• No results found

Implementation Execution at a Coal Mine Underground Development

N/A
N/A
Protected

Academic year: 2021

Share "Implementation Execution at a Coal Mine Underground Development"

Copied!
5
0
0

Loading.... (view fulltext now)

Full text

(1)

Implementation Execution at a Coal Mine

Underground Development

Our client, a Long Wall mining operation in North America, was falling behind in its development due to the underperformance of its Continuous Miner: It was only moving at an average rate of 60% of target, that is, at about 45 feet per shift. The company had hired “consultants” on two separate occasions to help them with the problem to no avail. We convinced them that our approach and methodology could quickly identify what was causing the underperformance, fix the problems and get them back on track. After getting the green light, we sent our team underground to work with the unionized work force and observe the operation.

Our team worked directly with the crews across all three shifts and first, made observations continuously over many days to understand how each crew worked and what issues they encountered during their shift. We also analyzed the historical operational data: We were very interested in learning what caused the delays of the Continuous Miner.

(2)

We then created a mine model, which detailed the full cycle of the Continuous Miner, to help us understand the influence on performance that each step contributed:

(3)

After four weeks, we identified the root causes of the slow movement. Two significant ones were apparent. They were:

The Continuous Miner was stopping every three feet to apply the screen to the ceiling by drilling two holes, then strapping it into place.

The crews spent a lot of time changing the drill bits on the head of the Continuous Miner.

There were other factors which contributed to the loss of advancement feet. We assigned a project to each and put together an implementation plan that included our estimate of how many additional advancement feet each project would produce once implemented. A summary of that plan is shown below and indicates that they have the potential to exceed 80 feet per shift of advancement:

Complete Cycle Definition

Step Process Advance

Distance CM Time Expected Number of Straps 1 Mine 1 184 9.50 62 2 Move from 1 to 2 1.15 3 Mine 2 184 9.50 62 5 Move + Turnout 1.83 8 6 Mine 2 to 1 99.5 5.13 34

7 Move + Cut Corner 0.93 4

8 Move from 1 to 3 1.15

9 Mine 3 184 9.50 62

10 Move + Turnout 1.83 8

11 Mine 3 to 2 99.5 5.13 34

12 Move + Cut Corner 0.93 4

13 Move to 1 1.15

(4)

The implementation plan included project charters for each of the projects that detailed the project and its associated analysis; the approach to implementation; the team and implementation duration; and the measurement to be impacted and by how much.

Next, we implemented the work plan by working directly with the crews to fix the problems. We showed them the data from our observations and discussed the most significant factors in delays. The crews agreed with our analysis and revealed that the delays made their jobs more difficult and were excited about fixing these problems.

B as e li n e , 4 5 .0 In cr e as e t h e d is ta n ce fr o m s tr ap t o s tr ap , 6 3 .7 M o n it o r th e p ro je ct s as re q u e st e d t o im p ro ve th e 1 4 ED 2 5 a va ila b ili ty f ro m 8 3 % t o 9 2 % , 7 5 .6 In cr e as e CM d ri ll p e n e tr at io n r at e , 7 8 .0 R e d u ce t h e B o lt in g cycl e t im e ., 8 0. 1 Su p p lyi n g th e m in e r, 8 2 .1 R e d u ce CM t im e a w ay fr o m fa ce d u ri n g th e id le p e ri o d d u e t o a B e lt M o ve , 8 4 .0 R e d u ce CM t im e a w ay fr o m fa ce d u ri n g th e id le p e ri o d d u e P o w e r M o ve , 8 5 .9 De cr e as e t h e t im e t o m o ve e q u ip m e n t fr o m e n tr y to e n tr y, 8 6 .8 CM b it li fe , 8 7 .6 De cr e as e t h e t im e t o c u t co rn e rs , 8 8 .0 De cr e as e t h e t im e t o c o m p le te a t u rn o u t, 8 8 .3 Qu al it y o f Li fe , 8 8 .3 O p ti m iz at io n o f i d le t im e , 8 8 .3 0 10 20 30 40 50 60 70 80 90 100 Fe e t / Sh if t

Projects & Cumulative Feet / Shift

Projects Steps Chart

(5)

Second, we performed a Six Sigma Design of Experiments (DOE) on the drill bits and learned that their bits were wearing out far more quickly than other specific bits on the market. We chose a new bit, which was about the same cost as the former bit, and the result showed 21 bits were changed over a 10-shift pilot test period. Previously, they averaged 36 bits changes per shift.

Once implemented, these two improvements alone extended the average Continuous Miner movement from about 45 feet per shift to more than 70 feet per shift. Other projects we had identified helped further improvements and sustainability. Now, more than a year later, the crews are performing consistently at a rate of more than 75 feet per shift. This achievement exceeded the planned advancement and ensures the Continuous Miner development work is completed in time to move the Long Wall mining equipment into the area.

References

Related documents

Agglutinate-like particles have been produced in shock-recovery experiments using the Vertical Impact Facility in laboratory conditions from solid targets by repetitive impacts

My main message is twofold: first , as legal educators, all of us can participate in this professional identity social movement if we are willing to approach our work as a

To improve transparency in the seafood supply chain and ensure the successful implementation of eCDT systems, USAID Oceans engages a variety of fisheries stakeholders,

Our study shows that 60.4 % of Dutch university stu- dents were willing to be vaccinated in the hypothetical case of an offer of an MMR booster vaccination to con- trol a

• If the regular show Best of Breed/Variety, Best of Opposite Sex to Best of Breed/Variety, Select Dog & Select Bitch are not eligible, the judge may choose any eligible dog

Cultural adaptation and validating a Japanese version of the readiness for interprofessional learning scale (RIPLS).. Mahler C, Berger S, Pollard K, Krisam J, Karstens S, Szecsenyi

Rosl Fraxner had taken another of her disagreeable little snaps – Krischi Kauffman contemplating important documents – and I placed the image alongside the typed sheets and passed

This could be a play on the verb tsuku which can mean to push or poke something, or it can also mean to fed deep emotion for something (when something is touching to you