DBSA RENEWABLE ENERGY
FINANCING
Presented by Madalo Minofu
Project Preparation Specialist:
DBSA Project Preparation Funds Division
2 June 2014
Development Bank of Southern Africa
DBSA’s Product Offering
2
The following products are typically applied towards energy projects:
Debt
Long-term debt, 15 years ZAR financing
Mezzanine Debt
Subordinated debt to support the LEE/BEE partners
Arranging
Lead Arranger
Underwriting
Underwrite to ensure complete financing package
Other products that could potentially be applied to enhance the projects:
Equity
Direct equity in select projects to further enhance the project
Guarantees
Partial credit enhancement of capital market issues to
increase investor appetite and increase the tenor
Project Prep
Funding
Key Investment Considerations / Critical
Success Factors
Regulatory and Legal
Clarity in the regulatory environment
Transparent procurement system
Government’s role in setting of tariffs
Labour issues
Assignment of contracts
Securities
Termination clauses
Clarity in the
Regulatory
Framework:
Acts, Enabling
Legislation,
Licences and
Conditions
3Key Investment Considerations / Critical
Success Factors
Commercial Considerations
Government support and commitment
Technology
Strong sponsors
Experienced operators
Committed partners
Sponsors and
Operators with
experience and a
proven track
record
4Key Investment Considerations / Critical
Success Factors
Commercial Considerations
Key terms of the PPA/Offtake
Agreements
Viability and robustness of cashflows
Tariff mechanism
Availability of cost effective funding
Tenor considerations
Currency issues
Investment Returns
Sponsors and
Operators with
experience and a
proven track
record
5DBSA CASE STUDY 1 : 75 MW (64MW) LESEDI PV
PROJECT
TOTAL PROJECT COST :
ZAR2 581 million (US$258 million)
DEBT : EQUITY RATIO :
75:25
DBSA FUNDING :
ZAR200M Senior Debt; ZAR148M BEE Loan (Equity Finance)
PROJECT DEVELOPERS :
Kensani Capital, Oakleaf Investments (Pty) Ltd and Solar Reserve
OTHER FUNDERS : Rand Merchant Bank (RMB)
EPC/ O&M CONTRACTORS: ACS Cobra, Gransolar and Kensani (Combined net worth
R89.4 billion)
6
Purpose: Loan
Type:
Tenor: Grace Period: Pricing: Margin
Interest Capital
Construction Senior 16.5 years 2 years 2 years 3 Months Jibar 300-500bps
BEE Equity Financing Junior 13 Years 2 years 2 years 3 Months Jibar 600-900bps
Source of repayment
DBSA CASE STUDY 2 : 75 MW LESEDI PV PROJECT
DBSA CASE STUDY 2 : 75 MW (NET 64MW) LETSATSI
PV PROJECT
TOTAL PROJECT COST :
ZAR2 568 million (US$256.8m)
DEBT : EQUITY RATIO :
75:25
DBSA FUNDING :
ZAR200M Senior Debt; ZAR148M BEE Loan (Equity Finance)
PROJECT DEVELOPERS :
Kensani Capital, Oakleaf Investments (Pty) Ltd and Solar Reserve
OTHER FUNDERS : Rand Merchant Bank (RMB)
EPC/ O&M CONTRACTORS: ACS Cobra, Gransolar and Kensani (Combined net worth R89.4
billion)
The Letsatsi (75 MW) and Lesedi (75 MW) projects, located in the Free State and Northern
cape respectively, boast 150 MW of installed capacity and are capable of powering more than
130 000 South African homes with clean energy.
Both projects have executed 20-year power purchase agreements with Eskom and were
completed in mid-2014 (Bid Window 1 projects)
8
Purpose: Loan
Type:
Tenor: Grace Period: Pricing: Margin
Interest Capital
Construction Senior 16.5 years 2 years 2 years 3 Months Jibar 300-500bps
DBSA CASE STUDY 3 : 72.5 MW
(Net 69MW)
SCATEC
KALKBULT PV PROJECT
TOTAL PROJECT COST :
ZAR2 581 million
DEBT : EQUITY RATIO :
75:25
DBSA FUNDING :
ZAR248M Senior Debt; ZAR105M BEE Loan (Equity Finance)
PROJECT Developers : Scatec, Simacel (Pty), Standard Bank and Old Mutual
OTHER FUNDERS : Standard Bank and Old Mutual
EPC/ O&M CONTRACTORS : Scatec Solar (Norway)
Solar Plant physical completion was reached in September 2013 on budget, 3 months ahead of schedule. The plant earned early operating revenues at 60% of the tariff price during October to December 2013. However, Scheduled Commercial Operation Date (SCOD) of 01 January 2014 was not met due to non-compliance with grid code connection requirements. The plant was operating at a reduced capacity of 63.5MW (net) versus the base case of 69MW (Net) for the 01 January to 10 March 2014 period.
NERSA granted temporary exemption to allow the plant to operate at 69MW until 31 August 2015, whilst the plant implements remedial action. Resolution of SCOD is in progress and is expected to be finalized by 30 April 2015, well before the August 2015 deadline. The project is performing above budget and is expected to reach revised SCOD with no debt cost overruns.
9
Purpose: Loan
Type:
Tenor: Grace Period: Pricing: Margin Potentia l Exposu re Current Exposure (28 Feb 2014) Interest Capital
Construction Senior 16 years 14 months 20 months
6 Months Jibar 300-500bps R248 million
R248 million BEE Equity Financing Junior 12 Years 14 months 20
months
6 Months Jibar 600-900 bps R105 million