Capital Projects Report

(2)

Capital Plan Progress Highlights

The construction for Sci-High is ahead of schedule with pile driving

almost complete and concrete pile caps being placed.

McMain Envelope Repair Phases 1 through 4 have been completed,

with the exterior repair and painting proceeding on schedule. The

project is scheduled to be complete in the 3

rd

quarter of 2019.

Hynes ES Envelope Repair work began on 12/20/18.

Ben Franklin ES Envelope Repair Phase 2 contract was signed on

12/20/18, and work began on 1/2/19.

Construction, which is being managed by the RSD, is underway on the

(3)

DBE Participation

OPSB’s DBE Program finished strong in CY-2018, with respect to

capital projects. All General Contractors have displayed strong

leadership by strategically partnering with DBE Subcontractors, both

Tier 1 and Tier 2.

Since May 2018, Certified State & Local DBE Contractors have 35.05%

participation on 9 construction projects at a value of $13,827,469.

Thirty-five (35) DBE Contractors (~78%) are currently participating on

45 individual subcontracting opportunities and are performing 30+

specialized scopes of work.

Eight (8) DBE contractors are participating on multiple projects, which

currently entails 40% of all DBE subcontracting opportunities at OPSB.

(4)

DBE Participation (Committed)

Project

Contract

Value

Current DBE

Participation Value

% of DBE

Participation

# DBE

Vendors

Ben Franklin Elementary School –

Refurbishment: Phase 1

$ 1,980,000

$ 700,000

35.35%

1

McMain High School – Building Envelope

$ 3,540,000

$956,300

26.31%

6

New Orleans Charter Science and Math High

School – New Construction

$ 27,496,000

$9,775,004

35.73%

20

Douglass Gymnasium - Renovation

$ 490,000

$ 174,000

35.51%

5

Mahalia Jackson Child Center –

Reconfiguration – Phase 1

$ 150,000

$68,400

45.6%

2

Mahalia Jackson Child Center –

Reconfiguration – Phase 2

$ 113,372

$80,532

100%

2

Rosenwald Response Action

$1,296,772

$336,720

34.97%

3

Hynes Elementary Exterior Envelope

$ 422,500

$ 165,000

39.05%

3

Ben Franklin Elementary School –

Refurbishment: Phase 2

$3,960,000

$1,396,645

35.27%

6

(5)

Funding Overview

5

Eligible/Approved/Reimbursed To Date (thru 8/2018)

$ 311,091,446

Eligible Expenditures/Reimbursement Submissions Under

Review

$ 3,612,080

Follow-Up on Eligible Executed Work and Execution of

Remaining Eligible Work (Includes contents to be

purchased for the new Karr HS and the new New Orleans

Charter Science and Math High School)

$ 60,263,516

Total Eligible/Obligated FEMA Dollars (Hurricane Katrina:

(6)

Project Summary

Project

Current

Budget

Construction

Complete

Ben Franklin Elementary School – Refurbishment:

Phase 1

$ 7,665,367

December 2018

Ben Franklin Elementary School – Refurbishment:

Phase 2

July 2019

Hynes Elementary School – Envelope Repair

$ 423,000

February 2019

Karr High School – New Construction

$ 49,549,591

April 2020

McMain High School – Building Envelope

$ 5,148,000

August 2019

New Orleans Charter Science and Math High School

(7)

7

Ben Franklin Elementary School – Refurbishment Phase 1

Project Information

Owner: Orleans Parish School Board

Project Status: Construction

Funding Source: Bonds

Architect: NY Associates, Inc.

Contractor: Construction Masters, Inc.

Scope of Work

Refurbishment of existing elementary school

Asbestos & lead paint abatement, window refurbishment Brick repair & refurbishment

Interior demolition as needed for structural investigation & inspection

Project Status

Abatement complete, window refurbishment 100% complete. Substantial completion was 12/17/2018.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 7,665,367 $ 7,665,367 $ 0

Schedule Status

Task Planned Adjusted Actual

Design April 2014 --- May 2017

Procurement March 2015 --- September 2017

Construction Complete

December 2018 --- December 2018

DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

(8)

8

Ben Franklin Elementary School – Refurbishment Phase 2

Project Information

Owner: Orleans Parish School Board

Project Status: Procurement

Funding Source: Bonds

Architect: NY Associates, Inc.

Contractor: TBD

Scope of Work

Refurbishment of existing elementary school

Site work, ADA compliance, ceiling replacement, new elevator Floor repairs, update HVAC, sprinkler system & fire alarm

Project Status

Project bid in November 2018. Board approval in 12/2018. Notice to Proceed was provided on 1/2/2019.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 7,665,367 $ 7,665,367 $ 0

Schedule Status

Task Planned Adjusted Actual

Design October 2018 --- October 2018

Procurement November 2018 --- November 2018

Construction Complete

July 2019 ---

---Move-in August 2019 ---

---DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

(9)

9

Hynes Elementary School – Exterior Envelope Repair

Project Information

Owner: Orleans Parish School Board

Project Status: Construction

Funding Source: FEMA/Capital Projects

Architect: SCNZ

Contractor:

---Scope of Work

Repair of building envelope due to water infiltration

Project Status

Notice to Proceed was given 12/20/2018. Tile restoration work has been completed. Brick damaged due to issues with an expansion joint has been replaced. Brick has been removed in areas where water infiltration has been identified and further investigation is underway. Concrete repairs at the perimeter of the building are complete and parking lot repairs are ongoing.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 422,500 $ 422,500 $0

Schedule Status

Task Planned Adjusted Actual

Design February 2018 August 2018 August 2018

Procurement October 2018 --- October 2018

Construction Complete

February 2019 ---

---DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

(10)

McMain High School – Building Envelope

Project Information

Owner: Orleans Parish School Board

Project Status: Construction

Funding Source: FEMA

Architect: Concordia, LLC

Contractor: Tuna Construction

Scope of Work

Refurbishment of building envelope (excluding roof)

Including but not limited to windows, doors, stucco, and painting

Project Status

Phases 1 – 4 are complete. Exterior repair and painting are ongoing.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 5,148,000 $ 4,635,866 ($ 512,134)

Schedule Status

Task Planned Adjusted Actual

Design March 2018 --- March 2018

Procurement May 2018 June 2018 June 2018

Construction August 2019 ---

---DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

(11)

11

New Orleans Charter Science & Mathematics High School –

New Construction

Project Information

Owner: Orleans Parish School Board

Project Status: Construction

Funding Source: FEMA/Bonds/Capital Projects

Architect: Verges Rome

Contractor: McDonnel Group

Scope of Work

Demolition of Wicker Elementary School Construction of a new high school

Project Status

Pile cap and grade beam placement is ongoing. Sub-surface drainage and utility construction will begin during January.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 36,137,138 $ 33,884,511 ($ 2,252,627)

Schedule Status

Task Planned Adjusted Actual

Design April 2018 --- April 2018

Procurement May 2018 August 2018 August 2018

Construction December 2020 ---

---Move-In April 2021 ---

---DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

(12)
(13)

13

RSD Capital Project Summary – Phase II

Construction: 7

Bauduit ES- Refurb Booker T.

Washington-New

John McDonogh HS-Reno

Laurel ES- Refurb Marshall ES- Refurb

Tubman ES- Reno Village de L’Est

ES-Refurb

Design: 2

Johnson ES- Refurb McDonogh 32 ES- Refurb

Procurement: 1

New Karr- CMAR

Planning: 4

Behrman ES- CMaR CTE HS @ Kerleric- CMaR

McDonogh 7 ES- Refurb New Cohen HS- CMaR

Complete: 33

A Jackson ES- Refurb Fischer ES- Refurb McDonogh 28 ES- Refurb

Abrams ES- New Fisk-Howard ES- New McDonogh 42- Reno

Allen ES- Refurb Gaudet ES- Refurb Morial ES- New

Avery Alexander ES- New Gentilly Terrace ES- Refurb NO East HS @ Abramson-New

Bradley ES- New Green MS- Refurb Phase I &

Phase II Reed HS- Refurb

Carver HS- New D/B Habans ES- New D/B Rosenwald ES- Refurb Crossman ES- Refurb Harney ES- Refurb Schaumburg ES- Refurb

Douglass HS- Refurb Lafayette ES- Refurb Sherwood Forest ES- New D/B

Drew ES- Reno Lawless HS- New Sophie B. Wright HS- Reno

Dunbar ES- New Live Oak ES- Refurb Sylvanie Williams- Refurb

(14)

RSD: DBE Participation (Committed)

Project

Contract Value

Current DBE

Participation Value

% of DBE

Participation

# DBE

Vendors

Karr H.S. (CMAR)

$ 46,938,195

$ 14,563,362

31.03%

16

Booker T Washington (CMAR)

$ 55,164,066

$ 19,038,139

34.51%

34

John McDonogh (CMAR)

$ 32,143,589

$ 11,400,172

35.47%

29

Harriet Tubman Renovation

$ 13,947,000

$ ,048,926

29.03%

16

Thurgood Marshall Refurbishment

$ 4,867,000

$ 1,249,326

25.67%

12

Fisk Howard Exterior Envelope Repairs

$

180,165

$ -

0.00%

0

McDonogh #28 Flooring (Phase II)

$ 397,000

$ 150,360

37.87%

3

Harriet Tubman Cottage

$ 552,000

$ 118,329

21.44%

6

Schaumburg Roof Repairs

$ 2,031,362

$ 261,668

12.88%

6

Village de l'Est & Sarah T. Reed HVAC & Fencing

$ 1,474,000

$ 342,326

23.22%

4

Sophie B. Wright Interior Painting and Wood

Flooring

$ 167,122

$ 111,357

66.63%

1

(15)

15

RSD: Karr High School – New Construction

Project Information

Owner: Orleans Parish School Board

Project Status: Construction

Funding Source: FEMA

Architect: Trapolin Peer Architects, APC

Contractor: Core Construction Services, LLC - CMAR

Scope of Work

Construction of new high school – Construction Manager at Risk

Project Status

Structural steel and decking are being set. Framing contractor has mobilized.

Budget/Cost Information Phases 1 & 2

Transferred Projected Costs Projected Over/Under

$ 49,782,165 $ 48,773,696 ($1,008,469)

Schedule Status

Task Planned Adjusted Actual

Design November 2017 March 2018 March 2018

Procurement January 2018 March 2018 March 2018

Construction July 2020 ---

---Move-In --- ---

---DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

(16)
(17)

17

RSD: Booker T. Washington - New

Project Information

Project Control: Recovery School District

Project Status: Construction

Funding Source: FEMA

Architect: Hewitt Washington & Associates

Contractor: Core Construction Services, LLC - CMAR

Scope of Work

Construction of a New High School Restoration of existing Auditorium

Project Status

Installation of interior finishes is underway. Casework is being installed. Installation of storm-water retention structure is in progress. Installation of brick on facades of the Auditorium building is beginning.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$70,329,905 $67,380,498 ($2,949,407)

Schedule Status

Task Planned Adjusted Actual

Design --- --- December 2017

Procurement --- ---

---Construction January 2019 May 2019

---Move-In --- ---

---DBE Participation (Committed) Contract Value Current DBE

Participation Value

% of DBE Participation

# of DBE Vendors

References

Related documents

Shall the Orleans Parish School Board continue to levy a tax of one and fifty-five hundredths (1.55) mills on the dollar of the assessed valuation of property within the City of

Borders/Visiting (fee-paying) Study Abroad) and Programme of Study (SwB students, please select the Faculty of the programme you will be studying in Liverpool, Visiting Students,

Curved versus Straight Stem Uncemented Total Hip Arthroplasty Osteoarthritis Multicenter trial (CUSTOM): design of a prospective blinded randomised controlled multicentre

22-0015 – Superintendent Search Firm, I, the undersigned, authorized to represent the corporation, partnership, sole proprietorship (the Company) listed below,

Owner: Orleans Parish School Board Project Status: Construction8. Funding

Orleans Parish School Board | Strategic Plan 2021-2025 13 2A: Refine and Communicate Our Portfolio Strategy and Related Data.. to Improve

 The purpose of this report is to inform Council of the project status, provide an updated budget estimate for the capital projects associated with the new South Niagara

[r]