NTPC Ref no SIM/1/TS/1/41 B NTPC Ref no SIM/1/TS/1/41 B Plant area: BOILER 

Plant area: BOILER 

PROCEDURE

PROCEDURE FOR COMMISSIONING FOR COMMISSIONING COAL COAL FEEDER FEEDER  SLNO SLNO 1.0 1.0 2.0 2.0 3.0 3.0 4.0 4.0 5.0 5.0 6.0 6.0 7.0 7.0 8.0 8.0 9.0 9.0 LIST OF CONTENTS LIST OF CONTENTS PLANT DETAILS PLANT DETAILS OBJECTIVE OBJECTIVE PROPOSAL PROPOSAL SERVICES REQUIRED SERVICES REQUIRED SAFETY PERECAUTIONS SAFETY PERECAUTIONS EMERGENCY PROCEDURE EMERGENCY PROCEDURE

STATE OF THE PLANT STATE OF THE PLANT

METHOD METHOD

COMPLETION CRITERIA COMPLETION CRITERIA

(2)

1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 PLANT DETAILS

The Coal firing system consists of separate raw coal feeder  connected to each mill. This raw coal feeder is of Gravimetric belt type feeder with electronic weighing micro processor based control system type.

No. of Raw Coal feeders /Boiler - 9 Nos

Type - Gravimetric belt type feeder  With electronic weighing

Microprocessor based Control system

Size - 36 inches

Capacity - 85 TPH (Design)

Motor rating - 5.5 KW

Other features - Clean out conveyor  Paddle switch

Load cells

Observation port & light

(3)

NTPC Ref no SIM/1/TS/1/41 B Plant area: BOILER 

PROCEDURE FOR COMMISSIONING COAL FEEDER  SL.NO 2.0 3.0 4.0 4.1 4.2 4.3 4.4 4.5 OBJECTIVE

To commission the Coal Feeder and make it available for coal firing of the boiler.

PROPOSAL

It is proposed to commission the feeders by putting the equipments under 8 Hrs. trail run ( As per the normal operating mode )

SERVICES REQUIRED

 Availability of man power with required tools for attending any leak and cleaning of filters.

 Availability of operating personnal to carryout/co-ordinate activities.

 Availability of lighting arrangements and communication facilities in the Feeder areas.

 Availability of portable fire fighting equipment near test area.

 Availability of LT Power Supply

(4)

5.0 5.1 5.2 5.3 5.4 5.5 6.0 6.1 6.2 7.0 SAFETY PRECAUTIONS

Debris in and around feeders shall be removed.

First Aid Kit is available near the test area

Operation of local start/stop push button shall be ensured for  perfect operation to facilitate for stopping of equipment in case of  necessity.

 Approach / staircase / platform wherever required and made available..

Portable fire fighting system made available at test area.

EMERGENCY PROCEDURES

The test team should be aware of the procedure to be adopted in case of damage to machinery/injury of any personnel connected to the activity.

The test team should be well aware of the procedures to be adopted incase of any abnormality in the activity.

(5)

NTPC Ref no SIM/1/TS/1/41 B Plant area: BOILER 

PROCEDURE FOR COMMISSIONING COAL FEEDER  SL.NO 7.2 7.3 7.4 7.5 7.6 7.7 7.8 7.9

 All local instrumentation as applicable completed with proper  calibration.

.All erection Log Sheets are followed up / signed by concerned agencies with respect to feeder alignment

Mill Feeder gear box are filled with recommended lubricating oil to the correct level.

The clean out couveyer gear box checked for lubrication / oil filled to correct level.

Ffeeder drive motor & clean out couveyer motor checked for its IR value and cleared for commissioning.

Feeder inspected & cleared for any debris or any foreign material.

The illumination lamp inside the feeder energized for proper  lighting

The feeder inlet manual gates are checked for their freeness and the operation of full open / close limit swiches. The gates are kept in fully closed condition before taking up the commissioning of the feeder.

(6)

8.0 8.1 8.1.1 8.1.2 8.1.3 8.1.4 8.1.5 8.1.6 8.1.7 8.1.8 8.1.9 METHOD Commissioning of Feeder 

Check the meggar value of motor and ensure that the value is satisfactory.

Ensure that the feeder inside is clean without any foreign material.

Check that the weigh span rollers are properly aligned as per O & M manual.

Check that the belt tension is adjusted as per the instuction given in O & M manual.

Start the feeder.

 Adjust the take up pulley at the rear side so that the belt runs exactly at the center and doesn’t deviate slowly to any one side. When the belt slips to any one side, the corresponding side’s tension adjustment screw to be adjusted such a way that the belt tightness increases in that side marginally.

 Allow the feeder to run for 8 hr trial with belt running smoothly without requiring any adjustment.

Start the clean out conveyer and run for four hour trail run.

(7)

NTPC Ref no SIM/1/TS/1/41 B Plant area: BOILER 

PROCEDURE FOR COMMISSIONING COAL FEEDER  SL.NO

8.1.10

8.1.11

8.1.12

9.0

Check the indication of feeder speed / weight are same both in control panel and in UCB.

Check the operation of ‘No Coal’ alarm switch, ‘Feeder chute pluggage’ paddle switch, ‘Belt deviation’ limit switches by simulation.

Commission the other Feeders as per steps given above

COMPLETION CRITERIA

Commissioning of the coal feeder completed by carrying the proposals given in Section 3.0

(8)

References

Related documents

This Service Level Agreement (SLA or Agreement) document describes the general scope and nature of the services the Company will provide in relation to the System Software (RMS

This is the recurring motto of the unedited treatise Diez privilegios para mujeres preñadas 4 (Ten Privileges for Pregnant Women), written in 1606 by the Spanish physician

A synthetic jet flow which has a wide range of flow field features including high velocity gradients and regions of high vorticity was used as a rigorous test bed to determine

Note: if you want to burn your current movie production to a disc right away, go directly to the Create Disc module. In the Create Disc module you can create a disc menu, produce

Make measurements on timeslot 0 [FREQUENCY] {Timeslot Off} [Enter] Activate the ORFS measurement (figure 25) [MEASURE] {GMSK Output RF The default setting measures spectrum

q w e r t y Description Rod cover Head cover Cylinder tube Piston rod Piston Bushing Cushion valve Snap ring Tie rod Tie rod nut Wear rod Rod end nut Back up O ring Rod seal Piston

The kitchen, the dining room, the hall and even the downstairs bedroom all have French doors that open onto a large patio terrace and then the rest of the garden is laid to lawn..

de Klerk, South Africa’s last leader under the apartheid regime, Mandela found a negotiation partner who shared his vision of a peaceful transition and showed the courage to