• No results found

MRT Works General Specification

N/A
N/A
Protected

Academic year: 2021

Share "MRT Works General Specification"

Copied!
226
0
0

Loading.... (view fulltext now)

Full text

(1)

MASS RAPID TRANSIT CORPORATION SDN. BHD.

PROJEK MASS RAPID TRANSIT LEMBAH KELANG:

JAJARAN SUNGAI BULOH-KAJANG

GENERAL SPECIFICATION

FOR CIVIL ENGINEERING WORKS

MRT PROJECT OWNER:

MASS RAPID TRANSIT CORPORATION SDN BHD

(902884-V)

Tingkat 12, Bangunan Setia 1,

15, Lorong Dungun, Bukit Damansara, 50490 Kuala Lumpur

PROJECT DELIVERY PARTNER (PDP): MMC GAMUDA KVMRT (PDP) SDN BHD (927050-H)

55-61, Jalan SS22/23, Damansara Jaya, 47400 Petaling Jaya,

(2)
(3)

JAJARAN SUNGAI BULOH ‐ KAJANG 

       

GENERAL SPECIFICATION 

FOR CIVIL ENGINEERING WORKS 

     

Document Reference No.  : 

KVMRT/PDP/SBK/GEN/OP/GS/CS/0001

Revision 

01

Date Issued 

18

th

 October 2011

       

(4)

                Page Not Used     

(5)

   

AMENDMENT HISTORY 

 

REVISION NO.  DETAILS OF AMENDMENT  00  First issue.  01  Minor amendments made to Sections G1, G3, G4, G5, G7, G9, G11, G13, G16,  G17, and G18                       

(6)

                    Page Not Used       

(7)

   

TABLE OF CONTENTS 

  Page  SECTION G1 ‐ GENERAL  G1.1  Application of the General Specification ... G1‐1  G1.2  Abbreviations and definitions ... G1‐1  G1.3  Glossary of terms ... G1‐5  G1.4  Trials ... G1‐6  G1.5  Standards and Codes of Practice ... G1‐6  G1.6  Drawings... G1‐7  G1.7  Contractor’s Drawings ... G1‐7  G1.8  Metric and Imperial units ... G1‐8  G1.9  Dimensions from Drawings ... G1‐8  G1.10  Investigation data ... G1‐8  G1.11  Survey of the Site ... G1‐9    Appendix AG1.1 ‐ Requirements For As‐Built Surveys ... G1‐17  SECTION G2 – THE SITE  G2.1  Access to the Site ... G2‐1  G2.2  Site restrictions ... G2‐1  G2.3  Site services ... G2‐2  G2.4  Site cleanliness ... G2‐4  G2.5  Parking Facilities ... G2‐5  G2.6  Site Pest Control ... G2‐6  G2.7  Conditions for temporary land allocation ... G2‐6  G2.8  Site Security ... G2‐6  G2.9  General Works Trains ... G2‐6  G2.10  Contractor’s Own Rolling Stock... G2‐7  G2.11  Defined Area and Restricted Area Working and Works Train Operations ... G2‐8    Appendix AG2.1 ‐ Requirements of Works Package Contractor’s Own Rolling Stock ... G2‐11  SECTION 3 ‐ SITE ESTABLISHMENT  G3.1  Use of the Site ... G3‐1  G3.2  Submission of particulars ... G3‐1  G3.3  Survey of the Site ... G3‐2  G3.4  Fences and Signs on the Site ... G3‐2  G3.5  Site Office Accommodation for the PDP, PDPR and the Supervising Consultant ... G3‐3 

(8)

    Page    G3.6  The Works Package Contractor's Site Accommodation ... G3‐6  G3.7  Vehicles for the PDP and Supervising Consultant ... G3‐6  G3.8  Clearance of the Site ... G3‐8  G3.9  Attendance ... G3‐8  G3.10  Material Testing Laboratory ... G3‐9  G3.11  Provision For Survey Instruments and Chainmen ... G3‐10  G3.12  Photographic Records ... G3‐10  G3.13  Prohibition of Advertising ... G3‐12  SECTION G4 ‐ THE WORKS  G4.1  Project Execution Plan ... G4‐1  G4.2  Method Statements, and Inspection and Testing Plans ... G4‐2  G4.3  Normal working hours at Site ... G4‐2  G4.4  Drawings and schedules for plant and equipment ... G4‐3  G4.5  Stage notification and inspection of Works ... G4‐3  G4.6  Demolition works ... G4‐4  G4.7  Construction restraints ... G4‐4  G4.8  Temporary Works ... G4‐5  G4.9  Off‐Site Fabrication Works ... G4‐8  G4.10  Construction equipment and plant ... G4‐8  G4.11  Protection of the Works ... G4‐9  G4.12  Approvals from Relevant Authorities ... G4‐10  G4.13  Technology Transfer ... G4‐11  SECTION G5 – WORK IN ROADS  G5.1  Maintenance of Existing Roads, Bridges, Culverts, etc. ... G5‐1  G5.2  Temporary diversions and traffic management ... G5‐2  G5.3  Half‐width Construction and Traffic Control ... G5‐8  G5.4  Temporary Traffic Signs ... G5‐8  G5.5  Temporary Routes ... G5‐9  G5.6  Use of roads and footways... G5‐9  G5.7  Pedestrian requirements ... G5‐9  G5.8  Temporary street lighting ... G5‐10  G5.9  Reinstatement of roads and footways ... G5‐11  G5.10  Traffic Management Implementation Team ... G5‐11   

(9)

    Page  SECTION G6 – DAMAGE AND INTERFERENCE  G6.1  Damage and interference ... G6‐1  G6.2  Watercourses and drainage systems ... G6‐2  G6.3  Utilities and other services ... G6‐3  G6.4  Condition survey of existing buildings and structures ... G6‐6  G6.5  Structures, roads and other property ... G6‐6  G6.6  Trees and other similar obstructions ... G6‐6  G6.7  Avoidance of nuisance ... G6‐6  G6.8  Protection of Existing Railways ... G6‐7  G6.9  Electromagnetic Compatibility ... G6‐8    Appendix AG6.1 ‐ Reference List Of Standards Relating To EMC ... G6‐14  SECTION G7 – TEMPORARY ELECTRICITY SUPPLY  G7.1  Work on Site ... G7‐1  G7.2  Electrical ‐ general ... G7‐1  G7.3  Scope ... G7‐2  G7.4  Materials, appliances and components ... G7‐2  G7.5  Design considerations ... G7‐2  G7.6  Mains voltage ... G7‐2  G7.7  Types of distribution supply ... G7‐2  G7.8  Protection of circuits ... G7‐3  G7.9  Earthing ... G7‐3  G7.10  Plugs, socket outlets and couplers ... G7‐3  G7.11  Cables ... G7‐3  G7.12  Transformers and switchgear in tunnels ... G7‐4  G7.13  Lighting installation ... G7‐4  G7.14  Electrical motors ... G7‐4  G7.15  Inspection and testing ... G7‐5  G7.16  Identification ... G7‐5  G7.17  Maintenance ... G7‐5  G7.18  Maintenance record ... G7‐5  G7.19  Electricity supply for Other Works Contractors and trial operations ... G7‐5  G7.20  Metering ... G7‐7  G7.21  Payment of electricity charge ... G7‐7     

(10)

    Page  SECTION G8 – MATERIALS, EQUIPMENT, AND SPARE PARTS  G8.1  Materials ... G8‐1  G8.2  Materials and equipment provided by Other Works Contractors ... G8‐2  G8.3  Supply of Spare Parts and Special Tools... G8‐3  G8.4  Packing and Storage ... G8‐4  G8.5  Shipping and Delivery... G8‐7  SECTION G9 – SAFETY & HEALTH  G9.1  Works Package Contractor's Safety & Health Obligations ... G9‐1  G9.2  Laws and Regulations ... G9‐2  G9.3  Contractor's Safety and Health Personnel ... G9‐2  G9.4  Safety & Health Plan ... G9‐4  G9.5  Safety & Health Risk Assessment ... G9‐5  G9.6  Emergency preparedness and response ... G9‐6  G9.7  Incident notification and reporting ... G9‐7  G9.8  Control of Safety & Health Non‐Compliance ... G9‐7  G9.9  Traffic Management and Public Safety ... G9‐8  G9.10  General Safety and Health Requirements ... G9‐8  G9.11  Safety and Health Meetings ... G9‐15  G9.12  Safety & Health Documentation ... G9‐15  G9.13  Monthly progress report ... G9‐15  G9.14  Training ... G9‐16  G9.15  Safety and Health Inspection and Auditing ... G9‐16  SECTION G10 – QUALITY ASSURANCE AND QUALITY CONTROL  G10.1  Introduction ... G10‐1  G10.2  Minimum QA/QC Requirements ... G10‐1  G10.3  Quality Management Responsibility ... G10‐4  G10.4  QA/QC Program and Plan ... G10‐4  G10.5  Document Control ... G10‐6  G10.6  Product Identification and Traceability ... G10‐7  G10.7  Inspection and Testing ... G10‐7  G10.8  Non‐Compliance and Disposition of Non‐Conforming Materials ... G10‐10    and Constructed Works  G10.9  Corrective and Preventive Actions ... G10‐11  G10.10  Quality Audits and Training ... G10‐11 

(11)

    Page  SECTION G11 – ENVIRONMENTAL MANAGEMENT  G11.1  General Environmental Management ... G11‐1  G11.2  Legal Requirements... G11‐1  G11.3  Environmental personnel ... G11‐2  G11.4  Detailed Environmental Impact Assessment (‘DEIA’) ... G11‐2  G11.5  Environmental Management Plan (‘EMP’) ... G11‐2  G11.6  Erosion and Sediment Control Plan (‘ESCP’) ... G11‐4  G11.7  Deliverables ... G11‐4  G11.8  Environmental Protection Works ... G11‐5  G11.9  Stormwater Management ... G11‐8  G11.10  Environmental Incidents ... G11‐8  G11.11  Environmental Monitoring, Site Inspection and auditing ... G11‐8  G11.12  Training, Promotion and awareness ... G11‐9  G11.13  Meetings ... G11‐10  G11.14  Non Compliance ... G11‐10  SECTION G12 – PLANNING, PROGRAMMING AND PROGRESS MONITORING OF THE WORKS  G12.1  Planning and Programming ... G12‐1  G12.2  Planning and Programming Organization ... G12‐1  G12.3  Programme Submissions ... G12‐1  G12.4  Progress Monitoring... G12‐1  G12.5  Programme Requirements ... G12‐2  G12.6  Baseline Programme ... G12‐4  G12.7  Design, Procurement and Manufacturing Programme ... G12‐6  G12.8  Architectural Builder’s Works and Finishes (ABWF) and ... G12‐8    Building Services Programme  G12.9  Testing and Commissioning Programme ... G12‐9  G12.10  Co‐ordinated Installation Programme ... G12‐9  G12.11  Three Month Rolling Programme ... G12‐10  G12.12  Schedule of Design ... G12‐11  G12.13  Time Chainage Programme ... G12‐13  G12.14  Track Related Installation Programme (TRIP) ... G12‐13  G12.15  Construction Equipment & Labour Returns ... G12‐15  G12.16  Monthly Progress Meeting and Report... G12‐15  G12.17  Programme Analysis Report ... G12‐18   

(12)

    Page  SECTION G13 – LIAISON WITH OTHERS  G13.1  Liaison with others ... G13‐1  G13.2  Work by Other Works Contractors ... G13‐1  G13.3  Coordination and cooperation ... G13‐2  G13.4  Other Project Contracts and Co‐ordination ... G13‐2  G13.5  Interface Management Plans and Interface Control Documents ... G13‐4  G13.6  Coordination with Other Works Contractors in preparing CSDs and SEMs ... G13‐6  G13.7  Coordination Meetings ... G13‐8    Appendix AG13.1 ‐ Table of Contents for Interface Management Plan ... G13‐9    And Interface Control Document  SECTION G14 – DOCUMENT MANAGEMENT  G14.1  Documents, submissions and correspondence ... G14‐1  G14.2  Electronic File Formats ... G14‐2  G14.3  Submissions programme ... G14‐3  G14.4  Submission and review procedure ... G14‐4  G14.5  Project records ... G14‐5  SECTION G15 – GENERAL REQUIREMENTS FOR BUILDING SERVICES ANDARCHITECTURAL  BUILDERS WORKS AND FINISHES  G15.1  General ... G15‐1  G15.2  Submissions ... G15‐1  G15.3  Coordination ... G15‐1  G15.4  Submissions for Building Services Works ... G15‐1  G15.5  Submissions for Architectural Builders Works and Finishes ... G15‐6  SECTION G16 – SOFTWARE MANAGEMENT AND CONTROL  G16.1  General ... G16‐1  G16.2  Software Quality Assurance Plan ... G16‐1  G16.3  Software Release Control ... G16‐3  G16.4  Software Progress Tracking ... G16‐4  G16.5  Software Audit ... G16‐5  G16.6  Software Documentation ... G16‐6  G16.7  Safety Integrity Level ... G16‐6  G16.8  Software Deliverables and Licenses ... G16‐7  G16.9  Backup ... G16‐8    Appendix AG16.1‐ Typical Table of Contents for Software Quality Assurance Plan ... G16‐9 

(13)

    Page  SECTION G17 – SYSTEM SAFETY  G17.1  Construction Risk Management ... G17‐1  G17.2  System Assurance ... G17‐1  SECTION G18 – TESTING AND COMMISSIONING  G18.1  General ... G18‐1  G18.2  Testing and Commissioning ... G18‐1  G18.3  Operations and Maintenance Manuals ... G18‐2  G18.4  As Built Drawings ... G18‐2  G18.5  Training ... G18‐3  G18.6  Training Methods ... G18‐5                    END OF TABLE OF CONTENTS     

(14)

                          Page Not Used 

(15)

     

SECTION G1 

GENERAL 

 

Application of  the General  Specification 

G1.1  (1)  The  provisions  contained  in  the  Particular  Specification  and  the  Drawings  shall  in  the  event  of  any  inconsistency  or  discrepancy  prevail  over  the  provisions  contained  in  this  General  Specification  (GS)  and  the  Materials  and  Workmanship Specification. 

(2)  The  provisions  contained  in  the  GS  shall  prevail  over  the  provisions contained in the Standards, Codes of Practice and  similar standard documents stated in the Contract. 

(3)  This  GS  shall  be  read  in  conjunction  with  other  documents  included in the Contract. 

(4)  All clause and section references in the GS shall refer to the  Sections,  Sub‐Sections,  clauses  and  sub‐clauses  within  this  document unless specifically described otherwise. 

(5)  References  in  the  Contract  to  "General  Specification"  shall  mean this document and to the provisions contained herein.  (6)  Further  to  the  requirements  of  the  Conditions  of  Contract 

concerning  the  sufficiency  of  the  Contract  Documents,  the  Works  Package  Contractor  shall  promptly  notify  the  PDP  of  any  error,  omission,  fault  or  other  defect  in  the  Drawings  and/or Specifications which he discovers when reviewing the  Contract or Executing the Works. 

Abbreviations  and 

definitions 

G1.2  (1)  Abbreviations  used  in  the  GS  shall  have  the  following  meanings:      ABWF  :  Architectural Builders' Works and Finishes        AC  :  Alternating Current    ALARP  :  As Low As Reasonably Possible    ASTM  :  American Society for Testing and Materials    BMS  :  Building Management System    BS  :  British Standard     CAD  :  Computer‐Aided Drafting    CAR  :  Corrective Action Request    CICE  :  Contractor’s Independent Checking Engineer    CIDB  :  Construction Industry Development Board 

(16)

    CPM  :  Critical Path Method     CSD  :  Combined Services Drawings    DEIA  :  Detailed Environmental Impact Assessment    DID  :  Department of Irrigation and Drainage    DOSH  :  Department of Occupational Safety & Health    DSM  :  Deterministic Safety Analysis    E&M  :  Electrical and Mechanical    EMP  :  Environmental Management Plan    EN  :  European Standards    ERP  :  Emergency Preparedness and Response Plan    ESCP  :  Erosion and Sediment Control Plan    GS  :  General Specification (this document)    ICD  :  Interface Control Document    IEC  :  International Electrotechnical Commission    IEE  :  Institution of Electrical Engineers    IEEE  :  Institution of Electrical and Electronic        Engineers    IMP  :  Interface Management Plan    IP  :  Industrial Protection     ISO  :  International Organisation for Standardization    ITP  :  Inspection and Testing Plan    LBS  :  Location Breakdown Structure    M&WS :  Materials and Workmanship Specification    MSDS  :  Material Safety Data Sheet    NCR  :  Non‐Compliance Report    OBS  :  Organisation Breakdown Structure    PAT  :  Partial Acceptance Tests    PCMM :  Project Codes and Method of Measurement    PDM  :  Precedence Diagramming Method 

(17)

    PPE  :  Personal Protective Equipment    PRO  :  Pre‐Revenue Operation    QA  :  Quality Assurance    QC  :  Quality Control    SAMM :  Skim Akreditasi Makmal Malaysia    SAP  :  System Assurance Plan    SAT  :  System Acceptance Tests    SEM  :  Structural E&M Drawings    SIL  :  Safety Integrity Level    SOCSO :  Social Security Organization    TOC    :  Tests on Completion    TRIP  :   Track Related Installation Programme      (2)  Abbreviations of units of measurement used in the GS shall  have the following meanings:  C  :   degrees Celsius    g  :   gram    g/ml  :   gram per millilitre    g/m2  :   gram per square metre    ha  :   hectare    hr  :   hour    Hz  :   hertz    J  :   joule    kg  :   kilogram    kHz  :   kilohertz    kV  :   kilovolts 

(18)

 

    (3)  Further  to  Clause  1.1  of  the  Conditions  of  Contract,  the  following  words  or  phrases  used  in  the  GS  shall  have  the  meanings given to them below: 

  “Baseline  Programme”  means  the  Works  Package  Contractor’s coordinated detailed programme for the Works  prepared  in  accordance  with  Clause  G12.6,  and  which  is  referred  to  in  the  Conditions  of  Contract  as  the  ‘baseline  programme’,  ‘Approved  Programme’  or  ‘Approved  Revised  Programme’, depending on the status of the programme.    “Commissioning”  means  all  activities  and  operations  to  be 

performed by the Works Package Contractor to ensure that  all machinery, apparatus and systems, insofar as is possible,  is  capable  of  being  fully  operated  by  the  Works  Package  Contractor  to  satisfy  all  Integrated  Test  functions  and  tests  to be performed during the Test Running period. 

  “Completion  Tests”  means  tests  including  Installation  Tests,  PAT,  SAT,  TOC  and  PRO  to  be  executed  after  the  supply,  delivery and installation of the Permanent Works but prior to  practical  completion  of  the  Works  or  after  any  part  of  the  Permanent  Works  contained  in  any  section  of  the  Works  is  installed  but  prior  to  practical  completion  of  the  section  of  the Works in which the part is comprised. 

      “Contractor’s  Independent  Checking  Engineer”  means  the  Registered  Professional  Engineer  appointed  by  the  Works  Package  Contractor  to  independently  check  and  certify  the  design of Temporary Works. 

      "Defined Area" means an area of track as described in Clause  G2.11. 

  “Design Documents” means all drawings, design calculations,  software,  specifications,  samples,  patterns,  models,  written  procedures  and  all  other  documents  and  things  relating  to  the  design  of  the  Permanent  Works  and/or  the  Temporary  Works  which  are  prepared  by  or  on  behalf  of  the  Works  Package Contractor. 

      "General  Works  Train"  or  “Works  Train”  means  any  rolling  stock provided by the PDP or the Works Package Contractor  respectively for the purpose of carrying out installation and  testing works within the Defined Area or Restricted Area.    “Integrated Test” means those system‐wide operability tests 

to be undertaken by the Works Package Contractor whereby  the  Works  Package  Contractor  shall  demonstrate  the  compatibility  between  his  plant  and  the  plant  of  Other  Works Contractors. 

(19)

 

  “Monthly  Progress  Report”  means  a  report  which  shall  be  prepared and submitted by the Works Package Contractor to  the  PDP  on  a  monthly  basis,  detailing  the  progress  of  the  Contract and other matters as specified in Section G12.    "Operating  Railway"  means  the  existing  railway  tracks 

currently in revenue operation or in Trial Operations and any  ancillary areas such as the depots, sidings, stations, terminus  and  traction  power  feeder  stations  which  form  part  of  the  operating system. 

      "Railway Operator" means Prasarana (or one of its group of  companies), or KTM, or other such company which operates  or  will  operate  the  particular  railway  or  transit  system  referred to in the clause in which the term has been applied.    "Relevant Authority" means any Government department or 

public body having jurisdiction in relation to the Works.    "Restricted  Area"  means  the  location  in  the  railway  under 

construction  which  houses  electrical  or  mechanical  equipment that has become energised and hence potentially  dangerous to people working in the area.  When the term is  used for track area its associated power rail is energised and  it is barricaded from unauthorised access and trains may be  running at high speed for testing. 

      “  ‘S’  curve”  means  the  graphical  relationship  between  the  planned  (and  actual  where  appropriate)  quantity  of  completed  work  (or  resources)  and  time.    The  curve  produced is to be illustrated on an accumulative basis where  the  slope  of  the  line  indicates  the  rate  of  undertaking  the  work or rate of expenditure of the resources. 

  “Test Running” means that period of PAT, SAT, and TOC prior  to Trial Running when the Other Works Contractors shall be  testing  their  plant  and  equipment  and  run  the  same  in  conjunction  with  the  Railway  Operator.    In  addition  during  this period system‐wide tests shall be undertaken that shall  require the attendance of relevant Other Works Contractors.    “Trial Running” means that period immediately following the 

completion  of  a  section  of  railway  under  construction,  but  prior  to  opening,  when  the  Railway  Operator  shall  be  operating  the  rolling  stock  and  all  other  systems  and  generally  using  the  railway  as  though  a  scheduled  service  was  operating,  except  for  the  absence  of  fare‐paying  passengers. 

Glossary of  terms 

G1.3  (1)  Words  and  expressions  to  which  meanings  are  assigned  in  any Section of the GS shall have the same meanings in other 

(20)

 

Sections  of  the  GS  except  when  the  context  otherwise  requires. 

(2)  Utilities are electricity, lighting, traffic control, telephone and  other  communication  cables,  gas,  water  supply,  sewerage  and  drainage,  including  all  associated  protection,  supports,  ancillary structures, fittings and equipment. 

(3)  Survey  Datum  Levels  refers  to  the  prevailing  datum  system  applicable to the Klang Valley. 

(4)  The  survey  projection  and  the  coordinates  used  on  the  Drawings  refers  to  the  prevailing  survey  system  applicable  to  the Klang Valley. 

Trials  G1.4  (1)  Trials  shall  be  carried  out  as  stated  in  the  Materials  and  Workmanship  Specification  to  demonstrate  that  proposed  materials  and  methods  of  construction  will  produce  work  which complies with the specified requirements. 

(2)  Trials  shall  be  carried  out  before  the  construction  of  the  relevant  Permanent  Works  commences  so  as  to  allow  the  PDP a sufficient period to determine if the trial complies with  the specified requirements. 

(3)  Trials  shall  be  carried  out  using  materials  and  methods  of  construction of the types and locations approved by the PDP. (4)  If, in the opinion of the PDP, work which complies with the 

requirements of the Contract has not been produced in the  trial,  particulars  of  proposed  changes  to  the  materials  or  methods of construction shall be submitted for approval by  the PDP, and further trials shall be carried out until relevant  work  which  complies  with  the  specified  requirements  has  been  produced  in  the  trial,  unless  otherwise  agreed  by  the  PDP. Works for which trials are required shall not commence  until,  in  the  opinion  of  the  PDP,  work  which  complies  with  the specified requirements has been produced in the trial.  (5)  Unless permitted by the PDP, the materials and methods of  construction used to produce work which complies with the  specified requirements in a trial shall not be changed unless  further trials have been carried out to demonstrate that the  proposed changes are satisfactory.  Standards and  Codes of  Practice 

G1.5  (1)  The  particular  edition  of  any  Standard  or  Code  of  Practice  applicable  to  the  Works,  shall  be  the  edition  stated  in  the  Specifications.    If  no  edition  is  specified,  the  Standard  or  Code of Practice shall be deemed to be the edition current at  the time of Tender, unless otherwise approved by the PDP. If  the Malaysian Standard exists, which the PDP determines to  be equivalent to the British or other Standard specified, then 

(21)

 

the Malaysian Standard shall be followed. 

(2)  In  the  event  of  any  discrepancy  between  the  provisions  of  the  Specifications  and  the  provisions  within  the  relevant  Standards  or  Codes  of  Practice  as  mentioned  in  this  Specification,  then  the  provisions  of  the  Specifications  shall  take precedence. 

(3)  The  Works  Package  Contractor  shall  provide  for  the  use  of  the  PDP  such  Standards  and  Codes  of  Practice  as  may  be  required in the execution of the Works.  These shall remain  the property of the Works Package Contractor. 

(4)  The  Permanent  Works,  and,  where  appropriate,  materials  and workmanship, shall be in accordance with the Materials  and Workmanship Specification and the requirements of the  Contract,  or  where  no  standard  is  identified,  the  Works  Package  Contractor  shall  make  a  proposal  which  shall  be  subject to approval by the PDP. 

Drawings  G1.6  (1)  A  list  of  those  drawings  forming  part  of  the  Contract  (Drawings) is included in the Specifications if applicable.  (2)  All  references  to  drawing  numbers  shall  refer  to  the  latest 

amendment  of  that  drawing,  unless  a  specific  revision  or  version number is stated in such references. 

(3)  On  completion  of  each  section  of  the  Works  the  Works  Package  Contractor  shall  be  responsible  for  modifying  the  Drawings to reflect the as‐built condition.  This exercise shall  include  for  all  amendments  to  dimensions,  removal  or  amendment  to  notes,  changes  from  future  tense  to  past  tense and materials used. 

(4)  For  ‘build  only’  contracts,  the  as‐built  drawings  shall  be  carried  out  on  soft  copies  of  the  Drawings  which  shall  be  provided to the Works Package Contractor for this purpose.  (5)  For  ‘design  and  build’  contracts,  the  as‐built  drawings  shall 

be  endorsed  by  the  Works  Package  Contractor’s  Design  Consultant. 

Contractor’s  Drawings 

G1.7  (1)  The  preparation  and  submission  of  drawings,  sketches,  figures,  diagrams,  illustrations  and  the  like  by  the  Works  Package Contractor in the execution of the Works, shall be in  accordance  with  the  PDP’s  CAD  requirements  or  other  standard approved by the PDP.  Any soft copies of drawings  provided  for  the  use  of  the  Works Package Contractor  shall  be  modified  by  him  if  necessary  to  ensure  that  his  submissions comply with the approved CAD requirements.  (2)  The  Works  Package  Contractor  shall  be  responsible  for  the 

(22)

 

production  of  “As‐Built”  drawings.    These  shall  include,  but  are  not  limited  to:  structural  design  drawings;  architectural  drawings including detail drawings, framing plans, fixings etc;  E&M  drawings  including  details  of  components,  fixing,  conduit  locations;  drawings  of  all  services;  and  any  Temporary  Works  which  have  been  left  in  place  with  the  approval of the PDP.  These shall be prepared and submitted  in accordance with Section G14. 

(3)  The Works Package Contractor shall submit the following no.  of copies of “As‐built” drawings: 

a)  Four  sets  of  A1  size  drawings  comprising  1  set  of  original reproducible drawings and 3 sets of non‐fade  prints. 

b)  Six sets of A3 size prints reduced from the original A1  size drawings. 

c)  Four sets of electronic copies stored on CD‐ROM.  (4)  The  Works  Package  Contractor  shall  be  responsible  for  the 

production  of  all  drawings  required  for  submission  to  statutory bodies, other Government Departments, and utility  undertakings in order to progress the Works. 

Metric and  Imperial units 

G1.8  Specifications  in  imperial  units  shall  not  be  substituted  for  Specifications  in  metric  units  stated  in  the  Contract  without  the  prior approval of the PDP. 

Dimensions  from Drawings 

G1.9  Dimensions  shall  not  be  obtained  by  scaling  from  the  Drawings.   Dimensions  which  are  not  shown  on  such  drawings  or  calculable  from  dimensions  shown  on  such  drawings  shall  be  obtained  from  the PDP. 

Investigation  data 

G1.10  (1)  Utility  investigation  data,  ground  investigation,  laboratory  investigation,  laboratory  testing  data,  rock  cores  and  soil  samples  taken  from  ground  investigation  commissioned  or  obtained  by  the  PDP  in  connection  with  the  Project,  are  available for inspection on application to the PDP. 

(2)  The utility investigation data, ground investigation data and  laboratory  testing  data  are  made  available  to  the  Works  Package  Contractor  solely  for  the  purpose  of  assisting  the  Works Package Contractor to make his own interpretation of  the ground conditions and utility locations.  The accuracy or  reliability  of  the  information  given  in  the  information  supplied, prepared or commissioned at any time by the PDP  in  connection  with  the  Works  and  adjacent  or  interfacing  works is not warranted and the PDP shall have no liability to  the Works Package Contractor in any manner whatsoever for  such information. 

(23)

 

(3)  All other additional utility investigation, ground investigation  and  laboratory  testing  required  for  the  execution  of  the  Works shall be carried out by the Works Package Contractor  in accordance with the Contract.

  G1.11  Survey of the Site 

Survey Works   G1.11.1  (1)  The  PDP  has  established  a  Primary  Control  Survey  Network  for  the  Project.  The  Works  Package  Contractor  shall  reference  this  network  and  undertake  all  survey  works  necessary  to  establish,  maintain  control  of  and  record  the  locations,  alignments  and  levels  of  the  Works.    The  survey  works shall, without limitation, include: 

  a)  A Survey Control Network for the Works.  The Works  Package  Contractor  shall  within  two  (2)  calendar  months  from  the  date  of  the  Letter  of  Acceptance  complete  and  submit  for  the  PDP’s  approval  his  “Survey Control Network”. 

b)  An  Initial  Land  Record  Survey  or  surveys  of  parts  of  the  Site,  which  shall  be  completed  together  with  drawing records prior to commencement of work on  that part of the Site. 

c)  All surveys required during the progress of the Works  to  control  and  record  the  location,  alignment  and  level of the Works. 

d)  The as‐built surveys of the Permanent Works and the  preparation  of  Survey  Records  Drawings  in  accordance  with  the  requirements  of  this  Section  G1.11. 

e)  Where applicable, the deformation monitoring of any  Permanent  Works  which  are  constructed  on  reclaimed land. 

f)  Precondition  surveys  of  buildings,  structures  and  other facilities potentially affected by the works.  g)  Video surveys of all existing drains and sewers within 

the  Site  and  to  the  nearest  manhole  or  catchpit  outside the Site boundary. 

  (2)  For  the  Survey  Control  Network,  the  Works  Package  Contractor  is  required  to  establish  a  first  order  Horizontal  Survey  Control  Network  that  consists  of  Primary  Control  Stations plus a Vertical Survey Control Network at grade level  to  be  established  that  consists  of  Bench  Marks.  The  requirements  and  standards  of  accuracy  for  the  networks 

(24)

  shall be :      Horizontal Network Requirements Accuracy    • 1:100,000 for underground works sections.  • 1:60,000 for elevated works sections  Origin  • Major Trigonometrical Stations.  • Distances between adjacent stations established  to be between 500m and 1000m.  Vertical Network Requirements Accuracy    • Levelling route shorter than 1 km:  +/‐ 1mm  √N (where N is number of set‐up)  • Levelling route over 1 km:  +/‐ 4mm  √K (where K is in kilometres) for  underground works sections  +/‐ 6mm  √K (where K is in kilometres) for  elevated works sections  Origin    • At least 2 agreed permanent benchmarks at  both ends of the levelling route should be  selected. 

  (3)  The  location  of  control  stations  and  benchmarks  must  be  safe,  stable  and  easily  accessible.    The  Works  Package  Contractor  is  responsible  for  site  clearance  to  ensure  inter‐ visibility  between  horizontal  control  stations  and  to  obtain  all relevant permits for performing the survey.    (4)  Survey Station Markers to be installed for the new Horizontal  Control Network Stations and Benchmarks shall be in one of  the following types:      Survey Marker Ground Conditions  Triangulation Monument (Concrete  pillar)  Hilltop Picket Box Open ground  Survey Nail Kerbstones, pavement, concrete  sumps, concrete roof or structures  Stainless Steel Rod Bench Mark Concrete wall / structures or natural  rock    (5)  Prior to the commencement of field observations, the Works  Package  Contractor  must  submit  for  approval  a  Survey  Method  Statement  that  includes  the  following  information  to  demonstrate  that  the  survey  is  capable  of  achieving  the  accuracies and standards of this GS: 

a)  The routing and configurations of the Networks,  b)  The pre‐analysis reports, 

(25)

 

materials  and  data  processing  and  computing  software packages, 

d)  Survey operation scheme and quality procedures,  e)  Staffing qualifications and experience, and 

f)  Data  handling  procedures  and  data  format  for  final  result submissions. 

  (6)  On completion of the survey, the Works Package Contractor  shall submit the following deliverables: 

a)  A  survey  report  summarizing  instruments  used,  survey  procedures,  approach  to  adjustment  computation and analysis result. 

b)  Hard  and  softcopy  of  a  Survey  Album  that  includes  network  diagrams  and  location  sketches,  Station  Summary sheet for each Station and Bench Mark with  a co‐ordinate list of all the Stations and Bench Marks.  c)  Original  field  notes,  data  disks,  field  sketches, 

computation  sheets  for  all  reduction  computation  and adjustment results. 

d)  A valid calibration certificate for each instrument and  valid  license  for  each  software  package  used  in  the  survey. 

  (7)  The  Initial  Land  Record  Survey  shall  be  undertaken  prior  to  the commencement of  works on Site and no works may be  carried out on any part of the Site until it has been surveyed  and the survey records approved by the PDP.  It shall: 

  a)  Record all original landforms, features, levels and the  like. 

b)  Establish  the  lines,  levels  and  boundaries  of  the  Works. 

c)  Locate  or  confirm  the  details  and  location  of  all  utilities and services on or in the Site. 

d)  Check  where  relevant  adjacent  roads,  buildings,  structures and any construction work not associated  with the Contract are located. 

  (8)  The  Initial  Land  Record  Survey  shall  be  undertaken  with  a  view  to  providing  sufficient  detailed  information  of  major  existing  features  which  are  to  be  demolished  or  altered  during the course of the Works and form the basis for future  Site  reinstatement  and  as  a  record  for  details/standards 

(26)

 

required for such reinstatement. 

  (9)  Precondition  surveys  of  buildings  and  structures  shall  be  carried  out  by  a  suitably  qualified  engineer  or  qualified  building  surveyor,  as  necessary  for  the  nature  of  the  structure  concerned  and  which  shall  produce  an  accurate  record  (together  with  photographic  records)  of  the  existing  state of the structure prior to the commencement of work in  the concerned area.  In addition to any reports issued to the  Relevant  Authorities,  the  Works  Package  Contractor  shall  submit three (3) copies of the precondition survey reports to  the  PDP  not  less  than  twenty‐eight  (28)  days  prior  to  the  commencement of work in that area. 

  (10)  The  Works  Package  Contractor  shall  conduct  video  record  surveys of all existing drainage and sewerage systems within  and directly adjacent to the Site and submit to the PDP two  copies  of  all  survey  records  and  video  footage  prior  to  commencement  of  any  works  within  the  relevant  parts  of  the  Site.    The  surveys  shall  extend  to  the  first  manhole  outside the Site boundary. 

  (11)  The  Works  Package  Contractor  shall  conduct  video  record  surveys  of  all  existing  and  new  drainage  and  sewerage  systems within the Site and submit to the PDP two copies of  all survey records and video footage within twenty‐eight (28)  days  of  the  issue  of  the  Certificate  of  Practical  Completion  for the Works.  Survey Quality  Plan  G1.11.2  The Works Package Contractor shall submit for approval by the PDP  within one (1) month from the date of the Letter of Acceptance, a  Survey Quality Plan or plans for the control of all survey work.  The  Survey Quality Plan shall define: 

a)  The  organization,  responsibilities  and  authorities  given  to  identified personnel. 

b)  The  methods  and  procedures  for  establishing,  maintaining  control of and recording all survey activities required by the  Contract. 

c)  The  proposed  method  of  recording  the  data  arising  from  these  surveys  and  the  electronic  digital  format  for  such  records. 

e)  The Survey Plan in accordance with this Section. 

f)  The  method  and  procedure  for  notifying  the  PDP  of  all  survey activities. 

g)  The  methods  and  procedures  for  the  calibration  of  the  survey equipment. 

(27)

  h)  The frequency of monitoring for all Survey Control Network  Points.  The Survey  Manager  G1.11.3  The Works Package Contractor shall appoint a suitably qualified and  competent person as the Survey Manager, to be responsible for the  task  of  ensuring  that  the  requirements  of  the  Survey  Quality  Plan  are  implemented  and  maintained.    The  Works  Package  Contractor  shall at the time of submission of the Survey Quality Plan, submit for  approval  by  the  PDP  details  of  the  qualifications,  experience,  authority and responsibilities of the proposed Survey Manager.  Survey Plan  G1.11.4  Each  survey  undertaken  by  the  Works  Package  Contractor  shall  be 

deemed  to  be  a  quality  control  activity.  A  Survey  Plan  or  plans  suitably structured to comply with the relevant requirements of this  section shall be submitted for approval by the PDP. The Survey Plan  shall define the programme and frequency required for:    a)  The establishment of survey control or reference points.  b)  Construction surveys, which are to be undertaken to control  the work during each construction process.  c)  Progress surveys, which are to be undertaken to record the  status of the work for purposes such as the achievement of  Key Access Dates and Milestones. 

d)  As‐built  surveys,  which  are  to  be  undertaken  to  record  the  location,  alignment  and  level  of  all  completed  elements  of  the Permanent Works.  e)  Where applicable, the monitoring of the levels of Permanent  Works which are constructed on reclaimed land.  f)  A schedule for monitoring of deformation and settlement of  existing structures and buildings within the zone of influence  of construction shall be maintained where applicable.  Monitoring of  Survey Works  G1.11.5  The Works Package Contractor shall provide all reasonable facilities  to the Supervising Consultant, and others authorised by the PDP to  witness  any  survey  activity  and  to  check  the  accuracy  of  the  measurements and the records of such activities.  This shall include  without  limitation,  the  provision  of  all  survey  measurements  in  electronic digital format and other records upon request. 

As Built  Surveys 

G1.11.6  Unless  otherwise  agreed  with  the  PDP,  the  Works  Package  Contractor  shall  ensure  that  the  as‐built  surveys  are  undertaken  within two (2) days of the completion of each stage or section of the  Permanent Works and the survey record submitted for approval by  the PDP within seven (7) days thereafter and shall be such that: 

    (1)  the  determination  of  frequency  of  the  location  and  level  of  each element of the Permanent Works shall comply with the 

(28)

 

requirements of Appendix AG1.1; 

(2)  the  determination  of  accuracy  for  the  location  and  level  of  the  Permanent  Works  shall  be  commensurate  with  the  construction tolerances that are applicable to the Permanent  Works; and 

(3)  if  a  concession  has  been  permitted  by  the  PDP  for  a  deviation  from  the  required  level  and  or  alignment,  then  sufficient  additional  points  shall  be  provided  to  define  the  full extent of each deviation. 

Measurement  Units 

G1.11.7  The  units  of  measurement  for  recording  the  as‐built  location  and  level of the Permanent Works shall be as follows:      • Linear Measurements:  Metres  • Vertical Measurements :  Metres  • Angular Measurements:  Clockwise from 0 to 360 Degrees.  • Azimuth:      Local Plane Rectangular System  Deformation  Monitoring  G1.11.8  Where a part or a section of the Permanent Works is constructed on  reclaimed land, the Works Package Contractor shall submit, at least  twenty‐eight  (28)  days  prior  to  the  completion  of  any  part  of  such  work,  details  of  the  surveys  required  for  the  monitoring  of  both  vertical  and  horizontal  movement  of  the  completed  works.    These  details shall, without limitation, define:      a)  The extent of each survey.  b)  The time between the completion of the work and the Initial  Survey.  c)  The frequency of the subsequent surveys.  d)  The format in which the data will be recorded.  e)  The format and frequency for reporting the results of these  surveys to the PDP.  Main Survey  Control Points  for Other  Works  Contractors 

G1.11.9  The  Works  Package  Contractor  shall  provide  and  protect  until  handed  over  a  series  of  Main  Survey  Control  Points  for  the  Other  Works  Contractors.    They  shall  be  ready  one  month  prior  to  the  access  of  the  Other  Works  Contractor.    The  maximum  spacing  between  the  Main  Survey  Control  Points  shall  be  no  more  than  250m and shall be inter‐visible.  The materials for the survey marker  shall  be  proposed  by  the  Works  Package  Contractor  and  approved  by  the  PDP.    Main  Survey  Control  Points  shall  be  placed  such  that  they  remain  accessible  before,  during  and  after  track  construction.   Detailed  requirements  for  the  Main  Survey  Control  Points  for  different structures are specified below. 

(29)

 

    a)  Tunnel and Station Structure 

  Main  Survey  Control  Points  shall  be  established  for  each  tunnel  bore  on  each  track  inside  the  Stations.    The  Survey  Control  Points  shall  be  located  on  the  tunnel  roof  or  walls  clear  of  the  track  and  walkway  concrete.    Additional  points  shall be installed at each level within the station to suit the  Other Works Contractor’s requirements. 

b)  Viaduct Structure 

  Main Survey Control Points shall be established for the Down  Track only if they are visible for both tracks on  the viaduct.   Otherwise  additional  Main  Survey  Control  Points  along  the  Up  Track  will  be  required.    The  Main  Survey  Control  Points  shall  be  located  on  the  upper  surface  of  the  viaduct  deck  within 1m distance from the column pier at the fixed end of  the viaduct deck. 

    c)  At Grade 

  Main  Survey  Control  Points  shall  be  established  within  20m  of  the  mainline  tracks.    Otherwise  additional  Main  Survey  Control  Points  will  be  required  for  other  tracks.    The  Main  Survey  Control  Points  shall  be  located  offset  from  track  centre line and clear of the ballast on fixed structures. 

As Built Survey  Record 

Drawings 

G1.11.10  The  Works  Package  Contractor  shall  prepare  and  maintain  a  set  of  drawings  of  the  Permanent  Works  to  show  the  as‐built  survey  records  in  accordance  with  Appendix  AG1.1  and  to  identify  all  deviations  thereto,  whether  due  to  the  PDP’s  instructions,  the  Works Package Contractor’s method of construction, site conditions  or  any  other  reason.  Unless  otherwise  permitted  by  the  PDP,  the  Works  Package  Contractor  shall  ensure  that  the  data  from  the  as‐ built  surveys  is  incorporated  into  the  As  Built  Survey  Record  Drawings  and  submitted  for  approval  within  fourteen  (14)  days  of  the  date  of  the  as‐built  survey.  The  preparation  and  submission  of  As Built Survey Record Drawings shall comply with the requirements  of the PDP’s CAD standards. 

Deliverables  G1.11.11  (1)  One  complete  set  of  As  Built  Survey  Record  Drawings,  in  a  form  acceptable  to  the  PDP,  shall  be  signed  by  the  Works  Package Contractor’s Survey Manager as being a true record  of the Permanent Works as built.  The As Built Survey Record  Drawings shall be submitted to the PDP and approval prior to  applying  for  a  Certificate  of  Practical  Completion  for  the  relevant Section or for the whole of the Works. 

    (2)  One  complete  set  of  As  Built  Survey  Record  Drawings  shall  comprise the following: 

(30)

 

    (a)  Three (3) A1 size paper prints of each drawing. 

(b)  One (1) A1 size negative copy of each drawing.  (c)  Two (2) sets of electronic CAD files. 

    (3)  Further  to  Clause  G1.7(2),  As  Built  Survey  Record  Drawings  may also form part of the “As‐built” drawings, if acceptable  to the PDP, and provided in the quantities specified in Clause  G1.7(3).  Monthly  Report  G1.11.12  The Works Package Contractor shall include in his monthly report a  section  covering  the  Survey  Works.    This  section  of  the  monthly  report  shall  comment  on  the  Survey  Works  undertaken  and  the  Survey  Records  completed.    The  report  shall  also  show  planned  Survey Programmes for the following month. 

   

(31)

 

APPENDIX AG1.1 

REQUIREMENTS FOR AS‐BUILT SURVEYS 

 

ITEM  REQUIREMENTS FOR AS‐BUILT SURVEYS  AS BUILT SURVEY 

RECORD DRAWINGS   EARTHWORK AND PAVEMENTS    1)  Earthworks and  landscaping  Location and levels at a grid of 20m centres Location Plan 2)  Roads & Footpaths Cross‐sections at maximum of 20m intervals for each layer.   Level points on each cross‐section not to exceed 10m intervals  and to include each change of horizontal and vertical  alignment, the centre‐line and the edges of each layer.  All  street furniture and manholes  Location Plan and  cross‐sections  showing all layers 

3)  Car‐parks  As for item 1  Location Plan and 

cross‐sections  showing all layers 

 

STRUCTURES 

 

4)  Piles and Pile Caps  Founding level, cut‐off level & locations. Location Plan

5)  Foundations,  footings  Founding levels at 5m centres; location & level of top  foundation concrete; location of anchor heads; location and  level of top of left in underground Temporary Works.  Location Plan 6)  Floor slabs  Location & levels of underside & finished floor surface at 5m  centres  Location Plan

7)  Columns  Location of centre‐point at column head & foot Location Plan

8)  Walls  Location of inner & outer faces at each end of wall, at vertical  construction joints and at any changes of alignment.  Where  top of wall is exposed the finished levels at 5m centres and at  any changes of alignment.  Location Plan 9)  Beams  Location of centre‐line and soffit level at each end of beam or  at maximum 10m centres  Location Plan

10)  Elevated slabs  Location & level to top surface at 5m centres Location Plan

11)  Tunnels and  Station Platforms  Eight points wriggle survey (as built) at 2m centres Location Plan 12)  Viaduct  Cross Sections not to exceed 5m intervals plus at all  Movement Joints  Location Plan   DRAINAGE WORKS    13)  Storm water drains  sewer drains, or any  graded pipe works  Location & level of storm water drains invert, sewer drains  invert, and pipe invert every 50m & at each change of  horizontal or vertical pipe alignment, type & size of storm  water drain, sewer drain, and pipe.  Plan and long‐ section showing  changes of grade,  invert levels, drain  types and sizes, pipe  types & sizes and the  depth below the  designed top of  earthworks or layer  work 

(32)

 

ITEM  REQUIREMENTS FOR AS‐BUILT SURVEYS  AS BUILT SURVEY 

RECORD DRAWINGS 14)  Manholes, Septic  Tanks & Soak‐aways Location, size & type of manhole, & manhole cover & invert  level.  Incoming & outgoing pipelines, size and invert level  Include in above  plans 

15)  Outfalls  Location and invert level Include in above 

plans 

16)  Headwalls  Location and level Include in above 

plans 

17)  Gullies  Location, level depth and size Include in above 

plans  18)  Sumps, pumps  rodding eyes, etc  Locations, size and type Include in above  plans  19)  Pipe work  Location, level of top of earthworks or layer works & level of  pipe centre‐line every 10m and at each change of horizontal or  vertical pipe alignment, pipe type and pipe size.  Location Plan

20)  Valves, Unions  Location, size and type Expansion Joints, Pump, etc. Location Plan

          END OF SECTION 

(33)

     

SECTION G2 

THE SITE 

 

Access to the  Site  G2.1  (1)  The Works Package Contractor will be given access to the Site  in accordance with the Conditions of Contract. 

(2)  The  Works  Package  Contractor  shall  at  all  times  permit  and  facilitate access to the Site and the Works by the staff of the PDP,  Supervising  Consultant,  and  all  other  personnel authorised by the PDP. 

(3)  The  Works  Package  Contractor  shall  at  all  times  permit  and  facilitate access to the Site by Government departments and utility  undertakers,  and  other  Relevant  Authorities  for  the inspection  and  maintenance  of  their  facilities  located  within the Site. 

(4)  The  Works  Package  Contractor  shall  permit  and  facilitate  access to the Site and the Works by Other Works Contractors  during  the  times  specified  in  the  Contract  or  as  otherwise instructed by the PDP. 

(5)  Unless  otherwise  permitted  by  the  Contract,  the  Works  Package  Contractor  shall  maintain  ingresses  and  egresses  (including  designated  emergency  access  routes)  to  all  properties  and  facilities  within  and  around  the  Site.    Any alternative  access  arrangements  proposed  by  the  Works  Package  Contractor  shall  be  safe  and  free  from  hazards  and  shall  be  subject  to  the  approval  of  the  Relevant  Authorities  and of the PDP. 

    (6)  The Works Package Contractor shall be responsible for liaising  with and obtaining permission from all owners / occupiers of private  land  and  properties  in  order  to  gain  access  to  such properties  for  the  purpose  of  carrying  out  survey  works,  monitoring works, investigation works and the like. 

Site restrictions  G2.2  (1)  The particular use to which the Site is put shall be submitted for  approval  by  the  PDP  and  the  Works  Package  Contractor shall: 

    a)  confine  his  use  of  the  areas  of  the  Site  to  purposes  having  been  approved  by  the  PDP  who  reserves  the right  to  extend,  amend  or  restrict  the  uses  to  which areas  of  the  Site  will  be  put,  which  right  shall  not  be unreasonably applied; 

    b)  refrain from depositing rubbish or causing nuisance or 

(34)

 

approved by the PDP, depositing earth on or removing earth from areas of the Site; 

    c)  refrain  from  obstructing  manholes,  utility  access

points and the like. 

    (2)  Work other than that necessary for completion of the Works  shall not be carried out on Site. 

    (3)  At all times whilst the Works Package Contractor has access to  the Site, he shall provide means of distributing loads imposed by  Works  Package  Contractor’s  Equipment  and  traffic  and  prevent damage to utilities and services. 

    (4)  Except  where  otherwise  provided,  the  Works  Package  Contractor shall not permit any person to reside on the Site. 

    (5)  Unless otherwise stated, the Works Package Contractor shall  pay all rates and charges of any nature whatsoever arising out  of  his  use  of  the  Site  and  all  other  works  areas  provided  therein under the Contract. 

    (6)  The  location  and  size  of  stockpile  material,  including excavated  material  within  the  Site,  shall  be  submitted  for approval by the PDP. All stockpiles  shall be maintained at all times in a stable condition. 

    (7)  The  Works  Package  Contractor  shall  not  allow  animals  to  be  brought onto the Site.  Site services  G2.3  (1)  The Works Package Contractor shall provide all site services as  necessary and appropriate for the construction of the Works, which shall include, but not necessarily be limited to:      a)  electricity;  b)  water;  c)  compressed air;  d)  site communication facilities;  e)  temporary drainage and sewage disposal;  f)  temporary fire protection systems;  g)  temporary lightning protection;  h)  dangerous goods stores; and  i)  temporary lighting facilities. 

    (2)  Such  services  shall  be  provided  by  the  Works  Package  Contractor  for  use  solely  in  connection  with  the  proper  execution  of  the  Works.  The  Works  Package  Contractor  shall 

(35)

 

comply  with  all  regulations  of  the  utility  undertakers  and  Government  Departments  concerned.  The  Works  Package  Contractor  shall  provide  and  maintain  all  installations  associated with such services and in relation thereto shall take all reasonable precautions to safeguard the safety and health of  all  persons  and  the  security  of  the  Site.  The  PDP  may require  the  immediate  disconnection  or  alteration  of  such  installations  or  portions  thereof  as  he  considers  to  be prejudicial to safety, health or security. As soon as any or all of the Works Package Contractor's installations are no longer  required for the execution of the Works, they shall be entirely removed to the satisfaction of the PDP. 

    (3)  All  installations  shall  comply  fully  with  all  appropriate statutory requirements. Pipes, tubes, ducts or cables crossing highways, footpaths, or rights of way shall be ramped over or recessed  below  the  surface.  Specific  services  shall  comply  with the following:‐ 

    a)  Electricity 

      The  electricity  supply  shall  comply  with  the

requirements of Section G7 herein. 

    b)  Water 

      An adequate supply of potable water shall be provided

at  the  Site,  including  provision  to  the  satisfaction  of the water supply authority of any storage tanks so that  sufficient  potable  water  is  always  available  for  the execution of the Works.  

    c)  Compressed Air 

      Except  in  pressurised  workings,  the  compressed  air

supply for pneumatic tools and equipment shall be at a pressure of not more than 0.9MN/m2 or other such  pressure  as  may  be  limited  by  prevailing  regulations.  Details  of  proposed  air  supply  for  use  in  pressurised  workings  shall  be  submitted  by  the  Works  Package  Contractor for approval by the PDP. 

    d)   Site Communication Facilities 

      The  Works  Package  Contractor  shall  install  efficient  means  of  site  communications  including  messenger, telephone  and,  where  appropriate,  two‐way  radio  to  the satisfaction of the PDP. In tunnel work, the Works  Package  Contractor  shall  install  telephone  communication  between  tunnel  faces,  bottoms  and tops  of  shafts  and  the  Works  Package  Contractor's  office  and  PDP's  office.    Temporary  telephone  points 

(36)

 

along tunnels shall be provided at every 500 metres. 

    e)  Temporary Tunnel and Subway Ventilation 

  The  temporary  ventilation  system  for  tunnels  and subways  shall  achieve  a  minimum  air  velocity  of  0.3  m/sec  and  shall  prevent  still  air  in  equipment  rooms,  cross  passages  and  niches.    The  Works  Package  Contractor  shall  ensure  that  all  emissions,  discharges  or  operations  shall  include  local  ventilation  to  ensure suitable  emission  dilution.    If  additional  ventilation  is  required  to  support  the  activities  of  the  Works  Package Contractor in accordance with the air quality  guidelines  of  BS6164,  this  shall  be  provided  by  the Works  Package  Contractor.    All  practical  measures  shall be taken, including the use of catalytic converters  to ensure that diesel operating plant is maintained and operated  to  a  high  standard  in  order  to  minimize emissions and ensure maximum dilution. 

    (4)  The PDP will instruct the Works Package Contractor as to the  requirements  for  site  services  to  be  connected  to  the  PDP's  portable  site  accommodation  at  any  given  location  and  the Works  Package  Contractor  shall  provide  and  maintain  these  services during his use of the Site. 

Site cleanliness  G2.4  (1)  The  Site  shall  be  maintained  in  a  clean  and  tidy  condition.  Materials,  including  materials  required  for  Temporary  Works shall be stored in an orderly manner.  Rubbish, debris, cement bags, disused formwork, disused packaging and the like shall  be  disposed  of  at  least  once  a  day  and  the  works  areas cleaned by flushing with water if necessary so that the Site is  kept  constantly  clean  and  tidy.    Notwithstanding  the  above, the Works Package Contractor shall also place rubbish bins at  strategic locations throughout the Site.  

    (2)  The Works Package Contractor shall throughout the period of  the Contract provide a central debris collection point on Site, as  approved  by  the  PDP.    Other  Works  Contractors  shall  be  required  to  deposit  their  debris  in  this  collection  point  on  a daily basis and the Works Package Contractor shall at his own  expense  procure  the  regular  collection  and  removal  of  such debris  from  the  Site.  After  every  works  shift,  all  work  areas shall be cleaned and made tidy to the satisfaction of the PDP.

    (3)  As  part  of  the  Works  Package  Contractor’s  general  housekeeping,  the  removal  of  all  unused  materials, construction  detritus,  general  waste,  redundant  packaging and  the  like,  shall  be  planned  and  carried  out  on  a  regular basis, and which shall also be part of his fire control strategy for  the  Site.  In  addition,  the  Works  Package  Contractor’s

(37)

 

housekeeping procedures shall also include the monitoring of waste  and  detritus  produced  and  left  on  the  Site  by  Other Works  Contractors  to  ensure  that  the  Other  Works Contractors  are  also  removing  such  materials  from  the  Site  expeditiously,  and  to  alert  the  PDP  in  cases  of  non‐ cooperation in such matters. 

    (4)  The  Works  Package  Contractor  shall  ensure  that  no  earth,  debris, or rock is deposited on public or private rights of way as  a  result  of  the  Works,  including  any  deposits  arising  from  the movement of Works Package Contractor’s Equipment. All  roads,  both  within  and  external  to  the  Site  which  are impacted on by the Works shall be kept in clean condition by the Works Package Contractor. All haul roads will be regularly  graded and watered, as necessary to minimise dust nuisance.

    (5)  The  Works  Package  Contractor  shall  provide  and  maintain  a  patrol  unit  for  the  duration  of  the  Contract.    The  unit  shall comprise one (1) foreman and two (2) labourers who shall all  be  delegated  full‐time  to  the  unit.    The  main  duties  of  the  patrol  unit  shall  include  the  up  keeping  of  proper  lighting,  signing and guarding provisions as well as other related duties as directed from time to time by the PDP. 

    (6)  The  patrol  unit  shall  be  required  to  work  outside  the  Works  Package Contractor's  normal  working  hours  if  so  required by  the PDP. 

    (7)  The  Works  Package  Contractor  shall  provide  all  necessary  protective  clothing,  safety  equipment,  hand  tools,  ladders, trestles,  power  supply,  replacement  equipment  and  the  like for the exclusive use of the patrol unit. 

Parking  Facilities 

G2.5  (1)  The  Works  Package  Contractor  shall  provide  adequate  parking  facilities  for  mobile  equipment  and  vehicles  on  or  close to the Site. 

(2)  The  parking  facilities  shall  provide  adequate  space  for  parking  all  mobile  equipment,  works  vehicles,  delivery  vehicles, staff transportation vehicles and visitors’ vehicles.  (3)  Where the parking facilities are located on the Site, covered 

walkways shall be provided between the parking areas and  Site  facilities  such  as  offices,  storage,  and  accommodation  areas. 

(4)  Where the parking facilities are located away from the Site,  shuttle  bus  services  and  covered  waiting  areas  shall  be  provided to facilitate the movement of people between the  parking facility and the Site. 

(38)

 

mobile equipment or vehicle to be parked in areas that are  not designated parking facilities. 

(6)  The Works Package Contractor shall at all times ensure that  public  nuisance  is  not  caused  by  the  parking  of  mobile  equipment and vehicles associated with the Works. 

  G2.6  Site Pest Control 

Rodent Control  G2.6.1  The  Works  Package  Contractor  shall  at  all  times  take  effective  measures  to  prevent  damage  by  rodents  to  the  Permanent  Works and  constituent  parts  thereof,  such  as  cables,  electronic  cards,  etc., during the  execution of the Works and shall advise the PDP of such measures taken accordingly. 

Prevention of  mosquito  breeding 

G2.6.2  Measures  shall  be  taken  to  prevent  mosquito  breeding  on  the  Site. The measures to be taken shall include the following: 

a)  Empty cans, oil drums, packings and other receptacles which may  retain  water  shall  be  deposited  at  a  central  collection  point and those not required for future use shall be removed from the Site regularly. 

b)  Standing  water  shall  be  removed  or,  where  this  is  not practicable  treated  at  least  once  every  week  with  an environmentally  acceptable  product  which  will  prevent  mosquito breeding. 

c)  Works  Package  Contractor’s  Equipment  and  other  items  on  the  Site  which  may  retain  water  shall  be  stored,  covered  or treated in such a manner that water will not be retained. 

Conditions for  temporary land  allocation 

G2.7  The  Works  Package  Contractor  shall  comply  with  the  obligations,  requirements  and  restrictions  applicable  to  any  land  allocation  for  the Works Package Contractor's use. 

Site Security  G2.8  (1)  The  Works  Package  Contractor  shall  establish,  operate,  and  maintain a security system for the Site in accordance with the requirements of the Particular Specification. 

    (2)  The  Works  Package  Contractor  shall  provide  adequate  training  for  his  security  staff  to  ensure  that  they  are  able  to  discharge their security duties properly. 

    (3)  The PDP’s security staff shall conduct inspections and security audits on the Site from time to time, and the PDP shall notify the  Works  Package  Contractor  of  any  required  remedial  measures  or  recommended  improvements  to  the  Works  Package  Contractor’s  security  system  arising  from  such  inspections and audits.  

General Works  Trains 

G2.9  (1)  The PDP will arrange for General Works Trains to be used by the  Works  Package  Contractor  and  Other  Works  Contractors 

References

Related documents