KONE MONOSPACE®, RELEASE 3.0
Copyright ©2012 KONE Corporation All rights reserved.
No part of the contents of this document may be copied, reproduced or transmitted in any form or by any means, or translated into another language or format, in whole or part, without prior written permission of KONE Corporation.
Authorization Notice
This publication is for informational purposes only. All persons participating in the installation and/or maintenance of KONE equipment and using these instructions must be qualified to perform such work, are required to have received equipment specific training as specified by KONE and must have KONE Corporation's authorization to install and maintain KONE equipment.
DISCLAIMER OF WARRANTIES AND LIABILITIES
KONE reserves the right at any time to alter the product design, specifications and procedures reflected in this document. NO STATEMENT CONTAINED IN THIS DOCUMENT IS TO BE CONSTRUED AS A WARRANTY OR CONDITION, EXPRESS OR IMPLIED, AS TO ANY PRODUCT, SPECIFICATION OR PROCEDURE, ITS MERCHANTABILITY OR FITNESS FOR ANY PARTICULAR PURPOSE OR QUALITY, OR AS A MODIFICATION OR REPRESENTATION OF THE TERMS OF ANY PURCHASE AGREEMENT.
KONE DISCLAIMS ANY LIABILITY RESULTING FROM OR IN CONNECTION WITH THE USE OR DISCLOSURE OF INFORMATION IN THIS DOCUMENT. KONE HAS NO LIABILITY FOR
TYPOGRAPHICAL OR OTHER ERRORS OR OMISSIONS CONTAINED IN THIS DOCUMENT OR ANYONE'S INTERPRETATION OF THE INSTRUCTIONS. THE USER OF THIS DOCUMENT ASSUMES ALL RISKS ASSOCIATED WITH THE USE OR DISCLOSURE OF THIS DOCUMENT. Confidentiality Notice
This proprietary and confidential document is provided to you only for purposes of installing and/or maintaining KONE products and it may not be used or its contents disclosed for any other purpose without KONE's prior written permission. Neither this document nor its contents may be copied or disclosed to third parties for any reason. KONE reserves the right to prosecute any breach of this obligation.
Trademark Notice
"KONE, MonoSpace, MiniSpace, EcoDisc, TranSys, Alta, KoneXion, KONE ECO3000 and all other product names are trademarks or registered trademarks of KONE Corporation in various countries."
TABLE OF CONTENTS
1 GENERAL . . . 8
1.1 Abbreviations. . . 8
1.2 Related and supplementary documents . . . 13
1.3 Daily installation order guide . . . 16
1.4 Customer experience . . . 19
1.5 Step numbering in the pictures . . . 19
1.6 Explanation for quality requirement table . . . 20
2 SAFETY . . . 21
2.1 General safety . . . 21
2.2 Recommended working postures and ergonomic methods . . . 25
2.3 Installation method safety . . . 26
2.4 Danger and personal protection signs. . . 28
3 SITE REQUIREMENTS AND TOOLS . . . 29
3.1 Site requirements . . . 29
3.2 Tools . . . 32
4 OFFLOADING AND DISTRIBUTION . . . 40
4.1 Offloading and distributing materials . . . 40
4.2 Offloading and transporting landing doors . . . 44
5 INSTALLING MAN RIDING HOIST AND OVERSPEED GOVERNOR . . . 45
5.1 Man riding hoist parts . . . 46
5.2 Work positioning equipment or restraint system . . . 48
5.3 Safety checks . . . 49
5.4 Transporting . . . 49
5.5 Routing the man riding hoist rope and cable. . . 50
5.6 Installing overspeed governor hanger . . . 51
5.7 Fixing the man riding hoist rope . . . 52
5.8 Lowering the man riding hoist hook to the pit . . . 53
5.9 Pit ladder . . . 53
5.10 Testing the hoist equipment. . . 54
6 PLUMBING . . . 55
6.1 Elevator shaft plumbing . . . 56
6.2 Plumbing table. . . 56
7 MECHANICAL INSTALLATION IN THE PIT . . . 58
7.1 Guide rail preparing . . . 59
7.2 Installing dividing beams (if applicable) . . . 61
7.3 Guide rail brackets . . . 61
7.4 Installing first guide rails . . . 63
7.5 Installing and aligning the first length of car guide rails (H 3500). . . 66
7.6 Installing counterweight buffer, OSG tension weight and OSG rope. . . 67
8 CAR INSTALLATION . . . 72
8.1 Contents of car packages . . . 73
8.2 Installing uprights. . . 74
8.3 Installing bottom beam (skewed type) . . . 76
8.4 Installing bottom beam (parallel type) . . . 79
8.5 Installing car floor . . . 81
8.6 Connecting ASGT rope to safety gear linkage . . . 84
8.7 Initial loading of counterweight . . . 85
8.8 Installing car walls . . . 88
8.9 Installing top beam . . . 98
8.10 Installing car top balustrade and car roof . . . 99
8.11 Tensioning overspeed governor rope . . . 103
9 ATTACHING HOIST TO CAR . . . 104
9.1 Installing swivel balustrade . . . 105
9.2 Attaching hoist and automatic safety gear trigger . . . 107
9.3 Testing ASGT . . . 108
9.4 Using ASGT. . . 109
10 CAR INTERIOR INSTALLATION . . . .110
10.1 Installing ceiling . . . .111
10.2 Mirrors and handrails. . . .115
10.3 Skirting . . . .119
10.4 Installing seat . . . 120
10.5 Installing buffer rail . . . 121
10.6 Installing tenant directory . . . 122
11 INSTALLING REST OF GUIDE RAILS AND BRACKETS . . . 123
11.1 Preparing for guide rail installation . . . 124
11.2 Installing third ring of guide rail brackets . . . 125
11.3 Preparing oil buffers . . . 128
11.4 Finalizing car installation . . . 129
11.5 Installing guide rails . . . 131
12 MECHANICAL INSTALLATION IN TOP OF ELEVATOR SHAFT . . . 133
12.1 Installing overspeed governor to final position . . . 134
12.2 Installing counterweight overspeed governor and tension weight . . . 135
12.3 Removing the extension rope . . . 136
12.4 Car sill . . . 137
12.5 Installing machine . . . 137
12.6 Installing rope hitches . . . 145
12.7 Parking plate . . . 146
13 LANDING DOOR INSTALLATION . . . 148
13.1 Installation order . . . 149
13.2 Installing landing sill . . . 150
13.3 Installing uprights and top parts. . . 154
13.4 Installing door panels. . . 158
13.5 Top track settings . . . 162
13.6 Installing panels and strips (front type version only) . . . 163
13.7 Installing landing toe guards . . . 167
14 CAR FRONT INSTALLATION . . . 168
14.1 Installing car front walls . . . 169
14.2 Finalizing car front installation . . . 171
14.3 Installing ceiling for steel roof . . . 172
15 INSTALLING CAR DOORS . . . 178
15.1 Unpacking and transporting the door operator . . . 179
15.2 Installation of Low duty door operator . . . 180
15.3 Installation of Mid and High duty door operator. . . 182
15.4 Installing finger protection list (window / glass doors) . . . 184
15.5 Door panel buffers . . . 184
15.6 Door panel fixings . . . 185
15.7 Door panel guides . . . 186
15.8 Installation of door panels . . . 187
15.9 Coupler . . . 189
15.10 Railing settings . . . 194
15.11 Emergency opening for car door lock . . . 197
15.12 Electrification . . . 198
15.13 Car door lock and contact measurements. . . 200
16 KONE SIGNALIZATION SYSTEM (KSS) INSTALLATION . . . 202
16.1 Hall indicator (KSH) and landing call station (KSL) . . . 203
16.2 Installing COP . . . 204
16.3 Hall display (KSJ) . . . 205
17 INSTALLING MAP . . . 206
17.1 Installing wall type MAP . . . 207
17.2 Installing door type MAP . . . 208
18 IDE300 (OPTIONAL) . . . 209
19 ELECTRIFICATION AT TOP OF THE ELEVATOR SHAFT (KDL16S) . . . 210
19.1 Overview (KDL16S). . . 212
19.2 Opening drive covers . . . 213
19.3 Installing SEP and drive panels, brake resistor and trunkings (KDL16S) . . . 214
19.4 Connecting machine cables (KDL16S) . . . 216
20 ELECTRIFICATION AT TOP OF THE ELEVATOR SHAFT (KDM40) . . . 218
20.1 Overview (KDM40) . . . 221
20.2 Installing SEP and drive panels, KDA module, brake resistor and trunkings (KDM40) . . . 222
20.3 Machine cables (KDM40) . . . 225
20.4 Cabling: MAP - KDA module, SEP - KDA module (KDM40) . . . 226
20.5 Cabling: KDA - drive module . . . 227
21 CABLES: SEP-MAP, MAIN SUPPLY, KRM . . . 228
21.1 Installing load weighing sensor, OSG cables and topmost lighting unit . . . 229
21.2 Wiring between SEP and MAP . . . 230
21.3 Connecting main supply cable to MAP . . . 231
21.4 Options . . . 231
21.5 Group connections . . . 233
22 INSTALLING TRAVELLING CABLES . . . 235
22.1 Installing travelling cables . . . 236
23 ELEVATOR SHAFT WIRING . . . 237
23.1 Shaft lighting . . . 238
23.2 Installing shaft wiring . . . 239
23.3 Wiring at the landings . . . 240
23.4 Installing segmented shaft network (if 16 served floors / group elevator) . . . 241
23.5 Installing support channel (optional) . . . 242
24 ELECTRIFICATION IN THE PIT . . . 243
24.1 Installing components under car . . . 244
24.2 Installing electrification under the car . . . 245
24.3 Installing pit electrification . . . 246
24.4 Installing pit toe guard . . . 247
25 CAR ELECTRIFICATION . . . 248
25.1 Magnet switches . . . 249
25.2 Installing car top connection box . . . 250
25.3 Installing electrification on the car roof (sliding guide shoes) . . . 252
25.4 Installing electrification on the car roof (roller guide shoes) . . . 253
25.5 Install the provision for lift announcer . . . 254
25.6 Install the intercom socket on the car roof. . . 254
25.7 Installing curtain of light . . . 255
25.8 Installing ramps and magnets (driving up). . . 260
25.9 Wiring of door operator and curtain of light (or photo cell) . . . 261
26 FINALIZING LANDING DOORS. . . 262
26.1 Uprights on slampost side (fire rated EI30/EI60/EI120-W doors) . . . 263
26.2 Uprights on non-slampost side . . . 264
26.3 Fire trims (frame version only). . . 267
26.4 Corner angles and wall gaps . . . 270
26.5 Top extension panel fire insulation (front version only) . . . 270
26.6 Carpet profile . . . 271
26.7 Quality check. . . 271
27 ROPING . . . 272
27.1 Lubrication of suspension ropes . . . 273
27.2 Roping principle (skewed car sling). . . 275
27.3 Roping principle (parallel car sling) . . . 276
27.4 Preparations . . . 277
27.5 Roping in the pit (skewed sling) . . . 278
27.6 Roping in the pit (parallel sling) . . . 279
27.7 Attaching compensation chain under the car (optional) . . . 279
27.8 Opening brakes for roping . . . 280
27.9 Roping at top of the elevator shaft . . . 281
27.10 Shortening the ropes . . . 282
27.11 Attaching compensation chain to counterweight . . . 284
27.12 Moving OSG rope in the large groove. . . 284
27.13 Installing brake release cable . . . 285
27.14 Testing manual brake release operation . . . 287
27.15 Dismantling man riding hoist from car . . . 288
27.16 Finalizing car installation . . . 289
28 COMMISSIONING . . . 293
28.1 Prerequisites . . . 294
28.2 Commissioning . . . 296
28.3 Final steps of commissioning . . . 298
28.4 Fine adjusting . . . 299
29 COMMISSIONING OF THE CAR DOOR . . . 300
29.1 Layout of drive 10 electronic assembly . . . 301
29.2 Layout of AMD drive 2 electronic assembly . . . 302
29.3 Testing factory adjusted door operation . . . 304
29.4 Adjusting closing force . . . 305
29.5 LEDs, drive 10. . . 306
29.6 DIP-switches, drive 10. . . 307
29.7 LEDs, drive 2 . . . 307
29.8 DIP-switches, drive 2. . . 309
30 FINAL STEPS AND ELEVATOR SHAFT CLEANING . . . 312
30.1 Correction of parameter settings . . . 313
30.2 Checking the levelling accuracy . . . 313
30.3 Volume adjustment (audible feedback) . . . 314
30.4 Group locking function . . . 314
30.5 Emergency lighting battery and KONE remote monitoring . . . 315
30.6 Emergency battery drive (EBD-A) test . . . 316
30.7 Testing the compensation chain . . . 317
30.8 Elevator shaft cleaning . . . 317
31 SAFETY INSPECTION. . . 318
31.1 Safety inspection . . . 318
32 MEASURING RIDE COMFORT . . . 319
33 HANDOVER . . . 320
33.1 Prerequisites . . . 320
33.2 QD-181.212, Quality control in installation – maintenance handover for KONE MonoSpace elevators . . . 320
34 FAULT FINDING . . . 321
34.1 Fault finding procedure . . . 321
34.2 Normal run. . . 322
34.3 Faults in drive system . . . 323
35 APPROVALS AND VERSION HISTORY . . . 324
36 FEEDBACK . . . 325
APPENDIX A. KDL drive related issues . . . 326
APPENDIX B. Balancing factors and loads . . . 328
APPENDIX C. Electrification panels, introduction . . . 335
APPENDIX D. Elevator shaft wiring with trunking . . . 350
APPENDIX F. Energy efficiency class A . . . 357
APPENDIX G. Ceiling types. . . . 359
APPENDIX H. Installing car floor, BB 1600 x DD 1400 . . . 363
APPENDIX I. Delivery above lowest floor . . . 366
1
GENERAL
The single and flexible man installation method described in this instruction is designed to ensure an efficient, trouble-free installation, whilst maintaining safe working practices. This is a general instruction which can be used for MonoSpace® release 3.0 elevators.
Some of the components may differ from those that are described in this instruction. In these cases refer to the delivery documents or component level AM instructions. Follow this instruction. If it is necessary to deviate from the method a carefully designed, risk assessed, method statement must first be obtained from your front line management.
All installation tasks must be controlled and verified during installation by filling in the QD-181.211 which is used as a checklist before:
– commissioning – safety inspection
– handover to maintenance and customer
1.1
Abbreviations
1.1.1 General
Abbreviation Term Definition
FFL finished floor level
CL central line
DBG distance between guide rails
A marking of entrance e.g. A-door/side usually main door, always MAP side B marking of entrance e.g. B-door/side
C marking of entrance e.g. C-door/side opposite main door D marking of entrance e.g. D-door/side
A B1 B2 C2 D2 D1 C1 1078299.wmf
1.1.2 Elevator shaft and car
NOTE: For more information on following cases, see AM-01.01.256:
- low pit devices
- low headroom, SH 3320 mm
- small car, BB 900 mm or DD 1000 mm
Abbreviation Term Unit Definition
elevator shaft
SH headroom height mm the vertical distance between the finished floor at the highest level served and the roof of the elevator shaft
PH pit depth mm that part of the elevator shaft located under the
lowest landing level served by the elevator
WW elevator shaft width mm the horizontal distance between the inner surfaces of the elevator shaft walls measured parallel to the car width
WD elevator shaft
depth
mm the horizontal distance between the inner surfaces of the elevator shaft walls measured parallel to the car depth
H travel height mm sum of interfloor distances
HF floor to floor
distance
mm given as a minimum
car
CH car clear height mm
BB car clear width mm
DD car clear depth mm
Elevator shaft vertical dimensions
Frame doors Front doors
HH CH SH H HF PH HR 1007040.wmf HB HB HB SH HH CH HH PH HF H HA HA 1007041.wmf
1.1.3 Landing/front and frame door
Elevator shaft horizontal dimensions, front door
Abbreviation Term Unit Definition
LW from clear opening to elevator shaft wall mm
LW1 from clear opening to elevator shaft wall mm
LD side wall depth mm
LR door raw opening width mm front door case LR=WW
HR door raw opening height mm
HA front door lintel height mm
HB front door extension height mm
LL door clear opening width mm
HH door clear opening height mm
1.1.4 Additional abbreviations
MAP = maintenance access panel SEP = shaft electrification panel
Elevator shaft horizontal dimensions, frame door
Abbreviation Term Unit Definition
FW front wall width mm
FW1 front wall width mm
FD front wall depth mm
LR door raw opening width mm LR=WW-2*FW or WW-(FW+FW1)
HR door raw opening height mm
LL door clear opening width mm
HH door clear opening height mm
1.2
Related and supplementary documents
In addition to this manual, you can find safety, quality, process and product-related information in the following documents:
Elevator level:
– AM-01.01.256, KONE MonoSpace, Release 3.0: Small car, low pit and low headroom solutions and FuRe
– Shaft vane diagrams, layout drawings, wiring diagrams
– AS-01.01.030 Rescue instruction for KONE MonoSpace type elevator
Safety:
– AM-01.03.001 Preventing falls from height when working on elevators, escalators and building doors
– AM-01.03.002 Take 5 - Electrical safety when working on elevators, escalators and autowalks
– AM-01.03.003 Take 2 - double security safety practice when using hoists for man riding purposes
– AM-01.03.010 Safe working in elevator shaft and machine room areas – AM-01.05.016 Installing light entrance protection (LEP)
– Man riding hoist manual
Quality & Environment:
– QD-181.211 Quality Document - KONE MonoSpace Elevators – QD-181.212 Quality control in installation - maintenance handover – AM-01.01.190 Environmental excellence - Installation
– AM-01.01.257, Visual inspection - quality control of the car interior and landings – AM-01.05.014 DT-5 user instructions
– AS-12.02.001 Instruction for handling electrostatic-discharge-sensitive-devices on site
Productivity:
– AM-01.01.260 5S guide book - Eliminating unnecessary actions in elevator installation – AM-01.01.261 5S advanced instructions - Eliminating unnecessary actions in elevator
installation
Car & Sling:
– AM-06.06.030 Hermes Car
– AM-06.12.010 Global accessories, suspended ceilings and lighting – AM-07.04.040 Progressive type safety gear AQ32
– AM-07.04.042 Progressive type safety gear CSGB-01
– AM-08.06.002 Roller guides; RG80, RG100, RG125 and RG200
Ropes:
– AM-09.01.006 Lubrication of suspension ropes – AS-01.01.010 Lubricant recommendation instruction
Doors:
– AM-03.12.064 Automatic landing door (AMDLY) – AM-03.12.066 Automatic landing door (AMDL) – AM-03.12.067 Automatic car door AMDC – AM-03.12.094 KES201 landing door
– AM-03.17.011 Formula systems slimscreen curtain of light FCU 0735 and FZU 1047 3D (for automatic car door AMD)
– AM-03.35.020 Electrical installation, commissioning, troubleshooting instruction, AMD drive 2 + car door operator
– AM-03.35.023 Fine tuning of AMD drive 2 car door operator
– AM-03.35.024 Advanced modular door, Drive 1.5 car door operator electronic
– AM-03.35.027 Electrical Installation, Commissioning and Troubleshooting Instruction - AMD Drive 10 Car Door Operator
– AM-03.90.111 ReNova slim car door AMDSC3 – AM-03.90.112 ReNova slim car door AMDSC4 – AM-03.90.113 ReNova slim car door AMDSC6 – AM-03.90.121 ReNova slim landing door
Machinery:
– AM-04.05.056 Hoisting Machine NMX07 / NMX11
Electrification & Commissioning:
– AM-10.60.028 Elevator shaft bundle (cables and connection boxes without trunking) – AM-11.65.038 ECB-1 single line ReGenerative unit
– AM-11.65.042 KDM drive for MonoSpace® and MonoSpace® Special: Installation, commissioning and safety inspection
– AM-11.65.045 Machine-Room-Less Elevators with KDL16S drive, Installing, Commissioning and Safety Inspection
– AM-12.20.005 KONE Signalisation System (KSS) installation
– AM-12.20.017 KONE Polaris™ 500 and 800 Destination Control Systems (DCS) – AM-13.20.018 KONE IDE300™ - Integration of doors and elevator
– AM-13.25.007 KONE remote monitoring (KRM) for elevators – 994525D01 KDM Parameter list (delivered with drive)
– 994525D02 KDM Diagnostic Code List – 994525D03 KDM Parameter Guide
– 972483D01 KDL16 Parameter Table (delivered with drive) – 972484D01 KDL16 Parameter Guide
– 972485D01 KDL16 Diagnostic Codes – 813138 Global LCE Fault Codes – 812281 F2K Remote Control Boards
– 813131 User Interface Menu Instructions for LCE – 818442 PIN Code Feature
– 827328 Configuration switch instruction
Product-related maintenance instructions and spare parts lists:
Elevator level:
– AS-01.01.039 General fault finding
– AS-01.01.076 Fault finding instruction for KONE MonoSpace 3.0
Doors:
– AS-03.12.036 Maintenance instruction for AMD doors
– ASG-03.12.036 Preventive maintenance instruction for AMD doors – AR-03.12.037 Spare parts manual for AMD car door
– AR-03.12.076 Spare parts manual for AMD landing door
Machinery:
– AS-04.06.005 Replacing NMX07 and NMX11 hoisting machine in machine-room-less elevator
– AR-04.06.015 Spare parts NMX07 – AR-04.06.016 Spare Parts NMX11
– ASG-04.06.003 Preventive maintenance for NMX07 and NMX11 machines – AS-04.07.005 Replacing encoders of NMX07 and NMX11
– AS-04.08.039 Replacing the brakes of hoisting machines NMX07 and NMX11 – AS-04.08.092 User instruction for electrical brake opening tool KM872759G01
Car & Sling:
– AS-07.03.016 Repairing Hermes car sling
Ropes:
– AS-01.01.010 Lubricant recommendation instruction
– AS-09.01.005 Semi-automatic relubrication for suspension ropes: maintenance instructions
– AS-09.05.001 Lubricating the suspension ropes
Electrification:
– AS-10.22.006 Repair instruction for KONE MonoSpace®, MonoSpace® 1.6 m/s and TranSys™ shaft electrification panels
– AR-10.22.006 Spare parts manual for KONE MonoSpace electrification
– AS-11.65.040 Repair instruction for KDM drive system in KONE MonoSpace Special – AR-11.65.040 Spare parts manual for KDM drive system
– AS-11.65.052 Repairing KDL16S
1.3
Daily installation order guide
1.3.1 Single man schedule
The table below indicates phases of the installation.
Elevator Prerequisites to meet the schedule
Elevator shaft
5 floors, 12 m travel, single side entrances
Complete on time / error free delivery Door type AMDL1 or AMDL2, frame non fire
rated, installation with expander bolts for guide rails and landing doors
Installation site fulfilling the 5 Site Absolutes
Car interior
One handrail and one mirror Fitter has installed 5-8 units prior. Working within allocated working hours.
Day Action
1 Arrival at site, transporting tools, receiving delivery. Installing man riding hoist, installing overspeed governor. Setting the lasers.
Plumbing and establishing plumbing table.
Installing first guide rail brackets and pit ladder, preparing counterweight frame. Installing and aligning first lengths of guide rails and brackets. Installing buffers and counterweight frame.
Installing sling and installing overspeed governor. 2 Installing car and initial loading of the counterweight.
Waste material handling.
Installing automatic safety gear trigger.
Attaching man riding hoist to car and installing third ring of guide rail brackets. Installing car interior.
Installing working light to the car roof.
Installing and aligning guide rails and brackets to intermediate floors. 3 Installing topmost floor lengths of guide rails and brackets.
Transferring the overspeed governor to its final position and setting the rope to final length.
Installing car sill.
Installing machine and rope fixings. Installing landing door sill brackets.
1.3.2 Flexible man schedule
The table below indicates in which phases of the installation two men are required and when the installation can be undertaking by a single man.
4 Installing landing doors.
Installing car front wall and car door. Installing last landing door.
Installing trunking and elevator shaft lighting. Waste material handling.
5 Installing MAP, SEP and drive panels.
Installing elevator shaft top wiring and brake lever.
Installing travelling cables, elevator shaft wiring and signalization. 6 Installing car wiring and setting positioning system and ramps.
Installing pit wiring. Waste material handling.
Installing car electrification and car operating panel.
7 Placing filler weights inside the car for balancing operations, roping. Closing the brake, re-checking the brake lever operation, safety checks, commissioning and removal of tools.
Balancing and final steps.
Cleaning down the elevator shaft and disposal of waste materials. Safety inspection (assistance with test weights).
Day Action Task split
fitter 1 / 2
1 Arrival at site, transporting tools, receiving delivery. 1 2 Installing the man riding hoist, installing the overspeed governor. 1 2
Setting the plumbing jig. 2
Cleaning guide rails and mounting fish plates. 1
Plumbing and establishing plumbing table. 2
Installing first guide rail brackets and pit ladder, preparing counterweight frame.
1 Installing and aligning first lengths of guide rails and brackets.
Installing buffers and counterweight frame.
1 2
Installing sling and installing overspeed governor for single man working.
1 2
2 Installing the car and initial loading of the counterweight. 1 2
Waste material handling. 1
Installing the automatic safety gear trigger. 1
Attaching the man riding hoist to car and installing the third ring of guide rail brackets.
2
Installing the car interior. 1
Installing and aligning guide rails and brackets to intermediate floors.
1
Preparing the car and counterweight guide rail brackets. 2
Preparing machine and landing door brackets 2
3 Installing top most floor lengths of guide rails and brackets. 1 Transferring the overspeed governor to final position and setting the rope to final length.
1
Installing the pulley beam and car sill. 1
Installing the machine and rope fixings. 1
Installing the landing door sill brackets. 1
4 Installing the trunking and elevator shaft lighting 1
Installing the landing doors, not finally adjusted. 1
Installing the car front wall and car door. 1
Installing the last landing door. 1
Waste material handling. 1
5 Final adjustment of the landing doors. 1
Installing the MAP, SEP and drive panels. 1
Installing the elevator shaft top wiring and brake lever. 1 Installing the travelling cables, shaft wiring and signalization. 1 6 Installing car wiring and setting positioning system and ramps. 1
Installing the pit wiring. 1
Waste material handling. 1
Installing the car electrification and car operating panel. 1 7 Placing filler weights inside the car for balancing operations, roping. 1
Closing of the brake and re-check of the brake lever operation, safety checks, commissioning and removal of tools.
1
Balancing and final steps. 1
Cleaning down the elevator shaft and disposal of waste materials. 1
Safety inspection (assistance with test weights). 1 (2)
Day Action Task split
1.4
Customer experience
The focus of your work must always be customer satisfaction. To reach and exceed the customers’ expectations, be polite, constructive and co-operative, and communicate clearly. Remember that for customers, you represent KONE, so ensure that you handle or at least communicate all customer requests and feedback to the correct persons.
For more information on how to deliver best-in-class customer experiences through behavior and communication, see the KONE Ambassador program in KONE intranet (search for Ambassador) or contact your supervisor.
1.5
Step numbering in the pictures
1. When reading this instruction, note that the numbers in the pictures refer to the step numbers. 2 3 1
1. Xxxxxxxxxx
2. Xxxxxx
3. Xxxxxxxx
1082830.wmf1.6
Explanation for quality requirement table
Quality Requirements:
Required mandatory outcomes upon completion of the chapter.
MAIN hazards identified. Other hazards are described
within each chapter.
!!! CAUTION - issues that affect reliability !!!
This area highlights the negative effects of failing to meet the
quality requirements. SORT STABILIZE SHINE STANDARDIZE SUSTAIN Reminder of 5S standards.
Method tools needed:
Tools from the installation kit. Hand tools needed:
Tools from the tool kit. 5S Installation Progress Report
Progressive reminder to complete this document.
QD-181.211
Progressive reminder to complete this document.
2
SAFETY
When you are working on your own ensure that: – someone in authority knows where you are – regular checks are made to ensure your safety
If you have any doubts about Single Man Working on your specific job site, discuss them with your supervisor.
Where required, discuss method statements and risk assessments with your supervisor and colleagues before starting work.
Work safely and follow local codes and agreed practices.
Certain components are from their characteristics, weight and size not suitable to be installed by Single Man Working methods. These components are highlighted in the installation chapter section, as an example car glass rear wall.
2.1
General safety
The words WARNING and CAUTION are used to highlight possible hazardous situations to persons or equipment as follows:
2.1.1 Safety instructions
Following safety instructions should be referred to in conjunction with this installation instruction:
– AM-01.03.001 Preventing falls from height when working on elevators, escalators and building doors
– AM-01.03.002 Take 5 - Electrical safety when working on elevators
– AM-01.03.003 Take 2 - Double security safety practice when using hoists for man riding purposes
– AM-01.03.010 Safe working in elevator shaft and machine room areas – Man riding hoist manual
WARNING: This is to warn about serious safety hazards.
CAUTION: This is to warn about damage to equipment which may also involve a safety
NOTE: Installation work must only be carried out by competent and qualified personnel.
2.1.2 Double security safety practise when using hoists for man riding purposes
Refer to AM-01.03.003 - Take 2 Double security safety practice when using hoists for man riding purposes.
To ensure your and your co-workers personal safety you must always be protected from falling by two independent devices.
It is not permitted to drive or to be on top of the suspended platform without double security: 1. Safety gear
The safety gear must be connected to the overspeed governor and automatic safety gear trigger.
2. Man riding hoist
The man riding hoist must be correctly attached to the car sling using the fittings provided with the hoist.
It is not permitted to disconnect the man riding hoist or remove the hook from the car until it has been double secured:
1. Safety gear
The car must be secured on the safety gear using the automatic safety gear trigger. 2. Chains
The parking chain(s) must secure the car to the agreed anchorage point in the shaft.
2.1.3 Electrical working safety
Familiarise yourself with the safety instruction AM-01.03.002 and follow it at all times. Refer to AM-01.03.002 "Take 5 - Electrical Safety when Working on Elevators".
The following 5 steps must be taken in the specified order unless there are essential reasons for doing otherwise:
1. Disconnect the power supply completely. 2. Secure it against re-connection.
3. Verify that the installation is de-energised.
4. Check requirements for earthing in special circumstances.
(This operation may only be carried out by qualified personnel in co-operation with the person responsible for the building electrification who must ensure that the technique can be safely employed in this situation.)
2.1.4 General safety precautions
Safety precautions Note
Follow your national lift codes and other safety related regulations.
In case of conflict between the code and this instruction, rely on your code.
The local safety codes and rules must be obeyed at all times.
Refer to your local procedures for the type of entrance protection required.
Follow this instruction. Do not skip any step, otherwise there may be a potentially
dangerous situation which you have not considered.
Warning signs highlight possible hazards. (See page 28.)
ENSURE THAT ELECTRICAL
EQUIPMENT AND CONDUCTORS ARE SAFELY DE-ENERGISED BEFORE WORKING ON THEM.
A locking off system for main electric supply isolator or other system (for example fuse removal, locking and tagging system, etc.) must be agreed with main contractor before installation commences.
Do not connect or disconnect any connectors when the power is ON. Personal safety equipment must be available and used as required.
Refer to the list of Personal safety items on page 28.
Use only approved manual handling techniques.
Do not work at different levels within the same / adjacent elevator shaft enclosures. The rust protection must be removed from
the rails. Otherwise, the safety gear will not operate correctly.
Refer to page 59 for specific safety notes.
Prevent falls from height:
1. Identify all possible fall hazards. 2. Remove the fall hazards, if possible.
3. If it is not possible to remove a fall hazard, then reduce the risk of fall using fall prevention methods.
4. If it is not possible to protect against a fall hazard using fall prevention methods, then use fall arrest equipment but only when verified through specific risk assessment. The provision of suitable rescue equipment, instruction and training must be available to ensure the timely rescue in case of a fall.
CAUTION: Safety harnesses with
lanyards.
When your safety harness is not secured to a life line or other approved anchorage point, ensure the lanyard does not cause a catching or tripping hazard.
If applicable, safety harnesses must be used in accordance with your national codes.
Always position the car at a safe level relative to landing before accessing or egressing. NEVER WORK UNDER A SUSPENDED
LOAD!
Ensure that the lifting equipment is correctly rated for the task and in good condition. Always use the hoist in accordance with your local regulations.
Refer to AM-01.03.003 Take 2 - safe working when using hoists for man riding purposes.
Additional safeguards ensure that there is no unwanted movement of the car due to hoist control or other failure.
Take care handling waste materials in accordance with your local regulations.
2.2
Recommended working postures and ergonomic methods
These recommended working postures and ergonomic methods has been identified to contribute a better workplace and your well-being.
NOTE: If work is being carried out by kneeling, with bent back/legs or with hands elevated
above chest or object is further than length of forearms, ensure to limit time of exposure and alternate the working postures. Make sure that the working area is un-obstructed and not hindering you.
Working height Adjust
height of working to enable your hands to be within the vertical area of chest and belt buckle.
Working distance Adjust working distance to enable the object to be within length of forearms. Lifting
Focus on the lift, even if the lifted object is light! 1. Go close to the lifted object
2. Use your legs 3. Keep your back untwisted and straight 4. Keep both feet on the same lane
Carrying
1. Keep the lifted object as close to the body as possible
2. Keep your back untwisted and straight
Loading of transport cart
Slide the component onto the KONE transport cart instead of lifting it.
Moving heavy objects without a handle
If the object doesn't contain a handle, push/ slide the object instead of pulling.
2.3
Installation method safety
Special feature Note
The car is used as the working platform. Do not drive on the car roof until the balustrade is fitted and the safety gear is connected.
The man riding hoist is positioned on the car roof and an additional securing rope is attached to the overspeed governor lifting eye.
The man riding hoist is used to move the car during the initial stages of the
installation.
The man riding hoist and overspeed governor are suspended from lifting eyes in top of the elevator shaft.
The elevator’s own overspeed governor and safety gear are used during installation.
Refer to AM-01.03.003 Take 2.
The automatic safety gear trigger engages the safety gear automatically in the event of hoist rope failure or manually when it is necessary to secure the car.
The parking chain is used to secure the car to a car guide rail bracket whenever the hoist hook is disconnected from the car or when you are working under the car in the pit.
Always keep the chain as tight as possible.
When working from the car roof you must always park the car using both the parking
chain and the safety gear before
disconnecting the hoist hook.
At certain times the hoist hook is removed from the car whilst it is still used as a working platform. During these operations the safety gear must be engaged and the
parking chain must be used.
Emergency descent from the car roof. If there is a power failure on site, it is always possible to move the car to a lower landing level using the brake releasing lever. For emergency descent refer to the man riding hoist handbook.
Guide rails are lifted using the car. Guide rails are fitted in the conventional way using the sliding clamp to lift each rail.
Blocking device
After roping, whenever working on the
traction or suspension elements the blocking device must be used.
WARNING: The blocking device is not
strong enough on its own to support the weight of the car. In situations where the car is not supported by the ropes it must be secured using the parking chain and safety gear.
When moving the car on manual brake release, do not let it overspeed. Check speed indication LEDs on LOP-CB board.
Do not leave the brake open. (Try to limit the motor rotation to 1 second intervals.)
If you are working on your own, ensure that someone in charge knows where you are and that regular checks are made to ensure your safety.
If you have any doubts about single man working on a specific site, discuss with your supervisor.
2.4
Danger and personal protection signs
Safety gloves, overall, safety shoes with ankle protection, safety helmet, safety goggles, dust mask, hearing protection and safety harness are provided for your personal protection. USE THEM AS REQUIRED.
Danger signs
Danger Sign Danger Sign Danger Sign
Electric shock Risk of falling Magnetic field
Risk of fire Corrosion
Dermatological risk
Entry prohibited
General hazard warning
Suspended load Pinching hazard
Personal protection signs
Mandatory Sign Mandatory Sign Mandatory Sign
Safety helmet Overall Dust mask
Hearing protection Safety shoes with ankle protection Safety gloves Rubber gloves Fall prevention equipment
Safety goggles Fall prevention
measures Man riding hoist
mandatory inspection
3
SITE REQUIREMENTS AND TOOLS
THE FIVE SITE ABSOLUTES
1. The elevator shaft is clean and dry before installation work starts.
2. The shaft is constructed according to KONE layout drawings and the shaft openings are sealed for safety.
3. The lifting eyes and the ventilation ducts specified by KONE are in place. 4. 3-phase power supply for elevator and installation hoisting is provided.
5. A 30 m2 storage space is provided on the ground floor close to the shaft and the access ways to the shaft are clear.
3.1
Site requirements
Before installation can start, ensure that the following things have been done: – The site must be 100 % ready.
– Transport routes must be defined and agreed as close as possible to the elevator shaft. – Elevator shaft tolerances must be checked by the supervisor.
– Delivery must be complete and on site.
– Installation start date must be agreed with the customer.
– When starting the installation and the wall mounted MAP is delivered, ask the builder to finalise the wall at the location of the MAP. This ensures that the wall mounted MAP can be installed without re-adjustment.
– A locking off system for main electric supply isolator, or other system (for example fuse removal, locking and tagging system, etc.), must be agreed with main contractor before installation commences. Refer to AM-01.03.002 Take 5.
– Installation tools must be available on site. – Recommended hand tools must be available. – Personal safety equipment must be available.
– The site inspection should take place minimum one week before the installation is scheduled to start, in accordance to the delivery process milestones “835”.
Requirement Note
Adequate lighting and 3 -phase power supply must be temporary or permanent positioned for both the elevator and the man riding hoist according to the layout drawing.
Where required, the elevator shaft lighting can be lowered from the top floor and temporarily secured to the entrance protection horizontal stands.
Lifting eyes must be positioned in the top of the elevator shaft according to the layout drawing and marked with the safe working loads.
If the lifting eye is screw type, the lifting eye must be securely fastened to avoid
untightening. Right handed elevator:
1. Lifting eye for man riding hoist
(2000 kg)
2. Lifting eye for machine (1500 kg) 3. Lifting eye for overspeed governor
(1500 kg)
• front side if skewed sling • rear side if parallel sling 4. Lifting eye for KDM drive
(if applicable, 1500 kg) Typical lifting eye construction:
Maximum diameter of hook section 18 mm.
Finished floor marks must be on each landing.
For group elevators setting out reference lines must be marked on the lowest common floor area.
Elevator shaft and pit must be cleaned and pit waterproofed.
The elevator shaft must be watertight. C-inserts (if used) must be correctly positioned and cleaned.
Suitable material storage areas must be agreed with builder, adjacent to the elevator shaft.
Materials should be stored within 20 metres or close range from the elevator shaft. Suitable storage area must be provided for installation tools.
Clear, unobstructed access routes to at least one entrance, at or next to the ground floor, for long or bulky items, (guide rails, car components, doors and so on), must be defined and clear of obstructions.
WW WD 2 1 3 1077488.wmf 4 3 max 65
!
1078300.wmfALL landings must be protected with full height entrance protection according to the local safety codes and regulations.
Fit temporary barriers around the top and bottom landing entrances wherever
temporary protection is removed or landing doors must remain open.
The entrance protection must be
imperforate. See AM-01.05.016, Installing
light entrance protection (LEP).
The bars must be secured so that they cannot be moved unintentionally horizontally or vertically.
Elevator shaft dimensions and tolerances must be in accordance with layout drawings. Suitable provision for disposal of waste
materials must be available.
According to the local requirements. Appropriate fixing points for safety
harnesses must be available.
Requirement Note
3.2
Tools
MonoSpace® tools Pcs. Tool Pcs. Tool 2 or 3 Support bars Drawing number: 7161613 support bars are needed if plumbing jig is used.
1 1 1
Automatic safety gear trigger Drawing number: 803140G01 Brake wire rope bracket: Drawing number: 803144G01 Brake wire rope:
Drawing number: 772277G01
1 Rope fixing plate
Drawing number: 803146
1 Telescopic pipe, Bahco AP-5M Drawing number: KM823588H04
1 Parking chain 2 m, 1500 kg Drawing number: 266828
2 Plumbing supports (pit) Drawing number: 716177G01
1 Guide rail lifting clamp for guide rails T70, T82, T89
Drawing number: 716165G01
2 2
Guide rail securing to car roof Drawing number: 773444G01 Guide rail lifting pocket Drawing number: 762396G01 1082712.wmf 1007069.wmf 1027222.wmf 1010242.wmf 1007070.wmf 1007072.wmf 1007079.wmf P17000195.wmf
1 Counterweight guide rail positioning tool Drawing number: 716175G01
1 Unwinding device
Drawing number: 504610G01
1 Hoist test bracket, max. load 2000 kg Drawing number: 716157G01
1 Counterweight guide rail alignment tool Drawing number: 716180G01 4 Eyebolt RUD RS-M12 Drawing number: 266824 2 Eyebolt RUD RS-M8 Drawing number: 934990 1 1 1 Hoisting chains: Extension chain 1.5 m, 500 kg Drawing number: 266827 Shortenable chain 2 x 1.5 m, 500 kg Drawing number: 266826
Car/door installation chain 2 x 0.5 m, 500 kg Drawing number: 266825 4 Eyebolt RUD RS-M6 Drawing number: 50300433 3 Shackle 12 mm tap, 1500 kg Drawing number: 754257 MonoSpace® tools Pcs. Tool Pcs. Tool 1007076.wmf 1007084.wmf 1007074.wmf 1031357.wmf 1031357.wmf 1007078.wmf 1031357.wmf 1007081.wmf
1 Rope grip for rope reeler securing, 9 mm Drawing number: 754257
1 Shackle for car roof rope reeler securing, 8 mm tap, 350 kg
Drawing number: 754257
1 Plumbing jig (optional, see APPENDIX
E. Plumbing jig)
Drawing number: 754257
2 Plumbing weight (optional, if plumbing jig is used)
Drawing number: 50077610G01
Other installation tools
Pcs. Tool Pcs. Tool
1 Guide rail transportation tool Drawing number: KM971149G01
1 or 2
Swivel balustrade
2 sets in case of TTC (1 set = 2 balustrade parts, upper and lower). Drawing number: KM50026878G02 MonoSpace® tools Pcs. Tool Pcs. Tool 1007083.wmf 1007082.wmf 1007071.wmf 1080362.wmf 1060909.wmf 1078014.wmf
1 Man riding hoist + pulleys, 750 kg / 1000 kg capacity.
See hoist equipment parts on page 46.
1 Manual chain hoist, capacity 500 kg (Yale compact 500 or equivalent). A = 289 mm
H = 190 mm
1 Overspeed governor extension rope Drawing number: 772277G05
1 set Machine transporting wheels Drawing number: 715802
1 Elastic grip L = 1 m
1 Site trolley
Drawing number: 589519
1 Overspeed governor hanger kit including:
– OSG hanger assembly – Pulley bracket assembly – Climbing rope
Drawing number 823588G01
Other installation tools
Pcs. Tool Pcs. Tool 1007086.wmf 1033403.wmf 1007090.wmf 1031365.wmf 1078301.wmf 1010244.wmf
1 Battery tool
Cable (Drawing number: 859326) and 9V battery (supplied locally)
Used with construction-time power supply.
2 Transportation tool (used with transportation wheels and axle) Drawing number: 854900D01
1 Rope clamp
Drawing number: KM839679G01
2 Hilti PMP34 / PMP45 point laser
2 Target plate 1 Carpenters ruler
1 Laser alignment tool
Drawing number: 50077847G01
2 Levelling plate
Other installation tools
Pcs. Tool Pcs. Tool 1039959-1.wmf 1078366.wmf M8x50 4 x 1060910.wmf 1078890.wmf +1 0 +2 0 +3 0 +1 0 +2 0 +3 0 H I L T I PM P 34 1080768.wmf 1048308.wmf
1 Work stool Drawing number: 265173 1 Telescopic ramps Drawing number: KM966635 1 Rope socket 6-8 Drawing number: KM971423G01
1 Electrostatic discharge (ESD) kit
Needed to protect the components from damage if any PC boards are replaced. (KM857505)
2 Installation jig
Drawing number: KM756128 Included in AMD door delivery
2 Plate for ramps
Drawing number: KM50077171
Other installation tools
Pcs. Tool Pcs. Tool 1073236.wmf 1077935.wmf 1060911.wmf 1072347.wmf 1073260.wmf 1082413.wmf
3.2.1 Hand tools (recommended)
Tool Tool
Carpenter’s pencil Lockable tool box for the normal hand tools
Tape measure, L 3.0 m Carpenter’s ruler
Multimeter, protected against high voltage Plastic tuning screw driver
Hammer drilling machine, with dust collector Adjustable spanner, L 200 - (250) mm Cordless drilling machine; with adjustable torque
for car and landing doors and car installation. One extra accumulator (battery), bit cassette including Phillips head and flat heads in different sizes, drill bit cassette (sizes 1.5 - 10 mm). Phillips head bit 150 - 200 mm.
Drill bits:
6 mm (light fitting, pit stop switches) 8 mm (trunking)
10 mm (pit ladder, travelling cable wall fixing) 12 mm L (150) (Hilti, for cutting through reinforcing bars)
Tool for concrete inserts Crow bar, L 500- 700 mm
Spanners:
U end and ring end.
Sizes 10, 11, 12, 13, 15, 16, 17, 18, 19 mm. Min. thickness for 16 - 19 mm spanners is 5 mm.
Screwdrivers:
Flat headed 5 mm L 200 mm.
Electrical, isolated 2.5-3 mm head L150-200mm Phillips head: Standard size L 200 mm.
Ratchet 1/2" drive Ratchet 1/4" drive small model
Extension L 200 mm 1/2" Extension 1/4", L 40 - 150 mm
Sockets (deep) 1/2", 13, 15, 16, 17, 18, 19 mm Sockets 1/4" drive, 10, 11, 12, 13 mm Carpenter’s hammer, 6 Oz. rubber handle,
“shock absorbent”
Sledge hammer, 1000 gram Hammer side flat, end drop forged
Vice grip/polie grip: L 150 mm and L 250 mm Magnetic spirit levels, lengths 700 and 1500 mm Engineers squares:
300 x 150 - 200 mm and 750 x 350 mm
Rivet pliers, replaceable head to cover the different rivet sizes
Side cutter, isolated handles (L 170 mm) Long nose pliers, medium model (L 170 mm) File for guide rail joints, normal model Rope cutting pliers, 8 mm
Knife Hacksaw, standard model
Disc cutter, disc > 125 mm 4 pcs plumbing weights, max. 10 kg/each (diameter max. 40 mm, length max. 300 mm) Engineers square, adjustable block width 30 mm
Pulling rope to pull the man riding hoist rope (plastic, 70 m, Ø6...8 mm)
Sheet metal cutters, professional quality for 0.6...1.5 mm steel sheet
Allen keys, set 3 - 12 mm 2 vacuum handles, capacity 40 - 80 kg
2 G-clamps
1010245.wmf 1007097.wmf
3.2.2 Installation blister pack KM50091308G02
Material in installation blister
Item Reason Pcs.
M10 x 50 bolt Car guide rail fish plates (standard type) are thicker than before. M10 bolt from the CWT guide rail joint is not long enough to permit the method of leaning back the topmost car guide rail at machine installation.
1
– 5 x 70 wood screw – plastic wall plug – 20 mm plastic tube,
35 mm long
CWT screen secured to shaft wall for TAKE 2 method of guiding hoist rope tension weight.
4
CWT edge trim, 50 mm long
Required to be installed to the guide rail clips of the lowest guide rail brackets.
4
M12 x 80 expander fixings
– 2 x fixings to install a tethering anchor bracket
– 2 x fixings for the hoist test – 1 x fixing to hold temporarily
bracket for rail jointing – 1 x fixing to hold temporarily
bracket for ladder securing
WARNING: Use M12 anchor bolts
only in concrete! If other wall material exists, locally source suitable fixings. Consult your local support function. 6 – 8 x 50 coach screw – M8 mudguard washer – plastic plug
Required to temporarily fix pit ladder to the lowest floor sill area.
NOTE: Required due to the safety
codes of various frontlines.
2
M10
M12
35
4
OFFLOADING AND DISTRIBUTION
Introduce yourself to the person responsible for the site. Familiarise yourself with the site facilities, the local rules, safety requirements and site management procedures.
4.1
Offloading and distributing materials
CAUTION: For personal safety and to prevent any damage to the components:
– Keep the working areas clear and unobstructed. – Never go under any suspended load.
– Use correct manual lifting techniques. – Wear gloves to protect your hands. – Always wear a helmet.
– Wear safety harness and fix it to an approved fixing point while working in areas where there is risk of injury from falling.
– Wear goggles and dust masks as necessary. – Use hearing protection as necessary.
– When using the telescopic ramps ensure they are parallel and cannot slip off leading edge.
NOTE: The 150 kg (300 kg / pair) maximum WLL (working load limit) marking of the
telescopic ramps is based on single axle trolley usage. On specific tested method steps, where a twin axle assembly is used (such as machine transport), the load is more evenly distributed across the ramps. In such cases the WLL is increased to 380 kg / pair of ramps. Always follow the designated method description.
WLL 300 kg / pair of ramps WLL 380 kg / pair of ramps
1. Fix the transportation wheels to machine package while unloading. 2. Use wooden blocks to tilt machine box when removing the wheels.
Offload the material to the destinated storage area. Arrange the materials to ensure easy access to each component in the installation order.
NOTE: Car floor is at the oppposite side of the packing list.
NOTE: A number at top of each crate indicates the installation order.
Place the machine box so that the side with the holes is downwards.
When offloading the machine from the vehicle, put it into vertical position and use a forklift to place machine onto the axle and wheels. Push the machine into the storage area. Remove the axle and wheels and leave the crate in upright position on two pieces of wood.
The female end of the guide rail bundle is marked with tape. Locate the bundle so that the male side faces the elevator shaft. Handle the bundle carefully so as not to damage ends. Put the guide rail bundle on a higher stable working level to achieve a good working height of 1.0 m.
It is important that the tools and materials are positioned according to the installation order to achieve and maintain a controlled installation environment throughout the installation.
Do not open the packages until you are ready to install the equipment. Check against the material documentation that the delivery is complete. Position the tools and materials to correct levels before the installation starts.
xxxxxxxx (Draft -) 2012-05-24 All rights reserved. Copyright © 2012 KONE Corporation Mono3 -Unloading order Compiled by: Information Product Author / V ille Malmiala Checked by: Global Installation Support / Solution Manager , Global Packing / Konsti V ille Approved by: Global Installation Support / Anssi V enho 1079322.pdf
Package group Group header Package label Package label text 100 Installation requisites 110 120 Installation requisites Overspeed governor
200 Guide rails and shaft
beams
210 220 230
Guide rails Guide rail fixings Shaft beams 300 Doors 311 312 330 331 Frame / Fronts Door panels Door operator Railing 400 Machine room 410 420 430 Machine Ropes
Shaft electrification panel
500 Shaft and machine
room 510 440 / 540 Shaft equipment Wiring 600 Car 610 Car
700 Car sling and frame 710
720 730 Car sling Counterweight frame Filler weights A Topmost landing – Long tool box – Hand tools
– Man riding hoist top pulley
– Elevator shaft lighting (if applicable) – Overspeed governor and rope – Parking plate
– Rope suspension, counterweight side B Entrance level / Storage area
– Smaller tool box
– Man riding hoist, ASGT – Working stool
– Counterweight guide alignment tools – Guide rails and brackets
– Counterweight, filler weights – Car sling, car
– Machine
– Car door and landing doors – SEP, MAP, drive panel, COP – Elevator shaft electrification – Pit ladder – Ropes – Wiring material 1007099.wmf
A
B
4.2
Offloading and transporting landing doors
1. Keep the area on the side of the crate with the identification label “OPEN THIS SIDE” unobstructed.
2. Always transport parts of door one at a time.
3. The top tracks will be stored in the shaft mechanics box.
4. Open the narrow side of the card board box marked “Open this side” by cutting the vertical edges of the side. This is to gain access to the door panels.
5. Remove the top wooden support to access to the sills.
6. When extracting the door panels, do not break the two wooden rings around them. Slide the door panels out the opening.
7. When the panels are stored into the car or at the landing, ensure that the guide shoes are facing up in order to not damage them.
5
INSTALLING MAN RIDING HOIST AND OVERSPEED GOVERNOR
Quality Requirements:
Man riding hoist and accessories
– inspected and certified (inspection period validity to
meet local code)
– ONLY TRAINED PERSONS TO USE THE HOIST!
– lifting hook in shaft tested
Car overspeed governor
– installed to temporary position
– check data label to ensure correct type and tripping
speed
– ensure correct tripping direction
– ensure the rope is on the small pulley
!!! CAUTION - issues that affect reliability !!!
N/A
NOTE:
Check carefully that the OSG rope is correctly on the groove and UNDERNEATH the internal rope guard!
SORT STABILIZE SHINE
STANDARDIZE SUSTAIN Method tools needed:
Man riding hoist test bracket, overspeed governor hanger, telescopic pole, site trolley, man riding hoist + rope + accessories + hoist test plate (fuse plate)
Hand tools needed:
Pencil, tape measure, hammer drill, hammer, 2 x spanner (19 mm), pulling rope
5S Installation Progress Report N/A
QD-181.211 QD 1 completed
1075605.wmf
5.1
Man riding hoist parts
NOTE: The man riding hoist type described in this instruction is Tirak X750.
Pos. Item Greifzug component no.
1 Diverter pulley including the safety rope 33009
2 Electric hoist
3 Tension weight 57497
4 Manual rope reeler for maximum 60 m rope. Minimum rope length = 2 x elevator shaft height.
30158
5 Safety pin no. 2. 6 mm 12056
6 Electric supply extension cable for main power supply, 45 m, 5 x 1.5 mm2
16537 7 Pendant controller
8 Extension cable for the pendant control
9 Car adapter for the hoist 53877
10 Car adapter for the hook 53887
11 Adapter axle 72415
12 Split pin 6.3 x 40 63496
13 Diverter pulley Ø160 mm 53997
14.1 Safety pin 5 x 32 mm for diverting pulley 63656
14.2 Safety pin no. 2. 6 mm 12056
15 Tension weight pulley Ø130 mm 20205
P17000140.wmf 1. 2. 3. 4. 5. 6. 7. 8. 11. 10. 11. 12. 16. 13. 14.1 9. 14.2. 15.
5.2
Work positioning equipment or restraint system
NOTE: For more information, see AM-01.03.001 Preventing falls from height when
working on elevators, escalators and building doors.
Work positioning or restraint systems are systems of personal protection designed to secure the user in a safe position where it is not possible to fall. The restraint may also be used as an additional measure to prevent fall when working close to or leaning over the basic entrance protection, for example, when installing components at the top of an elevator shaft. The area around the fall hazard must be segregated to prevent risks to others.
KONE methods do not support the use of work positioning or restraint systems as primary fall prevention systems. This system is suitable as additional protection to the primary protection or where there is a limited risk of injury. They are only to be used where no other better solution is possible, subject to site specific risk assessment. (for example, existing elevator with no car top balustrade).
Work positioning system
NOTE: Wall fixings are located with
KM50091308G02 (Blister - Installation hardware). Use these fixings only in concrete! If other wall material exists, consult your local support function to source suitable fixings.
CAUTION: Work positioning or restraint
systems must not be used to arrest a fall.
Typical equipment includes: – Body belt.
NOTE: A full body harness is sometimes
used but is less suitable for low level anchor point.
– Adjustable lanyard (without shock absorber). Keep the lanyard as short as possible and take extreme care that the lanyard cannot be damaged by sharp edges.
– Suitable fixing point. The anchorage point strength requirements vary, but they must be capable of supporting around double the maximum pull force of a person and be in accordance with local regulations.
5.3
Safety checks
Make the following safety checks.
5.4
Transporting
1. Use site trolley to transport the man riding hoist.
Item Requirement Risk
Lifting equipment and suspension eyes.
Must be load marked, tested and in good condition according to local requirements.
Falling loads.
Hoist and lifting equipment. Must be tested according to local requirements.
Plugs and cables. Must be in good condition. Electric shock. Emergency stop button and
limit switches (if applicable).
Must prevent movement of hoist when contacts are open.
Uncontrolled movement of hoist/car.
Safety harnesses and ropes.
Must be inspected and in good condition. When used, they must always be
securely attached to approved fixing points.
Falling.
SMW06.wmf
1060916.wmf
5.5
Routing the man riding hoist rope and cable
1. Lower the power supply cable from the topmost landing to the pit. Connect to hoist. Check the operation of the hoist safety functions.
2. Drive out the hoist rope and pull it to the top floor using the lifting rope. 1 = rope entry, 2 = rope exit
If the hoist motor does not run, reverse two phases in the plug by rotating the phase changer* in the plug housing
3. Pull the hoist rope to the topmost landing. Allow 8 metres of slack to reach the elevator shaft ceiling. Loop the hoisting rope through the pulley.
WARNING: When there is a risk of falling wear a tethering system when working at
unguarded landing entrances. Always install the hoist from the lowest landing level. For more information, see AM-01.03.001.
P17000199.wmf 2 1 P17000107.wmf
*
1072131.wmf5.6
Installing overspeed governor hanger
NOTE: The counterweight overspeed governor (if any) must have higher tripping speed than the car overspeed governor.
1. Route the pulling rope through the hanger. Tighten the lower hook to maintain in correct position. *) Make a loop at the rope end to enable pulling the rope back to the landing. 2. Lift the hanger to the lifting eye.
WARNING: Check the correct orientation for the overspeed governor. The rope guard
must face the shaft wall.
~4
m
~4
m
*
1079201.wmf3. Pass the rope over the small groove of the OSG. Check the tripping direction.
4. Secure rope ends together and lower to the pit. Check that ropes do not get entangled. 5. Pull the overspeed governor to hanger. The rope guard must face the wall.
6. Remove the pulling rope. It is needed for car floor installation.
5.7
Fixing the man riding hoist rope
1. Attach the securing rope of the hoist diverting pulley to machine lifting eye. Use telescopic pole and adaptor bracket. Strengthen adaptor bracket:
1 = M6 flange nuts from car bolt delivery, 2 = M6 x 40 bolt, provided locally.
2. Fit hoist rope over the diverting pulley. Attach the pulley to the hoist suspension eye.
1078306.wmf
1
2
5.8
Lowering the man riding hoist hook to the pit
1. Drive out the hoist rope and lower the hook to the pit. 2. Clip the hoist hook over the suspension bar on the hoist.
3. Fit the car parking chain (capacity 1500 kg) to the underside of the hoist and drive the hoist into the elevator shaft
5.9
Pit ladder
1. When using the ladder, ensure the suitable angle between the ladder and the pit floor. 2. Secure the pit ladder for installation time use according to method A or B. Install the CWT
guide rail bracket while entrance protection is fitted.
3. Fix the pit ladder wall fixing bracket to the machine side wall.
4. Fix the securing strap is to the wall to prevent unwanted removal of the ladder.
P17000146.wmf 1009514.wmf 1078313.wmf PH PH/3 1 m A B
5.10
Testing the hoist equipment
If the lifting eye or suspension element for the man riding hoist diverter pulley has not been tested and certified, perform and record the test. The test ensures that the hoist equipment will take the maximum load hoisted during the installation.
1. Install the hoist test bracket on the side wall of the elevator shaft.
NOTE: Fixings* are located with KM50091308G02 (Blister - Installation hardware). Use
these fixings only in concrete! If other wall material exists, locally source suitable fixings 2. CAUTION: If "double" adapter is used, use direct line pulling to prevent hoist damage. 3. Attach the dynamometer or test plate (breaking strength 1500 kg or 2000 kg, supplied
locally) between the hoist and the hoist test bracket. Shorten the parking chain to 300 mm.
NOTE: Select the chain capacity according to the hoist capacity.
4. Drive the hoist slowly upwards until the hoist ropes are almost under tension. Take up the tension smoothly. Sudden loadings may damage the equipment.
5. Run continuously until the load limit of the hoist is reached or the test plate breaks. Motor power supply is automatically disconnected. Drive the hoist downwards to reset it.
6. Write your name and test date on the test plate and store it. Fix it to the tested lifting point after guide rail installation.
WARNING: No one is allowed to be in the elevator shaft during this test.
WARNING: The hoist can be used for material transportation after test. Do not use the
hoist for man riding.
1010613.wmf
1082349.wmf 2
6
PLUMBING
Quality Requirements:
– plumbing table is completed
– dimensions in the pit are similar to those in layout
drawings
– lasers are positioned on the pit floor according to the
plumbing table
– laser tools are calibrated, clean and batteries checked
!!! CAUTION - issues that affect reliability !!! SORT
STABILIZE SHINE
STANDARDIZE SUSTAIN Method tools needed: Pit ladder, lasers Hand tools needed:
Tape measure, pencil, spirit level 5S Installation Progress Report N/A
QD-181.211 QD 2 completed
1075617.wmf