INSTRUCTIONS TO CONTRACTORS
APPLICATION FOR REGISTRATION AND CATEGORISATION OF ELECTRICAL CONTRACTORS FOR THE YEAR 2009/10 GENERAL NOTE:
INFORMATION SUPPLIED IN THIS APPLICATION MUST, WHERE NECESSARY, BE ACCOMPANIED BY SUPPORTING DOCUMENTS OTHERWISE NO POINTS WILL BE ALLOCATED
1. All contractors should submit their application forms to Procurement Office on or before 6th March 2009 at 12:00 noon.
2. It is important that the contractor answers each and every question fully, with supporting document where required, as the responses shall be carefully examined. 3. The applicants must note that they may be called for an interview on some or all
answers in the application form; and some of the responses may be physically verified.
4. The applicants must note that no individual, partnership or company shall be allowed to register more than one electrical contracting company with Lesotho Electricity Company; otherwise such applications will be disqualified.
5. The application form will not be considered if the Traders License is not attached. 6. Tools like comealong and ratchet are pre-requisite to be in category B, B+, A and
A+.
7. Any false information supplied in this form shall automatically disqualify the applicant. 1.0 IDENTIFICATION 1.1 Name of Contractor ……… 1.2 Physical address ………... ………... ………... 1.3 Postal address: ………... ………... ………... 1.4 Contact Name: ………
Contact numbers: Telephone: ……… Cell phone ………. Fax:………
2.0 LEGAL STATUS
2.1 State whether you are a (by ticking where appropriate)
Company
Partnership Joint Venture
Sole Proprietor
Any other (please specify) 2.2 For Companies
2.2.1 State the following:
a) Registration number………. b) Place of Registration……… c) Names of the shareholders
……….………. ……….………. ……….………. ……….………. ……….. ……….. d) Are there any shareholders that are Lesotho Citizens - yes/no e) If the answer to the above is yes, state the percentage of their
Shareholding……… f) Names of the Board of Directors
……….………. ……….………. ……….………. ……….………. ……….. ……….. g) Contact Person………..
2.2.2 Attach copies of:
a) Certificate of incorporation (certified copy),
b) Memorandum and Articles of Association (certified copy),
c) Board resolution authorizing the application for LEC registration (original). 2.3 For Partnerships
2.3.1 State the following:
a) Registration number………. b) Place of Registration……….. c) Names of the Partners
……….……….. ……….……….. ……….……….. ……….……….. ………... ………... d) Are there any partners that are Lesotho Citizens yes/no?
e) If the answer to the above is yes, state the percentage of their financial interest into the partnership
……….……….. f) Names of the Governing Body/Committee
……….……….. ……….……….. ……….……….. ……….……….. ………... ………... g) Contact Person……….. 2.3.2 Attach copies of:
a) A registered copy (certified) of a Deed of Partnership
b) Resolution by Partners authorizing the application for LEC registration (original)
2.4 For Joint Ventures (JV) 2.4.1 State the following:
……….……….. ……….……….. ……….……….. b) The Registration Numbers of the JV Partners
……….……….. ……….……….. ……….……….. c) Places of Registration of JV Partners
……….……….. ……….……….. ……….……….. c) Are there any JV partners that are Lesotho Citizens - yes/no? d) If the answer to the above is yes, state the percentage of their
Financial contribution into the JV Partnership
……….. e) The Chief Accounting Officers of the JV Partners
……….……….. ……….……….. ……….……….. f) JV’s Contact Person……….. 2.4.2 Attach copies of:
a) A copy (certified) of the JV Agreement
b) Resolution by JV Partners authorizing the application for LEC registration (original)
2.5 For Sole Proprietors
a) Nationality of the applicant……….. b) Passport/ID Number………. 3. 0 LICENSE TO TRADE & PROFESSIONAL REGISTRATION
a) A certified copy of license to trade in Lesotho must be attached (If not attached, the application will be disqualified).
b) Attach a certified proof of registration with a relevant body in the electrical industry if you have been registered with any such body
4.0 TAX CLEARANCE
Attach certified copies of tax clearance certificates including VAT and Income Tax. 5.0 FINANCIAL PERFORMANCE
a) Submit the audited accounts of the business for at least the past 2-years.
b) If audited accounts are not available, please provide a letter from the bank stating to which level they can provide you with a credit.
6.0 RESOURCES – PROPERTY, PLANT AND TOOLS (LEC may physically ascertain the availability of these resources)
6.1 Immovable Property (Indicate whether rented or owned by company, attach lease if owned or confirmation letter from owner if rented)
Property State whether
owned or rented
Value if owned by company
6.2.1 Plant and Vehicles (attach certified copies of ownership documents)
Item Number owned
Truck Crane truck
4 x 4 van 2 x 4 van
Compressor
6.2.2 Detailed information of Plant and vehicles (attach certified copies of ownership documents that reflect either name of contractor or name of any of the company’s Directors)
Vehicle/ Plant Make (e.g. Toyota)
Year of Manufacture
REGISTRATION/SERIAL NO.
6.2.3 Heavy duty tools
(i.e. Drill rigs, ladders, etc)
6.2.4 Light duty tools
Description of the Tools Number/QTY
6.2.5 Protective Clothing/ Equipment
7.0 KEY PESONNEL
7.1 Attach signed CVs and certified copies of educational certificates of full time employees 7.2 Please draw company structure on the space below or attach a separate sheet.
7.1 Engineers
Name Qualifications Experience (Years)
7.2 Contract/Project Managers
Name Qualifications Experience (Years)
7.3 Technician
Name Qualifications Experience (Years)
7.4 Health & Safety Inspector
Name Qualification Experience In (Years)
7.5 Foremen
Name Qualification Experience In (years)
7.6 Electricians
Name Qualification Experience In (Years)
7.7 Technical staff total
Category Total Average Experience (Years) Engineers
Technicians Electricians Linesmen
7.8 Additional information
Provide any additional information that may enhance this application concerning the resources that have ………
……….. ……….. ……….. ……….. ……….. ……….. ……….. ……….. 8.0 EXPERIENCE IN ELECTRICAL CONSTRUCTION WORKS
List all principal/major projects carried out in the last three years (chronologically) Project Description Project
Amount
Client (Name and telephone number of contact person)
9.0 TRADE REFERENCES
Please provide your trade references (i.e. suppliers, sub-contactors, clients, customers) at least three with name, address, and telephone number
9.1 ……… ……… ……… ………
………
9.2
………
……… ……… ..……….. ……… 9.3 ………. ……… ……… ……… ……… 10.0 PREVIOUS WORKSHave you ever failed to complete any work awarded to you under the style in which you apply or any other style? State the circumstances.
……… ……… ……… 11.0 PREVIOUS APPLICATION OF A PENALTY CLAUSE
Has the penalty clause been invoked against you on any project? If yes, state with whom, on what issue, under what circumstances.
……… ……… ……… ……… 12.0 PREVIOUS APPLICATION OF ARBITRATION CLAUSE
Has an arbitration clause ever been invoked against you on any project? If yes, state with whom, on what issues, under what circumstances.
……… ……… ……… ………
13.0 LIQUIDATION OR ESQUESTRATION
Has there been any company that has been liquidated which company you had shares in or were involved in its Management and or has estate ever been sequestrated? If ye state the circumstances ……… ……… ……… ……… 14.0 CRIMINAL CONVICTION
Have you or any of your business partners been convicted of any offence? (State details) ……… ……… ……… ……… ……… ……… 15.0 THIRD PARTY INSURANCE
16.0 CONTRACTORS EVALUATION CRITERIA
The following criteria will be used to evaluate proposals submitted by the contractors Criteria No. Criteria Criteria Weight
1 LEC Registration (2) 2 if you have a valid LEC Wiring Test Certificate
Quality of work (21) 2 Previous experience with LEC
(30) Period for delivery of services (9) 3 3rd Party Insurance (3) 3 for 3rd Party Insurance
1 for having safety officer.
2 for full protective clothing (attach list of available items)
4 Safety Consciousness (5).
2 for trained first aid personnel. 5 if <M50, 000
6 if >M50, 000-M100, 000 7 if >M100, 000-M500, 000 5 Value of Previous Projects done
to date. (10) 10 if >M500, 000 1 for 2 Artisans 2 for >2 Artisans 3 for 2 Electricians 4 for >2 Electricians 4 for 2 Technicians 5 for >2 Technicians 6 Qualification of Staff (20).
6 for Engineer or Project Manager 1 for 5 light tools and 2 for >5 light tools.
2 for 3 heavy tools and 4 for >3 heavy tools
3 for 1 light vehicle and 5 for >1 light vehicles
4 for 1 heavy vehicle and 6 for >1 heavy vehicles
8 for owned plant (regardless of the number)
7 Company Assets (25)
4 for property
17.0 CATEGORIZATION
17.1 Evaluation Levels
Contractors are categorized according the level of evaluation score as follows:
Total Points Category
From 25 to 29 points C From 30 to 49 points C+ From 50 to 65 points B From 66 to 70 points B+ From 71 to 80 points A From 81 to 100 A+
17.2 Area of work for each category
Category Area of works Comment A+ Overhead lines and underground cables from
0.4kV to 132kV, installation of all sizes and types of transformers and switchgears
Can construct more than two (2) electrification projects concurrently A Overhead lines and underground cables from
0.4kV to 33kV, installation of transformers and switchgear up to the voltage level of 33kV
Can construct up to two (2) electrification projects concurrently
B+ Overhead lines and underground cables from 0.4kV to 11kV, installation of transformers and switchgear up to the voltage level of 11kV
Can construct one (1) electrification project at the time
B Low voltage overhead lines and service cables of 0.4 kV and installation of meters
C+ Installation of 0.4kV cables and prepaid meters More than 10 Service Connections at a time C Installation of 0.4kV cables and prepaid meters 10 Service Connection at
a time
18.0 DECLARATION UNDER OATH TO: MANAGING DIRECTOR LEC
I, THE UNDERSIGNED CERTIFY UNDER OATH, TO THE TRUTHFULNESS AND CORRECTNESS OF ALL THE STATEMENTS, INFORMATION AND ANSWERS TO THE QUESTIONS MADE ABOVE:
……….
Name of applicant/representative in full capitals ………..
SIGNATURE
COMMISSIONER OF OATH……….. DATE STAMP……….