P
P
REPARATION
REPARATION
W
W
ORKBOOK
ORKBOOK
FOR
FOR
PROJECT MANAGEMENT PLAN
PROJECT MANAGEMENT PLAN
(PMP)
(PMP)
ABOUT THIS DOCUMENT – PREPARING THE PROJECT MANAGEMENT PLAN...II STARTING WITH THE TITLE PAGE...V
1.0 PROJECT OVERVIEW ...1
2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE...5
3.0 SCOPE ...7
4.0 PROJECT DELIVERABLES AND METHODOLOGY...9
5.0 PROJECT WORK...19
6.0 PROJECT MANAGEMENT AND CONTROLS...22
7. 0 PROJECT CLOSE...37
ATTACHMENTS...37
REVISION HISTORY
REVISION HISTORY
RREVISIONEVISION N NUMBERUMBER DDATEATE CCOMMENTOMMENT
1.0 July 27th, 2007 DoIT Project Management Office Revision
2.0 2.1 2.2
ABOUT THIS DOCUMENT – PREPARING THE PROJECT
ABOUT THIS DOCUMENT – PREPARING THE PROJECT
MANAGEMENT PLAN
MANAGEMENT PLAN
This workbook is built around helping the project manager and the project team to use the Project Management Plan in support of successful projects.
Project Oversight Process Memorandum – DoIT, July 2007
Project Oversight Process Memorandum – DoIT, July 2007
1 “Project management plan” is a formal document approved by the executive sponsor and the Department and developed in the plan phase used to manage project execution, control, and project close.
2 The primary uses of the project plan are to document planning assumptions and decisions, facilitate communication among stakeholders, and documents approved scope, cost and schedule baselines.
3 A project plan includes at least other plans for issue escalation, change control, communications, deliverable review and acceptance, staff acquisition, and risk management. 4 “Project manager” means a qualified person from the lead agency responsible for all aspects
of the project over the entire project management lifecycle (initiate, plan, execute, control, close). The project manager must be familiar with project scope and objectives, as well as effectively coordinate the activities of the team. In addition, the project manager is responsible for developing the project plan and project schedule with the project team to ensure timely completion of the project. The project manager interfaces with all areas affected by the project including end users, distributors, and vendors. The project manager ensures adherence to the best practices and standards of the Department.
5 Project product” means the final project deliverables as defined in the project plan meeting all agreed and approved acceptance criteria.
6 “Product development life cycle” is a series of sequential, non-overlapping phases comprised of iterative disciplines such as requirements, analysis and design, implementation, test and deployment implemented to build a product or develop a service.
CONCEPTS BEHIND PROJECT MANAGEMENT PLANNING
CONCEPTS BEHIND PROJECT MANAGEMENT PLANNING
WWHATHATISISAAPROJECTPROJECT??
0 “A project is a temporary endeavor undertaken to create a unique product, service or result” PMBOK©
W
WHATHATISIS P PROJECTROJECT M MANAGEMENTANAGEMENT??
Is about how we create and manage a temporary organization to deliver the unique product, service or result!
is more about the interested parties, technical teams and the solution building process!
P
PROJECTROJECTMANAGEMENTMANAGEMENT Q QUESTIONSUESTIONS
1 What is the unique product, service or result?
2 What do we need to do to accomplish the goal or goals? 3 How do we know when we are finished?
4 Who is doing what for whom? 5 How do we know how we are doing? 6 How do we handle uncertainty or conflict?
U
UNIQUENIQUE P PRODUCTRODUCT, S, SERVICEERVICEOROR R RESULTESULT
0 Product – what are we trying to accomplish and how will we know when we are finished?
7 Product Development
Project Objectives-> Business Requirements -> System Requirements-> Architecture-> Solution Design-> Build-> Pilot-> Deploy
Quality of Product
0 Trace-ability and Quality Assurance-> Test Cases, Test Planes, Pilot and Deployment Success Criteria
8 Deployment of Product
9 Resource Requirements and staffing for new product 10 Deployment Plan and “Transition To Operations” 11 Operations and Support for product
12 Cost- What is the estimated cost of creating and implementing?
W W
HOHOISISDOINGDOING W W HATHATFORFOR WW HOMHOM??
7 Roles and Responsibilities
0 For Whom
0 Project Sponsor
1 Project Funding Source 2 End User
3 Beneficiaries of new solution
1 W ho
0 Project Team
1 Subject Matter Experts 2 Vendors
3 Operations
H
HOWOWAREAREWEWEDOINGDOING??
8 Time
9 Calendar of tasks, task targets
0 Work Breakdown Structure – What needs to be done 1 Time estimation – how much time will be needed?
10 Budget
Do we have funding for project and product development, implementation and on-going support?
0 How much money have we spent?
1 Are we spending the right amount of money for specific tasks?
11 Quality and IV&V
0 Are we doing what we have set out to do?
12 Metrics
0 How many changes are we making?
H
HOWOWWELLWELLORGANIZEDORGANIZEDAREAREWEWE
13 Are we meeting with stake holders and team members?
15 Do we document disagreements and work towards resolutions?
16 Do we secure formal approval of changes and requirements from stakeholders? 17 Do we keep stake holders informed?
P
PROJECTROJECT M MANAGEMENTANAGEMENT P PLANLAN
0 Is about how we create and manage a temporary organization to deliver the unique product, service or result!
1 Is not a Microsoft Project© file -MS Project © is a scheduling aid
STARTING WITH THE TITLE PAGE
STARTING WITH THE TITLE PAGE
Even the title page has significant information, and assumptions. It tells us what the project calls itself, who the project benefits, who is running the project, and if the Project Charter has been revised during the project, which is okay and expected.
THE TITLE
THE TITLE
Does the title convey to the reader the essence of the project? Is the title of the project required by any funding considerations?
THE EXECUTIVE SPONSOR AND BUSINESS OWNER
THE EXECUTIVE SPONSOR AND BUSINESS OWNER
Project sponsorship is about the resources required to do the project, whether they are the financial resources from state or federal funding/appropriation or from the agency’s own operating funds.
Many State of New Mexico projects list the agency Cabinet Secretary as the Executive Sponsor and a combination of the agency CIO and business process owner as the business owners of the project.
The following are some key responsibilities of project sponsorship:
• Appoint an appropriately skilled project manager
• Understand the project complexity
• Champion the project and the team
• Formally manage the project scope
• Provide guidance for business strategies
• Approve plans, schedules and budgets
• Ensure sustained buy-in
• Ensure timely availability of resources
• Review project progress
Both executive sponsor and business owner are listed. While both may sit on the project steering committee, usually the business owner is more involved in the project after the project charter is established. More discussion on the steering committee will be covered under 6.2 Project Governance Plan.
THE PROJECT MANAGER
THE PROJECT MANAGER
According to the “IT PROJECT OVERIGHT PROCESS” memorandum from Roy Soto, Secretary of the Department of Information Technology:
“Project manager” means a qualified person from the lead agency responsible for all aspects of the project over the entire project management lifecycle (initiate, plan, execute, control, close). The project manager must be familiar with project scope and objectives, as well as effectively coordinate the activities of the team. In addition, the project manager is responsible for developing the project plan and project schedule with the project team to ensure timely
completion of the project. The project manager interfaces with all areas affected by the project including end users, distributors, and vendors. The project manager ensures adherence to the best practices and standards of the Department.
WHAT IS THE ORIGINAL PLAN DATE AND WHY THE REVISION DATE
WHAT IS THE ORIGINAL PLAN DATE AND WHY THE REVISION DATE
AND REVISION NUMBER?
AND REVISION NUMBER?
As the project develops and the sponsors, project manager and team learn about the project, it is expected that the content of the project charter will change. Because the project charter is so critical to the agreements between the sponsors and the project, change management should be followed once the project charter is a signed document.
THE IMPORTANCE OF REVISION HISTORY
THE IMPORTANCE OF REVISION HISTORY
Although not on the title page there is a revision history table in the template. This should be used as tracking device to capture the nature of changes made to the project charter document. Used in conjunction with change management, the process will facilitate the response to such questions as when did this get added to the project?
The Project Overview sets the stage for the details of the project and begins the “story” of the project and plan. It states the vision for the project (and larger effort, if applicable) in terms of a business need – not a solution. It answers “What is the specific answer that will move the business owner from the current state to a valuable future state?” The Project Overview describes the difference (gap) between the current state and future state in terms of the business need. The content structure order is the introduction, which provides background, the current state, the future state, and the need.
1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT
1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT
In this section should be enough information to portray the situation or problem that the project results will resolve, without getting into too much detail.
Some suggestions:
The Business Problem and Opportunity section of the one page business case
• Briefly explain the business problem faced by the agency and the opportunity the agency has to solve the problem through an IT solution. Briefly present essentials to relay the problem and opportunity presented including the agency’s business performance,
mission, goals, objectives, and strategic plan and, if any, cross agency collaborations and impacts
The Problem Statement-Recommendation approach:
• A problem statement that outlines what the existing situation is and how the business of the agency is being negatively impacted
• A brief “root cause” analysis listing factors that if resolved by the project would eliminate the problem, thus benefiting the agency.
• The project recommendation as the solution, stating clearly that the solution will address the root cause issues of the problem, resolving the problem and eliminating the negative impact to the agency.
The current state-future state- need approach
• The current state with its issues is described
• The ideal future state is described as if the solution were in place
• The need provides a description of the gap and tells how the work of the project will resolve the gap between the current and future states
• Imagine that you are in an elevator with the executive sponsor or Cabinet Secretary and can take advantage of the few minutes to pitch the project. You have a limited amount of that person’s attention to sell the problem and the solution to the problem.
1.2 FUNDING AND SOURCES
1.2 FUNDING AND SOURCES
This question is also asked in the request for certification and release of funds document. A project is not a project unless it has actually funding. Provide the funding source(s), amount(s), any
restrictions, and who the approvers are for the specific sources).
SOURCE
SOURCE AMOUNTAMOUNT ASSOCIATED ASSOCIATED
RESTRICTIONS
RESTRICTIONS APPROVERS
APPROVERS
1.3 CONSTRAINTS
1.3 CONSTRAINTS
Constraints are factors that restrict the project by scope, resource, or schedule. Constraints can include parameters that force the project or work effort to fit a particular timeframe. They lead us into a certain way of doing things. Constraints limit the project management team’s options. Contractual provisions will generally be considered constraints.
N
NUMBERUMBER DDESCRIPTIONESCRIPTION
1.4 DEPENDENCIES
1.4 DEPENDENCIES
Literally dependencies are items required for something else to happen. My success in being able to drive for hundreds of miles is to have enough gas in my car’s gas tank, which usually means finding an open gas station, having cash or a credit card with which to pay for the gas.
The table in this section asks for a reference number, a description and whether the dependency is:
• Mandatory dependencies are dependencies that are inherent to the work being done. • D- Discretionary dependencies are dependencies defined by the project management
team. This may also encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle.
activities and non-project activities such as purchasing/procurement
By way of simplification, having enough gas in my car’s gas tank would be Mandatory; a specific gas station might be considered External, as our favorite corner gas station might not be open; Cash or credit card would be Discretionary.
Dependencies help the reader and the project manager/team view the playing field realistically. A back-ordered part becomes a dependency for meeting a project schedule.
NUMBER
NUMBER DESCRIPTIONDESCRIPTION TYPE M,D,ETYPE M,D,E
1.5
1.5
ASSUMPTIONS
ASSUMPTIONS
Assumptions may contain little or significant amount of risk. We can assume that members of our teams will always show up, and that the project manager will stay through the project, but people get sick, or get better offers.
Here is an exercise. List all of the people, factors, and things we take for granted around the project environment that if they were not there would negatively impact the project. We assume vendors will stay in business, and that their key technical staff will remain in place.
Assumptions are planning factors that, for planning purposes, will be considered true, real, or certain. Assumptions generally involve a degree of risk. They may be documented here and converted to formal risks.Assumptions define conditions not known but under which the project is planned, budgeted, and managed. They can include anything that supports the scope. Aim to tie risks to assumptions and place risks in risk documentation.
N
NUMBERUMBER DDESCRIPTIONESCRIPTION
1.6 INITIAL PROJECT RISKS IDENTIFIED
1.6 INITIAL PROJECT RISKS IDENTIFIED
In this section identify and describe how each risk will be managed. Include the steps that will be taken to maximize activity that will result in minimizing probability and impact of each risk.
Section 6.1 Risk Management calls for an understanding of how the project will be handling risks.
Projects By their temporary nature and unique outcomes are risky –Project management reduces the impact of the threats by making them explicit and the working on reducing their impacts or by eliminating those Risks are always around. A project is not judged on how many risks are identified, but by its strategy and success at planning through the risks.
See 6.1.2 Project Risk Identification for a listing of typical project risks.
Description - Probability Impact
Mitigation Strategy Contingency Plan
Risk Name – should easy reflect the challenge without detail
Description - Describe the risk’s characteristics and explain why this risk is perceived to have
the potential to affect the outcome of the project.
Probability and Impact - - Probability should be measured as the likelihood of that the risk will
occur. Impact should be measured in terms of deviations from the schedule, effort, or costs from the schedule if risks occur.
• Probability Levels: Certain, Expected, Likely, Possible, Unlikely • Impact Levels: Very High, High, Medium, Low, Very Low
Mitigation Strategy - Identify what actions can be taken in order to reduce the probability of the
risk, or to reduce its impact on the project.
Contingency Plan Identify what actions will be taken when the risk materializes and threatens
the scope, budget, or the schedule of the project.
[Risk 1 Name]
Description - Probability and Impact Mitigation Strategy Contingency Plan
[Risk 2 Name]
Description - Probability and Impact Mitigation Strategy Contingency Plan
2.0 PROJECT AUTHORITY AND ORGANIZATIONAL
2.0 PROJECT AUTHORITY AND ORGANIZATIONAL
STRUCTURE
STRUCTURE
The Project Organization describes the roles and responsibilities of the project team. It also identifies the other organizational groups that are part of the project and graphically depicts the hierarchical configuration of those groups. It exists to clarify interaction with the project team.
2.1 STAKEHOLDERS
2.1 STAKEHOLDERS
List all of the major stakeholders in this project, and state why they have a stake. Stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be positively or negatively affected as a result of project execution or project completion. They may also exert influence over the project and its results.
The PMBOK© of the Project Management Institute defines project stakeholders:
“Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They also exert influence over the project’s objectives and outcomes.” This all encompassing definition would have us think about such stakeholders as:
• Cabinet Secretaries
• Agency Division directors
• CIO-IT Leads
• Project Manager
• IT operations staff
• Business process owners
• System user representatives
• Key project team members
• Training staff
NAME
NAME SSTAKETAKEININ P PROJECTROJECT OORGANIZATIONRGANIZATION TTITLEITLE
2.2 PROJECT GOVERNANCE STRUCTURE
2.2 PROJECT GOVERNANCE STRUCTURE
2.2.1 D2.2.1 DESCRIBEESCRIBETHETHEORGANIZATIONALORGANIZATIONALSTRUCTURESTRUCTURE – O – ORGRG C CHARTHART
A key element in the project governance is the Organization chart for the project.Describe the process that is going to be used to manage the scope of the project. Make sure to address managing stakeholder expectations. Describe at a high-level how issues will be escalated and resolved and how change requests will be processed.
2.2.2 D
2.2.2 DESCRIBEESCRIBETHETHEROLEROLEANDANDMEMBERSMEMBERSOFOFTHETHEPROJECTPROJECTSTEERINGSTEERINGCOMMITTEECOMMITTEE
In many projects the business owners sit as the members of the steering committee. The role of the steering committee is set the tone for the project, manage the project charter authorizing the role of the project manager, manage the scope of the project in terms of cost, schedule and quality of the project, deal with issues escalated to them, and also to accept or deny project team recommendations especially in go-no go decision matters.
2.2.1 O
2.2.1 ORGANIZATIONALRGANIZATIONAL B BOUNDARIESOUNDARIES, , INTERFACESINTERFACESANDANDRESPONSIBILITIESRESPONSIBILITIES
Use this section to describe any special considerations regarding contact between the project team, the project manager, and individuals from various organizations involved in the project: “The key interface between the organizations is between the Project Manager from the DoIT and the Project Managers from Contracting Vendor and between the Project Manager and the
assigned Team Leaders.. The primary methods utilized will be the Status Report/Briefing, ad-hoc meetings, electronic mail, and phone conversations. Interaction may occur directly between the technical components of all teams. However, overall task direction can only come from the Project Manager. Final decisions will be made at the Steering Committee level.”
2.3 EXECUTIVE REPORTING
2.3 EXECUTIVE REPORTING
Use this section to describe the method that will be used to effectively disseminate information to the project ‘s Executive Sponsor and/or the Business Owner and other governing bodies such as the Office of the Chief Information Officer and the Information Technology Commission. Indicate how, when, what type of information, to whom, and how often project related
information will be conveyed. This section does not replace the need for the project manager to develop a detail communication plan as part of the project plan.
Keep In mind here the project’s obligation: “. For all projects that require Department oversight, the lead agency project manager shall submit an agency approved project status report on a monthly basis to the Department.” PROJECT OVERSIGHT PROCESS memorandum
3.0 SCOPE
3.0 SCOPE
3.1 PROJECT OBJECTIVES
3.1 PROJECT OBJECTIVES
As the project progresses it must be able to answer the following question as “Yes!”:” Has the project established the ability to verify that business requirements can be traced through
technical design, system building or software coding/ configuration and test phases to verify that the system performs as intended and contains no unnecessary elements?”
3.1.1 B
3.1.1 BUSINESSUSINESS O OBJECTIVESBJECTIVES
Business objectives are the high level business requirements of the project. The following table comes from a requirement collection template. It suggests the ingredients of a well written business objective.
Description <Enter concise description of requirement>
Rationale <Provide a brief rationale, and or business value for the requirement.>
Acceptance/Fi
t Criteria <Provide a target that makes it possible to test if requirement was satisfied>
The typical problems with business objectives include:
• Lumping more than one objective into a business objective
• Use of too many loose phrases such as more, better, improve, fix, solve
3.1.2 T
3.1.2 TECHNICALECHNICAL O OBJECTIVESBJECTIVES
Technical objectives relate to the technical issues or goals the project is to accomplish. These maybe related to acquisition of hardware, software, consulting, training, application development and other “how’s” of the project.
The business requirement table presented in the section above is useful here as well, with one addition, the parent Objective/ requirement which should be one of the Business Objectives presented.
Parent Requirement #
<Enter the unique id #(s) for each requirement that this requirement supports (This field will be empty for high level requirements e.g., business
requirements)>
Description <Enter concise description of requirement>
Rationale <Provide a brief rationale, and or business value for the requirement.>
Source <Name of Reqmnt. Provider> Source Document
<filename>
Acceptance/Fi t Criteria
<Provide a target that makes it possible to test if requirement was satisfied>
N
NUMBERUMBER DDESCRIPTIONESCRIPTION Bus. Objective 1
N
NUMBERUMBER DDESCRIPTIONESCRIPTION Tech. Objective 1
Because technical objectives should be trace-able to specific Business Objective, when there is more than one business objective, it would be advisable to present the technical objectives in a hierarchical manner: The following is an example of such a presentation of technical objectives.
N
NUMBERUMBER DDESCRIPTIONESCRIPTION
Bus. Objective 1 Reduce cost of government operations through IT
Tech. Objective 1 Identity Management and Directory Services
Tech. Objective 2 Common Business Functions and data interchange and discovery methodology for all agencies to access and use for report creation.
Bus. Objective 2 Reduce cost of IT operations through an enterprise Model
Tech. Objective 4 Common IT service architecture and operating environment, including Standards, SLA (Service Level Agreements) approach, governance model and improved funding mechanism
3.2 PROJECT EXCLUSIONS
3.2 PROJECT EXCLUSIONS
The project should list items, features, would like to haves that stakeholders might associate with this project but that the project would not be providing.
3.3 CRITICAL SUCCESS FACTORS
3.3 CRITICAL SUCCESS FACTORS
Identify the critical success factors for achieving success in this project. Metric are key to understanding the ability of the project to meet the end goals of the Executive Sponsor and the Business Owner, as well as the ability of the project team to stay within schedule and budget.
NUMBER
NUMBER DESCRIPTIONDESCRIPTION QUALITY METRICS
1
4.0 PROJECT DELIVERABLES AND METHODOLOGY
4.0 PROJECT DELIVERABLES AND METHODOLOGY
A deliverable is any measurable, tangible, verifiable outcome, result, or item that is required to complete a project or part of a project. The term is often used more narrowly in reference to an external deliverable (i.e. this deliverable is subject to approval by the project sponsor or
customer). Analyze the project scope and objectives outlined in the Project Proposal and Charter to develop a list of deliverables.
In its efforts to move from the high level business objectives to the desired end product/service the project team will need to deliver specific documents or work products. The State of New Mexico Project Management Methodology distinguishes between the project and the product. Project Deliverables relate to how we conduct the business of the project. Product Deliverables relate to how we define what the end result or product will be, and trace our stakeholder
requirements through to product acceptance, and trace our end product features and attributes back to our initial requirements
4.1 PROJECT MANAGEMENT LIFE CYCLE
4.1 PROJECT MANAGEMENT LIFE CYCLE
The project should present here a summary of its approach, and its phases:
Phase Summary of Phase Key Deliverables
Here is some background:
The following is a description of a Project Management Life Cycle based on the PMI (Project Management Institute’s PMBOK©.
Key Project Deliverables of each of these five processes are identified as including the following:
Initiating:
Project Charter Project Scope
Business Requirements – Business Case Assumptions
Constraints
Authorization to proceed with planning
Planning:
Project Plan
Critical success factors Work Break down Structures Project Schedule
Controlling:
Performance/Status Reports Corrective Action
Measurement Metrics Plan Change Requests Product Change Request Risk Management Issues Management
Execution:
Actual efforts
Project Deliverables completion
Closing:
Deliverable or Product Acceptance Lessons Learned
As a companion to the five major project processes, PMI through the PMBOK has instituted nine management focuses that will be followed in this project:
The purpose of integration management is to ensure coordination of the different elements of a project to achieve the needs and expectations of project stakeholders. It includes project plan development, project plan execution, and integrated overall change control.
Scope Management
The purpose of scope management is to ensure the work performed in a project is necessary to the successful completion. It includes initiation, scope planning, scope definition, scope verification, and scope change control.
Time Management
The purpose of time management is to ensure a project completes in a timely manner. It includes activity definition, activity sequencing, activity duration estimating, schedule development, and schedule control.
Cost Management
The purpose of cost management is to ensure a project completes within its approved budget. It includes resource planning, cost estimating, cost budgeting, and cost control.
Quality Management
The purpose of quality management is to ensure the products and services produced by a project satisfy the needs for which the project was undertaken. Quality – the satisfaction of project needs – is a measure of adherence to stated requirements combined with fitness for use. The Quality Management Knowledge Area includes quality planning, quality assurance, and quality control.
Human Resource Management
The purpose of human resource management is to ensure effective use of the people involved in a project. It includes organizational planning, staff acquisition, and team development.
Communications Management
The purpose of communications management is to ensure timely and effective flow of information for a project. It includes communication planning, information distribution, performance reporting, and administrative closure.
Risk Management
The purpose of risk management is to ensure the identification, analysis, and appropriate response to the risks encountered by a project. It includes risk management planning, risk
identification, qualitative risk analysis, quantitative risk analysis, risk response planning, and risk monitoring and control.
Procurement Management
The purpose of procurement management is to ensure effective acquisition of products and services from sources external to the project’s organization. It includes procurement planning, solicitation planning, solicitation, source selection, contract administration, and contract closeout.
Project Deliverables are work products or artifacts that are driven by the project management methodology requirements and standard project management practices regardless of the product requirements of the project. Examples are project, phase, and iteration plans, and project schedules. Project Deliverables must be reviewed and approved by the project’s Executive Sponsor prior to their implementation.
Description - Deliverable description conveys the features and/or the functions that will be
included in the project product. Each deliverable is a subsidiary element of the project product (final deliverable), each with its own separate but interdependent deliverable scope
Deliverable Acceptance Criteria - Acceptance Criteria are quantifiable measures of the success
of each deliverable (or set of deliverables). Its how the executive sponsor and the project team know when a deliverable is acceptable and can be approved. Acceptance criteria are similar to measures of success except they are for a specific deliverable. The criteria may include
functional and technical testing and utility verification at defined points in the process; methodology and criteria should be published.
Standards for Content and Format - Standards for Content and Format describe the format
that the executive sponsor can expect to receive the deliverable. This section ensures that the deliverable will be usable to meet its objective upon delivery. The tools, techniques, and
processes used to develop the deliverable must compliment the executive sponsor’s environment and enable the executive sponsor to use the deliverable
Quality Review - Quality review provides the opportunity for peer and cross-discipline reviews
of the deliverable. This process will improve the Quality Control metrics by reducing the testing cycle and the number of exceptions reported by Quality Control and eventually the executive sponsor.
4.1.1.1 [Deliverable 1 Name]
Description - Deliverable Acceptance Criteria - . Standards for Content and Format -
Quality Review -
4.1.1.2 [Deliverable 2 Name]
Standards for Content and Format - Quality Review -
4.1.2 D
4.1.2 DELIVERABLEELIVERABLE A APPROVALPPROVAL A AUTHORITYUTHORITY D DESIGNATIONSESIGNATIONS
Complete the following table to identify the deliverables this project is to produce, and to name the person or persons who have authority to approve each deliverable. Each deliverable should be assigned a control number for tracking. The date approved column serves as a log of when each deliverable was approved.
D
DELIVERABLEELIVERABLE
N
NUMBERUMBER
D
DELIVERABLEELIVERABLE AAPPROVERSPPROVERS (W (WHOHO CAN
CANAPPROVEAPPROVE))
D DATEATE
A
APPROVEDPPROVED PRJ-DEL-001 Project Management Plan (PMP)
4.1.3 D
4.1.3 DELIVERABLEELIVERABLE A ACCEPTANCECCEPTANCE P PROCEDUREROCEDURE
Describe the process that this project will use for the formal acceptance of all deliverables. Generally, a Deliverable Acceptance Form is utilized with specific timeframes allowed for review, approval, rework, etc. Issues identified in this Deliverable Acceptance Procedure should follow the Issues Escalation Process that is defined in a later section.
4.2 PRODUCT LIFE CYCLE
4.2 PRODUCT LIFE CYCLE
This section is intended to have the project present the product development life cycle. “During the project management lifecycle, agencies shall select and implement a phase product
development lifecycle methodology approved by the Department.” PROJECT OVERSIGHT PROCESS Memorandum
example is presented here. What is a product life cycle?
“A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project. “ Project Management Institute’s PMBOK Guide 2000, Glossary p. 205 .
The Product Life Cycle includes identifiable and distinct phases, each of which encompasses the critical five project management processes. Each phase has its own initiation, plan, execute and control aspects and each will have its own close process. The close process or gate will include project approval to enter the next phase of the project.
Where the DoIT Project Management Office has not yet published product life cycle
development templates to use, projects have used documents similar to those mentioned in this approach. The following is a high level description of project document-deliverables per phase
Initiation
Product development Rationale End Vision and purpose
Project Scope
Plan
Work Breakdown Schedules Project Schedule
Business Requirements Initial technical requirements
Initial deployment and transition to operations plan Initial Operations and Support Plan
Analysis of the current state Technical Requirements
Systems Specifications Requirements Initial Training Requirements
System Architecture Document System Use Cases where appropriate Test Cases or system acceptance criteria
Revised deployment and transition to operations plan Revised Operations and Support Plan
Design
Systems Design Documents Training Curriculum
Revised deployment and transition to operations plan Revised Operations and Support Plan
Build
Systems Design Documents applied Training Materials ready
Revised deployment and transition to operations plan Revised Operations and Support Plan
Pilot Acceptance Criteria
Pilot
Systems Design Documents applied Training Materials ready
Revised deployment and transition to operations plan Revised Operations and Support Plan
Pilot Run, Evaluated Pilot Acceptance
Deploy
Systems Design Documents applied Training Materials Used
Deployment and transition to operations plan Operations and Support Plan
4.2.1 T
4.2.1 TECHNICALECHNICAL S STRATEGYTRATEGY
Discuss the key technical strategies for achieving success in this project. Among these might be:
• Build-reuse-buy approach
• Commercial Off The Shelf –COTS- criteria development
• Hardware-Operating System choices
• New Mexico Enterprise IT Standards or exceptions or requests for new standards
• Hosting location with justification
• Outsourcing with justification
• Adoption of new technologies
4.2.2 P
4.2.2 PRODUCTRODUCTANDAND P PRODUCTRODUCT D DEVELOPMENTEVELOPMENT D DELIVERABLESELIVERABLES
Product Deliverables are work products or artifacts that are driven by the product management methodology requirements and standard project management practices regardless of the product requirements of the project. Examples are project, phase, and iteration plans, and project schedules. Product Deliverables must be reviewed and approved by the project’s Executive Sponsor prior to their implementation.
Description - Deliverable description conveys the features and/or the functions that will be
included in the project product. Each deliverable is a subsidiary element of the project product (final deliverable), each with its own separate but interdependent deliverable scope
Deliverable Acceptance Criteria - Acceptance Criteria are quantifiable measures of the success
of each deliverable (or set of deliverables). Its how the executive sponsor and the project team know when a deliverable is acceptable and can be approved. Acceptance criteria are similar to measures of success except they are for a specific deliverable. The criteria may include
functional and technical testing and utility verification at defined points in the process; methodology and criteria should be published.
Standards for Content and Format - Standards for Content and Format describe the format
that the executive sponsor can expect to receive the deliverable. This section ensures that the deliverable will be usable to meet its objective upon delivery. The tools, techniques, and
processes used to develop the deliverable must compliment the executive sponsor’s environment and enable the executive sponsor to use the deliverable
Quality Review - Quality review provides the opportunity for peer and cross-discipline reviews
cycle and the number of exceptions reported by Quality Control and eventually the executive sponsor.
4.2.2.1 [Deliverable 1 Name]
Description - Deliverable Acceptance Criteria - . Standards for Content and Format - Quality Review - .
4.2.2.2 [Deliverable 2 Name]
Description - Deliverable Acceptance Criteria - Standards for Content and Format - Quality Review -
4.2.3 D
4.2.3 DELIVERABLEELIVERABLE A APPROVALPPROVAL A AUTHORITYUTHORITY D DESIGNATIONSESIGNATIONS
Complete the following table to identify the deliverables this project is to produce, and to name the person or persons who have authority to approve each deliverable. Each deliverable should be assigned a control number for tracking. The date approved column serves as a log of when each deliverable was approved.
D
DELIVERABLEELIVERABLE
N
NUMBERUMBER
D
DELIVERABLEELIVERABLE AAPPROVERSPPROVERS (W (WHOHO CAN
CANAPPROVEAPPROVE))
D DATEATE
A
APPROVEDPPROVED PRJ-DEL-001 Project Management Plan (PMP)
4.2.4 D
4.2.4 DELIVERABLEELIVERABLE A ACCEPTANCECCEPTANCE P PROCEDUREROCEDURE
Describe the process that this project will use for the formal acceptance of all deliverables. Generally, a Deliverable Acceptance Form is utilized with specific timeframes allowed for review, approval, rework, etc. Issues identified in this Deliverable Acceptance Procedure should follow the Issues Escalation Process that is defined in a later section.
5.1 WORK BREAKDOWN STRUCTURE (WBS)
5.1 WORK BREAKDOWN STRUCTURE (WBS)
A WBS is a deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Each descending level represents an increasingly detailed definition of the project work. Include at least the highest level grouping for the project in this section Describe the work activities that comprise the work breakdown structure (WBS) or the work packages within the WBS. Identify the WBS element or other work package identifier and provide a general description of the tasks or activities, the definition or objectives, and the milestones and deliverables of each work package.
Identifier Work Package Description Definition/Objective Milestone/Deliverable
5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE
5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE
The project timeline is a high-level view of project activities with a focus on project milestones. The project timeline does not replace the need for a detailed project schedule and it is to
highlight key events such as deliverable due dates and when go/no-go decisions are made. The table below should provide a high level view of the project time line, or a summary-level Gantt chart can be used to meet the timeline requirement.
Please provide a more detailed project schedule as an attachment to this plan
Identifie
5.3 PROJECT BUDGET
5.3 PROJECT BUDGET
Costs estimates are the costs applied to an activity in a project by assigning resources with associated rates or fees. Resources can include equipment, material, technology, processing cycles, or people. The total cost is critical and should be consistent with the proposal; include breakdowns as needed. Match these cost estimates with the actual billed amounts. Use an appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or deliverable).
Identifier Work Package or Budget Category Cost
Or..
Phase / Activity Associated Deliverables Estimated
Budget Umbrella Tasks Phase 1 Project Preparation & Planning Project plan Project Schedule Phase 2 Phase 3 Phase 4 Project Closing TOTALS
5.4 PROJECT TEAM
5.4 PROJECT TEAM
Insert a graphical Organization Chart here. The Organizational Structure (OS) is a hierarchical configuration defining levels of program management and may identify all project personnel. The OS should be simple and straightforward. Include role names and people’s names. Consider identifying the core project team by shading their respective boxes on the chart. On complex projects, consider using a second OS to identify core project team. The OS can also be used for management reporting.
5.4.2 P
5.4.2 PROJECTROJECT T TEAMEAM R ROLESOLESANDAND R RESPONSIBILITIESESPONSIBILITIES
List the team members, their role, responsibility and functional manager. Make sure to include a comprehensive listing including those from the organization managing the project, business members involved to ensure business objectives are met and the vendor members that may have a specific role.
R
ROLEOLE RRESPONSIBILITYESPONSIBILITY NNAMEAME FFUNCTIONALUNCTIONAL
A AREAREA
5.5 STAFF PLANNING AND RESOURCE ACQUISITION
5.5 STAFF PLANNING AND RESOURCE ACQUISITION
Complete the chart below identifying the project team members and details concerning their project commitment. Type should be State, Contract, Customer (Business Owner), or Vendor.
5.5.1 P
5.5.1 PROJECTROJECT S STAFFTAFF
Resource
Cost Estimate
Estimated
5.5.2 N
5.5.2 NONON-P-PERSONNELERSONNELRESOURCESRESOURCES
Use this section to list services or product (HW/SW and such) needed for project
Resource Cost Estimate Estimated units/hours Availability Source Work Product/Deliverable
5.6 PROJECT LOGISTICS 5.6 PROJECT LOGISTICS
Logistics describes how the project manager, project team, the business owner/customer and any vendor resources will physically work together. Include anything to do with moving or starting resources. Identify a role to coordinate logistics with the business owner/customer and vendors. Logistics includes factors, issues, notes, etc. relating to operational details (space, materials, access, etc.) at the customer or vendor site. It can also be used to describe the need and use of a forthcoming logistics document. Cross-reference any risk, assumption or exclusion that is related to logistics. Training specifically related to project team members should be included here.
5.6.1 P
5.6.1 PROJECTROJECT T TEAMEAM T TRAININGRAINING
Describe training if any needed by project team members. This is not to include training for end users, system administrators or business owners; those should be handled within a training document or part of the transition to operations planning.
Resource
Cost Estimate
Estimated
Hours Availability Skill Set Work Product/Deliverable
6.0 PROJECT MANAGEMENT AND CONTROLS
6.0 PROJECT MANAGEMENT AND CONTROLS
6.1 RISK AND ISSUE MANAGEMENT
6.1 RISK AND ISSUE MANAGEMENT
project’s objectives.”
Issue: “A point or matter in question or dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.”
Both Risks and Issues can significant impact a project’s success, and both should be handled in similar ways.
• Project Management IS Risk Mitigation. Is about how we create and manage a
temporary organization to deliver the unique product, service or result!
• By providing structure to the temporary organization and the solution
development/deployment process we reduce the risk of counterproductive Chaos. • By communicating with stakeholders we keep them in the loop, and often involve them
in risk mitigation or lessening its impact
• By acknowledging that there is risk, we can structure ways of avoiding or effectively dealing with specific risk.
6.1.1 R
6.1.1 RISKISK M MANAGEMENTANAGEMENT S STRATEGYTRATEGY
Provide a detailed explanation on the strategy for how risks are identified, analyzed/ quantified, mitigated, reported, escalated and tracked. Include the use of tools such as project management software, forms, and templates. A separate risk management plan may also be developed if needed for the project and included as an Appendix to this document. If that is the case, a high level summary of this plan needs to be included here with the specific reference.
6.1.2 P
6.1.2 PROJECTROJECT R RISKISK I IDENTIFICATIONDENTIFICATION
• Organizational
– Project Organization • Resource
– Staff, Skills, Etc • External Risks – Vendors, suppliers • Planning Risks – Uncertainty, Complexity • Technical Risks – Requirements, Reliability
Organizational Risks
• Poor Initiation • Sponsor Changes• Priorities Change • Unrealistic Deadline • Funding
• Lack of internal stakeholder support • Delayed Approval/Decisions
• Lack of Technical or business direction • Project Manager Experience or inexperience • No organization history
• No established project templates or processes • No organizational understanding of RISK
Resource Risks
• Lack of Resources • Staff Availability • Staff Inexperience • Holiday and Vacation • Personal or Family Illness • Retirement or resignations • Overbooking • Personalities • Ineffective training • Contractor or Consultant • Team Morale • Ineffective Communication
External Risks
• Vendor/Supplier– Quality
– Lack of incentive or penalty • Misunderstood requirements
• Statement of Work incomplete
• Too Many External vendors or suppliers • Weather Issues
• Key Staff issues or sickness • Dependencies on other projects • Purchasing or hiring
Planning Risks
• Lack of Planning • Lack of Anticipation • Poor Estimation
• Lack of stakeholder involvement • Lack of end customer involvement • Poor Project Definition
• Unrealistic expectations
• Number of implementation sites • Training process
• Government or Regulatory Changes • Poor Communications
• Poorly Run or attended meetings • No record keeping
Technical Risks
• Incomplete Requirements • Scope Creep
• No or Poor Change Management Process • Complex or Overly Complex Designs • Technology Readiness
• Technical Dependencies • No Test Environment • Cutting Edge Components • Inadequate Documentation • Vendor Technical Support
• Code or Patch directly to Production Environment • No Pilot
6.1.4 R
6.1.4 RISKISK R REPORTINGEPORTINGANDAND E ESCALATIONSCALATION S STRATEGYTRATEGY
The DoIT Risk and Issue Log Template uses a calculation based on the following values:
• Probability Levels: Certain, Expected, Likely, Possible, Unlikely • Impact Levels: Very High, High, Medium, Low, Very Low
The following table suggests the values at which the risks should be tracked, reported and escalated:
Minimum risk - Acceptable
Some risks - Monitor at PM/Team Level
High risks - Active monitoring with ongoing Contingency/Mitigation activity Show stoppers - Active participation with steering committee to mitigate
This is an example of the calculation that indicates a serious risk that needs to be escalated to the Steering Committee.
Number Risk Probability Impact Rating
6.1.5 P
6.1.5 PROJECTROJECT R RISKISK T TRACKINGRACKING A APPROACHPPROACH
In the DoIT Risk and Issue Template the risk log provides a risk log that not only calculates the risk level, but also provides space for inputting the contingency and mitigation plan summary highlights.
Number Risk Probability Impact Rating Contingency
Plan
Mitigation Plan
1 Example Certain High 0.7125
6.1.6 ISSUE MANAGEMENT 6.1.6 ISSUE MANAGEMENT
For either type of issue, projects should consider using the DoIT Risk and Issue Log template as is presented below:
Issue Log:
Issue
No. Issue Person Responsible Month/Day/yearDate Opened -
1 Example Project Manager 03/15/07 Issue Form Issue No. (From Issue Log) Responsible Party (From Issue Log) Level (High, Medium, Low) Class (Impact Area) Date Opened (From Issue
Log) Date Closed Originator
Status (From issue Log)
1 Project Manager 03/15/07 Open
Issue (From Issue Log)
Example
Consequence(s)
If not resolved this issue could delay the project by 30 days, resulting in a fine for non-compliance
Resolution
6.1.6.1 Internal Issue Escalation and Resolution Process
This internal process is provided for issues that involve project resources, processes, procedures, or methodology that should be resolved within the Division that is responsible for managing the project without affecting the overall project schedule, cost, or quality. This process should be used for improving project processes as the project is executed and where the implementation of such improvements should not be postponed to Lessons Learned during Project Close.
6.1.6.2 External Issue Escalation and Resolution Process
The external process is provided for issues that involve project resources, processes, procedures, or methodology that cannot be resolved within the Division that is responsible for managing the project without affecting the overall project schedule, cost, or quality.
6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V
6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V
Independent Verification and Validation (IV&V) means the process of evaluating a system to determine compliance with specified requirements and the process of determining whether the products of a given development phase fulfill the requirements established during the previous stage, both of which are performed by an organization independent of the development
organization. Describe the process that will be employed to meet IV&V requirements. See Project Charter for Certification Workbook for some details.
6.3 SCOPE MANAGEMENT PLAN
6.3 SCOPE MANAGEMENT PLAN
Describe the process that is going to be used to manage the scope of the project. Make sure to address managing stakeholder expectations.
6.3.1 CHANGE
6.3.1 CHANGE CONTROL CONTROL
6.3.1.1 Change Control Process
Change Control establishes how change will be managed, including capturing, tracking,
communicating, and resolving change. Due to much ambiguity regarding change, it is vital that we document and discuss the change process with the executive sponsor.
6.3.1.2 Change Control Board (CCB)
Insert a graphic or textual description identifying the Change Control Board (or function) for this project. The CCB may be an individual or group of individuals authorized to approve changes to the project plan.
A project might want to formalize Change Management through a form such as shown below:
P
P
ROJECT
ROJECT
CHANGE
C
HANGE
REQUEST
R
EQUEST
PROJECT: PROJECT: AGENCY: DATE: PROJECT MANAGER: PROJECT #:
AGENCYAND PROJECT INFORMATION:
REQUESTED BY: DATE:
AUTHORIZED BY: DATE:
ACTION PLAN:
MARK ONE:
THIS CHANGE: Is Is NOT Within Scope.
THIS CHANGE IS: Accepted Denied On Hold Delayed
6.4 PROJECT BUDGET MANAGEMENT
6.4 PROJECT BUDGET MANAGEMENT
Costs estimates are the costs applied to an activity in a project by assigning resources with associated rates or fees. Resources can include equipment, material, technology, processing cycles, or people. The total cost is critical and should be consistent with the proposal; include breakdowns as needed. Match these cost estimates with the actual billed amounts. Use an appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or deliverable).
6.4.1 B
6.4.1 BUDGETUDGET T TRACKINGRACKING
6.5 COMMUNICATION PLAN
6.5 COMMUNICATION PLAN
Communication planning involves determining the information and communication needs of the stakeholders, executive sponsors, project team and others as needed. The communication plan needs to address who needs what information, when they will need it, how it will be given to them, and by whom. The complexity of the project may require a separate communication plan; however a high level summary of that plan will need to be included here and a reference made to the appropriate Appendix.
6.5.1 C
6.5.1 COMMUNICATIONOMMUNICATION M MATRIXATRIX
6.5.2 S
6.5.2 STATUSTATUS M MEETINGSEETINGS
6.5.3 P
6.5.3 PROJECTROJECT S STATUSTATUS R REPORTSEPORTS
6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)
6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)
The Project Manager and Executive Sponsor define the project metrics that will be used to control the project. Each project will need to have an established metrics program. Metrics are collected for measuring the progress of a project against its planned budget, schedule, resource usage, and error rates, and of establishing a historical database, which will aid in planning and forecasting future projects. At a minimum metrics must be established for time (schedule), cost (budget) and quality.
Project Area Category Measure
Example used by another state:
Common Project Issue Area Category Measure
Schedule and Progress Milestone Performance • Milestone Dates Work Unit Progress • Component Status •
Requirement Status • Test Case Status • Critical Paths Tested • Problem Report Status • Reviews Completed • Change Request Status
Incremental Capability • Build Content – Component • Build Content – Function Resources and Cost Personnel
• Effort • Staff Experience • Staff Turnover
Financial Performance
• Earned Value • Cost
Availability • Resource Availability Dates • Resource Utilization
Growth and Stability Product Size and Stability
• Lines of Code • Components • Database Size
• Change Request Workload Product Quality Defects • Problem Reports • Defect
Density
Complexity • Cyclomatic Complexity Rework
• Rework Size • Rework Effort Development Performance Process Maturity • Capability Maturity Model Level
Productivity • Product Size/Effort Ratio • Functional Size/Effort Ratio
6.6.1 B
6.6.1 BASELINESASELINES
6.6.2 M
6.6.2 METRICSETRICS L LIBRARYIBRARY
6.7 QUALITY OBJECTIVES AND CONTROL
6.7 QUALITY OBJECTIVES AND CONTROL
Quality Management includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It includes all activities of the overall management function that determine the quality policy, objectives, quality assurance, quality control, and quality improvement, within the quality system. If a separate Quality Plan is used, include a high level summary in this document and refer to the appropriate appendix.
6.7.1 Q
6.7.1 QUALITYUALITY S STANDARDSTANDARDS
Describe the agency, industry or regulatory project performance standards that will be followed and assessed by the project. These quality standards will be used to assess whether the quality objectives were achieved.
Identify each of the project quality standards that are directly related to the project and not to the performance of the actual product and/or service. For each quality standard, identify the tracking tool or measure such as number of project reviews or Project Status.
From another state’s planning process
No. Quality Standard Tracking Tool or Measure
1 Project phase is completed by the established finish date. • Project Schedule • Project Status 2 Project is completed within budget. • Project Charter
• Project Status 3 Quarterly project reviews show contractors deliver requirements
specified in the contract by due dates or pay penalties.
• Vendor Contract • Final Customer
No. Quality Standard Tracking Tool or Measure 4 Project issues are resolved and documented within 10 calendar days of
identification or extensions are justified.
• Issues Tracking
5 Project will be completed based on the original project scope and approved scope changes.
• Project Charter • Project Plan • Control Change Request • • • 6.7.2 P
6.7.2 PROJECTROJECTANDAND P PRODUCTRODUCT R REVIEWEVIEWANDAND A ASSESSMENTSSSESSMENTS
Review Type Quality Standard Tools Reviewer Reports Requirements
Plans Milestones Testing
6.7.3 A
6.7.3 AGENCYGENCY/C/CUSTOMERUSTOMER S SATISFACTIONATISFACTION
The project manager should assess the on-going sense of the customer agency about how they feel the project is going, and how team members are acting on the project. This feedback would be helpful to the success of the project and the professional growth of the project team members. Examples:
Areas of feedback When How Often
Agency awareness
Quality of communications Manages project tasks Productive Meetings .
An example used by some State of New Mexico agencies:
S
SSTANDARDSSTANDARDS ApplicableNot DisagreeStrongly
Disagree Somewhat Agree
Agree Strongly Agree
The level of business or agency
knowledge of [project’s name] meets your
expectations.
[Project’s name] performs in a
professional and cooperative manner.
The level of communications by
[project’s name], both written and oral, meet your expectations.
[Project’s name] project team works well
with you and your staff.
[Project’s name] project management team is accessible when you need them. [Project’s name] provides adequate
information and training resulting in
effective knowledge transfer.
[Project’s name] completes project tasks within the agreed upon schedule.
The level of technical or business
expertise of [project’s name] meets your
expectations.
You are receiving full value from the [project’s name] project management team.
The overall service provided by [project’s name] is fully meeting your expectations.
6.7.4 P
6.7.4 PRODUCTRODUCT D DELIVERABLEELIVERABLE A ACCEPTANCECCEPTANCE P PROCESSROCESS
How the client takes procession of the product. Delivery of media; manuals; contracts; licenses; services agreements; configuration settings; status of patches to COTS products; in-house or vendor developed code; test cases, routines, and scripts; and other items required to operate the product.
Deliverable Final Approval Process Customer Acceptance Criteria
6.8 CONFIGURATION MANAGEMENT
6.8 CONFIGURATION MANAGEMENT
Configuration Management determines how project information (files, reports, designs, memos, documents, etc.) will be managed (tracked, approved, stored, secured, accessed, version control, etc.) and owned by (e.g., Agency managing the project or the Customer). Standards and team awareness are critical.
6.8.1 V
6.8.1 VERSIONERSION C CONTROLONTROL
Documents should be tracked for version control, on the title page, and using a revision history table such as used for this PMP. Document file names should have project name agency revision number reflected. Best practice involves change management for documents, and a numbering scheme such as 1.0, 2.0, 3.0 to reflect a project’s phases and toll gates or approval processes per phase.
6.8.2 P
6.8.2 PROJECTROJECT R REPOSITORYEPOSITORY (P (PROJECTROJECT L LIBRARYIBRARY))
“Provide to the Department all project management and product deliverables. Deliverables shall include but not limited to the project plan, project schedule, initial and periodic risk assessments, quality
strategies and plan, periodic project reports, requirements and design documents for entire project. The lead agency must make available all deliverables in a repository with open access for the Department to review” PROJECT OVERSIGHT PROCESS Memorandum.
6.9 PROCUREMENT MANAGEMENT PLAN
6.9 PROCUREMENT MANAGEMENT PLAN
Projects often have some element of procurement, i.e. the requirement to purchase goods and/or services from outside the organization. The procedures to be used to handle these procurements should be included here. Activities such as a make-or-buy analysis; writing requirements; solicitation planning, evaluation and selection; inspection and acceptance; contract closeout should all be included.
State of New Mexico RFP, IT Contract and other procurement processes should be followed by all state agencies’’ IT Projects.
Project Close will always consist of administrative project activities and possibly contractual project activities and an external vendor is employed. Completing both sets of activities is a mandatory step in the project life cycle. Administrative activities complete the internal needs for the Agency/Unit that is responsible for managing the project, such as lessons learned, recording the last hours against the project, and providing transition for the staff to other assignments. Contractual activities meet the contractual needs, such as executing a procurement audit and formal acceptance of the project work products.
7.1 A
7.1 ADMINISTRATIVEDMINISTRATIVE C CLOSELOSE
Administrative Close occurs at both the end of phase and end of project. This closure consists of verification that objectives and deliverables were met. Acceptance is formalized and phase activities are administratively closed out. Administrative closure occurs on a “by-phase” basis in accordance with the WBS and should not be delayed to project end. At that point, the burden of closing is too great and audits inaccurate. The specific project close activities for a given project are contingent on the project’s complexity and size. Project managers should work with the project’s project management consultant to tailor Project Close procedures to compliment the project’s objectives
7.2 C
7.2 CONTRACTONTRACT C CLOSELOSE
Contract close is similar to administrative close in that it involves product and process verification for contract close.
Projects that have been certified need to complete the required DoIT project closure certification processes.
ATTACHMENTS
ATTACHMENTS
Attachments are included for additional information, but are not formally considered part of the Project Plan for approvals and change management purposes. Examples
• Acronyms, abbreviations and definitions
• Technical glossary of IT terms
• Project Work breakdown schedule
• Project timeline
ATTACHMENT A ACRONYMS, ABBREVIATIONS AND DEFINITIONS
ATTACHMENT A ACRONYMS, ABBREVIATIONS AND DEFINITIONS
PMI Project Management Institute.PMBOK Project Management Body of Knowledge