• No results found

Fig. 4 Railway incursion prioritisation process 128

N/A
N/A
Protected

Academic year: 2021

Share "Fig. 4 Railway incursion prioritisation process 128"

Copied!
6
0
0

Loading.... (view fulltext now)

Full text

(1)

Fig. 4 – Railway incursion prioritisation process

C h a p t e r 9 – S t r u c t u r e s L i f e c y c l e M a n a g e m e n t P l a n

9

(2)

Fig. 5 – Strengthening Prioritisation Process

(3)

Fig. 6 – Simplified BA79 Process C h a p t e r 9 – S t r u c t u r e s L i f e c y c l e M a n a g e m e n t P l a n

9

PM produces schedule of bridges to be assessed Carryout Level 1 assessment Complete Form E1 (review every 2 years)

Apply interim measure

Carry out higher level assessment work as appropriate Determine monitoring procedure and include in inspection programme Update results in BMS YES YES YES NO NO YES End End NO Does the structure pass? Substandard Bridge? Is the structure an immediate risk structure? Is monitoring by inspection sufficient? Does the structure pass?

(4)

Scheme

Fees

Works

Project Total (£)

Old Weybridge (residual costs

of 2003/04 scheme) 2,500 10,000 12,500

A31 Weydon Lane 10,000 85,000 95,000

A31 Hatch Mill 23,000 220,000 243,000

Slipshatch (major

maintenance contribution) 7,000 70,000 77,000

A31 Bourne Place 10,000 90,000 100,000

Ruxley Farm (residual costs

of 2003/04 scheme) 1,500 5,000 6,500

Puddenhole Copse 22,000 210,000 232,000

A22 Lagham (residual costs

of 03/04 scheme) 1,500 5,000 6,500

A30 Cricketers (residual costs

of 2002/03 scheme) 1,000 1,563 2,563

Tilford (New and West) 68,000 668,000 736,000

Ash Vale 55,000 550,000 605,000

Totals 201,500 1,914,563 2,116,063

Table 9.12 – Bridge Strengthening Programme (2004/05)

In addition, there will still be approximately 400 bridges which have not had the benefit of capital

investment, although it has to be acknowledged that most of the larger and more significant bridges would have been dealt with. Present day calculations indicate that we spend only one fifth of the recommended money on routine structural maintenance. Capital investment is relied upon to make up the difference. Further work is required, in conjunction with the development of the bridge management system, the CSS Bridge Condition Indicator and the continuous assessment programme, to refine the extent of the problem. Work is now underway to determine a second five year programme to the end of the Ten Year Transport Plan which, subject to funding, should enable all bridges to be brought up to acceptable current standards. Consideration will be given to the effect of differing funding levels.

The 2004/05 bridge strengthening programme is given in Table 9.12.

Subways and Footbridges

The Bridge Management Strategy of the LTP included a desire to improve the access to footways and subways where they did not meet current standards. This was part of the overall strategy to improve accessibility as well as to start to meet the requirements of the Disability Discrimination Act. Details are given in Table 9.13.

(5)

Asset Description

Disposal Activity

Drivers

Disposal Programme

Subway Infill of subway Lack of use Lightwater subways

are under review General structures Closing of structures Stopping up of roads No current actions

programmed Footbridges Removal of disused Provision of alternative No current actions

footbridges high quality at-grade programmed facilities

Location

District

Project Cost (£)

2004/2005

Hall Grove Footbridge Surrey Heath 50,000

2005/2006

Stones Road Subway Epsom and Ewell 300,000

2006/2007

Watchetts Wood Footbridge Surrey Heath 200,000

Table 9.13 – Subway and Footbridge Accessibility Programme

9.12 Disposal Plan

Disposal is any activity that removes a decommissioned asset, including sale, demolition or relocation. Disposal of structures assets will generally occur as part of disposal of a larger asset grouping like roads and footways. However, other drivers may result in development of a disposal programme as shown in Table 9.14. Sustainable development objectives also need to be taken into account.

Table 9.14 – Structures Disposal Activities and Drivers

9.13 Sustainable Development

There are many definitions of sustainable development but perhaps the most common is:

‘Sustainable development meets our present needs without compromising the ability of future generations to meet theirs.’ Brundtand Commission (1987)

Doctoral research work sponsored by SCC at the University of Surrey enabled a method to be developed which would allow environmental pollution effects of bridge management activities to be quantified. Recent

C h a p t e r 9 – S t r u c t u r e s L i f e c y c l e M a n a g e m e n t P l a n

(6)

In order to take the longer term view, we will:

maximise reuse of existing materials when repair and reconstruction is carried out

ensure that materials incorporated in works will be recyclable at the end of their useful life

maximise the use of renewable resources whenever possible

One of the best ways to demonstrate economic stewardship of assets is to quantify the asset value in monetary terms and monitor how this is changing with time. This will indicate if costs are being passed to future generations and can provide compelling arguments for investing in the preservation of the asset base. It is likely that this approach will form the basis of a future national performance indicator.

Prior to the development of such an indicator a more simplistic approach is to calculate the amount spent on maintenance as a percentage of the asset valuation – as described above.

9.14 Future Developments

It is recognised that the development of a Lifecycle Plan within the overall Asset Management Plan is a continuous improvement process. Future versions of this Plan will cover, and be influenced by, the following topics in greater detail:

Implementation of CSS Bridge Condition Indicators

Interpretation of data from the CSS Bridge Condition Indicators

Development of a continuous assessment programme

Development of a bridge strengthening and upgrading programme through to the end of the 10 year Transport Plan

Introduction of national key performance indicators for bridges

Development of deterioration models for bridges

Development of Asset Valuation models

Introduction of an advanced Bridge Management System

Introduction of a national Code of Practice for Bridge Maintenance

Implementation of sustainable development indicators for bridges

9.15 References

1. Brooman, H., Implementation of Bridge Condition Indicators, The 11th Annual Surveyor Bridge Conference, March 2003

2. CSS, Bridge Condition Indicators – Volume 3, Guidance Notes on Evaluation of Bridge Condition Indicators, July 2002

3. Johnston, F., Developing Whole Life Strategies for Highway Networks

Assessment for Roads: Development and Implementation, Aston University, November 2003 4. CSS, ‘Funding for Bridge Management’, February 2000

5. Cole, G., Funding for Bridge Management – An Update Report Structures Group Report, December 2003

6. Cole, G., Best Value in Structures, SEABIG – An Interim Report Structures Group Report, February 2001

7. Highways Agency, The Management of Sub-Standard Highway Structures, BA79, 1998

References

Related documents

Description: An all-in-one guide to online marketing from the New York Times bestselling author of Never Cold Call Again In Never Cold Call Again, Frank Rumbauskas shows salespeople

During the reading period the teacher should not ask a child to sound out a word if he has not been taught the sounds, For example, if the child has learned the sounds of

(1) When applying our method to Haskell source code that contains a single type error; Do we show improvement in locating the errors compared to the Glasgow Haskell Compiler.. The

The Quarterly financial statistics Survey covers a sample of private enterprises operating in the formal non-agricultural business sector of the South African economy. It

diagnosis of heart disease in children. : The role of the pulmonary vascular. bed in congenital heart disease.. natal structural changes in intrapulmon- ary arteries and arterioles.

повышается также скорость входа протонов в матрикс (рис.. Влияние МрТр на трансмембранный обмен ионов в митохондриях. Открывание МРТР, как уже было показано нами

It was decided that with the presence of such significant red flag signs that she should undergo advanced imaging, in this case an MRI, that revealed an underlying malignancy, which