• No results found

Estimating the Mean and Variance of. Activity Duration in PERT

N/A
N/A
Protected

Academic year: 2021

Share "Estimating the Mean and Variance of. Activity Duration in PERT"

Copied!
8
0
0

Loading.... (view fulltext now)

Full text

(1)

International Mathematical Forum, 5, 2010, no. 18, 861 - 868

Estimating the Mean and Variance of

Activity Duration in PERT

N. Ravi Shankar1, K. Surya Narayana Rao2, V. Sireesha1 1

Department of Applied Mathematics ,GIS GITAM University, Visakhapatnam, India

[email protected]

2

Department of Mathematics, Al-Ameer College of Engineering & IT Visakhapatnam,India

Abstract

The traditional PERT (Program Evaluation and Review Technique) model uses beta distribution as the distribution of activity duration and estimates the mean and the variance of activity duration using “pessimistic”, “most likely” and “optimistic” time estimates proposed by an expert. In the past several authors have modified the original PERT estimators to improve the accuracy. In this paper, on the basis of the study of the PERT assumptions, we present an improvement of these estimates. At the end of the paper, an example is presented to compare with those obtained using the proposed method as well as other method. The comparisons reveal that the method proposed in this paper is more effective in determining the activity criticalities and finding the critical path.

Keywords: Estimating the mean and the variance of activity times; Beta distribution; PERT; Critical Path

1.

Introduction

In recent years, the range of project management applications has greatly expanded. Project management concerns the scheduling and control of activities

(2)

in such a way that the project can be completed in as little time as possible [1,2]. PERT [12] is a well known technique with proven value in managing large-scale projects. In 1959, the creators of PERT [12] considered beta distribution

, , , 0. ) ( ) ( ) ( ) ( ) ( ) ( ) ( 1 1 1 > < < − − − Γ Γ + Γ = − + − α β β α β α β α β α b y a a b y b a y y fy (1)

as an adequate distribution of the activity duration y where α and β are parameters of the beta distribution. They suggested the estimates of the mean and variance values ( 4 ), 6 1 b m a+ + = μ (2) ( ) , 36 1 2 2 a b− = σ (3) where a,m and b are the “optimistic”, “most likely” and “pessimistic” activity time estimates respectively determined by a specialist. In the last five decades, numerous attempts have been made to improve the PERT analysis based on the subjective determination of a, m and b. By using PERT, managers are able to obtain[9,10,11] :

(i) A graphical display of project activities. (ii) An estimate of how long the project will take.

(iii) An indication of which activities are the most critical for timely project completion.

(iv) An indication of how long any task can be delayed without delaying

the project.

There are, indeed, few areas as open until now to such a sharp criticism as in PERT applications.One of the criticism about PERT estimates as pointed by Clark[10] , Grubbs[11] and Sasieni[8] is that the estimates eq.(2) and eq (3), which are based on the three activity times a, m and b cannot be obtained directly from (1), implying a lack of a sound theoretical basis. Ginzburg [6] assumed p+q = z (constant) as an extension of earlier assumptions, saying, on the basis of statistical analysis and some other intuitive arguments, the creators of PERT [12]

assumed that p + q ≅ 4. In [13], Ravi Shankar and Sireesha generalize the

assumption on parameters in original PERT and obtained new approximation for the mean and variance of a PERT activity duration distribution. Based on beta activity time distribution, we assumed p = qz and obtained new approximations for the mean and the variance of activity time in PERT. By comparison with actual values, it was shown that the proposed approximations have the lowest average absolute error compared to the existing ones.

The rest of this paper is organized as follows. In Section 2, we briefly review Original and Ginzburg’s PERT approximations. In Section 3, we proposed PERT approximation. In Section 4, we given a numerical example for PERT approximations. In section 5 we summarizes contributions of this paper.

(3)

Estimating the mean and variance 863

2 Traditional and Ginzburg’s PERT approximations

2.1 Traditional PERT approximation

Since in PERT applications aand b of the density function (1) are either known or subjectively determined, we can always transform the density function to a standard form, (1 ) ,0 1, , 0, ) ( ) ( ) ( ) ( 1 − 1 < < > Γ Γ + Γ = − − α β β α β α α β x x x x f (4) where . a b a y x − − =

Note that simple relations

a b a m m a b a b a y x y x y x − = − = − − = μ , σ σ , μ (5) hold.

Let α-1 = p , β-1 = q. The density function (4) becomes

(1 ) ,0 1, , 1, ) 1 ( ) 1 ( ) 2 ( ) ( − < < >− + Γ + Γ + + Γ = x x x p q q p q p x f p q (6)

with the mean, variance and mode as follows :

2 1 + + + = q p p x μ , (7) , ) 3 ( ) 2 ( ) 1 )( 1 ( 2 2 + + + + + + = q p q p q p x σ (8) . q p p mx + = (9) From (6) and (9) we obtain

. ) 1 ( ) 1 ( ) 1 ( ) 2 ( ) ( − (1/ −1) + Γ + Γ + + Γ = xp x p mx q p q p x f (10)

Thus value mx, being obtained from the analyst’s subjective knowledge, indicates

the density function. On the basis of statistical analysis and some other intuitive arguments, the creators of PERT assumed [2] that

p+q ≅ 4. (11) It is from that assertion that estimates (2) and (3) were finally obtained, according to (6) – (9).

(4)

2.2

Ginzburg’s [6] PERT approximation

Ginzburg[6] showed that the PERT assumptions (11) is poor because the actual standard deviation may be considerably smaller than 1/6 , especially in the tails of the distribution[7,8]. In order to make the assumption more flexible, he assumed that the sum p+q in (6) is approximately constant but not predetermined; i.e., relation

p + q ≅ Z = constant (12) From (9) we obtain

p= Zmx , (13)

and values μx and σx2 are

, 2 1 ) ( + + = Z Zm m x x x μ (14) ) 3 ( ) 2 ( 1 ) ( 2 2 2 2 2 + + − + + = Z Z m Z m Z Z m x x x x σ (15) To satisfy the main PERT assumption the average value σx2(mx) for 0 < mx <1

has to be equal to 1/36; i.e.,

36 1 ) ( 1 0 2 =

σx mx dmx (16) Substituting (15) in (16), integrating and solving (16) for Z, obtained Z = 4.55. Approximating Z to 4.5 and getting

p = 4.5 mx, q = 4.5 (1-mx) (17)

from (12) and (13) , finally obtained

(1 ) . ) 5 . 4 5 . 5 ( ) 1 5 . 4 ( ) 5 . 6 ( ) ( 4.5mx 4.5(1 mx) x x x x m m x f − − − Γ + Γ Γ = , (18)

with the mean and variance

13 2 9 + = x x m μ , (19) (22 81 81 ), 1268 1 2 2 x x x = + mm σ (20) For the general beta distribution of the activity time, estimates (19) and (20) are transformed to , 13 2 9 2a m b y + + = μ (21) 22 81 81 . 1268 ) ( 2 2 2 ⎥ ⎥ ⎦ ⎤ ⎢ ⎢ ⎣ ⎡ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ − − − − − + − = a b a m a b a m a b y σ (22)

(5)

Estimating the mean and variance 865

By assuming that p =1, q = 2 and m= 3 2a+b

, he further improved these estimates

when the estimated mode of the activity time is located in the tail of the distribution as follows. μy =0.2(3a+2b) (23) 2 ( )2 0.04( )2 1268 40 a b a b y = − ≅ − σ (24)

Thus estimates (2) and (3) are replaced by estimates (21) and (24).

3. Proposed PERT approximation

Let z

q p

= (constant)where p and q are equal to α-1 and β-1 respectively. By substituting p = qz in (7) - (9) we obtain 2 1 + + + = q qz qz x μ (25) 1 + = z z mx (26) ) 3 ( ) 2 ( ) 1 )( 1 ( 2 2 + + + + + + = q qz q qz q qz x σ (27) From (27) , 2 3 ) 1 ( z q z x + ≅ σ (28) We assume that original PERT assumption,

6 1

=

x

σ , to solve (28) using (26) to

obtain the following values for p and q.

p=36m2x(1−mx), (29) q=36mx(1−mx)2 (30) Substituting p and q values in (7) and (8) we obtain

2 ) 1 ( 36 1 ) 1 ( 36 2 + − + − = x x x x x m m m m μ (31)

(

)

(

)

(

36 (1 ) 2

) (

36 (1 ) 3

)

1 ) 1 ( 36 1 ) 1 ( 36 2 2 2 + − + − + − + − = x x x x x x x x x m m m m m m m m σ (32)

Using relations (5) in (31) and (32) and also substituting

3

2a b

my

+

= which is

used by Ginzberg[7] in variance σy2, we obtain

2 2 ) ( 2 ) )( ( 36 ) )( ( ) )( ( 36 a b m b a m a b a b m m b a m y − + − − − + + − − = μ (33)

(6)

2 2 ) ( 03 . 0 b a y = − σ (34) Thus estimates (2) and (3) are replaced by estimates (33) and (34).

4. Numerical Example

The data for activities is represented in table I including mean and variance estimates for original , Ginzburg and proposed approximations. The estimated project duration has approximately same value by using the original, Ginzburg and proposed methods.

Table I. Mean and variance estimates

5. Conclusion

Based on beta activity time distribution, we obtained new approximations for the mean and the variance of activity time in PERT. By comparison with actual values, it was shown that the proposed approximations are identical with the existing ones. The estimated project duration has approximately same value by using the original, Ginzburg and proposed methods.

Activity a m b Original approximation Ginzburg approximation Proposed approximation μ σ2 μ σ2 μ σ2 A 5 12 17 11.66 4.00 11.69 4.49 11.81 4.32 B 8 10 13 10.16 0.69 10.15 0.78 10.57 0.75 C 9 11 12 10.83 0.25 10.84 0.28 10.65 0.27 D 5 8 9 7.66 0.44 7.69 0.50 7.88 0.48 E 9 11 13 11.00 0.44 11.00 0.50 11.00 0.48 F 14 18 22 18.00 1.78 18.00 2.01 18.00 1.92 G 21 25 30 25.16 2.25 25.15 2.55 25.09 2.43 H 8 13 17 12.83 2.25 12.84 2.55 12.90 2.43 I 14 17 21 17.00 1.30 17.15 1.54 17.09 1.47 J 6 9 12 9.00 1.00 9.00 1.13 9.00 1.08

(7)

Estimating the mean and variance 867

References

[1] Chen,C.T. and Huang,S.F.,(2007), “Applying fuzzy method for measuring criticality in project network”, Information Sciences,177,2448-2458.

[2] Azaron, A., Katagiri, H., Sakawa,M., Kato,K. and Memariani,A.,(2006), “A multiobjective resource allocation problem in PERT networks”, European Journal of Operational Research, 172, 838-854.

[3] Stevenson,W.J.(2002),Operation Management, seventh edition, McGraw-Hill.

[4] Roy, G. Nava, P. and Israel, S. (2002) , “Integrating system analysis and project management tools”, International Journal of Project management ,20, 461-468

[5] Avraham, S., (1997), “Project segmentation- a tool for project management”, International Journal of Project Management, 15, 15-19.

[6] Ginzberg, DG.,(1988), “On the distribution of activity time in PERT”, Journal of the Operations Research Society”,39,767-771.

[7] Farnum, N.R. and Stanton, L.W.,(1987), “Some results concerning the estimation of beta distribution parameters in PERT”, Journal of Operations Research Society, 38,287-290.

[8] Sasieni, M.W.,(1986), “A note on PERT times”, Management Science, 32,1652-1653.

[9] Moderi, J.J. and Rodgers, E.G., (1968), “Judgment estimates of the moments of PERT type distributions”, Management Science, 15, B76-B83.

[10] Clark, CE.,(1962), “The PERT model for the distribution of an activity time”, Operations Research, 10,405-406.

[11] Grubbs, FE.,(1962), “Attempts to validate certain PERT statistics or ‘picking on PERT”, Operations Research, 10, 912-915.

[12] Malcolm D.G., Roseboom J.H., and Clark C.E., (1959), Application of a technique of research and development program evaluation, operations research, 7 , 646-669.

(8)

[13] Ravi Shankar N.,and Sireesha V.,(2009), An Approximation for the Activity Duration Distribution, Supporting Original PERT ,Applied Mathematical Sciences, Vol. 3, no. 57, 2823 – 2834.

Figure

Table I.    Mean and variance estimates

References

Related documents

We primarily discuss the major agriculture applications – Land Parcel Identification System (LPIS) and National and Regional Planning Information System (TeIR) – from the aspect

This essay asserts that to effectively degrade and ultimately destroy the Islamic State of Iraq and Syria (ISIS), and to topple the Bashar al-Assad’s regime, the international

This handbook will help iden- tify these opportunities, and presents ideas for potential measures and projects to be developed in the next programming cycle in the field of

The projected gains over the years 2000 to 2040 in life and active life expectancies, and expected years of dependency at age 65for males and females, for alternatives I, II, and

There are infinitely many principles of justice (conclusion). 24 “These, Socrates, said Parmenides, are a few, and only a few of the difficulties in which we are involved if

And the fish species richness, total abundance, total biomass and total abundance and total biomass dominant fish species were significantly changed in seasons in

19% serve a county. Fourteen per cent of the centers provide service for adjoining states in addition to the states in which they are located; usually these adjoining states have

The ergodic distribution (shown in the last row of each table) offers a more radical view since, according to the discrete information, probability mass concentrates increasingly in