2015
MANAGEMENT
OVERSIGHT
PROJECT
Executive Summary
This semi‐annual Report on Project Management Oversight details Service Board efforts in implementing their capital programs. Included are details on all state‐funded projects, regardless of budget, and all systemwide projects with budgets of $10 million or more, regardless of funding source. Information in this report was collected by direct interviews, project meetings, and documented submissions from Service Board project management teams.
The State of Good Repair backlog for the region currently stands at $19.5 billion, and the 10‐ year capital need for normal reinvestment is $16.6 billion. The 49 projects detailed in this report together represent $4,219,298,865 worth of construction, maintenance, and procurement. Many of these projects will address outstanding capital needs, while others are directed to compliance with federal requirements or enhancing customer experience, safety, and security.
Uncertainty of state funding is significantly affecting the capital program, and while all projects are either within budget or under budget, only 48% are on schedule, with many projects on hold due to the unavailability of state funds. If these delays are not considered, 83% of the projects are on schedule. Regarding change orders, the vast majority of the added budget came from decisions by the Service Boards to add value to projects or comply with federal requirements. The remaining change orders were mostly for unforeseen conditions, and a minimal amount was due to errors and omissions.
Although the progress being made on these projects is significant, current capital funding will not support much needed renewal of the region’s aging transit infrastructure. Deferring infrastructure maintenance and replacement has negative impacts on the quality of service provided, including deteriorating service reliability. RTA, in accordance with the Strategic Plan, is committed to seeking stable, long‐term capital funding solutions critical to renewing and maintaining the region’s transit system. RTA and the Service Boards must collectively work to educate the public on the region’s transit needs and advocate for funding.
RTA recognizes the commitment, collaboration, cooperation, and level of effort each Service Board provided for the Report on Project Management Oversight to be a success. RTA is appreciative and pleased to note the exemplary and ongoing commitment of transit agency personnel during this process. RTA will continue to work with the CTA, Metra, and Pace to advocate for more capital funding at both the state and federal level to ensure our transit system continues to prioritize and work towards a State of Good Repair.
Table of Contents
Section I – State‐Funded Projects ...1 Project List ...2 CTA ...3 Metra ...16 Pace ...24 Budget Performance ...28 Schedule Performance ...29 Change Orders ...31 Section II – Systemwide Projects over $10,000,000 ...33 Systemwide ...34 CTA ...40 Metra ...51 Pace ...63Section I
STATE‐FUNDED PROJECTS
SERVICE BOARD PROJECT TITLE BUDGET
CTA Wilson Transfer Station $169,959,391 CTA Perform Rail Car Overhaul (3200 Series) $53,132,149 CTA 95th Street Terminal Improvements $45,451,332 CTA O’Hare Blue Line Station Improvements – Addison to Cumberland $37,334,803 CTA North Red Line Stations – Sheridan $24,000,000 CTA Jefferson Park Intermodal Facility Renovations $15,236,957 CTA Rail Shop Roofs and Bus Washer Replacements $13,457,053 CTA Purple Line Express Track Renewal $11,000,000 CTA 98th Shop – Replace Hoist and Spin Jacks $7,325,000 CTA 74th, 98th, and Midway Shops Tuckpointing $1,930,340 CTA Dearborn Subway Station Improvements – Grand, Chicago, and Division $1,028,240 Metra Replace 160 Bi‐Level Electric MU Commuter Cars $585,100,000 Metra Union Pacific West Line Expansion $44,500,000 Metra Positive Train Control – System Integrator $44,000,000 Metra Auburn Park New Station – Rock Island District $21,500,000 Metra Calumet Station – Metra Electric District $5,500,000 Metra Hazel Crest Station – Metra Electric District $5,000,000 Metra Peterson Ridge New Station – UPR North Line $5,000,000 Metra Romeoville New Station – Heritage Corridor $2,000,000 Pace Purchase 40’ Compressed Natural Gas Buses $49,000,000 Pace Purchase Approximately 84 Paratransit Vehicles $7,290,500 Pace Construct Toyota Park Transportation Center $2,000,000 Pace Bus Stop Improvements – Joliet Multi‐Modal Transportation Center $1,709,500
Wilson Transfer Station
Description:
Replace the existing Wilson Street Station and elevated structure from Montrose Avenue to Leland Avenue with a new four track station with platforms between the express and local tracks. The entire elevated structure will be replaced with new steel columns and concrete track bed from Sunnyside Avenue on the south to Leland Avenue on the north, also replacing the existing bridge over Broadway Street with a full span, eliminating piers in the street right‐ of‐way. The architectural facades of historic buildings under the structure will be preserved.
Status:
Construction is now in Phase 1, which began in March 2015. This phase includes demolition of the existing Track 1 structure, drilling foundation caissons for the new structure, and construction of the new Track 1 structure, southbound platform, and part of the new Track 2 structure.
Budget:
The state‐funded budget amount is $169,959,391. Including additional federal and local funding, the total overall budget is $206,050,539.
Budget Obligated Expended Expended %
State‐Funded Budget $169,959,391 $161,640,984 $33,165,340 20% Overall Project Total $206,050,539 $189,827,051 $53,703,523 26%
Schedule:
The project is on schedule. The Phase 1 Start milestone marked the beginning of three‐track operation through Wilson Station and enabled the start of construction of the station track‐by‐ track. The project is on schedule to begin Phase 2 in March 2016.
Milestone Baseline Schedule Actual (A) / Forecast
Advertise for Proposals March 2014 March 2014 A
Environmental Clearance April 2013 June 2014 A
Notice to Proceed July 2014 July 2014 A
Start Phase 1 March 2015 March 2015 A
Start Phase 2 March 2016 March 2016
Wilson Transfer Station
(continued)
Highlights:
The completed station will provide platforms on all tracks and will allow passengers to change between Purple Line express trains and Red Line local trains. A canopy will cover both platforms; the track beds will be constructed of concrete to reduce noise. New station entrances will be provided on both sides of Wilson Avenue; Sunnyside Avenue will have a station entrance for the first time. There will be no support columns for the track structure within Broadway Street. The terracotta facades of the Gerber Building and Majestic Menswear will be restored. Transit Oriented Development is being pursued for the Gerber Building.
Construction Phase 1 includes the construction of the new Track 1 and the Southbound Platform. The former Track 1 structures have been demolished, caisson foundations were drilled and new columns on the west side of the station have been erected. The work now involves construction of the trackbeds, track, and platform. Partial entrances serving the new Southbound Platform will be opened at Wilson Avenue and Sunnyside. Future site of north auxiliary entrance Foundation walls for ADA ramp at Sunnyside
Rail Car Overhaul and Mid‐Life Rehabilitation
Description:
A programmed rail car overhaul program will provide for renewal of truck, propulsion, and other subsystem equipment on rail cars in the CTA 2600 Series and 3200‐Series rail car fleets to maintain a good state of repair. CTA is also retrofitting the 3200 Series cars with new air conditioning units, auxiliary power supply, destination signs, LED lighting, and security cameras.
Status:
Skokie Shop has completed the 100 cars in the 2600 Series cars project. The 3200 Series project covers 257 cars. The parts contract was awarded and the first kits were received in March 2015. The component rebuild, car overhaul work, and equipment installation is being done by CTA Skokie Shop staff. Some delay was experienced due to the Yellow Line closure and the need to find alternate subsystem manufacturers.
Budget:
The project is on budget.
Budget Obligated Expended Expended %
Project Total $53,132,149 $45,666,613 $8,618,556 16%
Schedule:
Skokie Shop completed the 100 car 2600 Series project phase in June 2015.
For the 3200 Series cars, parts kits were first received in March 2015. Alternate manufacturers were needed for some subsystem equipment; new units are now arriving but some testing will be needed. During the Yellow Line closure, CTA assigned some staff to work in the maintenance shops to get an early start on some modifications and maintain continuous employment of the staff assigned to this project. Based on a production rate of roughly 2 cars per week, these disruptions have introduced about 12 months of delay into this project phase.
Milestone Baseline Schedule Actual (A) / Forecast Complete 100 2600‐Series Cars December 2014 June 2015 A First 3200‐Series Kits Received March 2015 March 2015 A Complete 257 3200‐Series Cars July 2017 July 2018
Rail Car Overhaul and Mid‐Life Rehabilitation
(continued)
Highlights:
In addition to the purchase of new rail cars, CTA has embarked on an aggressive rail car overhaul program to restore these cars to a state of good repair. Performing overhauls as scheduled reduces unscheduled maintenance, improves reliability, and preserves comfort and ride quality. Many underfloor components will not require overhaul for another 12 to 15 years. A Quality Assurance process is in place both at the Contractor and at CTA for this project.
CTA’s innovative use of an outside contractor to provide kitted material has reduced the workload on CTA Procurement and Materials Management and has avoided mixing program material with CTA spare parts. All material was procured from CTA pre‐approved vendors.
For the 3200 Series project, CTA is modernizing subsystems to increase reliability and security including: Air Conditioning System o New Air Conditioning Unit o New AC Controller Propulsion System o Rebuilt Cam Control Group o New Resistor Bank Trucks o New Wheels o Rebuilt Motors, new Armatures Interiors o New LED Lighting o End Door Floor Panels o New Ribbed Flooring Doors o New Door Motors o New Door Hangers o New Thresholds Cab o Rebuilt Master Controller o Rebuilt Hydraulic Pressure Control Auxiliary Power Supply Systems o Security Cameras o Programmable Message Signs
95th Street Terminal Improvements
Description:
This project will expand and greatly improve the 95th/Dan Ryan Red Line station as well as its bus terminal with a new stationhouse comprising north and south bus terminal facilities for the 14 CTA and 5 Pace bus routes that serve the station, in addition to improved pedestrian access.
Status:
Design reached the 90% milestone, at which point, pursuant to the original Construction
Manager/General Contractor (CM/GC) At‐Risk contract, CTA and the CM/GC were to establish a Guaranteed Maximum Price (GMP) for the major scope of the project. Agreement was not reached, and CTA has awarded a Design‐Build contract to begin at the complete the design and construct the project. Advance Package work is ongoing, but is behind schedule. Acquisition of nearby land is nearly complete, with six out of eight parcels purchased.
Budget:
The project is within its revised budget. The state‐funded budget amount is $45,451,332. Including additional funding, the total overall budget is $280,000,000.Budget Obligated Expended Expended %
State‐Funded Budget $45,451,332 $26,877,587 $11,781,612 26% Overall Project Total $280,000,000 $75,249,840 $47,253,007 17%
Schedule:
The project is behind schedule due to utility conflicts discovered during Advance Package work, but these delays are not expected to impact the overall project.Milestone Baseline Schedule Actual (A) / Forecast
Prime Contract Award March 2015 December 2015 A
Project Complete December 2018 December 2018
Highlights:
The conceptual design features safety improvements for CTA and Pace customers. The existing station does not provide direct access to 95th Street, requiring pedestrians to use bus terminal areas for access. The new design will eliminate this hazard while also connecting the north and south bus terminal areas with a pedestrian overpass, avoiding the need for crossings at street level.
O’Hare Blue Line Station Improvements –
Addison to Cumberland
Description:
The scope of work includes rehabilitation of the stations at Addison, Irving Park, Montrose, Harlem, and Cumberland to improve access, safety and convenience. At the station houses, the existing damaged curtainwall will be replaced. At the platforms, the existing canopies will be replaced and sections of the damaged platform edge will be repaired. An elevator will be added at Addison Station.
Status:
Design has reached the 100% milestone for all stations. The design for Addison Station was accelerated since its scope is more extensive. Initial work at Addison to extend the platform and make room for the new elevator is underway.
Budget:
The state‐funded budget amount is $37,334,803. Including additional funding, the total overall budget is $43,000,000.
Budget Obligated Expended Expended %
State‐Funded Budget $37,334,803 $4,853,834 $85,985 0% Overall Project Total $43,000,000 $9,650,228 $2,124,982 5%
Schedule:
The project is on schedule.
Milestone Baseline Schedule Actual (A) / Forecast Design‐Build Notice to Proceed April 2015 April 2015 A
Construction Start October 2015 October 2015 A
Substantial Completion October 2016 October 2016
Highlights:
This project is part of a larger capital improvement program known as “Your New Blue” for the O’Hare Blue Line, which includes additional projects involving track and station renewal. The estimated overall budget for the entire program is $492 million.
North Red Line Stations – Sheridan
Description:
Improvements will be made to Sheridan Station on the north Red Line to provide safe and dry conditions and aesthetic improvements. Various components will be renewed, including lighting, roofs and canopies, platform decking, painting, and accessibility features.
Status:
The project is in the planning phase. CTA has the Project Master Plan and started design. CTA Structure Maintenance forces are renewing steel structure on Track 1, which is out of service due to Wilson Transfer Station phasing and three‐track operation.
Budget:
The project is on budget.
Budget Obligated Expended Expended %
Project Total $24,000,000 $4,187,600 $1,932,387 8%
Schedule:
The project is on schedule. Milestones have been modified to coordinate with the Red and Purple Modernization as well as Wilson Transfer Station.
Milestone Baseline Schedule Actual (A) / Forecast Issue Design Task Order October 2015 October 2015 A
Notice to Proceed November 2015 September 2016
Substantial Completion July 2016 October 2017
Highlights:
Sheridan is one of the oldest stations in the CTA system and is exhibiting signs of deterioration, having reached the end of its useful life. The station structure was built in the 1920s. Historic preservation measures are being taken to maintain the stationhouse façade.
Jefferson Park Intermodal Facility Renovations
Description:
The proposed scope of work includes improvements at the bus turnaround, station and platform. Bus turnaround improvements include new paving, new lighting, replacement of the existing entry canopy with a new canopy to improve access both the Metra and CTA stations, and public art. Station improvements include replacement of the curtain wall, repainting the stationhouse exterior, and rehabilitation of lighting, escalators and stairs.
Platform improvements include the replacement of the canopy skylight system, replacement of lighting, and repairing and refinishing of surfaces.
Status:
This project is being prepared for the design phase. The Project Master Plan has been approved and CTA is advertising a Request for Proposals to solicit a design‐build contractor.
Budget:
The project is on budget. The state‐funded budget amount is $15,236,957. Including additional funding, the total overall budget is $25,000,000.
Budget Obligated Expended Expended %
State‐Funded Budget $15,236,957 $1,310,830 $1,537 0% Overall Project Total $25,000,000 $10,433,188 $9,053,790 36%
Schedule:
The project is on schedule.
Milestone Baseline Schedule Actual (A) / Forecast Design‐Build Notice to Proceed March 2016 March 2016
Design Complete October 2016 October 2016
Substantial Completion December 2017 December 2017
Highlights:
This project is part of a larger capital improvement program known as “Your New Blue” for the O’Hare Blue Line, which includes additional projects involving track and station renewal. The estimated overall budget for the entire program is $492 million. Jefferson Park is a multi‐modal station that provides a vital link between CTA rail, CTA bus, Metra, and Pace.
Rail Shop Roofs and Bus Washer Replacements
Description:
This project will provide for improvements at the Green Line Harlem Rail Shop, Blue Line Des Plaines Rail Shop, and 77th Bus Garage. The roofing component will replace existing roofs at Harlem and Des Plaines Rail Shops, with a new exterior rail car washer at Des Plaines as well. Two existing bus washers at 77th Garage will also be replaced.
Status:
Construction work on rail shop roofs is underway. Installation of the new roof at
Harlem Rail Shop is complete, and the contractor will be mobilizing at Des Plaines Rail Shop in Spring 2016. Design of washer replacements is at the 30% milestone.
Budget:
The state‐funded budget amount is $13,457,053. Including additional funding, the total overall budget is $32,523,142.
Budget Obligated Expended Expended %
State‐Funded Budget $13,457,053 $4,750,107 $143,180 1% Overall Project Total $32,523,142 $11,516,465 $3,441,212 11%
Schedule:
The project is on schedule.
Milestone Baseline Schedule Actual (A) / Forecast
Roof Replacement Start June 2015 June 2015 A
Roof Replacement Complete June 2016 June 2016
Washer Replacement Start January 2017 January 2018 Washer Replacement Complete January 2018 January 2018
Highlights:
The existing roofs at the Harlem and Des Plaines Rail Shops are approaching the end of their useful lives, both having been installed when the rail shops were first opened. Harlem Rail Shop was constructed in 1965 and Des Plaines Rail Shop was constructed in 1960. Both rail car washers are located exterior to the rail shop and are in poor condition, with much of their structures coated in rust. At 77th Garage, only one of the two bus washers is currently functional, putting a strain on the servicers at this facility to perform their duties on a daily basis.
Purple Line Express Track Renewal
Description:
This project will renew aging and deteriorated track components. Activities include tie replacement, partial or complete replacement of running rail, and renewal of certain special trackwork locations.
Status:
Work by CTA forces started in June 2013 and is now complete on the Evanston branch of the Purple Line, between Howard and Linden.
Work continues on the Evanston Express tracks between Belmont and Howard, with particular focus on the southbound track, which is out of service for Wilson Transfer Station phasing and three‐track operation. Crews are taking advantage of the efficiency gained by working on the out of service track.
Budget:
The project is on budget.
Budget Obligated Expended Expended %
Project Total $11,000,000 $8,511,821 $7,019,443 64%
Schedule:
The project is on schedule. No contracts have been executed because the work is being performed by CTA forces.
Milestone Baseline Schedule Actual (A) / Forecast
Project Start June 2013 June 2013 A
Project Complete May 2016 May 2016
Highlights:
This project is not a complete renewal, but represents a targeted heavy maintenance scheme until additional funding is secured for complete track replacement. On the Evanston branch between Linden and Howard, only 3% of the track is subject to slow zone. On Evanston Express track between Howard and Belmont, 43% remains subject to slow zone. These areas will be addressed by this project, mitigating slow zones during the near future while a more permanent solution is developed as part of the Red and Purple Modernization program.
98th Shop – Replace Hoist and Spin Jacks
Description:
CTA will replace the existing carriage hoists, spin posts, body hoists, turntables, and associated controls on two tracks, each of which can accommodate up to two cars at a time. This equipment is used to elevate and support rail cars during standard and special maintenance procedures.
Status:
This project is being pursued through CTA’s Job Order Contracting program. The low bidder has been awarded a construction contract and is in the process of procuring materials.
Budget:
The project is on budget. Including additional funding, the total overall budget is $8,535,000.
Budget Obligated Expended Expended %
State‐Funded Budget $7,325,000 $7,599,065 $0 0%
Overall Project Total $8,535,000 $8,106,029 $532,991 6%
Schedule:
The project is on schedule.
Milestone Baseline Schedule Actual (A) / Forecast
Work Order Award April 2015 April 2015 A
Construction Start March 2016 March 2016
Substantial Completion August 2016 August 2016
Highlights:
The equipment at 98th Shop was installed when the shop was opened in 1967, is considerably past its useful life, and has become difficult for CTA to maintain and repair. Replacing this equipment will not only improve reliability, but will also provide flexibility, as both tracks used to service rail cars will have the same equipment after the project is completed.
74th, 98th, and Midway Shops Tuckpointing
Description:
CTA will replace the mortar and sealant joints at the exterior masonry or precast. Additionally, repairs to the building caused by sealant degradation will be included. Key areas of concern are at the junctions of precast panels, dissimilar materials (e.g., masonry and steel), and at wall openings, such as windows and doors.
Status:
Repair work at 98th Shop started in May 2015 and is now complete. Design for 74th Shop is complete, and design for Midway Shop is nearing
the 100% milestone. Task orders for construction at both locations have been awarded.
Budget:
The state‐funded budget amount is $1,930,340. Including additional funding, the total overall budget is $3,046,746.
Budget Obligated Expended Expended %
State‐Funded Buget $1,930,340 $224,479 $0 0%
Overall Project Total $3,046,746 $529,220 $149,274 5%
Schedule:
The project is on schedule.
Milestone Baseline Schedule Actual (A) / Forecast
98th Shop Work Start May 2015 May 2015 A
Midway Shop Work Start April 2016 April 2016
74th Garage Work Start June 2016 June 2016
Substantial Completion August 2016 August 2016
Highlights:
74th Garage and Midway Rail Shop were constructed in 1993, and 98th Rail Shop was constructed in 1967. Replacement of the existing mortar and sealant joints is needed to avoid continued damage to the exterior construction, which would eventually migrate into the interior of the buildings.
Dearborn Subway Station Improvements –
Grand, Chicago, and Division
Description:
The proposed work includes improvements at the street, mezzanine, and platform levels. At the street level, new entry canopies will be installed at each stair opening with repairs to the stairs, new glazed tile walls, new lighting and repainted ceilings. At the mezzanine level, improvements include new finishes, lighting, and exit roto‐gates. At the platform level, improvements include new finishes, lighting, and furniture. Additional scope may include repairs to the elevators and stairs between the mezzanine and platform levels.
Status:
The project is in the later stages of planning. The Project Master Plan has been developed and is going through the approval process. Design is expected to begin in February 2017 under a design‐ build contract.Budget:
The state‐funded budget amount is $1,028,240. Including additional funding, the total overall budget is $39,000,000.
Budget Obligated Expended Expended %
State‐Funded Budget $1,028,240 $901,099 $351 0%
Overall Project Total $39,000,000 $2,015,330 $351 0%
Schedule:
The project is on schedule.
Milestone Baseline Schedule Actual (A) / Forecast Design‐Build Notice to Proceed February 2017 February 2017
Design Complete November 2017 November 2017
Substantial Completion March 2019 March 2019
Highlights:
The Dearborn Subway opened in 1951, and these stations are in need of upgrades and improvements to improve operations and customer experience. This project is part of a larger capital improvement program known as “Your New Blue” for the O’Hare Blue Line, which includes additional projects involving track and station renewal. The estimated overall budget for the entire program is $492 million.
Replace 160 Bi‐Level Electric MU Commuter Cars
Description:
Purchase 160 new electric multiple unit “Highliner” Cars for the Metra Electric District. The new cars will replace the existing cars, which are up to 45 years old, to reduce maintenance and increase reliability.
Status:
The project is in the manufacturing phase but behind schedule. Prototype Cars were delivered in September 2012. To date, 122 Highliner cars have been delivered to Metra.
Budget:
The project is under budget due to the accumulation of liquidated damages from missed delivery milestones. If future deliveries are made in accordance with the manufacturer’s expected schedule, liquidated damages will total approximately $9 million.Budget Obligated Expended Expended %
Project Total $585,100,000 $585,099,989 $533,166,064 90%
Schedule:
The project is estimated to be about fourteen months behind the baseline schedule. All Highliner car shells have been fabricated. Completed car deliveries for the second group of 80 cars began in late October 2014. Deliveries are planned for approximately six cars per month but have been inconsistent. Deliveries are expected to continue into summer 2016.
Milestone Baseline Schedule Actual (A) / Forecast
Notice to Proceed October 2010 October 2010 A
Prototype Car Delivery September 2012 September 2012 A
1st Car Delivery December 2012 November 2012 A
80 Cars Complete February 2014 July 2014 A
160 Cars Complete May 2015 June 2016
Highlights:
The rail car manufacturer, Nippon Sharyo, opened its manufacturing facility in Rochelle, Illinois in 2012 and has since also constructed a parts fabrication shop at Rochelle.
Final assembly of all Highliner Production cars is being done in Rochelle. Car body shells for cars #81 to #160 (80 cars) were manufactured in Rochelle.
Union Pacific West Line Expansion
Description:
Status:
Budget:
The project is on budget. RTA/IDOT funding will provide for design, environmental study, land acquisition, and construction. The state‐funded budget amount is $44,500,000. Including additional federal and local funding, as well as other components of the UP West Line Expansion, the total overall budget is $191,100,000. Metra and the Union Pacific Railroad are sharing these costs.
Budget Obligated Expended Expended %
State‐Funded Budget $44,500,000 $1,888,429 $309,687 1% Overall Project Total $191,100,000 $103,235,908 $100,487,179 53%
Schedule:
The project is on schedule.Milestone Baseline Schedule Actual (A) /Forecast
Design Completion March 2016 March 2016
Notice to Proceed July 2016 July 2016
Substantial Completion December 2018 December 2018
Highlights:
The addition of a third main line track will eliminate key bottlenecks and allow Metra to add more service, including more express trains, on the line. The potential for freight interference will also be mitigated.
The parking deck in Geneva was recently expanded through a separate project to accommodate the removal of surface spaces that will be eliminated when the new track is placed.
This project is part of a public‐private partnership between Metra and the Union Pacific Railroad to construct a new third main line track. The segments funded under this project are located between mileposts 10.0 and 11.8 in Maywood and Melrose Park and between mileposts 32.1 and 38.4 in West Chicago and Geneva.
Design is at the 30% milestone and progressing to 60%. The consulting contract for required environmental work has been awarded, and this work is ongoing, concurrent with track design.
Positive Train Control – System Integrator
Description:
Status:
Budget:
The project is on budget. The state‐funded budget amount dedicated to the System Integrator is currently $44,000,000. Including additional federal and local funding, the overall funded budget for PTC is $152,580,834; however, the final cost for PTC is expected to reach over $350 million. Metra is seeking additional funding to complete the required scope.Budget Obligated Expended Expended %
State‐Funded Budget $44,000,000 $40,000,000 $0 0%
Overall Project Total $152,580,834 $121,625,226 $51,485,489 34%
Schedule:
The project is on schedule. Metra is on track to implement PTC in advance of the federally‐ mandated deadline.
Milestone Baseline Schedule Actual (A) /Forecast
Contract Award August 2015 August 2015 A
Begin Implementation August 2015 August 2015 A
Substantial Completion April 2017 April 2017
Highlights:
For the overall PTC scope, Metra continues to make progress, and is in line with its peers in implementation. Congress has authorized an extension to the PTC deadline, which is now December 31, 2018.
The Positive Train Control (PTC) system is comprised of onboard and wayside equipment, including signals, GPS, computer hardware and software, and various other communications components. The system integrator functions to combine these components through design, testing, and implementation.
The contract for the System Integrator was reviewed and approved by RTA and IDOT, with the contract awarded in August 2015. Activities under this contract are underway.
Auburn Park New Station
Description:
Status:
Budget:
The project is on budget.Budget Obligated Expended Expended %
Project Total $21,500,000 $1,416,821 $1,213,422 6%
Schedule:
Uncertainty of state capital funding is delaying this project. The project was initially behind schedule due to an extended land acquisition process and additional design duration. The design process was made more complex by the selection of the Rock Island District right‐of‐way as a future high‐speed rail route. Uncertainty of state funding is now also adding delay. Forecast milestone dates are based on funding being available in 2016.
Milestone Baseline Schedule Actual (A) /Forecast
Design Completion January 2014 March 2016
Notice to Proceed September 2015 June 2016
Substantial Completion February 2017 November 2017
Highlights:
This project will bring a new station on the Rock Island District to the Auburn Park neighborhood in Chicago and is expected to increase transit accessibility and ridership in the community area. The station will also allow for connections to CTA buses on 79th Street.
The Auburn Park Station will be a new station stop on the Rock Island District in the City of Chicago. The scope includes a center platform with canopy, a landscaped area at 79th Street and Lowe Avenue featuring an ADA ramp to the stationhouse, and elevator access to the platform. A small parking lot will also be constructed. The scope was enhanced after additional state funding was provided.
The project is in design and progressing to the 90% milestone but is on hold pending availability of state capital funding. Land parcel acquisition is also on hold.
Calumet Station
Description:
This project includes rehabilitation of the Calumet Station, replacing the platform, shelters, warming house, north and south headhouses, lighting, elevator, painting, site work, landscaping and replacement of communications equipment.
Status:
Design and final drawings are complete. The project is awaiting availability of state capital funding required to award a construction contract.
Budget:
The project is on budget.
Budget Obligated Expended Expended %
Project Total $5,500,000 $640,106 $0 0%
Schedule:
Uncertainty of state capital funding is delaying this project. The project was previously behind schedule due to delays experienced at the Flossmoor station project. It is now behind schedule due to uncertainty of state capital funding. Forecast milestone dates are based on funding being available in 2016.
Milestone Baseline Schedule Actual (A) / Forecast
Design Completion February 2013 December 2013 A
Notice to Proceed April 2015 March 2016
Substantial Completion March 2016 January 2017
Highlights:
Calumet and Hazel Crest stations are adjacent and will be completed concurrently within operational constraints.
Hazel Crest Station
Description:
The project scope includes the rehabilitation of the station and entrances, and the addition of an elevator. The project will raise the depot, currently at street‐level, to allow space for vendors and restrooms at street level. Metra’s State Bond funding will not be applied to the new vendor spaces, however, design will allow for such improvements by the City of Hazel Crest in the future.
Status:
Design and final drawings are complete. The project is awaiting availability of state capital funding required to award a construction contract.Budget:
The project is on budget.Budget Obligated Expended Expended %
Project Total $5,000,000 $597,120 $277,789 6%
Schedule:
Uncertainty of state capital funding is delaying this project. The project was previously behind schedule due to delays experienced at the Flossmoor station project. It is now behind schedule due to uncertainty of state capital funding. Forecast milestone dates are based on funding being available in 2016.
Milestone Baseline Schedule Actual (A) / Forecast
Design Completion February 2013 December 2013 A
Notice to Proceed April 2015 March 2016
Substantial Completion March 2016 January 2017
Highlights:
Hazel Crest and Calumet stations are adjacent and will be completed concurrently within operational constraints.
Peterson Ridge New Station
Description:
Construct a new station on the Union Pacific North Line at Peterson Avenue and Ridge Avenue in the City of Chicago, including two 6‐8 car platforms, lighting, ramps, sheltered warming facilities, stairs, ADA ramps, ADA parking, kiss‐n‐ride, and parking spaces.
Status:
The land acquisition process is ongoing, with agreement reached between Metra and Union Pacific. Land acquisition and subsequent project
processes are on hold pending availability of state capital funding.
Budget:
The project is on budget. The state‐funded budget amount is $5,000,000. Including additional funding, the total overall budget is $15,000,000.
Budget Obligated Expended Expended %
State‐Funded Budget $5,000,000 $0 $0 0% Overall Project Total $15,000,000 $1,121,863 $1,102,376 7%
Schedule:
Uncertainty of state capital funding is delaying this project. Forecast milestone dates are based on funding being available in 2016.Milestone Baseline Schedule Actual (A) / Forecast
Design Completion June 2015 June 2015 A
Substantial Completion September 2016 March 2017
Highlights:
The project scope also includes rehabilitation work on the railroad bridges over Peterson Avenue and Ridge Avenue, extending their useful lives.
Romeoville New Station
Description:
Status:
Budget:
The project is on budget.Budget Obligated Expended Expended %
Project Total $2,000,000 $150,000 $0 0%
Schedule:
Uncertainty of state capital funding is delaying this project. The Village of Romeoville is developing its design while other project processes await state capital funding, and as such, milestone dates have yet to be established; however, the station is currently expected to be substantially complete in late 2017 if no further delays are experienced.Highlights:
The village is using a 99‐year lease with a refinery adjacent to the Heritage Corridor right‐of‐ way as the site for the new station. Transit‐oriented development opportunities are also being pursued.
Construction of a new station on the Heritage Corridor line in the Village of Romeoville at 135th Street. A parking lot with 600 spaces will also be constructed.
Metra has established a conceptual design with the Village of Romeoville, which is continuing its component of the design. The remainder of the project is on hold pending availability of state capital funding.
Purchase 40’ Compressed Natural Gas Buses
Description:
Status:
Budget:
The project is on budget.Budget Obligated Expended Expended %
Project Total $49,000,000 $43,678,299 $498,731 1%
Schedule:
Uncertainty of state capital funding is delaying this project. The project was previously behind schedule due to a lack of a fueling facility at Pace, but is currently behind schedule due to uncertainty of state capital funding, which has suspended project activity. Forecast milestone dates are based on funding being available in 2016.
Milestone Baseline Schedule Actual (A) /Forecast
Contract Award February 2015 February 2015 A
CNG Retrofit Complete June 2015 February 2016
91 Bus Delivery June 2016 June 2017
Highlights:
When Pace places the CNG buses into service, long‐term operational cost savings are expected. Although initially more expensive to procure, CNG buses have been shown to make up the cost difference prior to the end of their useful lives.Purchase new 40’ Compressed Natural Gas (CNG) buses for fixed route service. The current grant will provide for a minimum of 91 CNG buses. Fueling for these buses will be provided through a retrofit at Pace South Division in Markham, funded through other sources.
Pace awarded a production contract in February 2015. The first 20 buses have been delivered and received by Pace. The remaining 71 buses were previously on hold pending completion of a CNG fueling retrofit. Future deliveries are on hold pending availability of state capital funding. Construction is underway on the fueling facility, which will be complete in February 2016.
Purchase Approximately 84 Paratransit Vehicles
Description:
Status:
Budget:
The project is on budget.Budget Obligated Expended Expended %
Project Total $7,290,500 $3,343 $2,393 0%
Schedule:
Uncertainty of state capital funding is delaying this project. Activity has been suspended due to this lack of funding. Forecast milestone dates are based on funding being available in 2016.Milestone Baseline Schedule Actual (A) /Forecast First Vehicle Delivery November 2015 May 2016
Last Vehicle Delivery May 2016 November 2016
Highlights:
Cost savings from previous paratransit vehicle purchases have been reallocated to this project, allowing Pace to purchase more vehicles under the executed indefinite delivery/indefinite quantity contract.
State funding under this project will provide for the purchase of new 15‐passenger paratransit vehicles under an indefinite delivery/indefinite quantity contract, with orders placed as funding becomes available.
Pace plans to award the contract for this purchase after receiving concurrence from RTA and IDOT; however, the project is on hold pending availability of state capital funding.
Toyota Park Transportation Center
Description:
Status:
Budget:
The project is on budget.Budget Obligated Expended Expended %
Project Total $2,000,000 $1,241,556 $1,241,556 62%
Schedule:
Uncertainty of state capital funding is delaying this project. The project was initially behind schedule due to additional duration required for multiple redesigns and a subsequent re‐bid process. It is now further behind schedule due to the inability of Pace to award a construction contract, which would require state capital funding. Forecast milestone dates are based on funding being available in 2016.
Milestone Baseline Schedule Actual (A) /Forecast Phase 2 Notice to Proceed August 2013 March 2016
Phase 2 Completion May 2014 October 2016
Highlights:
State Bond funding is providing for the construction phase only. Design services are funded and managed by the Village of Bridgeview.
Construct new bus turnaround and passenger facility near Toyota Park in the Village of Bridgeview.
Phase 1, site and underground work, is complete. Phase 2, building and canopy work. was re‐bid in early 2015 after initially receiving high bids. Contract award is on hold pending availability of state capital funding.
Bus Stop Improvements – Joliet Gateway Center
Description:
Status:
Budget:
The project is on budget with zero expenditures. The overall terminal project budget does not affect the bus stop improvements budget.Budget Obligated Expended Expended %
Project Total $1,709,500 $0 $0 0%
Schedule:
The overall Joliet Gateway Center project is behind schedule. The Pace bus stop portion of the work is waiting on other components of the work. Milestone dates will be established once the overall project moves forward.Highlights:
The overall Multi‐Modal Transportation Center project is being managed by the City of Joliet. Pace has committed this project budget as pass‐through funding to improve the bus turnaround facility. As the project is bid and constructed, Pace will not be responsible for any additional funding, but will realize cost savings if the work is completed under budget.
Construct a new bus turnaround facility to serve the nine Pace routes that will connect with the upgraded transportation center in downtown Joliet on the Metra Rock Island District and Heritage Corridor lines, as well as Amtrak routes.
The overall Joliet Gateway Terminal project is being managed by the City of Joliet and is currently behind schedule, with estimates exceeding the available budget.
STATE FUNDED PROJECTS – BUDGET PERFORMANCE STATUS QUANTITY Under Budget 1 On Budget 22 Over Budget 0 PERCENTAGE OF TOTAL PROJECTS 4% 96% Under Budget On Budget Over Budget
STATE FUNDED PROJECTS – SCHEDULE PERFORMANCE (WITHOUT STATE FUNDING DELAYS) STATUS QUANTITY Ahead of Schedule 0 On Schedule 19 Behind Schedule 4 PERCENTAGE OF TOTAL PROJECTS 83% 17% Ahead of Schedule On Schedule Behind Schedule Projects Behind Schedule SB PROJECT REASON
CTA 95th Terminal Improvements Utility conflicts requiring new design and sequencing CTA Rail Car Overhaul Yellow Line closure; substitution of certain parts Metra Purchase 160 Highliner Cars Ongoing quality control issues
Pace Joliet Bus Stop Improvements Delay to overall project managed by City of Joliet
STATE FUNDED PROJECTS – SCHEDULE PERFORMANCE (INCLUDING STATE FUNDING DELAYS) STATUS QUANTITY Ahead of Schedule 0 On Schedule 11 Behind Schedule 12 PERCENTAGE OF TOTAL PROJECTS 48% 52% Ahead of Schedule On Schedule Behind Schedule Additional Projects Being Delayed by Uncertainty of State Funding SB PROJECT CURRENT STATUS
Metra Auburn Park New Station Design completion on hold
Metra Calumet Station Award of construction contract on hold Metra Hazel Crest Station Award of construction contract on hold Metra Peterson Ridge Station Land acquisition on hold
Metra Romeoville New Station Design completion on hold
Pace Purchase CNG Buses In procurement; future deliveries on hold Pace Purchase Paratransit Vehicles In procurement; future deliveries on hold Pace Toyota Park Transportation Center Award of construction contract on hold
STATE FUNDED PROJECTS – CHANGE ORDERS STATUS QUANTITY Projects With Change Orders 4 Projects Without Change Orders 19 Note: Some projects may have executed multiple change orders. PERCENTAGE OF TOTAL PROJECTS 17% 83% Projects With Change Orders Projects Without Change Orders
STATE FUNDED PROJECTS – CHANGE ORDER REASONS
REASON QUANTITY COST
Added Value 2 $17,961,645 Unforeseen Conditions 4 $3,728,391 Errors and Omissions 1 $193,395 Value Engineering 1 ($1,177,000) TOTAL 8 $20,416,431
The change order quantities and cost amounts represent the cumulative total for the 23 currently ongoing state‐funded projects.
Only three new change orders were executed for currently ongoing projects within this reporting period. Two of these change orders were for the 95th Street Terminal Improvements project. Multiple conditions have been discovered during construction that required design modifications. Additionally, CTA was required to extend the contract duration for its Owner’s Representative. When the project delivery method was changed from Construction Manager/General Contractor At‐Risk to Design‐Build, this left CTA without Construction Manager representation on the project. This necessitated a contract extension to the Owner’s Representative, which will act in such a capacity. The cost associated with this extension is reasonable given the nature of the services and the complexity of the project.
The third change order executed during this reporting period was necessary for the CTA Rail Car Overhaul project. Several miscellaneous hardware items were inadvertently omitted in the original contract document. CTA Rail Engineering determined that the change order was in CTA’s best interest, and that the circumstances determined to necessitate the change were not reasonably foreseeable at the time of performance.
As has been the case since the state bond program began in 2010, the majority of change order cost adds value to projects, particularly regarding the federally‐mandated implementation of Positive Train Control (PTC) on Metra’s procurement of 160 Electric Highliner Cars. For this change order, the opportunity to add PTC capability during initial fabrication was more efficient and less costly than a subsequent retrofit.
Section II
PROJECTS OVER $10,000,000
SERVICE BOARD PROJECT TITLE BUDGET
CTA Replace Approximately 714 Rail Cars $1,137,528,552 Metra Replace 160 Bi‐Level Electric MU Commuter Cars $585,100,000 CTA 95th Street Terminal Improvements $280,000,000 CTA Purchase Nova Buses $233,481,678 CTA Wilson Transfer Station $206,050,539 Metra UP West Line Expansion $191,100,000 Pace Purchase 40' Fixed Route Buses $167,974,976 Metra Replace Bridges ‐ UP North $156,800,000 Metra Positive Train Control $152,580,834 Metra Replace Bridges, 18th to 55th ‐ Rock Island District $120,492,060 Pace Purchase CNG Buses $119,913,100 Metra Lake Street Interlocker $66,869,804 CTA East Lake, Broadway, and Illinois Substations $65,344,926 CTA Perform Rail Car Overhaul and Mid‐Life Rehabilitation $53,132,149 Metra Locomotive Rehabilitation ‐ F40 $52,807,799 CTA Ravenswood‐Loop Connector Signal Renewal $50,000,000 CTA O'Hare Blue Line Station Improvements ‐ Addison to Cumberland $43,000,000 CTA Dearborn Subway Station Improvements – Grand, Chicago, and Division $39,000,000 Pace Purchase Paratransit Buses for Regional ADA Service $37,998,300 CTA Kimball, Princeton, and State Substations $34,726,123 CTA Rail Shops Roofs and Bus Washer Replacements $32,523,142 Pace Purchase Paratransit Buses for Suburban Dial‐A‐Ride $30,098,869 Pace Purchase 40' Over The Road Buses $28,872,150 Metra Traction Power System Augmentation ‐ MED $26,789,036 CTA Jefferson Park Intermodal Facility Renovations $25,000,000 CTA North Red Line Stations ‐ Sheridan $24,000,000 CTA Illinois Medical District Station Rehabilitation $23,000,000 Metra Auburn Park New Station $21,500,000 Metra Car Rehabilitation ‐ Amerail $21,297,642 Metra Locomotive Rehabilitation ‐ MP36 $21,000,000 Pace Purchase Vanpool Vehicles $20,011,498 Metra Commuter Car Rehab ‐ Budd $18,440,052 Metra Revenue Accounting System $15,770,000 CTA Quincy Loop Station Upgrades $15,700,000 Metra Peterson Ridge New Station $15,000,000 Metra Head‐End Power Modification $14,425,891 Metra 47th Street Yard Improvements $11,386,165 CTA Purple Line Express Track Renewal $11,000,000
PROJECTS OVER $10,000,000 BY SERVICE BOARD – QUANTITY AND BUDGET
SERVICE BOARD PROJECTS BUDGET
CTA 16 $2,273,487,109 Metra 17 $1,502,359,283 Pace 6 $404,868,893 TOTAL 39 $4,180,715,285 PERCENTAGE OF TOTAL PROJECTS 43% 43% 12% CTA Metra Pace PERCENTAGE OF TOTAL BUDGET 33% 57% 10% CTA Metra Pace
PROJECTS OVER $10,000,000 BY SERVICE BOARD – BUDGET RANGE 10M‐19M 20M‐49M 50M‐99M 100M‐249M 250M‐499M 500M+ CTA Metra Pace
PROJECTS OVER $10,000,000 BY BUDGET RANGE BUDGET RANGE PROJECTS Projects over $500,000,000 2 Projects between $250,000,000 and $499,999,999 1 Projects between $100,000,000 and $249,999,999 8 Projects between $50,000,000 and $99,999,999 5 Projects between $20,000,000 and $49,999,999 15 Projects between $10,000,000 and $19,999,999 8
PROJECTS OVER $10,000,000 BY SERVICE BOARD – BUDGET RANGE
BUDGET RANGE CTA METRA PACE
Projects over $500,000,000 1 1 0 Projects between $250,000,000 and $499,999,999 1 0 0 Projects between $100,000,000 and $249,999,999 2 4 2 Projects between $50,000,000 and $99,999,999 3 2 0 Projects between $20,000,000 and $49,999,999 7 4 4 Projects between $10,000,000 and $19,999,999 2 6 0
PROJECTS OVER $10,000,000 BY TYPE OF PROJECT
TYPE OF PROJECT QUANTITY COMBINED BUDGET
Construction 18 $1,312,202,684 Maintenance / Rehabilitation 10 $302,882,644 Procurement 11 $2,529,329,957
CTA
TYPE OF PROJECT QUANTITY TOTAL BUDGET
Construction 12 $816,821,588 Maintenance / Rehabilitation 2 $85,655,291 Procurement 2 $1,371,010,230 TOTAL 16 $2,273,487,109
Metra
TYPE OF PROJECT QUANTITY TOTAL BUDGET
Construction 6 $531,681,096 Maintenance / Rehabilitation 8 $217,227,353 Procurement 3 $753,450,834 TOTAL 17 $1,502,359,283
Pace
TYPE OF PROJECT QUANTITY TOTAL BUDGET
Construction 0 $0
Maintenance / Rehabilitation 0 $0
Procurement 6 $404,868,893
TOTAL 6 $404,868,893
PROJECTS OVER $10,000,000
SERVICE BOARD PROJECT TITLE BUDGET
CTA Replace Approximately 714 Rail Cars $1,137,528,552 CTA 95th Street Terminal Improvements $280,000,000 CTA Purchase Nova Buses $233,481,678 CTA Wilson Transfer Station $206,050,539 CTA East Lake, Broadway, and Illinois Substations $65,344,926 CTA Perform Rail Car Overhaul and Mid‐Life Rehabilitation $53,132,149 CTA Ravenswood‐Loop Connector Signal Renewal $50,000,000 CTA O'Hare Blue Line Station Improvements ‐ Addison ‐ Cumb $43,000,000 CTA Dearborn Subway Station Renovations ‐ G/C/D $39,000,000 CTA Kimball, Princeton, and State Substations $34,726,123 CTA Rail Shops Roofs and Bus Washer Replacements $32,523,142 CTA Jefferson Park Intermodal Facility Renovations $25,000,000 CTA North Red Line Stations ‐ Sheridan $24,000,000 CTA Illinois Medical District Station Rehabilitation $23,000,000 CTA Quincy Loop Station Upgrades $15,700,000 CTA Purple Line Express Track Renewal $11,000,000
PROJECT: Replace Approximately 714 Rail Cars SCOPE: Purchase new rapid transit cars to replace the aging equipment currently in service. The entire 2200 and 2400 Series fleets and up to 370 of the 2600 Series cars will be retired and replaced by the 5000 Series cars. BUDGET: $1,137,528,552; on budget. SCHEDULE: On schedule; estimated completion March 2016. HIGHLIGHTS: CTA has accepted all 714 cars, which are in service on the Red, Green, Pink, Purple, and Yellow Lines. The manufacturer is working on correcting various quality control issues and building spare trucks. CTA is holding retention until all quality issues are resolved. PROJECT: 95th Street Terminal Improvements SCOPE: This project will rehabilitate the 95th/Dan Ryan station on the CTA Red Line and its bus terminal, which currently serves 11 CTA and Pace routes. The new design will feature an improved layout for bus and rail customers as well as improved and updated amenities. BUDGET: $280,000,000; on budget. SCHEDULE: Behind schedule; estimated completion December 2018. HIGHLIGHTS: CTA awarded a design‐build contract for the main portion of the project scope. The project budget has been increased due to additional cost items discovered during initial design. Advance work is progressing, but is behind schedule due to utility conflicts.
PROJECT: Wilson Transfer Station SCOPE: Wilson Station on the Red Line will be completely reconstructed. The new facility will feature entrances on both the north and south sides of Wilson Avenue, as well as an auxiliary entrance at Sunnyside Avenue, all of which will be accessible. CTA will also preserve historical building elements. BUDGET: $206,050,539; on budget. SCHEDULE: On schedule; estimated completion April 2018. HIGHLIGHTS: Three‐track operation is in place to accommodate demolition and construction of the new station and superstructure. This will continue throughout the duration of the project. There has been minimal operational impact. CTA force account crews are taking advantage of the extended closure to renew track and structure components in nearby areas. PROJECT: Purchase Nova Buses SCOPE: Funding will provide for the purchase, engineering, training (including training equipment), and inspection for a minimum of 300 and a maximum of 450 fully accessible buses. BUDGET: $233,481,678; on budget. SCHEDULE: On schedule; estimated completion September 2016. HIGHLIGHTS: A contract for the minimum amount of 300 buses has been awarded and executed, and an option was exercised to add an additional 125 buses. To date, CTA has received 200 buses, with deliveries on schedule at the rate of five per week.
PROJECT: East Lake, Broadway, and Illinois Substations SCOPE: This project will provide for new traction power equipment with greater capacity and redundancy, new distribution cables to the right‐of‐way, as well as provide for repairs and upgrades for the building that houses the equipment. BUDGET: $65,344,926; on budget. SCHEDULE: On schedule; estimated completion December 2019. HIGHLIGHTS: CTA continues its traction power upgrade program with this project. The designer of record has started field investigations and is preparing the 30% design submittal and initial cost estimates. PROJECT: Perform Rail Car Overhaul and Mid‐Life Rehabilitation SCOPE: To reduce maintenance costs, 2600 Series cars are undergoing a 3/4 life overhaul and 3200 Series cars will receive a mid‐life overhaul. The project budget represents only the first year of a multi‐year overhaul program. BUDGET: $53,132,149; on budget. SCHEDULE: On schedule; estimated completion July 2018. HIGHLIGHTS: Overhaul of the 2600 Series cars is complete, and Skokie Shops crews are now moving forward with overhaul of the 3200 Series cars. During an extended closure of the Yellow Line, not caused by CTA, a workaround was place for rail car delivery. This did not impact the overhaul project schedule.
PROJECT: Ravenswood‐Loop Connector Signal Renewal SCOPE: Replace obsolete signal equipment beyond its useful life with new state‐of‐the‐art equipment on the branch of the Brown and Purple Lines known as the Ravenswood‐Loop Connector, which comprises the area between Merchandise Mart and Armitage Stations. BUDGET: $50,000,000; on budget. SCHEDULE: On schedule; estimated completion April 2017. HIGHLIGHTS: CTA is implementing this project through a design‐build contract. The contract was approved by the CTA Board of Directors and the contractor is awaiting Notice to Proceed. PROJECT: O’Hare Blue Line Station Improvements – Addison to Cumberland SCOPE: These Blue Line stations along the O’Hare branch will be rehabilitated with new canopies and replacement of damaged platforms, as well as repairs to existing damaged curtainwalls. An elevator will be added at Addison. BUDGET: $43,000,000; on budget. SCHEDULE: On schedule; estimated completion October 2016. HIGHLIGHTS: The design documents are complete and the project is moving into the construction phase. Extension of the platform at Addison to accommodate the new elevator is underway.
PROJECT: Dearborn Subway Station Improvements – Grand, Chicago, and Division SCOPE: The proposed scope of work includes improvements at the street, mezzanine, and platform levels. New entry canopies will be installed at each stair opening with new glazed tile walls, lighting, and repainted ceilings. Mezzanine and platform improvements will include new finishes, lighting, furniture, and exit roto‐gates. Elevators and stairs will also be replaced. BUDGET: $39,000,000; on budget. SCHEDULE: On schedule; estimated completion March 2019. HIGHLIGHTS: The Blue Line subway was originally opened in 1951. These three stations date back to that time and are in nee