frontierCities – Grantee Mobilisation Bootcamp
Funded by the Seventh Framework Programme of the European Union
• B-19 Country Club,
• Uccle,
• Brussels
22
nd-24
thJuly
2015
frontierCities – Grantee Mobilisation Bootcamp
Overview
• Inception Phase Key Goals
frontierCities – Grantee Mobilisation Bootcamp
Key Goals
– Get clarity on the detailed work plan
(internally, with fC team, with city counterparts etc.)– Detailed Work Plan of the 10 months grant cycle
– Hit the ground running for Development Phase
– Road map for development, deployment&
commercial success
frontierCities – Grantee Mobilisation Bootcamp
Are you ready?
• Questions to ask yourself:
– Is your team complete?
– Have you thought about obstacles/time constraints?
– Are you in contact with your test city?
– Do you have enough test subjects to be relevant?
– Is your test site ready?
– Do you dedicate enough time to the commercial phase/work?
– Do you have all permits/authorizations in place?
frontierCities – Grantee Mobilisation Bootcamp
Inception Report
– Collection of Test Site Data
– Actions regarding test users/test site arrangements
– Budget planning
– Planning of App Development Phase
– Approach to Deployment
– Commercialisation Strategy
– Communication with Cities
– Reviewing deliverables (what, when)
frontierCities – Grantee Mobilisation Bootcamp
Prepare your Inception Report
• Keep in mind:
– Collect necessary data while you plan
– Keep realistic targets
frontierCities – Grantee Mobilisation Bootcamp
Inception Reportin Requirements
INCEPTON REPORTING – WHAT’s REQUIRED:
1. Technical Requirements
2. Market Update Requirements
frontierCities – Grantee Mobilisation Bootcamp
List of Items in the Action Plan :
• Key Goals and Targets
• Obstacles and Challenges
• Timing
• Testing
• Reporting
frontierCities – Grantee Mobilisation Bootcamp
Key Goals and Targets
• Development planning is the most important management
exercise in the grant cycle.
– On-time delivery of the proposed solution
– Identify unforeseen issues (e.g. incompatibilities, missing
functionalities, etc.)
– Avoid cost overruns
– Ensure adequate resources are allocated
– Risks and their contingencies are considered
• Start by clearly articulating the goals/targets of the
development cycle.
– Goals must be SMART (Specific, Measurable,
Achievable, Realistic, Timed)
frontierCities – Grantee Mobilisation Bootcamp
Key Goals and Targets (ctd.)
• Achieving your goals. How about a framework that fits your
team’s style?
– Waterfall model – sequential design process approach.
– Spiral model – risk driven model which focuses on the uniqueness of each
development project
– Iterative and Incremental model – Incremental development and testing
until a complete solution is realised.
– Unified Modelling Language – supports model-driven architecture through
specification of platform-independent models, and the compilation of the
platform-independent models into platform-specific models
– Others? (e.g. Prototyping , rapid application development, ‘code and fix’,
Extreme Programming, Chaos model, Slow programming, etc.)
– A combination or grouping of frameworks?
frontierCities – Grantee Mobilisation Bootcamp
1.Key Development Goals or Milestones
•Web application (WA)
Coupon and POI management (CMS) and coordination (WMC) Policy statistical (PSS)
Policy Making (PMS) •Mobile application (MA)
Complete app based on Official Barcelona City Guide (OBCG) using Sparksee technology Application update service (US)
RAG
2. Brief Description of Development Process
•Initial phase
Design the aspects that will configure the work
•Implementation of the web app Integration of GEs Implementation of SEs Integration of SparsityHub
•Implementation of the mobile app
Recommendation, tracking and rating of routes POI and coupon advisor
5. List of KPIs
•User rating of POIs and routes
•User rating of mobile and web app
3. Key Risks and their Mitigation Plans
•Delayed development: We are experts in App development. We will double the efforts of the team, providing more developers if necessary.
•A team of the member quits: We have a very engaged team. We have enough knowledge and members in the team to already have a good replacement in-house.
•Low quality of the Ges: Some of the Ges have a low adoption and software maintenance has been scarce. We will talk with the frontierCities management to find a solution.
4. Timing – Key Dates
•Web application (WA): Month 2 to month 10. 12 person/month •Mobile application (MA): Month 2 to month 10. 6 person/month
Grantee Development Plan
(Technical)
frontierCities – Grantee Mobilisation Bootcamp
1. Key Development Goals or Milestones
Inception Report – Month 1
Technical design document – Month 2 UI Design sketches – Month 2
UI final design – Month 4
Integration of Fiware enablers (development) – Month 4
Visual identity completed – Month 5 Prototype ready - Month 6
RAG
2. Brief Description of Development Process
• Agile project management approach.
All team members can actively participate to mitigate risks. The risks are evaluated on our impact scale. High or very high items are fully reviewed.
5. List of KPIs
App launch / load time (performance), number of downloads (acquisition), Churn rate (retention), Time on app, user experience (though in-app ratings), monthly active users, daily active users, ARPU (average revenue per user), LTV (lifetime value).
3. Key Risks and their Mitigation Plans
Risk (inception): Market Study identifies unforeseen needs. Trigger: Market Study. Impact: High. Likelihood: Low.
Mitigation: Integrate tweaks and adjustments to the roadmap.
Risks (tech development): Delays on tasks. Trigger: Incorrect estimations on scrum meetings.
Likelihood: Medium. Impact: High. Mitigation: Short daily meetings with the team; Software bugs affecting essential functions. Trigger: Test reports. Likelihood: Low. Impact: High.
Mitigation: Test on code during development phase, code quality reviews.
4. Timing – Key Dates
• Inception Report (month 1), Technical design document (month 2), API development
completed (month 4), Mapi prototype (month 6), app development report (month 6)
Grantee Development Plan
(Technical)
frontierCities – Grantee Mobilisation Bootcamp
In Summary: SMART Goals(Specific, Measurable,
Achievable, Realistic, Timed)
M1
M3
M5
M7
M10
SMART 1
SMART 2
SMART n
SMART 1
SMART 2
SMART n
SMART 1
SMART 2
SMART n
SMART 1
SMART 2
SMART n
SMART 1
SMART 2
SMART n
P
roject M
ana
geme
n
t P
lan
De
velopme
n
t
1
De
velo
pmen
t
2
KPIs
Concrete
&
tested
frontierCities – Grantee Mobilisation Bootcamp
The Revised Architecture: A Practical Example
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Waterfall
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Waterfall
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Waterfall
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Agile
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Agile
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Agile
frontierCities – Grantee Mobilisation Bootcamp
A Practical Example: i.e. Agile
frontierCities – Grantee Mobilisation Bootcamp
Inception Reporting - Market
Update
Inception Reporting – Market Updake
Four Components Required for Inception Report:
1.
Market Uptake Strategy
2.
Market Uptake Action Plan
3.
SWOT
frontierCities – Grantee Mobilisation Bootcamp
Component 1:
Market Uptake Strategy
a.
Text document
b.
Three to five pages,
c.
Expansion on business model canvas covering all of the elements
of the BMC described in more detail
d.
Targets and objectives
frontierCities – Grantee Mobilisation Bootcamp
Component 2:
Market Uptake Action Plan
a. Step by step breakdown of every task needed to be achieved to
bring the app to market
b. Each task should have the associated stakeholders and inputs to be
identified
c. Each task should have the delivery month indicated
Template to be provided next week
frontierCities – Grantee Mobilisation Bootcamp
Component 3:
SWOT
a. Simple document outlining the strengths, weaknesses, opportunities
and threats of the proposed application and company
b. This will help to identify the supports required over the 10 months
frontierCities – Grantee Mobilisation Bootcamp
Component 4:
Deliverables & Milestones
a. Deliverables assigned to deadlines
Deadline
Date
Payment amount
Inception 31/08 (M1) 20% Dev 1.A 15/10 (M3) 15% Dev 1.B 15/12 (M5) 15% Dev 2 15/12 (M5) 10% Deploy 1.A 15/02 (M7) 10% Deploy 1.B 15/04 (M9) 10% Deploy 2 15/04 (M9) 5%
Final report 1 month after project end 15% is withheld until after
final payment made by the commission