S
ANITARY
S
EWER
O
VERFLOW
E
VALUATION
R
EPORT
MAY
2012
– SEPT
2013
Prepared by: James C. Hailey & Company
Draft for Review: November 13, 2013
City of Gallatin, Sumner County, TN Sanitary Sewer Collection Evaluation Report 2013
i
Sanitary Sewer Collection System
Corrective Action Plan/ Engineering Report
Table of Contents
Report Summary…....………..……….…..
1
Sanitary Sewer Overflow Report……….
2
Chronic Overflow Evaluation……….………
5
Woodvale Pump Station……….
5
Stephanie
Street……….……….
5
Number 1 Pump Station ……….
5
Bulls Creek Pump Station...……….
6
Isolated Overflows………..
7
Minor Overflows……….……….
7
City
of
Gallatin,
Sumner
County,
TN
Sanitary
Sewer
Overflow
Evaluation
Report
1
Report
Summary
In
May
2012,
an
Agreed
Order
between
the
Tennessee
Department
of
Environment
and
Conservation
and
The
City
of
Gallatin
became
effective.
As
part
of
the
Agreed
Order
Gallatin
Public
Utilities
(GPU)
agreed
to
submit
a
Sanitary
Sewer
Overflow
Evaluation
Report
annually.
This
report
encompasses
a
summary
of
the
documented
overflows
beginning
at
the
date
of
the
Agreed
Order,
May
2012,
thru
September
2013.
The
accompanying
spreadsheet
documents
each
overflow
that
has
been
recorded
over
the
last
16
months.
The
report
analyzes
the
cause
of
each
overflow
and
identifies
the
measures
needed
to
identify
and/or
correct
the
overflow.
The
Table
Key
is
as
follows:
Basin:
The
City
of
Gallatin
is
divided
into
three
drainage
basins
separated
by
topography
or
system
configuration.
Location:
Identified
as
the
manhole,
pump
station,
address,
etc.
where
the
actual
overflow
event
occurred.
Beginning
Date:
Identifies
on
what
calendar
day
the
overflow
started
End
Date:
Identifies
on
what
calendar
day
the
overflow
ended.
Duration:
Details
the
total
length
of
time
that
the
overflow
occurred.
Overflow
Cause:
Identifies
that
cause
of
the
overflow
event,
i.e.
rainfall,
mechanical
failure,
etc.
Remarks:
Identifies
any
specific
notes
related
to
the
overflow
event.
Rainfall
totals,
specific
system
problems,
actions
taken,
etc.
specific
to
any
given
event.
Long
Term
Capital
Plan:
This
section
identifies
each
overflow
location
and
where
each
stands
in
regards
to
GPU
and
current
and/or
future
capital
improvements.
N/A
–
Isolated
incident
Complete
d
–
A
current
project
has
been
completed
to
rectify
the
overflow
situation
Under
Construction
–
A
current
construction
project
is
underway
to
improve
the
Inflow
and
Infiltration
Current
Five
Year
Plan
–
These
events
have
projects
that
are
currently
in
the
Planning
and
Design
phase.
Under
Review
–
These
events
are
under
review
to
determine
what
if/any
improvements
are
needed
to
correct
the
issues.
BASIN OVERFLOW LOCATION BEG DATE END DATE DURATION OVERFLOW CAUSE REMARKS Long Term Capital Plan
C Hoeganaes Lift Station 9/25/2013 9/25/2013 .50 Hours Mechanical Failure Float Failure N/A
A Across from 900 Aqua Dr 9/9/2013 9/9/2013 4 Hours Mechanical Failure Replace Air Release Valve Completed - ARV was replaced
A Across from 900 Aqua Dr 9/6/2013 9/6/2013 2.25 Hours Mechanical Failure Air Release Valve N/A
A Number One Lift Station 8/12/2013 8/12/2013 4.5 Hours Rainfall 1.3 + Inches Current Five Year Plan - Looking at a capital investment for system Improvements
C Bulls Creek Lift Station 8/12/2013 8/12/2013 5 Hours Rainfall 1.3 + Inches Current Five Year Plan - Looking at a capital investment for upgrades
B Lakeshore Dr Lift Station 8/8/2013 8/9/2013 17.75 Hours Rainfall 4.5 + Inches Under Construction - Current Rehabilitation Project to reduce Inflow
C Bulls Creek Lift Station 8/8/2013 8/8/2013 7 Hours Rainfall 4.5 + Inches Current Five Year Plan - Looking at a capital investment for upgrades
A Number 1 Lift Station 8/8/2013 8/8/2013 14 Hours Rainfall 4.5 + Inches Current Five Year Plan - Looking at a capital investment for system Improvements
C Cairo Rd Lift Station 8/8/2013 8/8/2013 .5 Hours Mechanical Failure Under Review
A Manhole #A17-M1 8/8/2013 8/8/2013 .5 Hours Rainfall 4.5 + Inches N/A - However a Current Rehabilitation Project will also reduce Inflow at this location
C Bulls Creek Lift Station 7/30/2013 7/30/2013 .75 Hours Mechanical Failure Current Five Year Plan - Looking at a capital investment for upgrades
C 1830 Woods Ferry Rd 7/29/2013 7/29/2013 2.5 Hours Damaged Force Main N/A
C Bulls Creek Lift Station 7/29/2013 7/29/2013 5 Hours Damaged Force Main N/A - Not related to flow
A Manhole #A19-C01 7/27/2013 7/27/2013 .75 Hours Blockage N/A
C Baywatch Lift Station 5/14/2013 5/14/2013 4.7 Hours Excess Flow N/A
C Cairo Rd Lift Station 5/9/2013 5/9/2013 .25 Hours Mechanical Failure Under Review
A Manhole #A02-A08 5/6/2013 5/6/2013 .5 Hours Blockage N/A
A Number 1 Lift Station 5/5/2013 5/5/2013 16 Hours Rainfall 3+ Inches Current Five Year Plan - Looking at a capital investment for system Improvements
C Bulls Creek Lift Station 5/4/2013 5/5/2013 8.5 Hours Rainfall Current Five Year Plan - Looking at a capital investment for upgrades
A Manhole #A10A-A13 5/5/2013 5/5/2013 19 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
A Number 1 Lift Station 4/27/2013 4/29/2013 39 Hours Rainfall 5+ Inches Current Five Year Plan - Looking at a capital investment for system Improvements
C Bulls Creek Lift Station 4/27/2013 4/28/2013 28.5 Hours Rainfall 5+ Inches Current Five Year Plan - Looking at a capital investment for upgrades
B Lakeshore Drive Lift Station 4/27/2013 4/29/2013 49.5 Hours Rainfall 5+ Inches Under Construction - Current Rehabilitation Project to reduce Inflow
C Cairo Lift Station 4/27/2013 4/28/2013 2 Hours Rainfall 5+ Inches Under Review
A Manhole #A10A-A13 4/27/2013 0429-13 59.25 Hours Rainfall 5+ Inches Under Construction - Current Rehabilitation Project to reduce Inflow
BASIN OVERFLOW LOCATION BEG DATE END DATE DURATION OVERFLOW CAUSE REMARKS Long Term Capital Plan
A Manhole #A10A-N1 4/27/2013 4/29/2013 42.25 Hours Rainfall 5+ Inches Under Construction - Current Rehabilitation Project to reduce Inflow
A Manhole #A10A-PB1 4/27/2013 4/29/2013 42.25 Hours Rainfall 5+ Inches Under Construction - Current Rehabilitation Project to reduce Inflow
A Manhole #A19-B02 4/27/2013 4/28/2013 28.5 Hours Rainfall 5+ Inches Under Construction - Current Rehabilitation Project to reduce Inflow
A Manhole #A19-B03 4/27/2013 4/29/2013 42 Hours Rainfall 5+ Inches Under Construction - Current Rehabilitation Project to reduce Inflow
A Manhole #TA1 4/27/2013 4/28/2013 23 Hours Rainfall 5+ Inches N/A - However the current Five year plan will make
improvements that will affect this location A Number 1 Pump Station 4/11/2013 4/11/2013 4 Hours Mechanical Failure & Rainfall Current Five Year Plan - Looking at a capital investment for
system Improvements
B Manhole #B2-F03 3/9/2013 3/9/2013 1.75 Hours Blockage N/A
C Manhole #C12-A6 2/6/2013 2/6/2013 1 Hour Blockage N/A
A Number 1 Lift Station 1/30/2013 1/30/2013 4.25 Hours Rainfall Current Five Year Plan - Looking at a capital investment for system Improvements
A Manhole #A10A-PB1 1/30/2013 1/30/2013 0.75 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
A Manhole #A10A-A13 1/30/2013 1/30/2013 12 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
C Woodvale Lift Station 1/30/2013 1/30/2013 16 Hours Rainfall Completed - New station placed into service March of 2013
A Manhole #A10A-A13 1/13/2013 1/17/2013 104 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
C Woodvale Lift Station 1/13/2013 1/17/2013 95.5 Hours Rainfall Replacement Under
Construction Completed - New station placed into service March of 2013
A Number 1 Lift Station 1/13/2013 1/14/2013 30 Hours Rainfall Current Five Year Plan - Looking at a capital investment for
system Improvements
B Lakeshore Dr Lift Station 1/13/2013 1/14/2013 19 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce Inflow
A Manhole #TA-36 1/13/2013 1/14/2013 16 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
A Manhole #A19-B3 1/13/2013 1/14/2013 16 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
B Manhole #B15-A17 1/13/2013 1/14/2013 16 Hours Rainfall N/A
A Manhole #A23-J3 1/13/2013 1/14/2013 12.5 Hours Rainfall N/A
A Manhole #A10-A-PB1 1/13/2013 1/14/2013 22.5 Hours Rainfall Under Construction - Current Rehabilitation Project to reduce
Inflow
B 1059 Browns Ln 1/2/2013 1/2/2013 20 Minutes Mechanical Failure N/A
C Woodvale Lift Station 12/10/2012 12/10/2012 5 Hours Rainfall Completed - New station placed into service March of 2013
B LH Pk @ Buckingham Blvd 9/26/2012 9/27/2012 19 Hours Excavation Damage N/A
BASIN OVERFLOW LOCATION BEG DATE END DATE DURATION OVERFLOW CAUSE REMARKS Long Term Capital Plan
C Woodvale Lift Station 9/8/2012 9/8/2012 5 Hours Rainfall Completed - New station placed into service March of 2013
C Woodvale Lift Station 8/17/2012 8/17/2012 9.5 Hours Rainfall Completed - New station placed into service March of 2013
C Woodvale Lift Station 8/9/2012 8/9/2012 3.5 Hours Rainfall Completed - New station placed into service March of 2013
C Woodvale Lift Station 7/20/2012 7/20/2012 12 Hours Rainfall Completed - New station placed into service March of 2013
C Cairo Road Lift Station 7/19/2012 7/20/2012 3.5 Hours CEMC Power Failure Current Five Year Plan - Looking at a capital investment for a backup Generator
C Manhole C15-A02/
Steam Plant Lift Station 7/11/2012 7/11/2012 2 Hours Vandalization Copper Wire stolen N/A
C Woodvale Lift Station 7/6/2013 7/6/2013 3 Hours Power Outage Completed - New station placed into service March of 2013
A Number 1 Lift Station 5/13/2012 5/14/2012 26 Hours Rainfall Event Current Five Year Plan - Looking at a capital investment for system Improvements
C Woodvale Lift Station 5/13/2012 5/15/2012 40 Hours Rainfall Event Completed - New station placed into service March of 2013
B Lake Shore Lift Station 5/13/2012 5/14712 9 Hours Rainfall Event Under Construction - Current Rehabilitation Project to reduce Inflow