• No results found

60% Design Technical Memorandum

N/A
N/A
Protected

Academic year: 2022

Share "60% Design Technical Memorandum"

Copied!
18
0
0

Loading.... (view fulltext now)

Full text

(1)

99 North State Street

Concord, New Hampshire 03301

Tel: 603-230-9898 Fax: 603-230-9899

60% Design Technical Memorandum

To: Bruce Thomas, P.E. – Town of Hooksett File: 2447.08 From: David J. Mercier, P.E., Senior Project Manager

Cc: Ed Rushbrook, Robert Saunders, Liz Philpott, Keith Pratt Date: April 13, 2021

Subject: 60% Design – Route 3A Utilities Expansion – Contract 1

BACKGROUND

On January 22, 2020, Underwood Engineers submitted the final version of the Route 3A Utilities Expansion Project Planning Stage Technical Memorandum to the Town. That Memorandum recommended water and sewer utilities expansion in the Route 3A area of Hooksett under four major projects as follows:

Contract 1 – consisting of sewering the Phase 1 and Phase 2 areas, immediately surrounding the Route 93/ Exit 10 exchange. In addition to ~14,250 feet of gravity sewer, this contract includes construction of a new pump station serving the Kimball Drive area, a twin force main under the Merrimack River to transmit flows to the existing Martins Ferry Pump Station, and an upgrade of the existing Martins Ferry Pump Station.

Contract 2 – consisting of the Phase 3 construction of the Tri-Town Ice Arena Wastewater Pumping Station and gravity sewer main and water main through the Bayview Terrace Road and Meadowcrest Road neighborhoods to West River Road (3A) (~4,000 feet).

Contract 3 – consisting of the Phase 4 proposed gravity sewer main north of the Tri-Town Ice Arena Pumping Station to Hackett Hill Road (~4,800 feet).

Contract 4 – consisting of the Phase 5 gravity sewer main from the intersection of West River Road (3A) and Meadowcrest Road south to the Dunkin Donuts property (~5,700 feet), including a water main interconnection between the Hooksett Village Water Precinct and the Manchester

(2)

The Town is committed to the expansion of utilities along the Route 3A corridor and to initiate that process, has authorized preliminary and final design to be performed on all four contracts.

However, given the magnitude of these four contracts (~$21M) and limited funding currently available, a decision was made to give priority to the preliminary and final design of Contract 1 at this time. Preliminary and final design of Contract 1 is currently scheduled to be completed by June 2021, while the preliminary and final design of the other three contracts is currently anticipated for completion by the end of 2021.

The purpose of this Memorandum is to provide a description of the concepts being evaluated in the final design process. The issuance of this 60% Design Technical Memorandum focuses on Contract 1. It will be amended over time to provide details on the other three contracts as the overall project progresses.

CONTRACT 1 SUMMARY

The goal of Contract 1 is to establish municipal sewer service to the existing businesses that are within the Route 93/Exit 10 exchange area. Several of these existing businesses are known to have problematic private subsurface systems and several business owners have expressed a desire for municipal sewer service in the area. Given the limited Town funding available from the Tax Incremental Finance (TIF) zone that has been established, this project will focus on constructing sewers from the low point on Kimball Drive to the north and south sides of the Rte 93/Exit 10 exchange, ending at Rte 3A within a reasonable distance of the large businesses in order to make it affordable for them to construct additional sewer and sewer services to their individual businesses. In order for this concept to be successful, financial participation by Walmart, Bass Pro Shops, Market Basket, Dunkin Donuts and Subway will be required.

The proposed municipal sewer infrastructure to be constructed by the Town under Contract 1 includes a new wastewater pumping station located on a 0.5 acre easement between Quality Drive and Kimball Drive at the low point, new gravity sewer extending both north and south from the new Kimball Drive Pumping Station up to Rte 3A, a new double-barrel force main directionally drilled under the Merrimack River, and upgrades to the existing Martins Ferry Pumping Station on the east side.

The design flows being assumed in these evaluations are the projected 20-year flows for both the Kimball Drive Pump Station and Martins Ferry Pump Station.

(3)

GRAVITY SEWERS

Approximately 14,250 feet of gravity sewers are being designed under this contract (refer to Appendix A). It is assumed that ~9,250 feet will be constructed by the Town and ~5,000 feet by local businesses wishing to connect.

A further breakdown would be ~4,250 feet by the Town and ~3,800 feet by local businesses in Zone 1, and ~4,100 feet by the Town and ~1,200 feet by local businesses in Zone 2. An additional ⁓900 feet along Rte 3A in Zone 2 would be constructed by the Town to serve residential homes, but that piece is recommended to be postponed to a later date when the need arises. All sewer pipe is proposed to be either 8” or 10” SDR-35 PVC sewer.

Workplan 1 in Appendix A shows the proposed Town constructed sewers in solid purple and green; the private business constructed sewers are shown in solid pink. The 60% design drawings for all of the new gravity sewers (except Technology Drive) consists of 17 sheets and is contained in Appendix B (Dwg No.’s C4-C20).

KIMBALL DRIVE PUMPING STATION

The Town of Hooksett is in the process of obtaining a 0.5 acre permanent easement on Lot 29- 64-3 for construction of the new pumping station. The site is adequate in size to site a new submersible pumping station with room for growth and is accessible from both Kimball Drive and Quality Drive, with the main access being from Quality Drive.

Given the projected magnitude of wastewater flows, the pump station is proposed as a submersible pump station with the entire station fully enclosed within a small building footprint to provide ease of maintenance as well as protection from harsh winter weather conditions. The building consists of three sections including a) a fully-enclosed wetwell area which will house a grinder for the raw wastewater and two wetwells, each with a submersible pump; b) a drywell area which will consist of electrical and control components on the first floor level and a valve pit and flow meter on the below-grade level; and c) an enclosed building space to house a backup generator for the facility at ground level rather than in a stand-alone exterior enclosure.

The building structure will consist of concrete masonry unit block on the interior and split face architectural block on the exterior, with a flat, sloped concrete plank roof with membrane roofing. The overall dimensions of the proposed building are approximately 14’ wide x 36’ long with an 11’ first floor ceiling height. The building layout can be seen on the 60% design floor

(4)

Essential to the design of the station is the estimated 20-year design wastewater flow and the eventual full buildout flow projection. Projected flows at this station are based on available data given that the majority of the properties in Zone 1 and Zone 2 are occupied and currently served by municipal water from the Manchester Water Works (MWW). Utilizing a combination of existing water meter data from years 2016 to 2018, and assuming reasonable allocations for development on undeveloped lots based on the Hooksett Sewer Commission’s sewer use ordinance and NHDES commercial flow contributions guidelines, Underwood calculated the 20- year design and buildout flows which can be seen in Table 1 below.

TABLE 1 –KIMBALL DRIVE PUMP STATION BASIS OF DESIGN FLOWS

Zone 20-year Flow

Avg Day (GPD)

20-year Flow Peak Hour

(GPD)

Build-out Flow Avg Day

(GPD)

Build-out Flow Peak Hour

(GPD)

Zone 1 56,000 168,000 141,000 423,000

Zone 2 16,000 48,000 28,000 84,000

KDPS Design Q 72,000 216,000 169,000 507,000

Note: A peaking factor of 3 was utilized as all flow is from commercial businesses assumed to be generated during the 8-hr work day.

From Table 1, the average day and peak hour 20-year design flows for the Kimball Drive Pumping Station serving Zone 1 and Zone 2 are 0.072 MGD and 0.216 MGD.

Fortunately, both the projected 20-year and build-out design flows are reasonable for a single 10.1 pump to handle operating with a variable frequency drive motor. Two (2) pumps will be provided in duty/standby fashion, with one pump being capable of handling peak flows all the way to build-out. The pump can be operated from 352 gpm down to 175 gpm.

KIMBALL DRIVE PUMPING STATION FORCE MAIN

It will be necessary to convey flows from the Kimball Drive Pump Station to the east side of the river into the existing sewer. This will be provided by constructing a 1,000 linear foot long twin force main from the Kimball Drive Pumping Station to the Martins Ferry Pumping Station directionally drilled under the Merrimack River. The key constraints that exist for a directional drill are the need to maintain a minimum of 30 feet below the bottom of the riverbed at all points to minimize the potential for a “frac out”, with a maximum pipe slope of 20%. In order to make cleaning/servicing of the directional drilled force main pipes easier, an access vault with valving will be constructed on both sides of the river.

(5)

Given the effort required to perform a directional drill of this magnitude, Underwood recommends that two independent force mains be installed side-by-side under the river (a double-barrel force main) to provide backup capacity should either of the force mains become compromised in the future. Evaluations of the cost of a single versus a twin force main indicates that the difference in cost is relatively small since a majority of the cost is in the drilling process and not the pipe materials. The valve vaults on both sides of the river will allow an operator to choose which of the force mains to have online at any given time.

It is recommended that the directionally drilled force mains be constructed of 6” high-density polyethene (HDPE) pipe, which will result in a velocity of 4.0 feet per second at the projected buildout peak hour flow of 0.507 MGD or 352 gpm. In order to provide a minimum desired flushing velocity of 2.0 feet per second, the minimum pump flow rate provided should be at least 175 gpm. (Refer to Appendix B, Dwg No. C3 to view the 60% design configuration of the proposed double-barrel force main between the Kimball Drive Pumping Station and the Martin’s Ferry Pumping Station.)

It is important to note that the Kimball Drive Pump Station will pump right to the existing Martins Ferry Pump Station. The existing Martins Ferry Pumping Station cast iron force main is only 8” in diameter, is 50+ years old, and will be difficult and costly to replace given it is located within the PanAm Railroad right-of-way. At some point in the near future, the economic hydraulic capacity of the 8” CI force main will be exceeded and replacement is advisable.

Two options that have been evaluated to deal with this issue are a) design new pumps for the Martins Ferry Pump Station sized to force the required flows through the existing 8” force main (results in the need for 167 HP pumps pumping at 273 feet of TDH), or b) design new pumps for the Martins Ferry Pump Station that are large enough to handle the next 5 to 10 years of flow utilizing the existing force main, and also sized appropriately to handle the 20-yr design flows through a new larger and shorter force main directionally drilled under the adjacent wetlands and onto and across land owned by Manchester Sand and Gravel to a new gravity sewer to the WWTF. Given the location, age, and condition of the existing force main, and the fact that the larger pumps that would be needed to continue to use it long term are large, costly, and operating at the very edge of their capability, we recommend that option b) be pursued and the 60% design information below reflects that. It should also be noted that the Hooksett Sewer Commission is in full agreement with this approach and is committed to replacing the force main in the near future.

(6)

MARTINS FERRY PUMPING STATION UPGRADES

The Martins Ferry Pumping Station was originally constructed in 1968 and underwent one major upgrade in 1985. New pumps and controls were later installed in 2006. The station is a wetpit/drypit station. The wet wells on the wetpit side of the station are extremely small by standard practices. The station houses an influent channel with a mechanical grinder which then discharges to the two wet wells, each with a capacity of only 1,300 gallons.

On the dry side, electrical and controls and the backup generator exist on the ground-floor level.

Two centrifugal pump motors are also located at the ground level with drive shafts extending to the pumps at the basement level. A mezzanine level walkway/stairwell exists as well. The rated design capacity of the pumps, based on the 2006 upgrade, is indicated as 738 gpm at 130 feet TDH. Due to age of the equipment and/or the condition of the force main, pump tests performed by Underwood show the pumps currently max out at a flow of 650 gpm, or 88% of the initially rated capacity.

Current average flows to the Martins Ferry Pumping Station based on 5 years of data collected from 2015-2019 are 0.293 MGD. Because the chart recorder data is questionable in terms of calibration, the actual peak hourly flow is unknown. For the purpose of these evaluations, Underwood has assumed that the peak hour flow is equal to 650 gpm (0.936 MGD) because a second pump has not been called in the last year. This equates to a peak hour peaking factor of of 3.2.

Below in Table 2 are the suggested 20-year design flows for the Martins Ferry Pumping Station, assuming 10% growth and the addition of the Kimball Drive Pumping Station flows.

TABLE 2 – MARTINS FERRY PUMPING STATION BASIS OF DESIGN FLOWS Current Flow

Avg Day (GPD)

Current Flow Peak Hour

(GPD)

20-year Flow Avg Day

(GPD)

20-year Flow Peak Hour

(GPD) MFPS Basin

KDPS Basin MFPS Design Q

293,000 0 293,000

936,000 0 936,000

322,000 72,000 394,000

1,030,000 216,000 1,246,000

Note: 20-year design flows include 10% growth within MFPS sewer shed plus Kimball Drive Pumping Station Flows

From Table 2, the average day and peak hour 20-year design flows for the Martins Ferry Pumping Station are 0.394 MGD and 1.25 MGD. The existing lead/lag pumps are each 50 HP and the backup generator is a 60 KW unit. To accommodate the future 20-year design flows

(7)

using the existing force main, the pumps would have to be upsized to 150 HP and the backup generator would need to be significantly increased in size as well. Instead, we have designed the new 70 HP pumps to be able to handle short term peak flows up to 760 gpm (1.1 MGD) through the existing force main, and up to 1,078 gpm (1.55 MGD) through a new larger and shorter force main to the Manchester Sand and Gravel property.

In addition, Underwood recommends that the wet well capacity at the station be increased to prevent short cycling of the pumps during low flow periods overnight, and to accommodate new flows from the Kimball Drive Pumping Station. As a rule of thumb, the wet wells should be sized based on a filling time of 30 minutes or less at design average day flows. This would translate to 8,208 gallons at 0.394 MGD. The most cost-efficient way to accomplish this would be to provide additional wet well capacity (8,208-2,600=5,608gal) in the form of new exterior storage provided via a precast concrete tank installed immediately adjacent to the existing pumping station wet wells on the west side of the station.

For the 60% design, it has been assumed that a 10,000-gallon precast concrete storage tank would be provided as shown in the 60% preliminary drawings attached in Appendix B (Dwg No.’s C2, P4 &P5). Note: For the new tanks, not all 10,000 gallons is usable given the available pump operating band.

MARTINS FERRY PUMPING STATION FORCE MAIN EVALUATIONS

During 60% design development, Underwood investigated the condition of the existing 8” CI force main via pump flow rate and discharge pressure tests at the station. The existing pumps were designed in 2006 for 738 gpm, but in early 2020 were only able to pass 525 gpm. This suggested the force main might be constricted due to heavy scale buildup. However, after a series of investigations/corrections supervised by Underwood, including testing with temporary flow meters, replacing an inoperable air relief valve on the force main, and clearing the pump discharge lines and check valves at the station, it was determined that the existing pumps can pass 650 gpm through the existing 8” CI force main.

As noted previously, the force main will require replacement in the near future to economically pass future buildout flows.

(8)

COST OPINIONS

For Contract 1, Underwood has updated the conceptual cost opinion based on the 60% design documents. The 60% design engineer’s opinion of probable project cost, including the design of Contracts 2-4, but not including business constructed sewers, is $9.27M. A breakdown is as follows:

Gravity Sewer south along Kimball Drive to Rte 3A serving Zone 1: $2.73M Gravity Sewer north along Kimball Drive and cross-country in Zone 2: $1.54M

Kimball Drive Pumping Station: $2.0M

Kimball Drive Pumping Station Force Main and Vaults: $0.75M

Martins Ferry Pumping Station Upgrades: $1.5M

Contribution to Pinnacle Hill Water Main Extension: $0.0M

Final Design of Contracts 2-4: $0.75M

TOTAL= $9.27M

Business constructed sewers along Rte 3A and Technology Drive: $3.24M

For a more detailed breakdown of Contract 1 costs, refer to the cost opinions contained in Appendix C.

FUNDING

The Town has the following available and proposed funding to put towards the Route 3A Utilities Expansion Project:

Available:

Existing Remaining Funding from HSC $1.2M

Existing Funding from 2019 Warrant Article $2.5M

Existing Funding from TIF ($450K per year, 2018-2019) $0.9M Existing Funding from TIF ($150K per year, 2020-2022) $0.45M

Subtotal $5.05M

Proposed:

Proposed Funding from 2022 Warrant Article $2.45M

Subtotal $2.45M

TOTAL $7.50M

Notes:

1. Existing 2019 Warrant Article TD Bank Loan payment is ~$300K for 10 years (2020- 2029).

(9)

2. Proposed 2022 Warrant Article assumes 20-yr bank loan at 2% or $143K/yr (2023-2042).

3. If the non-engineering portion of the 2019 Warrant Article loan ($1.25M) can be refinanced to a 20-yr bank loan at 2%, then an additional $1.2M can be borrowed with annual TIF income.

(10)

APPENDIX A

WORKPLAN DRAWINGS 1-3

(11)

N

C'

C

C"

D

E E"

Z' Z

Z"

Y

PS A

B

(12)

N

E'

E D

C

B

A

A"

A' PS

W

X

X'

X"

(13)

N

D'

D

(14)

APPENDIX C

COST OPINIONS

(15)

4/13/2021 Opinion of Probable Construction Cost: Hooksett Zone 1

Parcels

Served Cost

Total (TIF)

Cross Country

Town

Road Comments

Along Route 3A

Crossing

Route 3A Manholes

Parcel

Easements Segment Publicly

Constructed PS-3A via Kimball 17(8) 5000 50 28 1 $ 2,730,000.00

To Bass Pro/ Walmart 6(6) 1335 6 $ 957,750.00

To Regal 4(4) 1367 750 13 1 $ 1,170,950.00

To NH Oncology 1(1) 300 1 $ 150,000.00

Opinion of Probable Construction Cost: Hooksett Zone 2

Parcels

Served Cost

Total (TIF)

Cross Country

Town

Road Comments

Along Route 3A

Crossing

Route 3A Manholes

Parcel

Easements Segment Publicly

Constructed PS to 3A Quality 31(14) 1925 1200 40 18 2 $ 1,543,750.00

Privately

Constructed To Irving 5(5) 1300 7 1 $ 960,000.00

Future To Gosselin Ave 7(0) 1175 5 $ 1,250,000.00

Privately Constructed Total $ 3,238,700.00

Linear Feet of Sewer Number of:

Linear Feet of Sewer Number of:

Privately Constructed

(16)

Item Unit Costs

Cross Country Sewer LF $350.00

Town Road Sewer LF $450.00

Town Road Deep Sewer (>12ft) LF $550.00

US Route 3A Sewer LF $650.00

Sewer Crossing Route 3A LF $1,000.00

Manhole each $15,000.00

Bridge Crossing each $200,000.00

Parcel Easements each $10,000.00

Sewer Under the River LS $750,000.00

Item Unit Costs

Cross Country LF $250.00

Town Road LF $350.00

Route 3A LF $550.00

Hydrants each $5,000.00

Bridge Crossings each $200,000.00

Parcel Easements each $10,000.00

*Note: Water costs assume construction is concurrent with sewer. If constructed separately, costs will be higher.

Hooksett Rte 3A Sewer Construction Costs

Hooksett Water Main Construction Costs

(17)

4/9/2021

ITEM QUANTITY UNIT UNIT PRICE PROBABLE COST

General Requirements (12%) 1 LS $ 101,971.26 $102,000

SITE

Site Work Allowance 1 LS $25,000.00 $25,000

Excavation and Backfill 365 CY $15.00 $5,475

Sheeting and Dewatering Allowance 1 LS $200,000.00 $200,000

Parking Lot Subbase - Bank Run gravel, 12", compacted 185 CY $25.00 $4,625

Parking Lot Subbase - Crushed gravel, 6", compacted 93 CY $30.00 $2,775

Paved Parking Lot - 4" Bituminous Pavement 115 Ton $120.00 $13,800

Fence and Gates 320 LF $105.00 $33,600

Plantings Allowance 1 LS $10,000.00 $10,000

Misc Concrete Pads 1 LS $6,000.00 $6,000

Concrete and Geotechnical Testing Allowance 1 LS $10,000.00 $10,000

Restoration allowance 1 LS $5,000.00 $5,000

Precast Concrete Vault 2 EA $20,000.00 $40,000

BUILDING

CMU Walls 1406 SF $ 29.00 $40,774

Split Face block exterior 1116 SF $ 35.00 $39,060

Concrete Plank Roof 645 SF $ 25.00 $16,125

Roofing Insulation 645 SF $ 29.00 $18,705

Slabs 20 CY $ 750.00 $15,000

Footings 18.70 CY $ 750.00 $14,025

Foundations Walls 27.00 CY $ 1,000.00 $27,000

Wetwell separation wall 12'x7.5'x0.67' and Inlet box 4.2 CY $ 750.00 $3,150

Fill Concrete in Wetwell 6 CY $ 750.00 $4,500

Painting Allowance 1 LS $ 75,000.00 $75,000

Trim 1 LS $ 5,000.00 $5,000

Mandoors/Doors 5 EA $ 2,500.00 $12,500

Handrails, Beams, Miscellaneous Metals Allowance 1 LS $ 25,000.00 $25,000

Metal Stairs 1 LS $ 8,500.00 $8,500

Diamond plate 152 SF $ 75.00 $11,400

EQUIPMENT

Grinder 1 EA $ 40,000.00 $40,000

Sluice Gates 3 EA $ 8,000.00 $24,000

New Submersible Pumps 2 EA $ 11,500.00 $23,000

Aluminum floor hatches 2 EA $ 7,500.00 $15,000

Valve Pit Sump Pump 1 EA $ 1,500.00 $1,500

Sink and Dehumidifier 1 EA $ 1,000.00 $1,000

FE, Lockout/lagout kit, Knoxbox 1 LS $ 500.00 $500

Equipment Installation Allowance (35%) 1 LS $ 36,750.00 $36,750

PROCESS PIPING Inside PS

6" DI Pipe 100 LF $ 75.00 $7,500

6" 90 Degree Elbows 6 EA $ 500.00 $3,000

6" Plug Valves 4 EA $ 1,000.00 $4,000

6" Check Valves 3 EA $ 1,500.00 $4,500

6" Wyes 1 EA $ 750.00 $750

6" 45 degree elbows 1 EA $ 500.00 $500

Presure gauge assemblies 2 EA $ 500.00 $1,000

6" Bauer Fittings 2 EA $ 500.00 $1,000

Plumbing Allowance 1 LS $ 2,500.00 $2,500

Inside Vault 1

6" Pipe 12 LF $ 75.00 $900

6" 45 degree elbows 1 EA $ 500.00 $500

6' 90 degree elbows 2 EA $ 500.00 $1,000

6" Plug Valves 7 EA $ 1,500.00 $10,500

6" Wyes 3 EA $ 750.00 $2,250

6" Blind flange 2 EA $ 250.00 $500

6" Tees 1 EA $ 750.00 $750

Air/Vac Relief valve 1 EA $ 7,500.00 $7,500

Inside Vault 2

6" Pipe 6 LF $ 75.00 $450

6" 45 degree elbows 4 EA $ 500.00 $2,000

6" Plug Valves 6 EA $ 1,500.00 $9,000

6" Wyes 4 EA $ 750.00 $3,000

6" Blind flange 3 EA $ 250.00 $750

Process Piping Installation Allowance (35%) 1 LS $ 22,347.50 $22,348

YARD PIPING PS to Vault 1

6" DI Pipe 10 LF $ 150.00 $1,500

6" 45 deg bends 2 EA $ 500.00 $1,000

Vault 2 to SMH 1041

8" SDR 35 PVC 20 LF $ 300.00 $6,000

8" SDR 35 45 deg PVC bends 3 EA $ 500.00 $1,500

Core existing SMH 1 LS $ 2,500.00 $2,500

HVAC

Gas Unit Heaters 3 EA $ 7,500.00 $22,500

Ventilation Allowance 1 LS $ 40,000.00 $40,000

ELECTRICAL

HOOKSETT, NH KIMBALL DRIVE PUMP STATION 60% DESIGN OPINION OF PROBABLE PROJECT COST

(18)

4/9/2021

ITEM QUANTITY UNIT UNIT PRICE PROBABLE COST

General Requirements (12%) 1 LS $ 91,493.25 $91,000

SITE

Demolish Propane Tank, Gas Piping and Pads 1 LS $5,000.00 $5,000

Pump and Process Piping Demolition Allowance 1 LS $10,000.00 $10,000

Site Work Allowance 1 LS $5,000.00 $5,000

Excavation and Backfill of Wet Well 186 CY $15.00 $2,790

Sheeting and Dewatering Allowance 1 LS $200,000.00 $200,000

Wet Well Subbase - Crushed gravel, 12", compacted 20 CY $ 30.00 $600

Parking Lot Repairs - 4" Bituminous Pavement 46 Ton $ 120.00 $5,520

Remove and Replace Fence 1 LS $ 5,000.00 $5,000

Concrete and Geotechnical Testing Allowance 1 LS $ 2,500.00 $2,500

Restoration allowance 1 LS $ 5,000.00 $5,000

Precast Concrete Vault for Wet Well 1 EA $ 25,000.00 $25,000

Manhole risers and covers 3 EA $ 750.00 $2,250

Fill Concrete in Wetwell 6 CY $ 770.00 $4,620

Precast Concrete Bypass Pump Manhole 1 EA $ 15,000.00 $15,000

Bypass Pumping 2 MO $ 30,000.00 $60,000

BUILDING

Structural Demolition 1 LS $ 10,000.00 $10,000

CMU Wall Repair 1 LS $ 10,000.00 $10,000

Painting Allowance 1 LS $ 3,000.00 $3,000

Trim 1 LS $ 5,000.00 $5,000

New Double Door 1 EA $ 10,000.00 $10,000

Beams, Miscellaneous Metals Allowance 1 LS $ 20,000.00 $20,000

EQUIPMENT

Sluice Gates 2 EA $ 8,000.00 $16,000

New Submersible Pumps 2 EA $ 37,000.00 $74,000

Equipment Installation Allowance (35%) 1 LS $ 31,500.00 $31,500

PROCESS PIPING Inside PS

8" DI Pipe 17 LF $ 100.00 $1,700

8" 90 Degree Elbows/Flared Ends 4 EA $ 750.00 $3,000

8" Plug Valves 5 EA $ 1,500.00 $7,500

8" 45 Degree Elbows 2 EA $ 750.00 $1,500

8" Tees/Coupling 2 EA $ 1,000.00 $2,000

8" DI Cross 1 EA $ 1,500.00 $1,500

8"x6" Reducer 2 EA $ 750.00 $1,500

6" DI Pipe 8 LF $ 75.00 $600

6"x4" Increaser 2 EA $ 500.00 $1,000

6" 90 Degree Elbows 4 EA $ 500.00 $2,000

6" Plug Valves 2 EA $ 1,000.00 $2,000

6" Check Valves 2 EA $ 1,500.00 $3,000

6" Wyes 0 EA $ 750.00 $0

6" 45 degree elbows 0 EA $ 500.00 $0

Presure gauge assemblies 4 EA $ 500.00 $2,000

Inside Bypass Manhole

8" DI Pipe 3 LF $ 75.00 $225

8"x6" Wye 1 EA $ 1,000.00 $1,000

8" Plug Valves 1 EA $ 1,500.00 $1,500

6" 45 degree elbows 1 EA $ 500.00 $500

6" Plug Valves 1 EA $ 1,000.00 $1,000

6" Bauer Fitting 1 EA $ 500.00 $500

Process Piping Installation Allowance (35%) 1 LS $ 11,908.75 $11,909

YARD PIPING PS to Wet Well

8" DI Pipe 24 LF $ 300.00 $7,200

8" Solid Sleeve Couplings 2 EA $ 1,000.00 $2,000

Core existing Wet Well 4 LS $ 2,500.00 $10,000

At Bypass Pump Manhole

8" DI Piping 35 LF $ 300.00 $10,500

8" Solid Sleeve Couplings 4 EA $ 1,500.00 $6,000

ELECTRICAL

Allowance 1 LS $ 290,000.00 $290,000

SUBTOTAL $990,000

Contractor OH&P - 15% $149,000

Contingency - 10% $99,000

TOTAL PROBABLE CONSTRUCTION COST $1,238,000

Admin, Engineering and Construction Services $247,600

TOTAL PROJECT COSTS YEAR 2021 $1,486,000

Notes:

HOOKSETT, NH

MARTINS FERRY PUMP STATION UPGRADE 60% DESIGN OPINION OF PROBABLE PROJECT COST

References

Related documents

Silicon Valley San Francisco San Francisco Peninsula Austin Seattle Raleigh-Durham Salt Lake City Denver Boston Baltimore New York Washington DC San Diego Pittsburgh

cell type, page size, and block size, on system-level metrics such as performance, cost, and power consumption in various applications with different characteristics, e.g..

Make measurements on timeslot 0 [FREQUENCY] {Timeslot Off} [Enter] Activate the ORFS measurement (figure 25) [MEASURE] {GMSK Output RF The default setting measures spectrum

A process was developed to identify potential defects in previous layers of Selective Laser Melting (SLM) Powder Bed Fusion (PBF) 3D printed metal parts using a mid-IR thermal camera

The testimony of the State Department employee was brought to public hearings in hope that he turned out to be a communist, showing that even in a case potentially dealing

administrators, parents, teen advocates and pregnant students often do not know that such protections exist. Lack of enforcement by the Department of Education’s Office of Civil

The kitchen, the dining room, the hall and even the downstairs bedroom all have French doors that open onto a large patio terrace and then the rest of the garden is laid to lawn..

de Klerk, South Africa’s last leader under the apartheid regime, Mandela found a negotiation partner who shared his vision of a peaceful transition and showed the courage to