• No results found

STANDARD OPERATING PROCEDURE NO. CM

N/A
N/A
Protected

Academic year: 2021

Share "STANDARD OPERATING PROCEDURE NO. CM"

Copied!
17
0
0

Loading.... (view fulltext now)

Full text

(1)

STANDARD

OPERATING

PROCEDURE

NO.

CM.13

-

00

-

00

Approved

by:

Date

Version

date:

Effective Date:

Replaces SOP

No.:

1 5 January

20

13

(2)

CONTENTS:

1. DEFINITIONS/REFERENCES……….……….….2.

2. PURPOSE……….………..2.

3. SCOPE………....2.

4. RESPONSIBILITIES………....2.

5. PROCEDURES………...2.

5.1 Creation of Clinical Management Plan ………..………...2.

5.2 Review of Clinical Management Plan...3.

5.3 Approval of Clinical Management Plan………...…3.

5.4 Revision and amending of Clinical Management Plan...3.

6. RELATED SOPs and GUDELINES……….….4.

7. APPENDICES/FORMS/SUPPORTING DOCUMENTS

Appendix 1 Main Procedural Differences from Previous Version

Appendix 2 Clinical Management Plan template

(3)

CLINICAL MANAGEMENT PLAN No: CM.13 – 00 – 00 Effective Date: 15 February 2013 Version Date: 15 January 2013

Version 15/01/2013

Page 2 of 7

Confidential

1. DEFINITIONS/REFERENCES

Clinical Management Plan: A plan developed by the Project Manager or designee that

identifies the overall contractual tasks and responsibilities and the processes of how each

of those tasks and responsibilities will be accomplished. This may include, but is not

limited to identification of all team members and associated clinical and data operations

responsibilities.

2. PURPOSE

To describe the procedures for the development, review, and approval of the Clinical

Management Plan

3. SCOPE

This process applies to all projects where the creation of a Clinical Management Plan is

identified as a contractual deliverable. The Project Manager is responsible for ensuring

that the Clinical Management Plan is developed, but may delegate tasks to other team

members, as appropriate.

4. RESPONSIBILITIES

Project Manager or designee: Develops the Clinical Management Plan with designated

team members. Obtains approval from the Line Manager and other designated reviewers.

Maintains the Clinical Management Plan. Distributes and explains the Clinical

Management Plan to appropriate clinical team members. Documents distribution of

designated sections to the investigational site, as appropriate.

Line Manager: Reviews and approves all versions of the Clinical Management Plan.

Distributes applicable sections of the Clinical Management Plan to the Sponsor in

accordance with the scope of work, and approves distribution of applicable sections to the

investigational site and any designated third party.

Quality Assurance Manager: may be requested to review and approve relevant sections

of the Clinical Management Plan, as appropriate, to ensure compliance with the

documented scope of work, applicable SOPs and project instructions.

5. PROCEDURES

5.1 Creation of Clinical Management Plan

The Project Manager or designee is responsible to:

1.

Develops and oversees process

2.

Determines, in conjunction with the sponsor, the template to be used for

the Clinical Management Plan

3.

Defines timelines for the development and review of the Project

Management Plan

4.

Notifies reviewers of upcoming review

5.

Ensures draft Clinical Management Plan is developed within the specified

timeline

6.

Versions document with version date and version number (v1, v2, v3 etc.)

7.

Forwards draft to the reviewers, providing timeline for review

(4)

The Project Manager or designee has options for creating the Clinical Management Plan;

use the sample template as provided in this SOP, or create new document, or

use Sponsor template, or a combination of options that may be described in the

contract, or at the request of the Sponsor.

Following items must be clearly documented in the Clinical Management Plan:

The clinical and related contractual obligations described in the scope of work,

the budget including assumptions, and the transfer of regulatory obligations.

Detailed information on the clinical activities to be performed, including the

communication plan, budget and assumptions, time lines and Clinical staff

resources necessary to perform these activities

References to applicable SOPs and project instructions

Management and monitoring of the progress of the project scope of work

according to contractual obligations, protocol specifications, GCPs and applicable

regulations, SOPs and project instructions including, but not limited to,

documentation of the following activities

Quality control of clinical deliverables

Identification and communication of out-of-scope activities

Project-specific training of clinical team members

Information dissemination, including updates of key documents (e.g.,

Investigator’s Brochure)

Coordination of the study completion process, including transfer of

files/data and archiving

Appendices such as the Monitoring Plan, Data Management Plan, or Safety Monitoring

Plan may be generated as separate documents, if required by Sponsor/contract.

5.2 Review of Clinical Management Plan

Project Manager or designee and the Line Manager shall identify the appropriate

reviewers for the Clinical Management Plan, including a designated Clinical reviewer

other than the PM or LM, which may include Quality Assurance Manager, Regulatory

Manager or any other qualified reviewer(s).

5.3 Approval of Clinical Management Plan

Project Manager or designee will incorporate Clinical reviewer’s comments if any and he

will return revised version to Clinical reviewers for final review, as appropriate.

After final review Clinical reviewers should sign the appropriate approval page on

Clinical Management Plan as a sign that the document has been approved.

After final review and approval Project Manager or designee will send approved Clinical

Management Plan to Sponsor for review if required by Sponsor and to the assigned

Clinical Research Associate(s) for filing.

5.4 Revision and amending of Clinical Management Plan

The Clinical Management Plan should be periodically reviewed and updated as the

clinical study progresses and/or procedures change or tasks are added to the clinical

(5)

CLINICAL MANAGEMENT PLAN No: CM.13 – 00 – 00 Effective Date: 15 February 2013 Version Date: 15 January 2013

Version 15/01/2013

Page 4 of 7

Confidential

component of the study. It is acceptable for an individual section(s) of the Clinical

Management Plan to be updated and distributed, provided that the required reviews and

distribution are documented.

The Project Management Plan will be amended based on changes in the scope of work

and associated changes in the clinical budget. All amendments will be approved by the

Line Manager, the Quality Assurance Manager or designated Clinical reviewer and any

other reviewer(s). All approved versions of the Clinical Management Plan will be

distributed to the PM for filing in the Project Management File, to appropriate Clinical

team members and filed in the Central Clinical Study Files

6. RELATED SOPs and GUDELINES/SUPPORTING DOCUMENTS

SOP CM.1Feasibility

7. APPENDICES/FORMS

Appendix 1 Main Procedural Differences from Previous Version

Appendix 2 Clinical Management Plan template

(6)
(7)

CLINICAL MANAGEMENT PLAN No: CM.13 – 00 – 00 Effective Date: 15 February 2013 Version Date: 15 January 2013

Version 15/01/2013

Page 6 of 7

Confidential

MAIN PROCEDURAL DIFFERENCES FROM THE PREVIOUS VERSION

SOP # MODIFICATION Version Date

(8)
(9)

CLINICAL MANAGEMENT PLAN

Page 1 of 9

EFFECTIVE DATE:

VERSION NO.:

*If amended, see section 8 and record details of changes from previous version

Project Name:

Project Number: Protocol Number:

Sponsor Name: Address: Telephone No.: Fax No.: PREPARED BY: Name/Title: Office/Address: Telephone No.: Fax No.:

APPROVED BY:

PROJECT MANAGER

NAME: SIGNATURE: DATE:

PROJECT TEAM LEADER

NAME: SIGNATURE: DATE:

QUALITY ASSURANCE REVIEW

NAME: SIGNATURE: DATE:

REGULATORY AFFAIRS REVIEW

NAME: SIGNATURE: DATE:

OTHER REVIEW (SPECIFY)

(10)

Purpose:

To establish and document practical working methods for the clinical team based upon the protocol, scope of work, and contract. To facilitate the exchange and documentation of relevant information and expectations between Altiora and the Sponsor (INSERT name of Sponsor), and where appropriate the Investigator

Scope:

This clinical management plan applies to the (INSERT project name/reference) from the time that Altiora assumed contractual responsibility for clinical trial management until those contractual obligations are completed.

(11)

CLINICAL MANAGEMENT PLAN

Page 3 of 9

1.0 CLINICAL PROJECT/ACTIVITIES DESCRIPTION

2.0 CLINICAL SCOPE OF WORK, RESPONSIBILITIES AND PROCEDURES 2.1 DESCRIPTION OF ACTIVITIES

2.2 SPONSOR OBLIGATIONS

2.3 TRANSFER OF REGULATORY OBLIGATIONS 3.0 CLINICAL PROJECT BUDGET AND ASSUMPTIONS 4.0 CLINICAL PROJECT TIMELINE

5.0 CLINICAL PROJECT TEAM

5.1 ALTIORA CLINICAL PROJECT TEAM 5.2 SPONSOR CLINICAL CONTACTS 5.3 SITE/THIRD PARTY CONTACTS 6.0 CLINICAL COMMUNICATIONS PLAN

6.1 COMMUNICATIONS WITH SPONSOR

6.2 INTERNAL CLINICAL TEAM COMMUNICATIONS 6.3 COMMUNICATIONS WITH STUDY SITES 7.0 QUALITY PLAN

8.0 AMENDMENTS TO THE PROJECT AND CLINICAL MANAGEMENT PLAN 9.0 ATTACHMENTS

(12)

A brief description (1-2 sentences, checklist or bulleted list) of the broad scope of the study (for example, phase of study, indication, multi-center trial, countries involved, etc).

2.0 CLINICAL PROJECT SCOPE OF WORK, RESPONSIBILITIES AND PROCEDURES

Reference where the overall list of responsibilities and referenced SOPs can be located, or provide details below:

CLINICAL AND RELATED TASK LIST

(To be customized for project)

RESPONSIBLE

ORGANIZATION PROCEDURE NUMBERS)*RELEVANT SOPs (LIST Site Identification

Site Selection Visits Investigator Selection Site Initiation Visits Investigator’s Meeting

Regulatory Document Collection Investigational Product

Shipment

Blinding/Unblinding Monitoring Visits Closure Visits

Adverse Event Reporting Data Management

*If Altiora is responsible for a task and non Altiora’s procedures are to be followed, list Sponsor SOP numbers here and see section 9 Attachments

(13)

CLINICAL MANAGEMENT PLAN

Page 5 of 9

Provide a more detailed description or specific reference for tasks listed in Table 2.0 (above). The goal is to completely and unambiguously specify the requirements and procedures to be followed for each. Specify if the referenced document is included as an attachment (see section 9.0). Indicate if a specific activity is “To be added” or “Not applicable”.

SPECIFIC ACTIVITY DESCRIPTION/REFERENCE

1. List of assigned sites and responsible clinical study monitors (current versions)

2. Description of team member training – to include:SOP specific training if Altiora SOPs will no

be used.

Project specific training, by whom and how often.

Where documentation of this training will be maintained.

3. List of all approved study specific forms (not including approved standard forms) and their intended use.

4. Process of clarifications for protocol

interpretation and CRF completion (as applicable to protocol)

Sponsor definition for screen failuresRandomization process

Procedures for obtaining protocol clarification/authorization of exceptionsPatient unblinding procedures

Definition for visit windows

Prohibited concomitant medicationsFrequency of required site activities and

maintenance of study equipment 5. Site monitoring visits – Can include reference to study specific monitor’s manual

Frequency of visits

Duration of visits, when knownHow deviations from the anticipated

monitoring schedule will be recorded and approved by Sponsor

Project specific guidelines for site visit reports and follow-up letters

Time frame and method for submission and review of site visit reports to the CTL or designate

6. Timing of CRF submission relative to site visits (for example, Who sends CRFs where/CRF Shipment procedures, CRFs sent as completed or collected by monitors after review at site visit). If eCRF is not in use.

(14)

7. Instructions for protocol deviation tracking by site and across project

8. Immediately Reportable Adverse Event (IRAE) Procedures: (as applicable to protocol)

Sponsor definition of IRAE

Sponsor definition of pre-existing conditionSponsor definition of a “planned hospital

admission”

Describe procedures for reporting IRAEs, including timelines to be met and contact details for the staff/offices/departments involved

9. Source Document Verification Procedures: (as applicable to protocol and scope of work)

Percentage of source document checkingIdentification of key variables, if percentage

of source document checking is different for key and non-key variables

10. Query Generation and Resolution

Frequency of query generation and cross checks to be performed by data

management

Procedures for resolution of data clarifications and the documentation and filing requirements for data clarificationsStandard procedure for documenting

authorization of site personnel (other than PI) to resolve (approve and sign) data queries

11. Method and frequency of communicating and transmitting site specific regulatory updates to clinical study monitors where applicable

12. Investigational Product: (as applicable to protocol and scope of work)

Frequency of Investigational Product accountability/reconciliation

Handling, and shipping instructions for Investigational Product

Investigational Product blinding procedures, if applicable

Investigational Product relabeling instructions, if applicable

Investigational Product recall instructions

13. Handling and shipping instructions for central or local laboratories, as applicable

(15)

CLINICAL MANAGEMENT PLAN

Page 7 of 9

protocol and scope of work)

Instructions for SiteInstructions for CRAsStatus Reports to Sponsor

15. Central Clinical Study File/Investigator Site FileProject specific Investigator Site File

contents (Table of Contents)

Project specific Central Clinical Study File contents (Table of Contents)

Reference manual for sites (Table of Contents)

Instructions for completion of study logs 16. Procedures for Study Closure

Archiving Instructions

2.2 SPONSOR OBLIGATIONS

Reference or list below the sponsor obligations, in particular any obligations which would affect Altiora ability to meet time scales and budgets.

Due Date: Due Date: Due Date:

2.3 TRANSFER OF REGULATORY OBLIGATIONS

Only complete this section if there are any specific regulatory responsibilities that the sponsor has transferred to Altiora. Or where applicable, include a copy of the Transfer of Regulatory Obligations.

3.0 CLINICAL PROJECT BUDGET

Provide information regarding the project budget and assumptions (issues that may need to specified include: fixed price, time and materials, consulting project with upper limit, incentive or penalty clause(s), version date and status of contract, specific work codes to be used, etc.). Reference can be made to the current version of the budget and assumptions being followed (see Section 9.0 Attachments).

4.0 CLINICAL PROJECT TIME LINE

Identify all Sponsor and Altiora deliverables (as a minimum). Reference can be made to a separate detailed project plan (see Section 9.0 Attachments).

TASK/MILESTONE START DATE END DATE

(16)

Identify principal Altiora and Sponsor Project Team members only.

Reference can be made to a separate detailed project team/contact list (see Section 9.0 Attachments).

5.1 ALTIORA CLINICAL PROJECT TEAM

NAME/

OFFICE/ADDRESS TITLE/ROLE TELEPHONE FAX EMAIL

5.2 SPONSOR CLINICAL CONTACTS

NAME/

OFFICE/ADDRESS TITLE/ROLE TELEPHONE FAX EMAIL

5.3 SITE/THIRD PARTY CONTACTS (including Central IRB, central laboratory, etc. as

applicable)

NAME/

OFFICE/ADDRESS TITLE/ROLE TELEPHONE FAX EMAIL

6.0 CLINICAL COMMUNICATIONS PLAN

6.1 COMMUNICATIONS WITH SPONSOR

Specify the regular communications with the Sponsor (for example, weekly teleconference, monthly progress report, quarterly meetings, etc.)

6.2 INTERNAL CLINICAL PROJECT TEAM COMMUNICATIONS

Specify internal communication channels (for example, Project Management and reporting structure, status reports to be circulated, etc.)

6.3 CLINICAL STUDY MONITOR COMMUNICATIONS WITH STUDY SITES

(17)

CLINICAL MANAGEMENT PLAN

Page 9 of 9

7.0 QUALITY PLAN

List the primary measures, checks and reviews to be performed for specified clinical deliverables. Specify any checks and review activities that will be performed by the Sponsor.

8.0 AMENDMENTS TO THE PROJECT AND CLINICAL MANAGEMENT PLAN

Provide a summary list of all amendments made to the Clinical Management Plan. For each

Amendment/Version issued, identify the specific section(s) updated in that version. Clearly summarize the major changes to be implemented including the effective date of the change(s).

9.0 ATTACHMENTS TO THE CLINICAL MANAGEMENT PLAN

References

Related documents

Business Case Management Transition Management Operation Management Domain Requirements Engineering Domain Design Domain Realization Domain Testing Product Line

Search Space of CACTI-6 Low swing Low-swing 30% Delay Penalty Least Delay. Design space with global and low

Secondly, I compared the areas of formally and voluntarily set-aside forests for biodiversity conservation in 40 (95%) of SFEs in Lithuania and, thirdly, I applied

An analysis of the economic contribution of the software industry examined the effect of software activity on the Lebanese economy by measuring it in terms of output and value

The Third Circuit’s Application of the “Quick Look Rule of Reason” Test After weighing the legislative intent behind the Hatch-Waxman Act and the rationale underlying the

Engineered to best analyze gaze on a plane (e.g., a retail shelf), both portable eye-tracking glasses and computer monitor–mounted hardware can play key roles in analyzing

To calibrate the method, we used 12 different “combi- nations” of protein targets (HIV-RT and ABL1), docking programs (ADvina and Dock) and ligand libraries (DUD- E active

For users who wish to have a pointer to the actual socket (so that socket operations like Bind(), setting socket options, etc. can be done on a per-socket basis), Tcp sockets can