• No results found

SITE VISIT MEMORANDUM

N/A
N/A
Protected

Academic year: 2021

Share "SITE VISIT MEMORANDUM"

Copied!
6
0
0

Loading.... (view fulltext now)

Full text

(1)

TEL (978) 923-0400 FAX (978) 399-0033

SITE VISIT MEMORANDUM 

 

Project Name:  Couper Farm Construction Observations Green Project No. 15002.030  Subject:  Site Visit 3 

Date / Time:  7/13/2017 (11:00 AM‐11:45 AM)

Location:  On site  

Weather:  Sunny, 70°F  

Prepared By:  Tom Bigelow, Green International (Green) Attendees:  Tom Bigelow (Green), Luke Boucher (Green)  

Site Visit Summary:   

Tom Bigelow (TB) and Luke Boucher (LB) performed a site visit at Couper Farm Estates on 7/13/2017.  The  Town  received  approximately  3‐inches  of  rain  in  approximately  90  minutes  the  previous  evening.  The  Contractor was not on site at the time of the site visit.      Equipment in use:    No equipment in use    Site Observations:   Green arrived on site at 11:00 AM.  The roadway subgrade was wet and appeared to be saturated.   As noted above, Littleton received approximately 3‐inches of rain the previous evening.     Standing water was observed in CB 20 and 21.  It does not appear that the outlet pipes have been  constructed from any catch basins; therefore, any water entering the basins is being retained within  the structure.  This does not appear to be groundwater.  The frame and grates are set on top of the  structures, approximately 1‐foot above the surrounding ground.  The Contractor should investigate  how water is entering these structures and confirm that sediment is not entering the structures in  the same manner.     Signs of significant erosion were noted throughout the site.   Significant erosion was noted at the inlet and outlet of the temporary 18” HDPE culvert located at  Couper Farm Sta. 10+50.  Additional erosion was observed between Sta. 10+50 and Great Road.   Stormwater appears to be sheeting from Great Road and from the nearby fields, concentrating at  the embankment toe, resulting in erosive flows.  Additionally, the temporary culvert appears to have  been  broken  by  the  Contractor  to  install  the  water  line,  introducing  additional  sediment  to  the  stormwater  flow  from  the  roadway  surface.    Green  recommends  the  Contractor  install  erosion  prevention and control measures at this location.  Green also recommends the Contractor install  the permanent culvert shown on the plans and stabilize the area as soon as possible. 

(2)

Site Visit 3     Couper Farm Construction Observations  7/13/2017 (11:00 AM‐11:45 AM)    Green Project No. 15002.030 

 

above.  While this area is not flagged as a wetland, the developer should take measures to prevent  sediment from discharging outside of the proposed limit of disturbance. 

 It  appeared  some  temporary  sediment  basins  were  constructed,  particularly  on  either  side  of  Infiltration Basin No 1  and No 2.    The previous  day’s  storm  appeared  to have  overwhelmed  the  temporary sediment basins.  It appears that water from at least one of the temporary sediment  basins had breached its wall and resulted in a significant sediment deposit in the adjacent wetland.   The site’s perimeter controls were breached in numerous locations behind Lots 5 – 10.  Silt fence  had recently been installed; however, portions did not appear to be keyed into the ground, as is  standard  practice.  This  allowed  water  and  sediment  to  bypass  under  the  erosion  controls.    The  Conservation Commission is aware of the situation and has since issued an enforcement order.  The  Developer has also retained the services of a wetland scientist to assist with remediation at this  location and others on site.   A stockpile of loam was located up‐gradient of Infiltration Basin No. 2.  No perimeter controls were  present around the stockpile.  It appears that material from the stockpile washed into Infiltration  Basin No. 2.  The Contractor should remove the excess material and the Infiltration Basin should be  monitored to ensure stormwater still infiltrates though the basin bottom. 

 Silt  fence  was  installed  downstream  of  the  outlet  of  flared  end  83,  between  Lots  13  and  14.   Sediment appears to have overwhelmed the silt fence; however, additional perimeter controls are  in place down‐gradient of the silt fence and did not appear to be breached.  The Contractor should  maintain and replace the erosion controls, as required. 

 Due  to  inaccessibility  resulting  from  the  saturated  soils,  a  review  of  erosion  downstream  of  Infiltration Basins No. 3 and No. 4 was not performed.   

(3)

 

  (Picture of the break in the temporary culvert at Sta 10+50 on Couper Farm Road.) 

  (Sediment in agricultural space (Open Space C) located south of Couper Farm Road) 

(4)

Site Visit 3     Couper Farm Construction Observations  7/13/2017 (11:00 AM‐11:45 AM)    Green Project No. 15002.030 

 

 

(5)

 

  (Sediment from a temporary infiltration basin breaching the perimeter erosion controls and       entering the flagged wetland)    (Evidence of runoff from loam stockpile entering Infiltration Basin No. 2) 

(6)

Site Visit 3     Couper Farm Construction Observations  7/13/2017 (11:00 AM‐11:45 AM)    Green Project No. 15002.030 

 

  (Erosion cut through embankment constructed near Lot 11)    (Sediment at the outlet of flared end 83)   

References

Related documents

CAPÍTULO 2 RECORRIDOS DE ESTUDIO Y DE INVESTIGACIÓN MONO DISCIPLINARES EN LA ESCUELA SECUNDARIA Vංඏංൺඇൺ Cൺඋඈඅංඇൺ Lඅൺඇඈඌ; Mൺඋටൺ Rංඍൺ Oඍൾඋඈ;

The Second Department, reversing Supreme Court, determined the plaintiff’s motion to vacate the order dismissing the complaint for failure to prosecute should have

Seven types of information are therefore identified and considered important for colleges to provide to their students: Appointment, Mental Disorders, Self-help

Together they are not be willing to construction site email request a meeting options and time and there are to help coach proposals to not.. The provision of links to

Medallion dye-sublimation fabric graphics shall be free from defects in material and workmanship for a period of three years from the original date of receipt by the retail

Segalal puji dan syukur penulis ucapkan kepada Allah SWT atas segala rahmat dan karunia-Nya, sehingga penulis dapat menyelesaikan penelitian dan penyusunan

• Copy of previous order placed on vendor for supply, installation and commissioning (in a single order) of Video Conferencing Equipment of same family /

Figure 6 shows the adsorption of Cu(II) with modified shea butter cake at varying adsorbent dosage (40beads- 200beads), 250mg/L of initial metal