• No results found

Project Management Office

N/A
N/A
Protected

Academic year: 2021

Share "Project Management Office"

Copied!
92
0
0

Loading.... (view fulltext now)

Full text

(1)

Continuing to safely, efficiently and effectively execute projects

Arch Staffing and Consulting Change Order: $3.75M

November 2020

Powering our way of life.

(2)

Goal

Find the

Balance of

Capacity and

Capability

Project demand peaks

Overall project management

Specific project needs

Capability

Find the correct resource balance by

determining organizational capacity needs

while increasing EPMO capabilities.

(3)

Tools to

Achieve

Goal

Find the

Balance of

Capacity and

Capability

Organization resource loading

Contracted resources

Capacity

Leverage existing EPMO Team members

Standardized project management

framework (v1 EOY)

Contracted resources

(4)

Current

Contracted

Personnel

Named

Resources

Rachelle McGillivray

Power Engineers

ESRI/GIS Project

(until E0P)

David Poulin

TMG Consulting

CCS Project

Dec 2020

(until EoP)

Brent Gregory

Arch Staffing and

Consulting

Project Management

Framework and misc.

project support

Dec 2022 (+)

Cliff Woods

Arch Staffing and

Consulting

Ephrata and Moses

Lake Service Centers

Dec 2022

(until EoP)

Ben Floyd

White Bluffs

Consulting

Facilities Master Plan

Dec 2021

(until EoP)

Thomas Karcz

Arch Staffing and

Consulting

OCM Program

Dec 2022 (+)

Ann Shiveley

VOLT

OCM project support

May 2021 (+)

(5)

Contracted

Personnel

To Be Named

Resources

Name

Consulting

Firm

Project

Estimated

Duration

EPMO 1

TBD

Project Control Services

Dec 2022 (+)

EPMO PD 1

TBD

OSS/BSS (Fiber tech) project

TBD (EoP)

EPMO PD 2

TBD

ECBID project

TBD (EoP)

EPMO PD 3

TBD

Invenergy project

TBD (EoP)

EPMO PD 4

TBD

Project Development –

NLL/Interconnect

Dec 2022 (+)

EPMO ET

TBD

Remaining HCMS modules

Dec 2021

EPMO ET

TBD

ET program support

July 2021 (+)

EPMO PP 1

TBD

PM for specific project being

determined

TBD

EPMO PP 2

TBD

PM for specific project being

determined

TBD

EPMO PP 3

TBD

Project Coordinator for specific

project being determined

TBD

EPMO PP 4

TBD

Project Coordinator for specific

project being determined

TBD

EPMO PP 4

TBD

Project Coordinator for specific

project being determined

TBD

Additional contracted needs to be determined on a project-by-project basis.

(6)

Contracted

Personnel

Potential PP

Projects for

Contracted

Resources

WAN/PR Station Service

2020

CO2 Replacement

2021

Maintenance Equipment Storage at WMC

2021

Power Production Tag in/Tag out System

2021

PRP Control Room Renovations

2021

WAN Bridge Cranes

2021

WAN Fish Ladder

2022

PR Fish Ladder Rehabilitation

2022

PR Hatchery Siphon Intake Renovation

2022

PR Warehouse

In progress

PR Right Embankment Improvement Project

In progress

PR Turbine Generator Rehab Project

In progress

(7)

Contracted

Personnel

Approach to

Acquire

Current: $2,250,000

Proposed: $6,000,000

(Increase by $3,750,000)

Arch

Current NTE: $2,350,000

VOLT

$600,000 for EPMO

AvanTech

To be identified on a project by project basis

Other

Find the right resource with the desired

capabilities for the project

(8)
(9)

Safety Report

November 2020

11

(10)

DAT E

INJURY

DESCRIPTION

CAUSES

PREVENTION

10/1/2020

Abrasion/Contusion

While working in W10 Turbine pit removing upper wicket

gate canisters an employee mis-stepped and slipped on the

surface of a wicket gate link arm resulting in a large

contusion and abrasion on their right thigh.

Poor walking

working surface

Complete an ongoing project to

install grating to walk on.

10/8/2020

Insect Sting

An employee was stung by a Yellow Jacket while setting up

COVID-19 testing.

Environmental

???

10/23/2020

Strain/cold weather

Employee didn't notice injury until the next day. Right wrist

was tender and had a bump on top of forearm, probably

tendonitis caused by overexertion and cold weather.

Overexertion

Stretch and flex prior to

exertion.

(11)

Monthly and Year to Date

2020

Month

YTD

Total Incidents Reported

3

26

Recordable Case(s)

1

4

Restricted Duty Case(s)

0

3

(12)

Date

Vehicle

Driver’s Account:

Prevention

10/15/2020

#337

Vehicle 337 was traveling north to Wanapum dam on Highway 243 near the

RR bridge. Suddenly the driver side window exploded as they passed an

apple truck traveling the opposite direction. The crew did not observe any

objects strike the vehicle's driver side window. No employees were injured.

???

10/21/2020

#504

​​While backing #504 out of Bay #1 the struck #494 in the front bumper with

the trailer hitch. A 360 walk-around was conducted with the bay door closed

not knowing that truck #494 had parked outside the door. The Bay door was

opened from inside the vehicle and could not see #494 parked behind using

the side mirrors. Vehicle speed was about 1 mile per hour.

Situational Awareness

10/23/2020

PT55

During operation of PT55 (District boat) in the Hanford Reach PT55 came

into contact with another boat during a fish transfer. The incident occurred

while pulling away (under low power) and the rear corner of PT55 struck the

side of an angler's boat causing minor damage (small dent and damage to a

decal). No injuries occurred and PT55 was not damaged.

(13)

Close Calls

Date

Location

Description

10/1/2020

Wanapum

Dam (W4)

It was identified that an isolation valve for the Brake Air Supply had been left CLOSED after the

Clearance Tag had been removed. This gave a false indication at the Governor Cabinet that the

Brakes were APPLIED when in fact only the piping to the brake isolation valve had been energized.

The valve did not have an identification label.

10/26/2020

Wanapum

Dam (W4)

The control room received a Field Ground Relay Indication for W04. Upon investigation, it was

discovered that a large cold metal chisel had been left inside the generator following installation of

the fairing covers during assembly for the commissioning overspeed inspection. The chisel appears

to have been making contact on a field pole connection causing indications of a ground and could

have caused catastrophic damage to the W04 generator.

10/27/2020

Quincy Chute

During winter clearance preparations, a water gate was inadvertently left open, and a tag incorrectly

placed. The error was not noticed by the fist proposed clearance holder but found by the secondary

check of the second clearance holder. The gate was closed, and the clearance was corrected.

(14)

Date

Location

Description

10/2/2020

Blue Lake

PUD contractor was excavating on private property and hit a unlocated private power conduit. There was no power outage, and

the conduit was scuffed. A third party locate company was called to locate the property prior to excavation.

10/14/2020

Quincy Area

A PUD Contractor while excavating discovered what appeared to be some type of explosive device. The Authorities were

notified, and the area evacuated. Once the authorities were on site the Washington State Patrol Explosive Technicians were

called in to evaluate the situation. Three used/spent blasting caps were identified as possibly being left from a previous

excavation. No injuries were reported, and the site was evaluated for any other materials that may have been left. None were

found.

10/20/2020

George Area

A PUD contractor working at the intersection of Baseline and Road T located in in George experienced a close call when a

Semi-Truck traveling along Baseline began approaching the work zone. The flagger recognized the truck was not slowing down

and alerted the crew to get off the road. The truck lost it’s brakes and drove by the flaggers stop paddle and into the work zone

without slowing down. The truck was able to stop after going through both flaggers and the work zone and then pulled to the

side of the road.

10/21/2020

Ephrata Area

A PUD Contractor crew was trenching from the pole to a residences home in Ephrata with a mini excavator when they damaged

a secondary neutral line. The incident occurred approximately 3 ft off locate. The damage of the secondary neutral line was a

small portion of the coating being peeled back. PUD was notified, and fixed the damage.

(15)

Contractor Close Calls & Incidents

Date

Location

Description

10/22/2020

Mountain View

Substation

A PUD Contractor was digging along the side of a foundation and at a depth of approximately 18” and hit the 1” fiber

conduit breaking the fiber line inside and immediately ceased excavation. The fiber line had previously been exposed

and rerouted to facilitate foundation installation. The crew momentarily lost focus regarding current location of the

fiber duct. The fiber line had been previously located and marked by the District. The District was immediately notified

by the contractor and the damaged fiber was repaired expediently.

10/27/2020

HWY 283

A PUD Contractor was returning from work at Cave B to the Ephrata yard on Highway 283. As they approached Kriete

road the driver dozed off and temporarily left the roadway creating a cloud of dust. The pickup was pulling a trailer

with a spool of fiber behind them. The employee called the Supervisor immediately to report the incident. There were

no injuries or visible damage to the equipment.

(16)

Level O - Other – Close Call

Level 1 – Serious Close Call

Level 2 – First Aid Case(s)

Level 3 – Recordable Injury Case(s)

Level 4 –Restricted Duty Case(s)

Level 5 – Lost Work Day Case(s)

Level 6 – Fatality or Hospitalization

19

0

2

0

0

0

0

2020

11

Recordable

Cases TTL.

2019

67

7

11

0

8

5

7

20

Recordable

Cases TTL.

Level O - Other – Close Call

Level 1 – Serious Close Call

Level 2 – First Aid Case(s)

Level 3 – Recordable Injury Case(s)

Level 4 –Restricted Duty Case(s)

Level 5 – Lost Work Day Case(s)

Level 6 – Fatality or Hospitalization

74

12

4

4

3

4

0

(17)
(18)
(19)

Other SST members include:

Bryan Mickle, Chris Heimbigner, Craig Bressan, Darlene Brooks, Gavin Clark, Jeff Grizzel, Randi Hovland, Rich

Wallen, Ryan Roeder, Val Hernandez, and Wade Johns

(20)

contaminated with COVID-19.

2. Safety

notifies Security/DSOC and Public Affairs

hotline that a building must be shut down for

cleaning.

3. Security

will hang signs and disable access to the

building.

4. Public Affairs Communications

is contacted by

Safety @ (509) 754-5035 and requests notification of

building closure to District employees.

5. Safety

contacts Mike Harr or Lori Thorpe requesting

the building to be sanitized.

4. Contractor

sanitizes affected building and notifies

Mike Harr or Lori Thorpe when complete.

5. Internal Services

notifies Safety and Public Affairs

Communications that the building has been sanitized

and arranges for reopening and communication to

District employees.

(21)

Safety Action Item Critical Success Factors

Incident Reporting (Date of Entry into System vs Data of Distribution

Systemwide)

• Number of Close Calls in

October

= 11

• Number of Close Calls sent Next day after being entered into the system = 3

Number of Open Action Items over 60 days old

As of

September

2020

As of

October

2020

Year 2017 = 9

Year 2017 = 7 (-2)

Year 2018 = 11

Year 2018 = 11

Year 2019 = 28

Year 2019 = 26 (-2)

Year 2020 = 12

Year 2020 = 11 (-1)

Month Total =

60

Month Total =

55

(22)

Incident Reporting for October 2020

(Date of Incident vs. Date of Entry into System)

• Total Number of Injuries Which Date of

Incident and Date Entered into System

Match = 2

Mobile

• Total Number of Mobile Incidents = 3

• Total Number of Mobile Incidents that Date

of Incident and Date Entered into system

match = 1

(23)

Powering our way of life.

(24)

This Photoby Unknown Author is licensed under CC BY-ND

Grant PUD Health Screening Policy v.4

This revised policy establishes new symptom reporting guidelines and testing requirements for the

purpose of mitigating the spread of the COVID-19 virus among Grant PUD employees and

contractors.

Why is it Important?

• We care about the safety of our employees and strive to ensure we have the measures in place to

effectively minimize transmission of the disease.

• An effective symptom reporting, testing, and quarantine program helps us identify employees who

are positive early in the disease progression.

• Our COVID-19 safety program allows us to prevent more infections and slow the rate of

transmission within the PUD.

• Employee adherence to these requirements aligns with our core values and Grant PUD’s ability to

provide critical services to our customers.

(25)

This Photoby Unknown Author is licensed under CC BY-ND

HR-BC-POL-315 – GRANT PUD COVID-19 HEALTH SCREENING

Symptom reporting

Report any of the following symptoms of COVID-19 per new CDC guidelines:

Fever or chills

Cough that cannot be attributed to another health condition

Shortness of breath or difficulty breathing

(not attributed to another health condition)

Fatigue

Muscle or body aches

Headache

New loss of taste or smell

Sore throat

Congestion or runny nose

Nausea or vomiting

(26)

This Photoby Unknown Author is licensed under CC BY-ND

Health Screening Reporting Requirement

Any Grant PUD employee or contractor

covered under this policy must immediately notify their

supervisor or District Representative if they have:

1) tested positive for the COVID-19 virus, or

2) are experiencing COVID-related symptoms, or

3) have been in Close Contact

(

within 6 feet of an infected or

symptomatic person for a total of 15 minutes within a 24-hour

period)

with someone who has tested positive for

COVID-19 or who has COVID-related symptoms.

Supervisor or District Reps must contact the

IMT COVID

Reporting Group at 509-754-1805 or x4111.

Please

call the

HOTLINE

, not an individual Safety Coordinator!

Direction will then be provided for any necessary

subsequent actions.

This requirement applies to all Grant PUD employees

and contractors, including those working from home.

Self-Monitoring When Arriving at

Work & While at Work

Take your temperature and check your symptoms prior

to leaving for work.

If you do not have access to a thermometer at home,

you must take your temperature at the nearest Grant

PUD facility sign-in location. Those who commute more

than 1 hour from their work location must retake their

temperature when they arrive at a Grant PUD facility.

While at work, Grant PUD employees and contractors

must monitor themselves for any changes in their

physical condition that might suggest the onset of

COVID-19.

(27)

HR-BC-POL-315 – GRANT PUD COVID-19 HEALTH SCREENING

Mandatory Testing Requirement

Employee health and safety is a core value. Testing helps us keep us safe!

Employees who fit one of the following criteria will be required to provide proof of COVID-19 testing:

• Employees who are experiencing COVID-related symptoms

• Employees who have experienced a Close Contact

(within 6 feet for a total of 15 minutes or more within a

24-hour period)

with someone who has related symptoms or with a confirmed case of

COVID-19.

• Employees who have been asked or referred to get tested by their healthcare provider or their local

or state health department.

Other considerations:

Persons living in the same household as a Grant PUD employee and who are experiencing COVID-related symptoms but who have

not been tested are presumed to be COVID-19 positive.

Grant PUD cannot and WILL not require a non-employee to be tested for COVID-19.

Grant PUD’s authority to require testing for employees who are symptomatic or who have experienced a close contact is based on

guidance provided by the federal Equal Employment Opportunity Commission (EEOC).

(28)

Disciplinary Action – Employees

• Employees who fail to adhere to these requirements will be subject to disciplinary action. Any full-time

regular employee who meets one of the testing criteria above but fails to provide proof of testing will

receive a written warning and will be required to use Personal Leave for the balance of their

quarantine period not covered under the Families First Coronavirus Response Act.

• Any full-time regular employee who violates the mandatory testing provisions a second time will be

terminated.

• Any temporary employee who meets one of the testing criteria but fails to provide proof of testing will

be terminated.

Notes:

Discipline will be carried out in accordance with Grant PUD’s policies and procedures.

(29)

HR-BC-POL-315 – GRANT PUD COVID-19 HEALTH SCREENING

Use of Paid Leave

Grant PUD will authorize paid leave under the Families First Coronavirus Response Act Policy for employees

under specific circumstances. Paid leave will be authorized for an employee who:

Has tested positive for COVID-19;

Has experienced COVID-related Symptoms (see Symptoms list above), has undergone COVID-19 testing,

and has provided proof of testing; or

Has experienced a Close Contact with someone who has COVID-related symptoms or with a confirmed case

of COVID-19, has undergone testing and has provided proof of testing.

(30)

Disciplinary Action - Supervisors

Supervisors

- Supervisors who has/had

knowledge

of and fails to report

an employee who has experienced a close contact or who is showing

COVID-related symptoms will also be subject to disciplinary action.

Any supervisor who fails to report will receive a written warning and will be

placed on Leave Without Pay for 80 hours. Any supervisor who fails to

report a second time will be terminated.

(31)

Powering our way of life.

(32)

Powering our way of life.

Commission Meeting

11/24/2020

Proposed 3-Year

20% Slice Sale

(33)

Items for Discussion

Rich Flanigan, Sr. Manger of Wholesale Marketing and Supply, Grant PUD

Tie to Strategic Plan

Proposed Slice Details

Indicative RFP Process

Non-carbon Language

(34)

Counterparty

Size

2021

2022

2023

2024

Avangrid Slice

10%

Morgan Stanley WSS

33%

Proposed Shell Slice

20%

2025

YEAR

(35)

Slice Attributes tie to Strategic Plan

Consistent with Strategic Plan Objectives

Maintain a Strong Financial Position

Revenue certainty (eliminates water risk)

Strong premium for ancillary services

Favored by bond rating agencies

Provide Long Term Low Rates

Insulates Grant from hydro variability (operational risk)

Maximizes value of Grant Hydro capacity, flexibility, energy, and

(36)

10% 3-year slice of Priest Rapids Project Output

(PRPO) to Shell Energy North America

Starting date of 01/01/2021

Ending date of 12/31/2023

Current 53.31% PRPO Wholesale Service Slice with

(37)

Deal Structure

Very similar to the terms of the current contract

Shell is entitled to the following attributes

Energy

Capacity

Pondage

Ancillary services

Green attributes

(language included to protect under new carbon legislation)

Dynamic signal (allows for in-hour energy changes)

(38)

The indicative RFP process was broken down into three (3) phases;

1.Phase I – Initial interest and bidding for a 20%, 3-year slice of PRP

2.Phase II – Indicative bidding round from interested bidders from Phase I

3.Phase III – Bilateral negotiations with top bidder from Phase II

The indicative RFP process was structured as a 20% slice of PRP with a fixed

volume of energy being returned (“buy-back”) to the District

Fixed energy buy-back shaped to Grant’s load

Energy “buy-back” was used to isolate the premium for the additional

attributes from PRP (green attributes, ancillary services, regulation, etc.)

and help staff make an apples-to-apples comparison between each bid

(39)

Contract Overview

8

Contract work with Winning Bidder

Used the existing Avangrid 10%, 3-year contract as the initial template

Review from internal council for legal compliance

Large internal stakeholder reviews

Finance

Accounting

Dispatch

Control Systems Engineering

Financial Planning and Analysis

Compliance

(40)

Part of final bilateral negotiations included new

contract language for Non-carbon Energy

Language is structured to provide Grant protection from

any new legislative carbon fee or tax

Option for Grant to receive non-carbon energy if Grant is

(41)
(42)

1

FROM:

John Mertlich, Sr. Mgr Financial Planning & Analysis

Jeremy Nolan, Lead Financial Analyst

SUBJECT:

3

rd

Quarter 2020 Financial Forecast Update

Purpose:

Provide Highlights of the Q3 Financial Forecast

Metrics:

The District has in place interim and long-term annual target milestones for five financial metrics

through 2025 (Exhibit C).

Over the 5-year forecast (thru 2025) the current metrics indicate (Exhibits A & B):

o

The following long-term targets are met through 2025 for:

Liquid Cash >$105 Million,

Debt to Net Plant < 60%, and

Debt Service Coverage > 1.80x

o

Return on Net Assets does not meet the interim or long-term targets thru 2025.

o

Retail Operating Ratio (ROR) meets the interim target in 2020, but does not meet the

interim or long-term targets from 2021 through 2025.

Comparisons between the 2020 Budget and Q3 2020 Forecast can be found in Exhibit D.

Debt to Net Plant Illustrative Example – Historic Cost vs Fair Market Value comparison found in

Exhibit H.

Notes of Interest:

Key forecast updates:

o

Interest rates updated for current market impact on Interest Income.

o

2020 Labor, O&M, and Capital updated for Q3 actual data and balance of year

projection. Forecast for 2021 and beyond is the same as 2021 Budget.

o

Cash Optimization was executed in Jan. 2020 and additional debt refunding in March

2020.

Load Forecast and Retail Revenue have been updated for Q3 actual data. Forecast for the

balance of 2020 and future years is the same as 2021 Budget.

o

Retail Revenue rate adjustment assumption is: 0.1% annually beginning 2021.

o

EUDL CRAC Revenue moved to begin after 2030 instead of 2021. The table below

shows the revenue that was in the 2020 Budget and 2020 Q1 forecast that was

removed for the Q2 Financial Forecast.

(43)

2

Scenarios:

All scenarios start with the Base assumptions

Five Scenarios were run for the 2020 Q3 Forecast:

o

Wholesale Price Increase (P85)

o

Wholesale Price Decrease (P15)

o

Low Load Growth at ½ Base

o

Low Load Growth at ½ Base and Wholesale Price Decrease (P15)

o

Low Water (P15)

Scenarios and Debt Service Coverage (Exhibit E)

o

Debt Service Coverage (DSC) is adversely affected in all scenarios through 2025 except

higher wholesale energy prices and some years with low load growth at ½ base.

o

Low Load growth scenario when combined with low wholesale energy prices and the

Low Water scenario create the two largest negative impact to DSC, indicating that

growing profitable loads and reducing Water risk are key controllable business drivers.

Scenarios and Debt to Net Plant (Exhibit F)

o

Debt to Net Plant is adversely affected in all scenarios through 2025, except higher

wholesale energy prices and low load growth at ½ base.

Scenarios and Return on Net Assets (Exhibit G)

o

Return on Net Assets is negatively affected by all scenarios through 2025, except higher

wholesale energy prices and low load growth at ½ base.

o

Return on Net Assets fails to meet the interim or long-term target though 2025.

Conclusions and Path Forward:

Growing profitable loads is a key controllable business success driver.

Lower wholesale prices combined with low load growth are a threat in the 2020-2025 period.

Recommendation:

(44)
(45)

4

(46)
(47)

6

(48)
(49)

8

(50)
(51)

10

(52)
(53)

M E M O R A N D U M

November 6, 2020

TO:

Kevin Nordt, General Manager/CEO

VIA:

Jeff Bishop, Chief Financial Officer

FROM:

Michael Facey, Senior Manager Accounting

SUBJECT:

Unaudited Financial Statements Third Quarter 2020

Financial Highlights:

All comparisons unless otherwise stated are year to date (January through

September) of 2020 versus 2019.

Statement of Revenues, Expenses and changes in net position:

o

Total operating revenues of $244.5M were $5.2M (2%) higher than the same period in

the prior year driven by a $9M (18%) increase in Wholesale revenues and a $2M (10%)

increase in Irrigation; partially offset by a $1.8M (8.4%) decrease in Sales to power

purchasers at cost, a $4.6M (3.4%) decrease in all other retail revenues. Overall retail

load was down 5.3% from budget, primarily due to Commercial, Industrial, Large

Industrial and Evolving Industry loads. Commercial experienced milder weather

conditions and some impacts from COVID-19 unemployment rates, which were 3%

higher than the prior year. Remaining load deviations were primarily due to some

individual large customers experiencing substantial reduced loads and others moving to

different rate schedules. Residential revenue decreased from the prior year by $1.4M

(4%) due to milder winter weather (average 26% degrees warmer than the prior winter).

The increase in irrigation is due to changes in weather from the prior year, noting a 78%

reduction in precipitation. The overall decrease in retail revenues drove the increase in

wholesale revenues because the District receives market prices when actual retail load

is lower than forecasted through the SENA & Morgan Stanley agreements.

o

Total operating expenses of $162M were $7.1M (4.6%) higher than the same period in

the prior year. The overall increase in operating expenses is largely due to the new CBA

Agreement, which increased wages an average of 5% in 2020. Depreciation expense

increased $2M or 3.6% largely attributed to a $77M or 3.6% increase in net utility plant.

Within operating expenses there are significant fluctuations within expense categories

as follows: Distribution expense ($6.5M or 49% increase), Generation expense ($1.5M or

6% increase), Administrative and general expense ($2.4M or 9% increase); partially

offset by License compliance expense ($2M or 17.5% decrease) and Transmission

expense ($2.8M or 61% decrease). These fluctuations are expected as part of the data

optimization project, which reallocated labor across the various FERC expense accounts

to improve reporting. The fluctuations do not have a significant impact to the overall

total operating expenses. We expect license and compliance expense to level out to

prior year amounts by year-end. The 2020 budget expected an increase in operating

expenses of approximately 3%. Use of Paid Administrative Leave and other delays

experienced by capital projects have caused $4M in labor expenses that were originally

expected to be capital. To date we have had $12.8M of labor costs charged to capital

projects; which is 23% less than the $16.8M budgeted through September.

(54)

the prior year. This decrease is largely due to the changes in operating revenues and

expenses described above, $3.1M of insurance proceeds related to the Central Ephrata

Substation claim, a $9.2M (73%) decrease in Contributions in aid of construction and the

impacts of the bond transactions that occurred in January, March, and September of

2020. The bond transactions have driven a $11.8M (26.5%) decrease in year to date

interest expense, but also had debt issuance costs of $2M to execute the transactions

and $3M in losses associated with the defeasance of $81.8M of outstanding bonds.

Statement of net position:

o

Total cash and investments of $446.7M were $96.4M (17.8%) less than the same period

in the prior year due to the planned use of funds for the defeasance of bonds and to

adjust to the new Electric System liquidity target of $105M. There was a corresponding

decrease in outstanding debt of $88.2M (6.8%).

o

Utility plant, net increased $74M or 3.5%.

o

Customer Deposits of $5.4M were $9.4M (63.7%) less than the same period in the prior

year due to two large refunds totaling $9.7M to an industrial and wholesale customer.

(55)

PUBLIC UTILITY DISTRICT NO. 2 OF GRANT COUNTY UNAUDITED

STATEMENT OF NET POSITION September 30, 2020 AND 2019 2020 2019 Difference CURRENT ASSETS Cash 1,547,058 4,959 2,828,868 Investments 76,037,008 97,849,954 (21,812,946) Restricted funds Cash 155,730 663,216 (1,794,254) Investments 82,592,778 128,379,118 (45,786,340) Customer accounts receivable, net 34,874,284 29,772,177 5,102,107 Materials and supplies 18,747,720 17,806,789 940,931 Other current assets 189,378 166,554 22,823 Total current assets 214,143,956 274,642,767 (60,498,811) NONCURRENT ASSETS Investments 10,641,710 3,078,831 7,562,879 Restricted funds Cash 205,617 1,894,808 (1,689,191) Investments 275,515,471 311,241,087 (35,725,615) Conservation loans 334,102 389,179 (55,077) Demand-side management 60,071 261,829 (201,758) Preliminary expenses 3,979,265 4,785,388 (806,123) Total other noncurrent assets 290,736,237 321,651,121 (30,914,885) Utility plant, net 2,192,111,005 2,114,960,971 77,150,034 Total noncurrent assets 2,482,847,241 2,436,612,092 46,235,150 DEFERRED OUTFLOWS

Net pension, change in proportion 6,409,454 5,753,562 655,892 Other Post Employment Benefits 2,290,950 2,290,950 Unamortized refunding loss 34,813,396 3,718,138 31,095,258 Total deferred outflows 43,513,800 9,471,700 34,042,100 TOTAL ASSETS AND DEFERRED OUTLFOWS OF RESOURCES 2,740,504,998 2,720,726,559 19,778,439

(56)

Accounts payable

Trade 15,133,108 10,174,119 4,958,988 Wages payable 11,813,110 7,503,880 4,309,229 Due to Power Purchasers 1,581,660 2,622,184 (1,040,524) Accrued taxes 6,162,564 5,680,081 482,483 Customer deposits 5,339,908 14,729,397 (9,389,489) Accrued bond interest 11,106,088 14,451,589 (3,345,501) Unearned revenue 9,173,155 210,181 8,962,974 Habitat liability 17,791,845 17,050,503 741,342 Other current liabilities 39,768 39,768 Current portion of licensing obligations 2,343,889 2,283,494 60,395 Current portion of long-term debt 29,295,000 30,580,000 (1,285,000) Total current liabilities 109,780,093 105,325,196 4,454,897 NONCURRENT LIABILITIES

Revenue bonds, less current portion 1,171,430,000 1,238,815,000 (67,385,000) Unamortized (discount) premium, net 13,813,141 33,373,781 (19,560,640) Licensing obligations, less current portion 70,704,367 46,307,467 24,396,900 Pension obligations 24,837,391 32,686,126 (7,848,735) Accrued other postemployment benefits 9,705,904 6,977,140 2,728,764 Long-term unearned revenue 8,507,207 2,076,906 6,430,301 Total noncurrent liabilities 1,298,998,009 1,360,236,420 (61,238,410) DEFERRED INFLOWS

Net pension, deferred inflow 14,701,254 13,692,570 1,008,685 Total deferred inflows 14,701,254 13,692,570 1,008,685 Total liabilities and deferred inflows of resources 1,423,479,357 1,479,254,186 (55,774,829) NET POSITION

Invested in capital assets, net of related debt 984,733,531 860,759,528 123,974,003 Restricted 285,951,546 321,101,100 (35,149,554) Unrestricted 46,340,564 59,611,745 (13,271,181) Total net position 1,317,025,641 1,241,472,373 75,553,268 TOTAL LIABILITIES, DEFERRED INFLOWS OF RESOURCES AND NET

(57)

PUBLIC UTILITY DISTRICT NO. 2 OF GRANT COUNTY UNAUDITED

STATEMENT OF REVENUES AND EXPENSES AND CHANGES IN NET POSITION For the Nine Months Ending September 30, 2020 and 2019

2020 2019 Difference OPERATING REVENUES

Sales to power purchasers at cost 19,344,375 21,126,807 (1,782,432) Retail energy sales

Residential 33,212,991 34,646,668 (1,433,677) Irrigation 22,638,448 20,588,307 2,050,140 Commercial and industrial 98,353,039 100,677,637 (2,324,598) Governmental and others 1,024,317 1,914,661 (890,344) Wholesale revenues, net 61,044,770 51,704,041 9,340,729 Fiber optic network sales 7,720,641 6,928,162 792,480 Other 1,177,956 1,684,963 (507,007) Total operating revenues 244,516,537 239,271,245 5,245,292 OPERATING EXPENSES

Generation 26,073,760 24,595,276 1,478,484 Transmission 1,782,419 4,611,757 (2,829,339) Distribution 20,060,510 13,505,225 6,555,284 Customer and information services 2,799,701 3,096,084 (296,383) Fiber optic network operations 1,809,693 1,895,328 (85,635) Administrative and general 29,552,605 27,087,949 2,464,656 License compliance and related agreements 9,586,727 11,621,773 (2,035,046) Depreciation and amortization 57,956,876 55,934,461 2,022,415 Taxes 12,834,759 13,030,354 (195,595) Total operating expenses 162,457,050 155,378,208 7,078,841 NET OPERATING INCOME 82,059,487 83,893,037 (1,833,549) OTHER REVENUES (EXPENSES)

Interest and other income 17,553,723 19,387,919 (1,834,196) Interest on revenue bonds and other, net of capitalized interest (32,745,275) (44,560,480) 11,815,205 Federal rebates on revenue bonds 7,903,261 7,913,646 (10,384) Amortization of debt discount/premium (4,181,218) 2,638,087 (6,819,305) Cost of debt issuance (1,995,613) (141,109) (1,854,503) Total other revenue (expenses) (13,465,121) (14,761,938) 1,296,817 CONTRIBUTIONS IN AID OF CONSTRUCTION 3,374,176 12,608,023 (9,233,846) CHANGE IN NET POSITION 71,968,542 81,739,121 (9,770,579) NET POSITION

Beginning of year 1,245,057,099 1,159,733,252 85,323,847 End of year 1,317,025,641 1,241,472,373 75,553,269

(58)

Powering our way of life.

(59)

2

P

O

R

T

F

O

L

I

O

Cash & Investments

Key Cash Flow Dates:

Q1 Debt financings- release of

cash for defeasance/escrow

Jan 2

nd

2020 bi-annual debt

service payment: $59.2M

July 1

st

2020 bi-annual debt

service payment: $20.7M

(interest only payments)

•Upcoming Jan 2nd bi-annual

debt service payment: $51.7M

CREB sinking funds are held

and increased to meet the

required principal payments in

2027, 2032, 2040

Notes:

Staff is evaluating the Insurance

Reserve fund and is planning to

bring forward a resolution for

Commission review to update

Public Utility District No. 2 of Grant County

Quarterly Treasurer's Report

Historical Cash and Investments Summary | Liquidity and Restricted

Market Value per Financial Statements in thousands $000

(1) Electric System R&C Fund liquidity target = $100M + interest earnings

(2) Electric System Revenue Fund minimul balance = $5M. Excess funds above liquidity target utilized for annual planning of equity financing of PRP capital (Junior Lien Bonds, see Note 4). (3) Other funds used in Days Cash On Hand metric include PRP Revenue, PRP Supplemental R&C, Service System, and Customer Deposit Fund

(4) Construction funds comprised of internally pledged funds for capital and issued bonds

(5) CREB sinking fund payments required by bond covenants to pay bullet maturities in years 2027 ($90M), 2032 ($42.4 M), and 2040 ($90M). Monthly deposits to sinking fund made, recalibrated every 6 months.

As of 09/30/2020

Cash & Investments 9/30/2018 12/31/2018 3/31/2019 6/30/2019 9/30/2019 12/31/2019 3/31/2020 6/30/2020 9/30/2020 Liquidity-ES R&C Fund (1) $ 122,318.8 $ 124,201.3 $ 126,043.9 $ 127,956.0 $ 129,622.4 $ 129,841.3 $ 106,096.3 $ 104,927.5 $ 106,039.8

Liquidity-ES Revenue Fund (2) (4) 126,127.2 133,651.3 152,637.6 46,539.4 58,689.4 72,734.1 40,693.8 47,061.4 58,362.8

Other DCOH Funds (3) 33,671.9 35,469.5 45,822.5 57,943.7 54,459.9 46,881.0 49,735.0 51,260.6 43,288.7

Liquidity and Other DCOH Funds $ 282,117.9 $ 293,322.1 $ 324,503.9 $ 232,439.1 $ 242,771.7 $ 249,456.4 $ 196,525.1 $ 203,249.5 $ 207,691.4

Restricted-Construction Funds (4) 51,896.7 27,422.9 11,607.7 107,080.3 90,957.5 74,368.7 54,421.5 42,973.0 31,495.0

Restricted-DS Reserve Funds 54,827.9 55,636.0 56,618.9 57,565.4 58,210.0 58,320.7 43,759.7 44,717.4 45,154.8 Restricted-DS P&I Funds 54,303.7 87,998.4 30,475.4 54,665.1 57,650.1 89,073.4 30,962.7 53,602.5 54,768.5 Restricted-DS CREBs Sinking Funds (5) 63,360.1 61,450.4 69,991.5 78,769.0 76,466.2 79,138.8 84,536.3 86,469.6 89,787.9 Restricted-Habitat Funds 16,563.1 16,224.4 18,242.2 17,588.3 17,056.5 15,888.5 18,063.4 17,906.7 17,797.8

All Restricted Funds $ 240,951.5 $ 248,732.1 $ 186,935.7 $ 315,667.9 $ 300,340.3 $ 316,790.1 $ 231,743.7 $ 245,669.1 $ 239,004.0

(60)

3

I

V

E

R

S

I

F

I

C

A

T

I

O

N

environment has impacted the ability to transact in all sectors consistently and efficiently

• The state LGIP remains an effective liquidity management investment program

•Based on economics the District has methodically decreased the concentration to

invest in other sectors within the policy limits

•Diversification if evaluated based on allocation of the total portfolio

Security Type ($ in Millions)Book Value Yield AllocationPortfolio Policy Max Target Range In Compliance

Municipal Bonds $ 155.2 3.80 35.2% 50% 25-40% YES WA State LGIP $ 63.0 0.26 14.3% 100% Varies YES Agency $ 91.2 1.03 20.7% 50% 10-30% YES Corporate Bond $ 47.8 1.44 10.8% 25% 5-15% YES US Treasury $ 60.9 0.41 13.8% 100% 20-40% YES Supranational $ 19.7 0.86 4.5% 50% 10-30% YES Commerical Paper $ 2.0 0.37 0.5% 25% 5-15% YES Bank Holdings (Cash) $ 1.2 - 0.3% n/a < $3M avg YES

(61)

4

M

A

R

K

E

T

Cash & Investments

Interest earnings are driven by UST rates both directly as an investment and as a driver to

underlying transactable yields

The Fed Funds target currently is at 0.00-0.25%

The District’s policy follows state requirements and strategy is based upon the tenants of

1) legality, 2) safety, 3) liquidity, and 4) return

LGIP rates have declined but has remained a strong liquidity management program vs

other short-term options

Short term liquidity management

Q3 average LGIP yield

0.26%

State LGIP 10/31/20 Yield

0.18%

3 month T-bill 10/31/20 Yield

0.10%

Overnight repo rate quoted 10/31/20

0.06%

(62)

5

Aggregate Portfolio Q3 Book Yield 9/30/20

2.07%

Aggregate Portfolio Q3 Modified Duration

1.96 Years

2020 Budget= $8.8M Interest Income @ 2% assumed earnings rate

E

R

F

O

R

M

A

N

C

E

January impacts earnings dollars (Elec R&C, Elec Rev, Bond Reserves)

Investment in muni’s return @ 3.8% yield, propping up overall aggregate yield amidst

falling rates

26% of portfolio matures > year 2022 (a large portion was executed when rates were

higher)

2019

Projected

2020

Investment Receipts

(Coupons/Accrued)

$ 10.3 $ 10.6

Realized G/L

(Premium/Discount

Amortization)

$ (2.2) $ (6.0)

Total Portfolio Return

$ 8.1 $ 4.6

Unrealized G/L (Market Fair

Value Adj)

$ 7.0 $ 7.3

FS Investment Income

$ 15.1 $ 11.9

shown in $ millions

$0 $5,000,000 $10,000,000 $15,000,000 2020 2021 2022 2023 2024 2025

Projected Earnings

Forecasted Interest Earnings Cash Flows Forecasted Accrual Based Earnings

(63)

6

Debt Portfolio

Principal and interest

payments Jan 1 annually

2

nd

half interest payments

7/1 annually

Variable rate interest

payments monthly

1/12

th

of fixed rate annual

debt requirements “set

aside” in P&I funds monthly

Defeasance in 2020 reduced

outstanding debt liability

Internal PRP financing of

capital (JLB bonds) has

historically resulted in

reduction of bond financed

capital by utilizing equity

Most recent debt transaction

closed on 9/1 and resulted in

yields of 0.5% and 0.65%

(yield to call)

Weighted average

coupon rate

of

fixed debt: 4.4%

Effective cost of debt

for entire

portfolio (net of interest rebates

and sinking funds): 3.4%

Weighted average life

of portfolio

12.2 years

Reduction in par outstanding

amount of $4.6 million due Electric

Sept transaction priced as

premium bonds

Overall debt activity financial

statement impact $4.3 million lower

due to favorable financings better

than budget

Total Consolidated Outstanding External Debt

Total = $1,200,725 as of 9/30/2020

2020 Budget

2020

2021

2022

2023

2024

Principal Due and Accrued $ 43.7 $ 29.3 $ 31.5 $ 34.2 $ 33.4 $ 35.8

Interest Due and Accrued $ 43.3 $ 44.2 $ 45.2 $ 44.1 $ 43.0 $ 41.7

CREB Sinking Fund Deposits $ 8.7 $ 9.3 $ 10.0 $ 10.0 $ 10.0 $ 10.0

Federal Interest Rebates $ (10.5) $ (10.5) $ (10.5) $ (10.4) $ (10.4) $ (10.3)

Projected New Debt Service $ - $ 1.8 $ 2.6 $ 4.1 $ 6.0

*Subtotal Cash Impact

$

85.2

$

72.2

$

78.0

$

80.6

$

80.2

$

83.2

Amortization of Discount/Premium/Issuance Cost $ (2.2) $ 6.4 $ 2.4 $ 0.7 $ 1.5 $ 1.1

**Net Debt Activity

$

83.0

$

78.7

$

80.4

$

81.2

$

81.7

$

84.3

Variance to 2020 Budget $ (4.3)

Shown in $ millions

(64)

7

The Strategic Plan target for debt to net plant ≤ 60% and is a factor in determining future financing

Par balance of Iinternal PRP Junior Lien Bonds (JLB) to the Electric System = $400.7 million

Current finance plan indicates equity financing for 2021 and 2021 with external bond issuances to

fund capital

2021 resolution to extend JLB program from authorization level

and cash funding for capital

•PRP construction fund balance as of 11/1- $26

million

•12-month avg fund mo. spend ~ $5M

•Scheduled PRP JLB -Q1 2020 ~ $30M,

transfer funds from Elec Revenue fund

(subject to change time/amount based on

need/availability)

•Balance of construction spending to be

funded by bond proceeds

•Electric construction fund – revenue funded

•12-month avg fund mo. spend ~ $5.5M

New money bond funding July of 2021 ~

$50M estimated (subject to change)

•July 2021 variable rate debt 2019-P required

refunding transaction ~$50 M

•Timing of new bond proceeds to

coincide with refunding – estimated ~ $50

million new proceeds

• Monitoring refunding opportunities that could meet

District policy of >3% PV savings and >50% escrow

efficiency

Series Outstanding Par Amount Coupon Range Final Maturity 2014JLB $ 40,170,000 2.38% - 4.25% 1/1/2044 2015JLB $ 27,040,000 5.034% 1/1/2045 2015JLB B $ 7,625,000 5.213% 1/1/2045 2016JLB $ 29,380,000 2.85% - 4.92% 1/1/2046 2017A JLB $ 24,810,000 2.87% - 5.00% 1/1/2047 2017B JLB $ 83,560,000 2.90% - 4.93% 1/1/2048 2019JLB $ 108,480,000 1.83% - 3.352% 1/1/2049 2020JLB $ 79,585,000 1.694% - 3.41% 1/1/2050

Total Junior Lien Debt $ 400,650,000

Internal Financing-Junior Lien Bonds

Priest Rapids Project (PRP)

F

I

N

A

N

C

E

P

L

A

N

(65)

8

Debt Management- Credit Ratings

During December 2019 and March 2020

the Utility received credit ratings from

Fitch, Moody’s, and S&P for the 2020

issuances

Electric System carries a slightly higher

rating than PRP for one rating

The Electric System was rated in August

by Fitch and S&P for the series R & S

transactions

(66)

9

Last Updated On: 2/20/2020

Notes

Resolution 8712 delegates banking and investment responsibilities to the Treasurer and provides certain guidance. Section 7 details that the Treasurer’s report

will include: cash/investment activity/balances, authorized list of banking institutions/brokers, authorized treasury staff to perform banking and investing activities,

and a summary of petty cash funds.

The Advanced Travel Imprest account was reduced due to inactivity, this separate account is required by RCW 42.24.130

The CS Refund Imprest account custodian was updated, this account is scheduled to significant reduced activity due to a process improvement to integrate into

the standard AP function as a result of the CCS upgrade.

(67)

Continuing to safely, efficiently and effectively execute projects

Quarterly Commission Update – November 2020

Powering our way of life.

(68)

2020

Q3 Review

Structure and Personnel

Safety Update

Budget Update

Q3 Accomplishment Updates

(69)

Acronym List

EPMO Enterprise Project Management Office

ET

Enterprise Technology

PP

Power Production

(70)

Department

Purpose

Improve the probability of successful

project delivery to create greater

business value

Improve

Become the source for guidance,

documentation and metrics for the

practices involved in managing and

implementing projects within Grant

PUD.

(71)

Department

Goals

Cultivate a business driven EPMO that

enables consistent, reliable data and

outcomes

Standardized business driven project

management framework

Employ change management

principles to allow greater adoption,

utilization and proficiency

The success of the EPMO is derived

exclusively from achieving greater

business value to the utility

(72)

Senior Manager EPMO

Julie Pyper

Manager Power

Production

Aaron Kuntz

Administrative

Assistant

Project Managers

Outage Coordinator

Manager

Facilities &

Project Services

Dustin Bennett

Project

Coordinators

Construction

Inspectors

Lead Project

Manager - QA

Randy Weisheit

Manager IT

Projects

Chris Roseburg

Project Manager

Project

Coordinators

Senior Training

Coordinator

Manager Power

Delivery

Allen Chatriand

Project Managers

Project

Coordinators

Business Analyst

Krissy MacKenzie

Administrative

Assistant

Mindy Klingenberg

(73)

District

Personnel

• Selected as EPMO Manager – Power Delivery

• Previously Senior Project Manager in EPMO Power

Production

• Backfilling his project manger position

Allen Chatriand

• Promoted to Project Coordinator from Administrative

Assistant

• Provides schedule management and OCM support

Mindy Klingenberg

• Selected as EPMO Power Delivery Senior Project

Manager - manage Quincy Transmission Expansion

Project

• Previously Senior Project Manager in EPMO Power

Production – PR Turbine Generator project

• Backfilling his position

Travis Wiser

• Hired as Project Manager for Power Production

• External hire (Palisades)

(74)

Contracted

Personnel

Named

Resources

Rachelle McGillivray

Power Engineers

ESRI/GIS Project

(until E0P)

David Poulin

TMG Consulting

CCS Project

Dec 2020

(until EoP)

Brent Gregory

Arch Staffing and

Consulting

Project Management

Framework and misc.

project support

Dec 2022 (+)

Cliff Woods

Arch Staffing and

Consulting

Ephrata and Moses

Lake Service Centers

Dec 2022

(until EoP)

Ben Floyd

White Bluffs

Consulting

Facilities Master Plan

Dec 2021

(until EoP)

Thomas Karcz

Arch Staffing and

Consulting

OCM Program

Dec 2022 (+)

Ann Shiveley

VOLT

OCM project support

May 2021 (+)

(75)

Power

Production

To Be Named

Resources

Name

Consulting

Firm

Project

Estimated

Duration

EPMO 1

TBD

Project Control Services

Dec 2022 (+)

EPMO PD 1

TBD

OSS/BSS (Fiber tech) project

TBD (EoP)

EPMO PD 2

TBD

ECBID project

TBD (EoP)

EPMO PD 3

TBD

Invenergy project

TBD (EoP)

EPMO PD 4

TBD

Project Development –

NLL/Interconnect

Dec 2022 (+)

EPMO ET

TBD

Remaining HCMS modules

Dec 2021

EPMO ET

TBD

ET program support

July 2021 (+)

EPMO PP 1

TBD

PM for specific project being

determined

TBD

EPMO PP 2

TBD

PM for specific project being

determined

TBD

EPMO PP 3

TBD

Project Coordinator for specific

project being determined

TBD

EPMO PP 4

TBD

Project Coordinator for specific

project being determined

TBD

EPMO PP 4

TBD

Project Coordinator for specific

project being determined

TBD

Additional contracted needs to be determined on a project-by-project basis.

(76)

Contracted

Personnel

Potential PP

Projects for

Contracted

Resources

WAN/PR Station Service

2020

CO2 Replacement

2021

Maintenance Equipment Storage at WMC

2021

Power Production Tag in/Tag out System

2021

PRP Control Room Renovations

2021

WAN Bridge Cranes

2021

WAN Fish Ladder

2022

PR Fish Ladder Rehabilitation

2022

PR Hatchery Siphon Intake Renovation

2022

PR Warehouse

In progress

PR Right Embankment Improvement Project

In progress

PR Turbine Generator Rehab Project

In progress

(77)

Safety Update: Safety Meeting Attendance

100% 100%

97%

94%

100% 100% 100% 100% 100%

JAN-20 FEB-20 MAR-20 APR-20 MAY-20 JUN-20 JUL-20 AUG-20 SEP-20

(78)

Projects managers

• Minimum 2 per active project per month

• Folks are encouraged to do more

• Folks are encouraged to do them together

Inspectors

• Minimum of 1 per month for each non-EPMO managed project

• Coordinate with Project Manager for each EPMO managed project

Enterprise Technology projects

(79)

Safety

Update

Q2 2020 Recordable

incidents: 0

Q2 2020 Vehicle incidents: 0

Continued emphasis on job

site reviews and contractor

safety

(80)

Budget

Update

Employee Activity

(81)
(82)
(83)
(84)

Overall

EPMO 2020

Initiatives

framework

• Roadmap development and implementation

• Project support

• Program support

Organizational Change Management

• Quality surveys continue for ET projects

Project Management Quality Management

Operations budget and financial analysis

(85)

Enterprise

Technology

• HCMS

o

Closing myHR

o

Initiating and planning LMS module

• Office 365 Migration

o

Complete by EOY

• Oracle CCS

• ESRI GIS and Work Order Design

(86)

Power

Delivery

• Wholesale Fiber Project

o

Continued construction

• Design Build 2

o

Construction started – Burke, Mountain

View and Quincy Plains

• Quincy Transmission Expansion Project

o

Allows for continued industrial growth

References

Related documents

A Navy Recruiting Station shall operate under a Leading Petty Officer (LPO) or Leading Chief Petty Officer (LCPO) who reports to the Commanding Officer of the parent

- When using transformers, ensure that each transformer is fused individually on the primary side or with a thermal fuse according to the manufacturer's specifications. -

The analysis for the correlation coefficients showed higher values for the ensemble model output than for the individual models over the Equatorial region with the stations in

Take Control of Your Company’s Spending Smartdata.gen2 delivers the comprehensive capabilities needed to better track and control expenditures, plus the versatility to customize

General Re Insurance Corporation is also excess and reinsures the MEL on a following form basis subject to terms and conditions of the underlying Indian Harbor Insurance Company

However, with increasing surgeon experience the overall positive margin rate decreased significantly and was comparable to the positive margin rate for patients with locally

In tumor cells exposed to DNA damaging therapy, p53 appears to be essential for senescence induction as tumor cell lines harboring mutant p53 failed to become senescent and

He has a bachelor’s degree in political science from Southern Illinois University, and is pursuing a master’s in public administration at Governors State University.... Kenneth