KABLE MYANMAR FACTORY PROJECT
KABLE MYANMAR FACTORY PROJECT
METHOD OF STATEMENT FOR ELECTRICAL WORK
METHOD OF STATEMENT FOR ELECTRICAL WORK
PRESENTED BY
PRESENTED BY
GOLDEN FUTURE MYANMAR POWER
GOLDEN FUTURE MYANMAR POWER
April 4th 2019
April 4th 2019
1.
1. IntroductionIntroduction 2.
2. Scope of WorkScope of Work 3.
3. Method of Statement for Excavation, Pipe Laying and Back FillingMethod of Statement for Excavation, Pipe Laying and Back Filling 4.
4. Method of Statement for Manhole CastingMethod of Statement for Manhole Casting 5.
5. Method of Statement for Lamp post ErectionMethod of Statement for Lamp post Erection 6.
6. Method of Statement for CablingMethod of Statement for Cabling 7.
7. Method of Statement for Transformer InstallationMethod of Statement for Transformer Installation 8.
8. Method of Statement for MV/LV Panel InstallationMethod of Statement for MV/LV Panel Installation 9.
9. Method of Statement for Termination of MV Method of Statement for Termination of MV CableCable 10.
10.Method of Statement for Lighting Fixture InstallationMethod of Statement for Lighting Fixture Installation 11.
1.
1. INTRODUCTIONINTRODUCTION
This Method of Statement is issued as a confidential document and at all times This Method of Statement is issued as a confidential document and at all times remains the property of GFMP. This MOS is a live document and will be remains the property of GFMP. This MOS is a live document and will be updated from time to time to incorporate changing site circumstance and updated from time to time to incorporate changing site circumstance and
client’s recommendations. Copies of this plan will be provi
client’s recommendations. Copies of this plan will be provided toded to subcontractors and other parties working under GFMP.
subcontractors and other parties working under GFMP.
2.
2. SCOPE OF WORKSCOPE OF WORK
Supply, Delivery and Installation of Electrical System. Supply, Delivery and Installation of Electrical System.
3.
3. METHOD OF STATEMENT FOR EXCAVATION, PIPE LAYING AND BACK FIMETHOD OF STATEMENT FOR EXCAVATION, PIPE LAYING AND BACK FI LLINGLLING 1.1
1.1 Scope of ActivityScope of Activity
The Scope of Method of Statement is to describe the method of The Scope of Method of Statement is to describe the method of excavation for HDPE Flexible pipe laying for the proposed KALBE excavation for HDPE Flexible pipe laying for the proposed KALBE Project, Thilawa SEZ A, Yangon, Myanmar.
Project, Thilawa SEZ A, Yangon, Myanmar. 1.2
1.2 Site ObservationSite Observation
Before Commencement of the planned work, carry out examination Before Commencement of the planned work, carry out examination of the physical condition of
of the physical condition of the area for ongoing activities, blockagesthe area for ongoing activities, blockages of Ingress/ Egress and the weather
of Ingress/ Egress and the weather condition.condition. 1.3
1.3 Method of StatementMethod of Statement Preparation Preparation
Load all equipment required for JobLoad all equipment required for Job
Report to KDK and received approvalReport to KDK and received approval
Put on personal protective equipmentPut on personal protective equipment
Inform all other contractors in the area of start to workInform all other contractors in the area of start to work
Liaise with Main contractor and other contractor to beLiaise with Main contractor and other contractor to be
ensure safe operation ensure safe operation
Cordon of work areaCordon of work area
Ensure the area to be worked and exit points are clear ofEnsure the area to be worked and exit points are clear of
obstruction obstruction
Determine location of underground servicesDetermine location of underground services
Producer Producer
Provide copies of the shop drawings, copy of the permit toProvide copies of the shop drawings, copy of the permit to
work & necessary instructions. Briefly introduce the work & necessary instructions. Briefly introduce the workers on the safety aspects & safe work procedures. workers on the safety aspects & safe work procedures. Barricade the area of working.
Barricade the area of working.
Mark out area to be excavated with marker paintMark out area to be excavated with marker paint
Bring excavator onto site following safety proceduresBring excavator onto site following safety procedures
listed above listed above
Ensure trained banksman is available to watch excavationEnsure trained banksman is available to watch excavation
work work
Dig out ground as per contract drawings to required sizeDig out ground as per contract drawings to required size
and depth and depth
All excavations must be left safe at the end of each dayAll excavations must be left safe at the end of each day
The bottom of trench will be compacted prior toThe bottom of trench will be compacted prior to
installation of
installation of sand bedding sand bedding for the pfor the pipeipe
The pipe will be laydown as The pipe will be laydown as indicated on the approvedindicated on the approved shop drawings and according to
shop drawings and according to manufacturemanufacturer’s writingr’s writing
instruction instruction
After pipe laying, back fill will start step After pipe laying, back fill will start step by step.by step.
1.4 Waste Management 1.4 Waste Management
All waste materials to be removed from site on a daily basis. Trash All waste materials to be removed from site on a daily basis. Trash collecting bags are to be provided at the working areas. All general collecting bags are to be provided at the working areas. All general waste to be thrown into the
waste to be thrown into the provided trash bags according to the typeprovided trash bags according to the type of garbage (Segregate waste before disposal) and should be disposed of garbage (Segregate waste before disposal) and should be disposed in to the relevant metal
in to the relevant metal waste bins provided.waste bins provided. Wooden crates or palettes must be
To perform general housekeeping every day after the
To perform general housekeeping every day after the workwork Mass housekeeping exercise to be performed on weekly basis Mass housekeeping exercise to be performed on weekly basis
4.
4. METHOD OF STATEMENT FOR MANHOLE CASTINGMETHOD OF STATEMENT FOR MANHOLE CASTING 1.1
1.1 Scope of ActivityScope of Activity
The Scope of Method of Statement is to describe the method of The Scope of Method of Statement is to describe the method of excavation and electrical manhole casting for propose KALBE Project, excavation and electrical manhole casting for propose KALBE Project, Thilawa SEZ A,
Thilawa SEZ A, Yangon, Myanmar.Yangon, Myanmar. 1.2
1.2 Site ObservationSite Observation
Before Commencement of the planned work, carry out examination Before Commencement of the planned work, carry out examination of the physical condition of the
of the physical condition of the area for ongoing activities, blockagesarea for ongoing activities, blockages of Ingress/ Egress and the weather
of Ingress/ Egress and the weather condition.condition. 1.3
1.3 Method of StatementMethod of Statement Preparation Preparation
Load all equipment required for JobLoad all equipment required for Job
Report to KDK and received approvalReport to KDK and received approval
Put on personal protective equipmentPut on personal protective equipment
Inform all other contractors in the area of start to workInform all other contractors in the area of start to work
Liaise with Main contractor and other contractor to beLiaise with Main contractor and other contractor to be
ensure safe operation ensure safe operation
Cordon of work areaCordon of work area
Ensure the area to be worked and exit points are clear ofEnsure the area to be worked and exit points are clear of
obstruction obstruction
Ensure that safe access and Ensure that safe access and egress is maintainedegress is maintained
Determine location of underground servicesDetermine location of underground services
Producer Producer
Provide copies of the shop drawings, copy of the permit toProvide copies of the shop drawings, copy of the permit to
work & necessary instructions. Briefly introduce the work & necessary instructions. Briefly introduce the
Barricade the area of working. Barricade the area of working.
Mark out area to be excavated with marker paintMark out area to be excavated with marker paint
Bring excavator onto site following safety proceduresBring excavator onto site following safety procedures
listed above listed above
Ensure trained banksman is available to watch excavationEnsure trained banksman is available to watch excavation
work work
Dig out ground as per contract drawings to required sizeDig out ground as per contract drawings to required size
and depth and depth
All excavations must be left safe at the end of each dayAll excavations must be left safe at the end of each day
The bottom of trench will be compacted prior toThe bottom of trench will be compacted prior to
installation of
installation of sand bedding sand bedding for the pfor the pipeipe
Start fabricating rebar work at the work shop and Start fabricating rebar work at the work shop and InstallInstall
rebar at designated manhole. rebar at designated manhole.
After finished rebar work, pour coAfter finished rebar work, pour concrete ncrete step by step.step by step.
1.4 Waste Management 1.4 Waste Management
All waste materials to be removed from site on a daily basis. Trash All waste materials to be removed from site on a daily basis. Trash collecting bags are to be provided at the working areas. All general collecting bags are to be provided at the working areas. All general waste to be thrown into the
waste to be thrown into the provided trash bags according to the typeprovided trash bags according to the type of garbage (Segregate waste before disposal) and should be disposed of garbage (Segregate waste before disposal) and should be disposed in to the relevant metal
in to the relevant metal waste bins provided.waste bins provided.
Wooden crates or palettes must be dismembered before disposal Wooden crates or palettes must be dismembered before disposal
5.
5. METHOD OF STATEMENT FOR LAMP POST METHOD OF STATEMENT FOR LAMP POST Erection.Erection. 1.1
1.1 Scope of ActivityScope of Activity
The Scope of Method of Statement is to describe the method of The Scope of Method of Statement is to describe the method of erection for the proposed KALBE Project, Thilawa SEZ A, Yangon, erection for the proposed KALBE Project, Thilawa SEZ A, Yangon, Myanmar.
Myanmar. 1.2
1.2 Site ObservationSite Observation
Before Commencement of the planned work, carry out examination Before Commencement of the planned work, carry out examination of the physical condition of the
of the physical condition of the area for ongoing activities, blockagesarea for ongoing activities, blockages of Ingress/ Egress and the weather
of Ingress/ Egress and the weather condition.condition. 1.3
1.3 Method of StatementMethod of Statement Preparation Preparation
Load all equipment required for JobLoad all equipment required for Job
Report to KDK and received approvalReport to KDK and received approval
Put on personal protective equipmentPut on personal protective equipment
Inform all other contractors in the area of start to workInform all other contractors in the area of start to work
Liaise with Main contractor and other contractor to beLiaise with Main contractor and other contractor to be
ensure safe operation ensure safe operation
Cordon of work areaCordon of work area
Ensure the area to be worked and exit points are clear ofEnsure the area to be worked and exit points are clear of
obstruction obstruction
Ensure that safe access and Ensure that safe access and egress is maintainedegress is maintained
Determine location of underground servicesDetermine location of underground services
Producer Producer
Provide copies of the shop drawings, copy of the permit toProvide copies of the shop drawings, copy of the permit to
work & necessary instructions. Briefly introduce the work & necessary instructions. Briefly introduce the workers on the safety aspects & safe work procedures. workers on the safety aspects & safe work procedures. Barricade the area of working.
Barricade the area of working.
Mark out area to be excavated with marker paintMark out area to be excavated with marker paint
After excavation put precast base at excavated area andAfter excavation put precast base at excavated area and
back filling. back filling.
Ensure all lifting tackle is check for its capacity andEnsure all lifting tackle is check for its capacity and
adequacy for the weight of pole
adequacy for the weight of pole being lifted.being lifted.
Attached a single loop sling around the Attached a single loop sling around the pole atpole at
approximately two third of overall height, taking care not approximately two third of overall height, taking care not to damage the pole finish. The slings shall not be
to damage the pole finish. The slings shall not be wrapped tight around the pole
wrapped tight around the pole
On the opposite side of the lifting side attached theOn the opposite side of the lifting side attached the
safety rope from the sling and attached the other end to safety rope from the sling and attached the other end to hook which is to be hooked into the access door. Ensure hook which is to be hooked into the access door. Ensure the safety rope is taught at all time
the safety rope is taught at all time
Began lifting the pole. After lifting the top of the poleBegan lifting the pole. After lifting the top of the pole
approximately approximately
After pipe laying, back fill will start step After pipe laying, back fill will start step by step.by step.
1.4 Waste Management 1.4 Waste Management
All waste materials to be removed from site on a daily basis. Trash All waste materials to be removed from site on a daily basis. Trash collecting bags are to be provided at the working areas. All general collecting bags are to be provided at the working areas. All general waste to be thrown into the
waste to be thrown into the provided trash bags according to the typeprovided trash bags according to the type of garbage (Segregate waste before disposal) and should be disposed of garbage (Segregate waste before disposal) and should be disposed in to the relevant metal
in to the relevant metal waste bins provided.waste bins provided. Wooden crates or palettes must be
9 9