• No results found

Ch06 Activity_planning.ppt

N/A
N/A
Protected

Academic year: 2020

Share "Ch06 Activity_planning.ppt"

Copied!
22
0
0

Loading.... (view fulltext now)

Full text

(1)

Chapter Six

(2)

Activity networks

It is a network which shows the different activities making up a project, their estimated duration, and their interdependencies.

These help us to:

Assess the feasibility of the planned project completion date

(3)

Defining activities

Activity networks are based on some assumptions: A project is:

Composed of a number of activities

May start when at least one of its activities is ready to start

(4)

Defining activities -continued

An activity

Must have clearly defined start and end-points Must have resource requirements that can be forecast: these are assumed to be constant throughout the project

(5)

Identifying activities

There are 3 approaches to identify activities: Activity based approach

Product based approach Hybrid approach

Work-based: draw-up a Work Breakdown Structure (WBS) listing the work items needed

(6)
(7)

Product-based approach

list the deliverable and intermediate products of project – product breakdown structure (PBS)

Identify the order in which products have to be created

(8)

Start and finish times

Activity ‘write report software’ Earliest start (ES)

Earliest finish (EF) = ES + duration

Latest finish (LF) = latest task can be completed without affecting project end Latest start = LF - duration

(9)

Example

earliest start = day 5 latest finish = day 30 duration = 10 days

earliest finish = ? latest start = ?

Float = LF - ES - duration

(10)

notation

Activity label, activity description

Duration

Earliest

start

Earliest

finish

Latest

(11)

Forward pass

Forward Pass is carried out to calculate the earliest dates on which each activity may be started and completed.

Start at beginning (Day 0) and work forward following chains.

Earliest start (ES) date for the current activity = earliest finish date for the previous

When there is more than one previous activity, take the latest earliest finish

EF = day 7

(12)
(13)

Complete the table

Activity ES

duration EF

(14)

Backward pass

This method calculates the LATEST DATE at which each activity may be started and finished without delaying the end date of the project. Start from the last activity

We assume that Latest finish (LF) for last activity = earliest finish (EF) of that activity.

If there are more than one activities as last activity, we consider activity which has highest EF .

We work backwards .

(15)
(16)

Complete the table

Activity ES Dur EF LS

LF

A

(17)

FLOAT

• Float is a measure of how much the start or

completion of an activity may be delayed without affecting the end date of the project.

• Any activity with a float of ZERO is critical , because

any delay in carrying out the activity will delay the completion date of the project.

Float = Latest finish - Earliest start - Duration

OR

(18)

Complete the table

Act-ivity

ES Dur EF LS

LF

Float

(19)

Critical path

Path : in activity network graph is any set of consecutive nodes and edges in this graph from the starting node to the last node.

Critical Path consists of a set of dependent tasks that need to be performed in a sequence and which together take the longest time to complete.

It defines the duration of project.

Note: the path through network with zero floats

Critical path: any delay in an activity on this path will delay whole project

References

Related documents

320 of The Revised Penal Code constituting Destructive Arson are characterized as heinous crimes "for being grievous, odious and hateful offenses and which,

Leaves simple, the blades 6–20 × 2.5–11 cm, elliptic to ovate, chartaceous, discolorous, adaxially dark green, abaxially whitish green, the adaxial surface sparsely

Only POM-QM for Windows 3 can be used to evaluate the earliest start, earliest finish, latest start and latest finish times, and calculate the total float for all activities

Hasil analisis faktor lingkungan menunjukkan bahwa masing-masing komponen biotik maupun faktor fisik lingkungan tidak memberikan pengaruh yang signifikan terhadap

Title IX requires that a school: publish a non-discrimination statement; 10 appoint a Title IX Coordinator; 11 adopt grievance procedures that are prompt and equitable and allow

India’s primary child nutrition intervention, the Integrated Child Development Services, aims to improve the physical and psychological well being of children under the age of

Our second main finding that the multiplier effects on different types of government spending differ substantially is further consistent with these supply-side models as we find

Database Engine Relational Data Management Replication Full Text Search Integration Services ETL Processing Data Profiling StreamInsight* Complex Event Processing