energy efficiency rules of thumb do not readily apply at UQ. 

 

 In the course of conducting lighting trials UQ was also able to develop its own rules of thumb or the  range of lighting opportunities listed above.  Voltage controllers, for example, come in different sizes.   For each size, the minimum number of tubes that need to be connected to the controller, to create a  cost effective outcome, was determined.  Similarly the minimum amount of lighting (wattage) that  should be controlled by a PIR to make this retrofit worthwhile was also established.  This means that  the University now has some idea of the opportunities it should be looking for. 

 

The next challenge that faced UQ was finding the opportunities.  Buildings at the St Lucia campus, for  example, contain a mixture of very old fit‐outs and new refurbishment.  A single floor could contain a  wide range of lighting technologies.  The most cost effective work process for UQ was to identify the  lighting technology in place, review it, identify specific retrofit opportunities and then let contracts to  carry out the work.  Electrical contractors could then plan around a specific number and type of retrofit  for each building.  They would also know the exact location of each opportunity (building, floor and  room number).  

 

Consequently a lighting survey methodology was developed.  Initially a system using handwritten  records and entry to Excel was used.  Then to increase productivity and reduce entry error, an iPad  based field data entry system was developed (Figure 5 below).   The full system was then tested from  survey through to retrofit at a full scale building scale.  A combination of lighting improvement  measures were applied to the JD Story Building, one of the main administration buildings on the St  Lucia campus.  This was highly successful.  122 T8 tubes and 77 50H lights were replaced by T5 tubes  and LEDs, respectively. 

 

Subsequently, a second more challenging building was retrofitted.  The survey based approach is now  considered proven.   In 2010/11 and 2011/12, further buildings were surveyed at St Lucia and other  campuses or sites.  During 2011/12, contracts were let for the lighting retrofit of a tranche of 8 

buildings on the St Lucia Campus.  Retrofits of indoor lighting have also been implemented at Moreton  Bay Research Station and the Long Pocket campus. 

   

(23)
(24)

Opportunity 3: Chiller Optimisation Package Voluntary Information

The installation of permanent electrical and thermal meters on the chillers in the Central Chiller Station  has enabled chiller performance to be monitored. Low coefficients of performance were observed  especially at low load. The current operating regime for the chillers, cooling towers and associate  pumps is fairly rudimentary. Condenser water flow, cooling tower staging and chillers load are not  closely matched, for example. The chilled water set‐point is also fixed rather than allowed to float  slightly with the load.  It is possible to operate a chiller station and its cooling towers in a closely  matched manner to optimise service delivery and energy efficiency. 

 

A combination of the right equipment and a suitable control strategy is needed to achieve optimal  performance. During 2011/12 the University explored this opportunity further and is now considering  proposals to retrofit a chiller optimisation package on the Central Chiller Station.    

 

The work needed involves installation of a combination of new hardware and software:  

• Installation of Three (3) 45kW Variable Speed Drives for Condenser Water Pumps  

• Installation of Ten (10) 5.5kW Variable Speed Drives for Cooling Tower Fans  

• Installation of differential pressure transducers and temperature sensors as required  

• Installation of  Chiller Optimisation unit to control:   a) Three (3) Centrifugal Chillers  

b) Three (3) Existing Chilled Water Pump Variable Speed Drives  

c) Three (3) Newly supplied/Installed Condenser Water Pump Variable Speed Drives   d) Ten (10) Newly supplied/Installed Cooling Tower Fan Motor Variable Speed Drives   e) Primary Chilled Water Bypass Valves  

 

• Provide a software package to provide system visibility and control via desktop and HMI   

• Install HMI in the plant room to provide local visibility and control.     

This type of retrofit can typically yield energy savings of up to 25%. Installation of a suitable 

optimisation package on the Central Chiller Station as a trial is planned for 2012/13. If it is successful  then similar packages could be installed on the other chiller stations at UQ sites. 

Equipment Type

Chiller Station Retrofit:

Variable Speed Drives, ChW Bypass Central Control Unit and IT Equipment

Business

Response TBI (To Be Implemented) Energy saved (GJ) 3,168 Greenhouse gas abated (CO2-e) 783.2 tones

$s saved $88,000 per year

Payback period

1.75 years

(25)

Part 3 – Transition to Second Cycle

This table should only be completed by 2005-06 trigger-year corporations transitioning to the second cycle.

In December 2011 many corporations reported energy efficiency opportunities that were still under investigation as at 30 June 2011. This report should advise what your business response to these opportunities has been – implemented or not to be implemented. If you intend to further investigate these opportunities, they should be reported in the future Public Reports as opportunities identified in the second cycle.

Status of opportunities identified to an accuracy of better than or equal to ±30%

Total Number of opportunities

Estimated energy savings per annum by payback period (GJ) Total estimated energy savings per annum (GJ) 0 – 2 years 2 – 4 years > 4 years

No of Opps GJ No of Opps GJ No of Opps GJ As reported in December 2011 Under Investigation Business Response as at 30 June 2012 Implemented Not to be Implemented To be evaluated/reported in the second cycle

Figure

Table 2.2 - Energy efficiency opportunities identified in the assessment
Figure 5:  Lighting Technologies ‐ iPad Based Field Data Entry

References

Related documents

[r]

lafo/kkudrkZvksaus lkekftd lerk izLFkkfir djus gsrq cMs gh fopkjiwoZd izko/kku fd;k rkfd Hkkjrh; lekt ds gj ?kVd dks] gj bdkbZ dks] gj O;Drh dks gj leqnk;] tkfr] /keZ]

compulsory annuity. “Compulsory annuity” is defined to mean the remainder of the retirement interest of a person payable in the form of an annuity as contemplated in.. a)

above D4 Check Alignment and Leveling is proper   AFC Drawing T10206-YQ01- POZEN-141313 Refer to attached Checklist N/A Refer to attached Checklist N/A E1 Check type of fittings

• Incorporate performance expectations for activity-level WP&C into future contracts that include incentives for identification and analysis of deficiencies and corrective

The market covered by this Magic Quadrant contains vendors of e-discovery software solutions for the identification, preservation, collection, processing, review, analysis

The main categories of activities found to be essential in business model greening include recognizing the potential of business model change, establishing the desired vision

• A prospective payment also known as the Hospital Outpatient Prospective Payment System (OPPS) used by Medicare to Prospective Payment System (OPPS), used by Medicare to