• No results found

Interface Control Document 

In document MRT Works General Specification (Page 185-195)

QUALITY ASSURANCE AND QUALITY CONTROL 

2.  Interface Control Document 

  The  Interface  Control  Document  shall  cover  the  content  set  out  in  the  following  table  wherever applicable.   The demarcation of works to be provided by each Works Package  Contractor shall be clearly stated.      Interface Control Document (Typical Table of Contents)    1    Introduction    2    Reference Documents    3    Abbreviations and Definitions    4    Interface Task Allocation      4.1  Interface Task Allocation Table    5    Interface Details:      5.1  System Configuration         5.1.1    Interface Demarcation Diagram      5.2  Physical Interface 

      5.2.1  Nature,  Naming  Convention,  Location  and  Quantity  Nature, Location and Quantity        5.2.2  Electrical Interface        5.2.3  Mechanical Interface      5.3  Functional Interface      5.4  Protocols      5.5  Software and Data Interface      5.6  Design Constraints      5.7  Environmental conditions and Electromagnetic Compatibility    6    Scope of Supply    7    Delivery and Installation    8    Inspection and Testing      8.1  Test Methodology      8.2  Protocol Tests      8.3  Independent Tests      8.4  Point‐to‐Point Tests      8.5  Integrated System Functional Tests      8.6  Logical sequence and dependence of the Tests    9    Interface Requirement Verification Matrix    10    Programme     

    Appendices and Drawings    App  1  Detailed Data Interface Schedules    App  2  Cables Termination Schedules / Drawings    App  3  System Start‐up parameters    App  4  Access dates, Key dates and schedule for information exchange    App  5  List of critical interface items     App  6  Table of Deliverables    App  7  Time Schedule for Inspection and Testing                    END OF SECTION 

     

SECTION G14 

DOCUMENT MANAGEMENT 

  Documents,  submissions and  correspondence 

G14.1  (1)  All  documents  which  shall  be  submitted  to  the  PDP  in  accordance with the requirements of the Contract, shall be  provided  in  the  standards  established  by  the  PDP.  Documentation  and  drawings  shall  consist  of  a  series  of  diagrams,  schematics,  drawings,  layouts,  plans,  tables,  method  statements,  handbooks,  manuals  etc.  which  together  shall  comprehensively  describe  and  detail  the  whole of the Works in every respect.  Such documentation  and drawings shall contain sufficient information and details  so as to facilitate provision of the Works and to permit the  Railway Operator to eventually maintain, operate and carry  out engineering modifications to the Works. 

    (2)  Copies  of  correspondence  relevant  to  the  execution  of  the Works  and  received  from  or  dispatched  to  Relevant Authorities,  utility  undertakings  and  Other  Works Contractors shall be provided to the PDP for information as soon  as  possible  but  in  any  case  not  later  than  one  (1) working day after receipt or dispatch. 

    (3)  All  documents  shall  be  submitted  to  the  PDP  in  both  hard and  soft  copy  format.  For  soft  copies,  the  associated electronic  files  shall  be  submitted  as  a  Portable  Document Format  (PDF)  file  converted  either  from  a  scanned  copy  of the  printed  document  or  directly  from  the  original  native electronic file.  Each document shall be submitted as a single PDF file, except in cases where the file size exceeds 100MB in which case the document may be submitted as multiple files. For  the  submission  of  deliverables,  a  copy  of  the  original native electronic files used to create the document shall also be provided. 

    (4)  All  documentation  shall  be  clearly  legible,  comprehensively indexed,  fully  cross  referenced,  set  out  logically  and consistent  in  the  use  of  symbols,  texts,  layouts,  title  boxes etc.    Each  and  every  sheet  of  documentation  and  drawings shall contain at least but not limited to the following: 

    a)  Project title; 

b)  Originator;  c)  Main title;  d)  Sheet Number; 

 

e)  Sheet Title; 

f)  Issue  Type  e.g.  Preliminary,  Inspection,  Approval, Construction, Testing, As‐Built etc.; 

g)  Modification Status; 

h)  Revision Number and Date; and 

i)  Signature  in  respect  of  preparation,  checking, approval of originating organisation. 

    (5)  The  hard  copy  of  all  documents  shall  be  the  contractual copy.  Before electronic files of documents are submitted to the PDP, the Works Package Contractor shall verify that the electronic files exactly match the hard copy documents. 

    (6)  Unless  otherwise  specified  or  as  instructed  by  the  PDP,  the Works Package Contractor shall submit the number of copies of  documentation  and  drawings  to  the  PDP  based  on  the following:  For Document Submissions:      Issue No. of Copies Inspection / Approval 3 (A4 or A3 size) Testing Records / Reports 2 (A4 or A3 size) Monthly / Weekly Reports 3 (A4 or A3 size) Commissioning / Maintenance Copies 2 (A4 or A3 size) Final As‐Built Records 4 (A4 or A3 size)

Final  Manuals,  Handbooks  etc.  (including  operational manuals) 

6 (A4 or A3 size)

General submissions other than the above 3 (A4 or A3 size)

 

      All of the above shall also include one (1) electronic copy on CD ROM in pdf format and in the native file format. 

    For Drawing Submissions: 

  One  (1)  A1  size  original,  three  (3)  sets  of  A1  prints,  six  (6) unbound  sets  of  A3  size  prints  reduced  from  the  A1  size original,  six  (6)  electronic  copies  (AutoCAD  and  pdf  file formats),  and  a  drawing  list  in  hard  copy  and  soft  copy (WORD or EXCEL file). 

  G14.2  Electronic File Formats 

Standard format  for electronic files 

G14.2.1  For deliverables which are to be submitted in electronic format, the submission  shall  be  in  English  version  and  shall  comply  with  the

  following formats compatible with Intel®/Windows® based personal computers, or their natural successors, unless otherwise specified in the Contract:      • Text documents – Microsoft Word (.doc or .docx format)      • Spreadsheets – Microsoft Excel (.xls or .xlsx format)      • Presentations – Microsoft PowerPoint (.ppt or .pptx format)      • Databases – Microsoft Access (file format to be agreed with the PDP)      • Programming / Scheduling – Primavera P6      • CAD produced drawings – Refer to the PDP’s CAD Guidelines      • Digital Photographs (as individual files) – JPEG format (minimum size of 5 megapixels and minimum resolution of 300dpi) 

    • Scanned  documents  –  PDF  format  at  a  minimum  resolution  of 300dpi 

Document layout  standard 

G14.2.2  To  ensure  consistency  and  to  enable  automatic  uploading  of submitted  electronic  data,  where  applicable  and  specified  in  the Contract, the Works Package Contractor shall:      a)  use the electronic document templates provided by the PDP in preparing his submissions; and      b)  use the application systems provided by the PDP in, but not limited to, entering and uploading project data, data analysis and report generation. 

Copy protection  G14.2.3  The  Works  Package  Contractor  shall  provide,  together  with  the submission,  any  applicable  decryption  key,  password  or  certificate to enable the PDP to review the submitted electronic data.  Submission media  G14.2.4  Electronic files shall be submitted on CD‐ROM discs or other media approved by the PDP.  Submissions  programme   

G14.3  (1) The  Works  Package  Contractor  shall,  within  thirty  (30)  days of the date of the Letter of Acceptance, submit a programme covering all proposed submissions to the PDP. 

(2) The  submissions  programme  shall  include  each  submission stated in the Contract as being required to be submitted.  (3)  The submission programme shall ensure that all submissions

are  properly  co‐ordinated  with  the  Works  Package Contractor’s  overall  programme,  particularly  in  respect  of the following:‐ 

  testing work;  b)  Co‐ordination with Other Works Contractors;  c)  Including due allowance for the PDP’s review process to be undertaken and including the time needed for any re‐submissions. 

(4)  The  Works  Package  Contractor  shall  include  in  the  monthly report, a full list of all submissions and their current status in comparison  to  the  submissions  programme.    Reasons  shall be  provided  for  any  delayed  submission  and  the  proposed corrective  action  that  will  ensure  that  the  delay  does  not affect  any  overall  or  stage  completion  dates,  particularly those that interface with other parties.  Submission and  review procedure    G14.4  (1)  Except where specific procedures are given for certain items, all submissions shall be submitted and reviewed according to the procedure laid down in the following clauses.  The Works Package  Contractor  shall  demonstrate  that  individual submission  documents  have  been  subject  to  his  internal review process prior to submission to the PDP. 

(2)  Each submission shall be made under cover of a submission form  and  include  a  brief  introduction  to  explain  to  which sub‐system,  part  or  section  of  the  Works  the  submission refers,  listing  the  documents  enclosed  with  the  submission, and  describing  in  outline  how  all  relevant  requirements  of the Specifications are achieved by the proposals.      (3)  Within twenty one (21) days of receipt of the submission, the PDP shall respond to the Works Package Contractor in one of three codes:  (a)  CODE 1: Approved (Work May Proceed);  (b)  CODE 2: Approved With Comment; and  (c)  CODE 3: Resubmit (Physical Work Cannot Proceed). 

    (4)  If  the  PDP,  having  reviewed  the  submission,  has  not discovered any non‐compliances under the Contract, he shall respond  with  the  review  status  ‘Approved’,  and  which  shall entitle the Works Package Contractor to proceed to the next stage of the programme of work. 

    (5)  If  the  PDP  discovers  minor  non‐compliances,  discrepancies, or  omissions  etc.  that,  in  his  opinion,  are  not  of  a fundamental  nature,  he  shall  respond  with  ‘Approved  With Comments’, including a list of the features that require to be amended, included or improved to comply with the Contract. Issue of such a response serves as a notice of Approval which

 

entitles  the  Works  Package  Contractor  to  proceed  to  the next stage of the programme of work provided that all of the PDP’s  comments  are  adequately  addressed  within  fourteen (14) days from the issue of the PDP’s comments. 

    (6)  If  the  PDP  discovers  major  non‐compliances,  discrepancies, or  omissions  etc.  that,  in  his  opinion,  are  of  a  fundamental nature,  he  shall  respond  with  ‘Resubmit’,  including  a  list  of the  features  that  require  to  be  amended,  included  or improved  to  comply  with  the  Contract.  Issue  of  such response  serves  as  a  notice  of  rejection  which  does  not entitle  the  Contractor  to  proceed  to  the  next  stage  of  the programme  of  work  until  all  of  the  PDP’s  comments  are adequately  addressed  and  a  re‐submission  has  been approved by the PDP. 

    (7)  The  Works  Package  Contractor  shall  attend  meetings  to review submissions and related activities on a regular and/or ad hoc basis, upon receiving reasonable notice from the PDP. 

    (8)  Any  approval,  check,  certificate,  consent,  examination, inspection,  instruction,  notice,  proposal,  request,  test,  or similar  act  by  the  PDP  (including  absence  of  disapproval) shall not constitute a waiver nor relieve the Works Package Contractor  from  any  responsibility,  obligations  or  liabilities he has under the Contract, including responsibility for errors, omissions, discrepancies and non‐compliances. 

Project records  G14.5  (1)  The Works Package Contractor shall use a database program for  registering  all  the  Project  documents  following  the document numbering schemes approved by the PDP. 

    (2)  The  Works  Package  Contractor  shall  ensure  the  full  and timely submission of the Contract Deliverables. 

    (3)  The  Works  Package  Contractor  shall  establish  and  maintain the  Project  records  containing  the  originals.  The  index  for the  Project  records  shall  be  kept  up  to  date  and  shall indicate the location of the files for ease of access. 

    (4)  The  Works  Package  Contractor  shall  maintain  the  Project records files in good condition, and filed in accordance with the prescribed document numbering system, if applicable, or any other established indexing system. 

    (5)  The  Works  Package  Contractor  shall  control  access  to  the Project  records  and  removal  of  the  records  temporarily  or permanently  until  the  Project  records,  in  part  or  in  their entirety, are handed over to the PDP on an on‐going basis or at the practical completion of the Works. 

 

identify the types of records to be handed over for review by the  PDP  ninety  (90)  days  in  advance  of  the  intended  hand over of any Project records or earlier as required by the PDP including  those  at  the  time  when  the  Works  Package Contractor applies for a Certificate of Practical Completion of the  Works.    The  final  documents  handed  over  to  the  PDP shall be in hard copy and include software copy on ROM disc media  or  hard  disk  format.  The  hard  copies  and  electronic files  shall  bear  document  numbers  and  revision identifications. 

    (7)  Site Records Office: 

a)  The  Works  Package  Contractor  shall  establish  and maintain  at  the  Site  a  records  office  which  contains the Project documents until such time the documents are all handed over to the PDP. 

b)  Site Records ‐ The Works Package Contractor shall file and  store  in  the  Site  records  office  all  documents which  relate  to  the  quality  and  as‐constructed condition of the Works including, without limitation: i)  Controlled  copies  of  quality  system

documents; 

ii)  Progress  records  or  progress  reports  not previously submitted to the PDP; 

iii)  Certificates  for  manufactured  goods  and materials; 

iv)  Records of sampling, inspections and tests;  v)  Records  of  inspections  by  Relevant

Authorities; 

vi)  Reports  of  nonconformities  and  their disposition; 

vii)  Reports and data relating to concessions;  viii)  Records of surveys of the Permanent Works or

E&M parts of the Permanent Works; 

ix)  Any  construction  or  manufacturing  drawings containing  marked  up  details  of  as‐built dimensions or properties; 

x)  Any other data relevant to the as‐constructed Permanent Works; and 

 

required by the PDP. 

    c)  The documents stored at the Site shall be the original

versions  and  not  photocopies  unless  the  original versions  have  been  dispatched  to  the  PDP  or  third parties  and  are  no  longer  in  the  Works  Package Contractor's possession. 

    d)  Filing and storage: 

  All  documents  shall  be  filed,  indexed  and  suitably stored  to  permit  easy  identification  and  access  on  a frequent  basis.  Media  containing  master  copies  of electronic  files  of  all  deliverables  and  Contract  data shall  be  stored  in  a  safe  with  a  four  (4)  hour  fire rating. 

    e)  Each records office shall be suitably sized, have a fire rating of at least 2 hours and, as a minimum, 24‐hour air  conditioning  for  humidity  and  temperature control. 

    f)  The Works Package Contractor shall ensure that each

records  office  is  provided  with  adequate  colour photocopying facilities and shall provide the PDP with such photocopies of the stored documents as he may request. 

    g)  Take over of documents: 

  The  Works  Package  Contractor  shall  ensure  that  the Project records are properly filed and indexed and in a  fit  condition  to  be  taken  over  by  the  PDP  at  the time that the Works Package Contractor applies for a Certificate of Practical Completion for the Works. The Works  Package  Contractor  shall  provide  the  Site records  documents  for  final  handover.    The  Works Package  Contractor  shall  provide  detailed  filing indexes  to  the  records  to  be  handed  over  when  the PDP notifies his intention to takeover the documents or the Works Package Contractor shall, not later than thirty  (30)  days  before  the  anticipated  date  of applying  for  a  Certificate  of  Practical  Completion  for the  Works,  notify  the  PDP  that  such  documents  will be available for collection. 

    h)  At the appropriate time as determined by the PDP, or

within fourteen (14) days of receipt of an application for  a  Certificate  of  Practical  Completion  for  the Works,  or  upon  termination  of  the  Works  Package Contractor's  employment  under  the  Contract,  the

 

PDP  may  notify  the  Works  Package  Contractor  that the PDP intends to take over the Project documents, in  which  case  the  Works  Package  Contractor  shall allow  the  PDP  immediate  access  to  such  documents and  shall  provide  a  detailed  filing  index,  provide  the materials and labour in packaging and transferring all the  records,  as  agreed  by  the  PDP,  certify completeness  of  the  records  and  do  all  other  things necessary for the purpose of transferring them to the custody of the PDP. 

    i)  Upon  notice  being  given  by  the  PDP  or  Works

Package Contractor the Project documents shall vest in the PDP. 

    k)  PDP's custody of documents: 

i)  The PDP shall establish and maintain premises in  which  he  shall  store  any  documents  of  the Works  Package  Contractor  taken  over  for  a period  of  not  less  than  six  (6)  years  from  the completion  of  the  Defects  Liability  Period  for the Works. 

ii)  The PDP shall not, without the consent of the Works  Package  Contractor,  otherwise  destroy or part with possession of any such documents prior to expiration of the period referred to in sub‐clause i) above. 

iii)  The  PDP  shall,  upon  reasonable  notice,  allow the  Works  Package  Contractor  access  to  all documents  taken  over  and  shall  provide copies  of  any  such  documents  as  the  Works Package Contractor might reasonably request.

    l)  Works Package Contractor's custody of documents: 

  The  Works  Package  Contractor  shall  maintain  in Malaysia  his  archive  of  all  documents  in  connection with  and  arising  out  of  the  Contract,  excluding  any documents taken over by the PDP, for a period of six (6) years from the completion of the Defects Liability Period for the Works.          END OF SECTION 

 

   

SECTION G15 

GENERAL  REQUIREMENTS  FOR  BUILDING  SERVICES  AND 

In document MRT Works General Specification (Page 185-195)